MIRUTS Wobari Last Pay.
MIRUTS Wobari Last Pay.
MIRUTS Wobari Last Pay.
የገንዘቡ ልክ ብር
አባሪ በሆነው የክፍያ ሰነድ ጥያቄ መሰረት እስከ ዛሬ ድረስ ተቋራጩ የሠራው ሥራና ያቀረበው ዕቃ ዋጋ Total Amount
As per the attached statement the value of work executed and for material supplied to date is 5,946,538.36
Privious Payment/አስቀድሞ የተከፈለ 5,946,538.36
ቁጥር ቀን የገንዘቡ ልክ ብር ተ.እ.ታ
No. Date Amount /Birr/ Vat
1 Advance Pay 1,490,465.39 223,569.81 ተቀናሽ የገንዘቡ ልክ ብር
2 1st pay 1,554,709.77 251,145.43 Deductions Amount/Birr
3 2nd pay 1,503,191.76 242,823.28 1.አስቀድሞ የተከፈለ
4 2nd pay - - Previous paymen 3,057,901.53
5 2.ቅናሽ
6 Rebate .0% -
7 3.መያዣ
ድምር Retention (2.5%) 148,663.46
Total 3,057,901.53 493,968.71 4.መቀጫ
Penalty -
5. የቅድምያ ክፍያ
20% Advance Payment Chek Advance Payment (30%) 1,490,465.39
Amount of advance taken 1,490,465.39 6. ድምር
Amount of advance repaied 1,490,465.39 Total 4,697,030.38 4,697,030.38
Out standing advance payment - 7. የተጣራ ክፍያ
Net Sum Before 15% VAT 1,249,507.98
8. 15% ተ.ዕ.ታ
VAT 15% 174,442.24
9. ጠቅላላ ድምር+15%ተ.ዕ.ታ
Total with 15% VAT 1,423,950.22
We certify that the contractor is now entitled to the sum of birr 1,423,950.22 //One Million Four Hundrend Twenty
Three Thousand Nine Hundrend Fifty Birr and Twenty Two Cents // only including 15% VAT.
ÃzUjW ፊርማ ቀን
ÃidqW ፊርማ ቀን
Approved By:- _____________________________ Signature ______________________ Date ______________________
Y^¨< ዋናው ውል
Project:- CONSTRACTION OF FINANCE & ECONOMIC GEVELOPMENT OFFICE BUILDING Main Contract 4,968,217.97
x¨<
Supplementry
Location:- WOBA ARI WOREDA, BOYEKA ( WUBHAMER) TOWN Contract-1 480,632.47
›W]¨< S/u?ƒ -
Var.Ord
Employer:- WOBA ARI WOREDA FINANCE & ECONOMIC GEVELOPMENT OFFICE
¾Y^¨< }s^ß Sum 5,448,850.44
Contractor:- MIRUTS GOITOM BUILDING CONTRACTOR 15% VAT 817,327.57
›T"] SG”Ç=e ድምር
Consultant:- SOUTH OMO ZONE URBAN & CONSTRUCTION DEPARTMENT Total sum 6,266,178.00
Previous VAT
የተከናወነው ሥራ መጠን
አስቀድሞ የተከፈለ ተ.ዕ.ታ
Amount // Birr//
ተ.ቁ ቀን የገንዘቡ ልክ የተ.እ.ታ. Amount Excuted Amount (Birr)
No. DATE Amount (Birr) (Birr) 5,946,538.36
ÃzUjW ፊርማ ቀን
Prepared By:- Signature __________________ Date _______________
iDÌL ርማ ቀን
Approved By ______________________________ Signature _________________ Date _______________
በደ/ብ/ብ/ህ/ክ/ መንግስት የደቡብ ኦሞ ዞን SNNPRG South Omo Zone Construction
ኮንስትራክሽን መምሪያ Departement
---------------------------- ---------------------------
_____________
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
በደ/ብ/ብ/ህ/ክ/ መንግስት የደቡብ ኦሞ ዞን ኮንስትራክሽን SNNPRG South Omo Zone Construction
መምሪያ Departement
---------------------------- ---------------------------
_____________
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
SPECIFICATION AND BILL OF QUANTITIES
FOR FINANCE OFFICE BLOCK
Ditto item 3.02 but for ramp & steps. Price shall include top 50cm
3.03
thick cement sand screed and other neseccary related works.
m3 8.50 14.40 1,900.00 16,150.00 27,360.00
Bottom width 100cm and top width 40cm thick stone masonry
retaining wall structure as per the instruction given by the
3.04 supervising Engineers in cements mortar 1:2 .price shall include
pointing exposed face ,concrete copping ,wipole and other related
works as per the drawing.
m³ 45.00 44.80 1,900.00 85,500.00 85,120.00
Total Carried to Summary Eth.Birr 452,200.00 628,626.40
Supply and fix G-28 Corrugated Iron sheet roof cover fixed to
wooden purlin and wooden truss all according to the truss
drawing. Price shall include G-28 roof ridge cover as the
6.01
required Development length of 300mm one coat of anti rust and
two coats of enamel. Roof cover measured in horizontal
projection and purlin measured separately.
m² 763.00 819.56 696.30 531,276.90 570,659.63
Supply and fix G-28 galvanized flat metal sheet gutter as per the
detail drawing. Price shall include all necessary accessories,
6.02
metal brackets, one coat of antirust paint and two coat of
synthetic enamel paint. - -
Development. length =800mm ml 119.00 100.00 253.20 30,130.80 25,320.00
Supply and fix 100mm diameter PVC down pipe as per the
6.03 drawing, price shall include metal strap supports c/c 1000mm,
wire strainer and all other necessary accessories
ml 103.00 131.20 190.00 19,570.00 24,928.00
Supply and fix G-28 galvanised flat metal sheet Side flash as per
6.04 the detail drawing. Price shall include all necessary accessories
to complete the work. - - -
Development. length =430mm ml 61.00 - 76.00 4,636.00 -
Supply and fix G-ribbed sheet eave size 100cm fixed to 40x50mm
6.05 wooden battens c/c 60cm both ways. Price shall include three
coats of oil paint. m² 112.00 80.80 316.50 35,448.00 25,573.20
Ditto as item above but 1mm thick chicken wire mesh ventilation
6.06
fixed to 5x4cm zigba wood purlin. m² 7.00 - 126.60 886.20 -
Total Carried to Summary Eth.Birr 621,947.90 646,480.83
7. CARPENTRY & JOINERY WORK
Supply and fix 8 mm thick chip wood ceilings as per the engineers
approval. Price shall include 40 x 50 mm Zigba wood battens
7.03
with c/c spacing of 600 mm both ways, middle and corner list,
and all other necessary accessories.
m² 558.00 681.88 203.00 113,274.00 138,421.64
Supply and fix flush type doors 40mm thick semi solid cored both
sides covered with 4mm thick mahogany ply wood with sides, top
and bottom lipped and edged with hard wood. Door frame shall
be 40mm thick kerero, wanza or equivalent and its width
7.04 according to the thickness of the wall. work shall be completed
with good quality hinges,cylinderical lock and key, handle and
door stoppers, Price shall include one coat of oil paint and two
coats of varnish. Sample doors has to be inspected and approved
by the consultant before mass production.
- -
a) Type WD1 - size 70x300cm Pcs 2.00 2.00 7,600.00 15,200.00 15,200.00
b) Type WD2 - size 90x200cm(Double swing) Pcs 20.00 21.00 5,000.00 100,000.00 105,000.00
Total Carried to Summary Eth.Birr 414,830.60 549,215.52
8 . METAL WORK
METAL WINDOWS
a) Type TW1 - size - 75x80cm No 44.00 44.00 3,481.50 153,186.00 153,186.00
b) Type TW2 - size -90x80cm No 5.00 5.00 4,304.40 21,522.00 21,522.00
Total Carried to Summary Eth.Birr 174,708.00 174,708.00
9. FINISHING WORK
Apply two coats of cement sand mortar (1:3) plastering and one
9.02 coat of rendering to External wall surface. Price shall include
pre-cleaning and preparation of the surface.
m² 449.40 - 177.20 79,633.68 -
All external stone masonry walls above ground level and entrance
9.03
ramp/steps shall be racked out and pointed in cement mortar 1:3.
m² 50.00 89.92 75.90 3,795.00 6,824.93
9.04 50mm thick cement sand screed floor floor finish with 1:3 mix.
m² 558.00 537.48 228.00 127,224.00 122,545.44
10cm high and 100cm long terrrazo skirting fixed to wall with
9.05
cement sand mortar 1:3. ml 315.00 479.60 76.00 23,940.00 36,449.60
Supply & lay 1000mm wide and 100mm thick C-20 precast
concrete pavement around the building on 100mm red ash base
9.05 and joints pointed in cement and sand mortar mix 1:3. Price shall
includes the sand/red ash base & pointing all as per the detail
drawings.
m² 120.00 123.60 190.00 22,800.00 23,484.00
Supply & lay Ø30cm Concrete half ditch for storm Water
drainage around the pavment .Price shall include red ash or
9.06
equivalent bedding material 40x20cm dressed stone Curb Price
shall include Metal grill Cover as per Engineers direction.
ml 119.00 123.60 177.20 21,086.80 21,901.92
Ditto as item above but ditch with grill for pedestrain made from
9.07
Dia. 16mm steel bar ml 8.00 - 506.50 4,052.00 -
9.08 Construct 5cm thick concrete flashing/coping above parapet wall.
ml 34.00 65.20 101.30 3,444.20 6,604.76
Total Carried to Summary Eth.Birr 819,086.28 652,683.78
------------------- .................
Contractore supervisor
8.00 m3 ---- add 4.10
242.64 m3 0.80
36.74 m3 ---- add
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
4.0 4.00 B./ Around sides of masonry foundation
3.80 Davg = 105cm, T = 50cm
0.80 2.0 30.40
48.64 m3 ---- add 0.50
2.0 4.00 1.05
3.70 31.92 m3 ---- add
0.80 2.0 25.50
23.68 m3 ---- add 0.50
2.0 4.00 1.05
4.50 26.78 m3 ---- add
0.80 2.0 24.10
28.80 m3 ---- add 0.50
1.0 3.80 1.05
3.70 25.31 m3 ---- add
0.80 2.0 17.80
11.25 m3 ---- add 0.50
2.0 2.55 1.05
4.10 18.69 m3 ---- add
0.80 3.0 4.10
16.73 m3 ---- add 0.50
1.0 5.50 1.05
4.10 6.46 m3 ---- add
0.80 2.0 27.40
18.04 m3 ---- add 0.50
1.0 3.80 1.05
8.70 28.77 m3 ---- add
0.80 2.0 18.60
26.45 m3 ---- add 0.50
1.0 3.80 1.05
7.90 19.53 m3 ---- add
0.80 2.0 15.20
24.02 m3 ---- add 0.50
2.0 1.30 1.05
4.50 15.96 m3 ---- add
0.80 6.0 4.00
9.36 m3 ---- add 0.50
4.0 1.30 1.05
3.80 12.60 m3 ---- add
0.80 4.0 3.80
15.81 m3 ---- add 0.50
2.0 1.30 1.05
3.70 7.98 m3 ---- add
0.80 6.0 1.30
7.70 m3 ---- add 0.50
4.0 3.80 1.05
1.40 4.10 m3 ---- add
0.80 Retaining wall L=30.40
17.02 m3 ---- add 1.0 30.40
2.0 6.00 1.05
1.40 0.50
0.80 15.96 m3 ---- add
13.44 m3 ---- add - 0.00 Steps and rizer
1.0 1.30 0.00
1.40 0.00
0.80 0.00 m3 ---- add
1.46 m3 ---- add 214.04 m3
1.0 1.70 214.04 m3 Total Back fill.
1.40 1.06/ Cart away surplus excavated material
0.80 to an appropriate tip.
1.90 m3 ---- add 0.2 1,183 236.7 m3 ---- add from site clear
2.0 3.80 2,248.4 m3 ---- add from bulk exca.
3.80 242.6 m3 ---- add from trench excav.
0.80 169.8 m3 ---- add from trench excav.
23.10 m3 ---- add (563.1) m3 ---- deduct for back fill
349.06 m3 2,334.4 m3 Total Cart away
------------------- .................
Contractore supervisor
1.07/ 25cm thick basaltic stone hardcore well
consolidated and blinded with crushed stone
2.0 4.00
4.50
36.00 m2 ---- add
4.0 4.00
3.80
60.80 m2 ---- add
2.0 4.00
3.70
29.60 m2 ---- add
4.0 2.80
4.10
45.92 m2 ---- add
2.0 3.80
4.10
31.16 m2 ---- add
2.0 3.80
3.80
28.88 m2 ---- add
2.0 2.55
4.10
20.91 m2 ---- add
1.0 5.50
4.10
22.55 m2 ---- add
1.0 3.80
3.70
14.06 m2 ---- add
1.0 3.80
8.70
33.06 m2 ---- add
1.0 3.80
7.90
30.02 m2 ---- add
1.0 3.80
4.50
17.10 m2 ---- add
2.0 6.00
1.40
16.80 m2 ---- add
4.0 3.80
1.40
21.28 m2 ---- add
2.0 1.30
4.50
11.70 m2 ---- add
4.0 1.30
3.80
19.76 m2 ---- add
2.0 1.30
3.70
9.62 m2 ---- add
1.0 1.30
1.40
1.82 m2 ---- add
1.0 1.70
1.40
2.38 m2 ---- add
453.42 m2
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
2.0/ Concrete Work B./ Under masonry foundation
2.01 50mm thick lean concrete quality C-5, 2.0 30.40
cement content 150 kg /m3, of concrete 0.50
A./ Under floor slabe 30.40 m2 ---- add
2.0 4.30 2.0 25.50
4.80 0.50
41.28 m2 ---- add 25.50 m2 ---- add
4.0 4.30 2.0 24.10
4.10 0.50
70.52 m2 ---- add 24.10 m2 ---- add
2.0 4.30 2.0 17.80
4.00 0.50
34.40 m2 ---- add 17.80 m2 ---- add
4.0 3.10 3.0 4.10
4.40 0.50
54.56 m2 ---- add 6.15 m2 ---- add
2.0 4.10 2.0 27.40
4.40 0.50
36.08 m2 ---- add 27.40 m2 ---- add
2.0 4.10 2.0 18.60
4.10 0.50
33.62 m2 ---- add 18.60 m2 ---- add
2.0 2.85 2.0 15.20
4.40 0.50
25.08 m2 ---- add 15.20 m2 ---- add
1.0 5.80 6.0 4.00
4.40 0.50
25.52 m2 ---- add 12.00 m2 ---- add
1.0 4.10 4.0 3.80
4.00 0.50
16.40 m2 ---- add 7.60 m2 ---- add
1.0 4.10 6.0 1.30
9.00 0.50
36.90 m2 ---- add 3.90 m2 ---- add
1.0 4.10 1.0 30.40
8.20 1.00
33.62 m2 ---- add 30.40 m2 ---- add
1.0 4.10 219.05 m2
4.80
19.68 m2 ---- add
2.0 6.30
1.70
21.42 m2 ---- add
4.0 4.10
1.70
27.88 m2 ---- add
2.0 1.60
4.80
15.36 m2 ---- add
4.0 1.60
4.10
26.24 m2 ---- add
2.0 1.60
4.00
12.80 m2 ---- add
1.0 1.60
1.70
2.72 m2 ---- add
1.0 2.00
1.70
3.40 m2 ---- add
0.00 m2
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
2.02/ Reinforced concrete quality C-25, cement b) In 10cm thick floor slab
content 360 kg of cement/m3 2.0 4.30
a) In Ground floor beams 4.80
2.0 30.40 41.28 m2 ---- add
0.30 4.0 4.30
0.25 4.10
4.56 m3 ---- add 70.52 m2 ---- add
2.0 25.50 2.0 4.30
0.30 4.00
0.25 34.40 m2 ---- add
3.83 m3 ---- add 4.0 3.10
2.0 24.10 4.40
0.30 54.56 m2 ---- add
0.25 2.0 4.10
3.62 m3 ---- add 4.40
2.0 17.80 36.08 m2 ---- add
0.30 2.0 4.10
0.25 4.10
2.67 m3 ---- add 33.62 m2 ---- add
3.0 4.10 2.0 2.85
0.30 4.40
0.25 25.08 m2 ---- add
0.92 m3 ---- add 1.0 5.80
2.0 27.40 4.40
0.30 25.52 m2 ---- add
0.25 1.0 4.10
4.11 m3 ---- add 4.00
2.0 18.60 16.40 m2 ---- add
0.30 1.0 4.10
0.25 9.00
2.79 m3 ---- add 36.90 m2 ---- add
2.0 15.20 1.0 4.10
0.30 8.20
0.25 33.62 m2 ---- add
2.28 m3 ---- add 1.0 4.10
6.0 4.00 4.80
0.30 19.68 m2 ---- add
0.25 2.0 6.30
1.80 m3 ---- add 1.70
4.0 3.80 21.42 m2 ---- add
0.30 4.0 4.10
0.25 1.70
1.14 m3 ---- add 27.88 m2 ---- add
6.0 1.30 2.0 1.60
0.30 4.80
0.25 15.36 m2 ---- add
0.59 m3 ---- add 4.0 1.60
28.30 m3 4.10
26.24 m2 ---- add
2.0 1.60
4.00
12.80 m2 ---- add
1.0 1.60
1.70
2.72 m2 ---- add
1.0 2.00
1.70
3.40 m2 ---- add
537.48 m2
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
2.03/ Provide, cut and fix in position sawn 3.0/ Masonry Work
structural wood or steel formwork. 3.01/ 40cm thick stone masonry foundation wall
a) To sides of grade beam 2.0 30.40 BNGL bedded in cement mortar mix (1:3).
4.0 30.40 0.40
0.20 1.00
24.32 m2 ---- add 24.32 m3 ---- add
4.0 25.50 2.0 25.50
0.20 0.40
20.40 m2 ---- add 1.00
4.0 24.10 20.40 m3 ---- add
0.20 2.0 24.10
19.28 m2 ---- add 0.40
4.0 17.80 1.00
0.20 19.28 m3 ---- add
14.24 m2 ---- add 2.0 17.80
6.0 4.10 0.40
0.20 1.00
4.92 m2 ---- add 14.24 m3 ---- add
4.0 27.40 3.0 4.10
0.20 0.40
21.92 m2 ---- add 1.00
4.0 18.60 4.92 m3 ---- add
0.20 2.0 27.40
14.88 m2 ---- add 0.40
4.0 15.20 1.00
0.20 21.92 m3 ---- add
12.16 m2 ---- add 2.0 18.60
12 4.00 0.40
0.20 1.00
9.60 m2 ---- add 14.88 m3 ---- add
8.0 3.80 2.0 15.20
0.20 0.40
6.08 m2 ---- add 1.00
12 1.30 12.16 m3 ---- add
0.20 6.0 4.00
3.12 m2 ---- add 0.40
150.92 m2 1.00
9.60 m3 ---- add
4.0 3.80
0.40
1.00
6.08 m3 ---- add
6.0 1.30
0.40
1.00
3.12 m3 ---- add
150.92 m3
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
3.02/ 40cm thick stone masonry foundation wall Super-Structure
ANGL bedded in cement mortar mix (1:3). 4.0/ Concrete Work
2.0 30.40 4.01/ Reinforced concrete quality C-25,
0.40 cement content of 360 kg of cement/m3
0.80 a) In elevation columns
19.46 m3 ---- add 64 3.00
2.0 25.50 0.20
0.40 0.20
0.80 7.68 m3 ---- add
16.32 m3 ---- add 20 2.50
2.0 24.10 0.20
0.40 0.20
0.80 2.00 m3 ---- add/above TTB
15.42 m3 ---- add 9.68 m3
2.0 17.80
0.40
0.80
11.39 m3 ---- add
3.0 4.10
0.40
0.80
3.94 m3 ---- add
2.0 27.40
0.40
0.80
17.54 m3 ---- add
2.0 18.60
0.40
0.80
11.90 m3 ---- add
2.0 15.20
0.40
0.80
9.73 m3 ---- add
6.0 4.00
0.40
0.80
7.68 m3 ---- add
4.0 3.80
0.40
0.80
4.86 m3 ---- add
6.0 1.30
0.40
0.80
2.50 m3 ---- add
120.74 m3
3.03/ Ditto item 3.02 but for ramp & steps.
5.0 2.00
1.80
0.80
14.40 m3 ---- add
14.40 m3
3.04/ Bottom width 100cm & top width 40cm
thick stone masonry retaining wall structure
1.0 32.00
2.00
0.70
44.80 m3 ---- add
44.80 m3
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
b) In top tie beam 4.02/ Provide, cut and fix in position sawn
2.0 30.40 structural wood or steel formwork
0.25 a) To sides of elevation columns
0.20 Perimeter, P = 0.25*4=1.0m
3.04 m3 ---- add 64 3.00
2.0 25.50 1.00
0.25 192.00 m2 ---- add
0.20 20 2.50
2.55 m3 ---- add 1.00
2.0 24.10 50.00 m2 ---- add
0.25 242.00 m2
0.20
2.41 m3 ---- add
2.0 17.80
0.25
0.20
1.78 m3 ---- add
3.0 4.10
0.25
0.20
0.62 m3 ---- add
2.0 27.40
0.25
0.20
2.74 m3 ---- add
2.0 18.60
0.25
0.20
1.86 m3 ---- add
2.0 15.20
0.25
0.20
1.52 m3 ---- add
6.0 4.00
0.25
0.20
1.20 m3 ---- add
4.0 3.80
0.25
0.20
0.76 m3 ---- add
6.0 1.30
0.25
0.20
0.39 m3 ---- add
2.0 19.80 - Cantileverd Beam
0.25
0.20
1.98 m3 ---- add
2.0 19.00
0.25
0.20
1.90 m3 ---- add
21 1.00
0.25
0.20
1.05 m3 ---- add
23.80 m3
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
b) To sides of and under top tie beam
Perimeter, P = 0.25*2+0.=0.50m 2 15.20
2.0 30.40 2.80
0.50 85.12 m2 ---- add
30.40 m2 ---- add 2 17.80
2.0 25.50 2.80
0.50 99.68 m2 ---- add
25.50 m2 ---- add 8 4.20
2.0 24.10 3.00
0.50 100.80 m2 ---- add
24.10 m2 ---- add 2 4.40
2.0 17.80 3.00
0.50 26.40 m2 ---- add
17.80 m2 ---- add 2 4.60
3.0 4.10 3.00
0.50 27.60 m2 ---- add
6.15 m2 ---- add - Deductions
2.0 27.40 -2.0 1.40
0.50 2.30
27.40 m2 ---- add -6.44 m2 ---- deduct D1
2.0 18.60 -20.0 0.85
0.50 2.30
18.60 m2 ---- add -39.10 m2 ---- deduct D1
2.0 15.20 -44.0 0.80
0.50 1.70
15.20 m2 ---- add -59.84 m2 ---- deduct W1
6.0 4.00 -5.0 1.00
0.50 1.70
12.00 m2 ---- add -8.50 m2 ---- deduct W2
4.0 3.80 855.72 m2
0.50 5.02/ 150mm thick class C-HCB partition wall
7.60 m2 ---- add 3 4.60
6.0 1.30 3.00
0.50 41.40
3.90 m2 ---- add 4 4.40
1.0 59.80 - Cantileverd Beam 3.00
0.50 52.80
29.90 m2 ---- add 9 4.20
218.55 m2 3.00
113.40
5.0/ Block Work 207.60 m2 ---- total 15cm HCB walling
5.01/ 200mm thick class C-HCB wall bedded 5.02/ 10mm thick class C-HCB sun break
in cement mortar ratio (1:3) 44.0 1.70
2 18.60 2.0 0.70
3.00 104.72 m2 ---- add
111.60 m2 ---- add 5.0 1.70
2 15.20 2.0 0.70
3.00 11.90 m2 ---- add
91.20 m2 ---- add 116.62 m2 ---- total 10cm HCB walling
8 17.80 6.0/ Roofing Work
3.00 6.01/ Supply and fix G-28 CIS roof cover fixed
427.20 m2 ---- add to wooden purlin and wooden truss
2 7.70
21.40
329.56 m2 ---- add
2 12.50
19.60
490.00 m2 ---- add
819.56 m2
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
6.02/ G-28 galvanized flat metal sheet gutter
2 19.80
39.60 ml ---- add
2 20.60
41.20 ml ---- add
4 4.80
19.20 ml ---- add/verenda
32 4.10
131.20 ml ---- add
131.20 ml ---- total
- 0.00
- ml ---- add
- ml ---- total
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
7.0/ CARPENTRY & JOINERY WORK 7.03/ Supply and fix 8mm thick chip wood ceiling
7.01/ Supply and fix all structural eucalyptus 2.0 4.30
wood members of truss well seasoned, straight 4.80
and free of any harmful defects 41.28 m2 ---- add
a) Diam. 10-12 cm for upper and lower chord. 4.0 4.30
2.0 19.00 4.10
9.60 70.52 m2 ---- add
364.80 ml ---- add 2.0 4.30
2.0 19.00 4.00
7.70 34.40 m2 ---- add
292.60 ml ---- add 4.0 3.10
2.0 18.00 4.40
13.80 54.56 m2 ---- add
496.80 ml ---- add 2.0 4.10
2.0 18.00 4.40
11.70 36.08 m2 ---- add
421.20 ml ---- add 2.0 4.10
2829.40 ml----- total Diam. 10-12 cm 4.10
33.62 m2 ---- add
b) Diam. 8-10 cm for Vertical and Diagonal 2.0 2.85
2.0 21.00 4.40
16.30 25.08 m2 ---- add
684.60 ml ---- add 1.0 5.80
2.0 20.00 4.40
18.40 25.52 m2 ---- add
736.00 ml ---- add 1.0 4.10
1420.60 ml----- total Diam. 8-10 cm 4.00
16.40 m2 ---- add
c) Supply and fix 5x7 cm zigba Wood purlin 1.0 4.10
2.0 20.60 9.00
11.00 36.90 m2 ---- add
453.20 ml ---- add 1.0 4.10
2.0 19.80 8.20
15.00 33.62 m2 ---- add
594.00 ml ---- add 1.0 4.10
1047.20 ml----- total 5x7 cm zigba Wood purlin 4.80
19.68 m2 ---- add
7.02/ Supply and fix 250x25mm fascia board 2.0 6.30
2 20.60 1.70
41.20 ml ---- add 21.42 m2 ---- add
4.0 4.10
2 19.80 1.70
39.60 ml ---- add 27.88 m2 ---- add
4 4.80 2.0 1.60
19.20 ml ---- add/verenda 4.80
100.00 ml ---- total 15.36 m2 ---- add
4.0 1.60
4.10
26.24 m2 ---- add
2.0 1.60
4.00
12.80 m2 ---- add
2.0 1.60
1.70
5.44 m2 ---- add
2.0 4.80
4.80
46.08 m2 ---- add/Verenda
- Corridor
2.0 17.80
1.50
53.40 m2 ---- add
2.0 15.20
1.50
45.60 m2 ---- add
681.88 m2
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
9. FINISHING WORK 2 18.60
9.01/ Apply three coats of plaster to the following 3.25
surfaces in cement sand mortar of (1:3) mix 120.90 m2 ---- add
a) To internal wall and concrete surfaces. 2 4.60
3 18.60 3.25
3.25 29.90 m2 ---- add
181.35 m2 ---- add 2 4.40
3 15.20 3.25
3.25 28.60 m2 ---- add
148.20 m2 ---- add 4 4.20
14 17.80 3.25
3.25 54.60 m2 ---- add
809.90 m2 ---- add 2 17.80
4 17.80 2.80
3.25 99.68 m2 ---- add
231.40 m2 ---- add 2 15.20
8 4.60 - Partition Wall 2.80
3.25 85.12 m2 ---- add
119.60 m2 ---- add -44.0 0.80
1.70
10 4.40 -59.84 m2 ---- deduct W1
3.25 -5.0 1.00
143.00 m2 ---- add 1.70
26 4.20 -8.50 m2 ---- deduct W2
3.25 680.66 m2
354.90 m2 ---- add c/ 10mm thick class C-HCB sun break
- Deductions 44.0 1.70
-2.0 1.40 2.0 0.70
2.30 104.72 m2 ---- add
-6.44 m2 ---- deduct D1 5.0 1.70
-20.0 0.85 2.0 0.70
2.30 11.90 m2 ---- add
-39.10 m2 ---- deduct D1 116.62 m2
-44.0 0.80 9.03/ All external stone masonry walls above NGL &
1.70 2 30.40 ramp/steps racked out and pointed in cement mortar
-59.84 m2 ---- deduct W1 0.80
-5.0 1.00 48.64 m2 ---- add
1.70 2 25.80
-8.50 m2 ---- deduct W2 0.80
1,874.5 m2 41.28 m2 ---- add
b) To external wall and concrete surfaces. 89.92 m2
4 17.80
3.25 9.05/ 10cm high and 100cm long terrrazo wall skirting
231.40 m2 ---- add 10.0 17.80
178.00 ml ---- add
2 15.20 6.0 18.60
3.25 111.60 ml ---- add
98.80 m2 ---- add 26.0 4.20
109.20 ml ---- add
8.0 4.60
36.80 ml ---- add
10.0 4.40
44.00 ml ---- add
479.60 ml
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
9.04/ 50mm thick cement sand screed floor floor finish 9.05/ Supply & lay 1000mm wide and 100mm thick
with 1:3 mix. C-20 precast concrete pavement
2.0 4.30 2.0 32.40
4.80 1.00
41.28 m2 ---- add 64.80 m2 ---- add
4.0 4.30 2.0 29.40
4.10 1.00
70.52 m2 ---- add 58.80 m2 ---- add
2.0 4.30 123.60 m2
4.00
34.40 m2 ---- add 9.06/ Supply & lay Ø30cm Concrete half ditch for storm
4.0 3.10 Water drainage around the pavment
4.40 2.0 32.40
54.56 m2 ---- add 64.80 ml ---- add
2.0 4.10 2.0 29.40
4.40 58.80 ml ---- add
36.08 m2 ---- add 123.60 ml----- total
2.0 4.10
4.10 9.07/ Construct 5cm thick concrete flashing/coping
33.62 m2 ---- add above parapet wall.
2.0 2.85 2.0 17.40
4.40 34.80 ml ---- add
25.08 m2 ---- add 2.0 15.20
1.0 5.80 30.40 ml ---- add
4.40 65.20 ml----- total
25.52 m2 ---- add
1.0 4.10 10. GLAZNG WORK
4.00 10.01/ Supply and fix quality clear & forested glass
16.40 m2 ---- add glazed to metal beads and putty.
1.0 4.10 a) 4mm thick clear glass to windows & top of
9.00 wooden doors
36.90 m2 ---- add 2 1.40 - Type WD1 - size 70x300cm
1.0 4.10 0.50
8.20 1.40 m2 ---- add
33.62 m2 ---- add - Type WD2 - size 90x200cm(Double swing)
1.0 4.10 21 0.90
4.80 0.50
19.68 m2 ---- add 9.45 m2 ---- add
2.0 6.30 - Type TW1 - size - 75x80cm
1.70 44 0.80
21.42 m2 ---- add 1.70
4.0 4.10 59.84 m2 ---- add
1.70 - Type TW2 - size -90x80cm
27.88 m2 ---- add 5 1.00
2.0 1.60 1.70
4.80 8.50 m2 ---- add
15.36 m2 ---- add
4.0 1.60 79.19 m2
4.10
26.24 m2 ---- add
2.0 1.60
4.00
12.80 m2 ---- add
1.0 1.60
1.70
2.72 m2 ---- add
1.0 2.00
1.70
3.40 m2 ---- add
537.48 m2
------------------- .................
Contractore supervisor
№ LxWxH Quantity Description № LxWxH Quantity Description
10. PAINTING WORK 10.02/ Apply three coats of synthetic paint to
10.01/ Apply three coats of synthetic paint to chipwoosd ceiling
internal wall
3 18.60 2.0 4.30
3.25 4.80
181.35 m2 ---- add 41.28 m2 ---- add
3 15.20 4.0 4.30
3.25 4.10
148.20 m2 ---- add 70.52 m2 ---- add
14 17.80 2.0 4.30
3.25 4.00
809.90 m2 ---- add 34.40 m2 ---- add
4 17.80 4.0 3.10
3.25 4.40
231.40 m2 ---- add 54.56 m2 ---- add
8 4.60 - Partition Wall 2.0 4.10
3.25 4.40
119.60 m2 ---- add 36.08 m2 ---- add
2.0 4.10
10 4.40 4.10
3.25 33.62 m2 ---- add
143.00 m2 ---- add 2.0 2.85
26 4.20 4.40
3.25 25.08 m2 ---- add
354.90 m2 ---- add 1.0 5.80
- Deductions 4.40
-2.0 1.40 25.52 m2 ---- add
2.30 1.0 4.10
-6.44 m2 ---- deduct D1 4.00
-20.0 0.85 16.40 m2 ---- add
2.30 1.0 4.10
-39.10 m2 ---- deduct D1 9.00
-44.0 0.80 36.90 m2 ---- add
1.70 1.0 4.10
-59.84 m2 ---- deduct W1 8.20
-5.0 1.00 33.62 m2 ---- add
1.70 1.0 4.10
-8.50 m2 ---- deduct W2 4.80
1,874.5 m2 19.68 m2 ---- add
2.0 6.30
1.70
21.42 m2 ---- add
4.0 4.10
1.70
27.88 m2 ---- add
2.0 1.60
4.80
15.36 m2 ---- add
4.0 1.60
4.10
26.24 m2 ---- add
2.0 1.60
4.00
12.80 m2 ---- add
2.0 1.60
1.70
5.44 m2 ---- add
2.0 4.80
4.80
46.08 m2 ---- add/Verenda
- Corridor
2.0 17.80
1.50
53.40 m2 ---- add
2.0 15.20
1.50
45.60 m2 ---- add
681.88 m2
------------------- .................
Contractore supervisor
Project:- CONSTRACTION OF WOBA ARI WOREDA FINANCE & ECONOMIC GEVELOPMENT OFFICE BUILDING
Location:- WOBA ARI WOREDA, BOYEKA ( WUBHAMER) TOWN
Client:- WOBA ARI WOREDA FINANCE & ECONOMIC GEVELOPMENT OFFICE
Consultant:- SOUTH OMO ZONE URBAN & CONSTRUCTION DEPARTMENT
Contractor:- MIRUTS GOITOM BUILDING CONTRACTOR
Reinforcement Bar on FED BLOCK, SUB-STRUCTURE Total Length of each Diameter
Location Bar № Shape Dia.(mm) Length(m) № of Item № of Bars Ø8mm Ø10mm Ø12mm Ø14mm Ø16mm
GFB-1 4 14 32.40 2 8 - - - 259.20 -
154 8 0.95 2 308 292.60 - - - -
GFB-2 4 14 27.50 2 8 - - - 220.00 -
129 8 0.95 2 258 245.10 - - - -
GFB-3 4 14 26.10 2 8 - - - 208.80 -
123 8 0.95 2 246 233.70 - - - -
GFB-4 4 14 18.80 2 8 - - - 150.40 -
91 8 0.95 2 182 172.90 - - - -
GFB-5 4 14 5.10 3 12 - - - 61.20 -
23 8 0.95 3 69 65.55 - - - -
GFB-6 4 14 29.40 2 8 - - - 235.20 -
139 8 0.95 2 278 264.10 - - - -
GFB-7 4 14 19.60 2 8 - - - 156.80 -
95 8 0.95 2 190 180.50 - - - -
GFB-8 4 14 16.20 2 8 - - - 129.60 -
78 8 0.95 2 156 148.20 - - - -
GFB-9 4 14 5.00 6 24 - - - 120.00 -
22 8 0.95 6 132 125.40 - - - -
GFB-10 4 14 4.80 4 16 - - - 76.80 -
21 8 0.95 4 84 79.80 - - - -
GFB-11 4 14 2.30 6 24 - - - 55.20 -
9 8 0.95 6 54 51.30 - - - -
0 - - - - -
0 - - - - -
0 - - - - -
Total Length (m) 1,859.15 - - 1,673.20 -
Weight Kg/m 0.395 0.617 0.888 1.210 1.580
Total Weight (Kg) 734.36 - - 2,024.57 -
1. PAINTING - -
Apply decorative & approved type Quartize paint to all external
1.01 cement plastered wall surfaces. Price shall includes pre cleaning
and surface preparation. m² 776.76 680.66 480.00 372,842.96 326,716.80
Ditto as item above but to external smooth plastered concrete
1.02
surface m² 120.00 118.70 480.00 57,600.00 56,976.00
1.03 Ditto but to external sun breaker m² 91.70 116.62 480.00 44,016.00 55,977.60
Apply three coats of synthetic paint to external rendered wall
1.04
surface m² -449.40 -449.40 63.30 -28447.02 -28447.02
Ditto as item above but to external smooth plastered concrete
1.05
surface m² -191.00 -191.00 63.30 -12090.30 -12090.30
1.06 Ditto but to external sun breaker m² -212.00 -212.00 63.30 -13419.60 -13419.60
Total Carried to Summary Eth.Birr 420,502.04 385,713.48
2. ROOFING WORK
Supply and fix precoated EGA-500, 0.4mm thick roof cover fixed
to wooden purlin and wooden truss all according to the truss
2.01
drawing. Roof cover measured in horizontal projection and purlin
measured separately.
m² 48.00 48.02 914.65 43,903.20 43,921.49
Total Carried to Summary Eth.Birr 43,903.20 43,921.49
3. CARPENTRY & JOINERY WORK
2 15.20 48.0 m2
3.25
98.80 m2 ---- add 3.0/ CARPENTRY & JOINERY WORK
2 18.60 3.01/ All structural eucalyptus wood members of truss
3.25 well seasoned, straight and free of any harmful defects
120.90 m2 ---- add a) Dia. 10-12cm eucalyptus upper and lower member
2 4.60 2.0 5.20
3.25 5.00
29.90 m2 ---- add 52.00 ml ---- add
2 4.40 2.0 4.90
3.25 5.00
28.60 m2 ---- add 49.00 ml ---- add
4 4.20 101.00 ml----- total Diam. 10-12 cm
3.25
54.60 m2 ---- add a) b) Dia. 8-10cm eucalyptus Vertical and Diagonal
2 17.80 2.0 12.00
2.80 5.00
99.68 m2 ---- add 120.00 ml ---- add
2 15.20 120.00 ml----- total Diam. 8-10 cm
2.80
85.12 m2 ---- add c) Supply and fix 5x7 cm zigba Wood purlin
-44.0 0.80 4.0 4.90
1.70 5.00
-59.84 m2 ---- deduct W1 98.00 ml ---- add
-5.0 1.00 4.0 0.60
1.70 5.00
-8.50 m2 ---- deduct W2 12.00 ml ---- add/0verlap
680.66 m2 110.00 ml----- total Diam. 8-10 cm
------------------- .................
Contractore supervisor