DUBAI MUNICIPALITY G+12 QUESTIONS 12.01.

2021
1. The purpose of concrete curing is

a) Keep the surface wet during concrete hardening

b) Increase strength of concrete

c) Increase workability of concrete

d) Other

2. Workability of concrete mean

a) Easing of concrete placing , mixing and compacting without segregation

b) Working stress of concrete

c) Working strain of concrete

d) Other

3. The core test for concrete if required is to be done after …. days from concrete casting

a) 7

b) 14

c) 28

d) 4

4. Density of water is

a) 1500 Kg/m3

b) 1000 Kg/m3

c) 2500 Kg/m3

d) 500 Kg/m3
5. Density of steel is

a) 1500 Kg/m3

b) 7800 Kg/m3

c) 2500 Kg/m3

d) 2400 Kg/m3

6. Admixtures are added to concrete mix in order to

a) Decrease the permeability to liquids

b) Increase durability

c) Reduce segregation

d) All

7. Columns mould ( shutter ) can be dismantled after minimum …… days from casting date

a) 14

b) 7

c) 2

d) 5

8. Moulds (shutters) of beams sides can be dismantled after minimum … days from casting

a) 1

b) 7

c) 14

d) 3.6

9. The eave connection is a connection between

a) Beams
b) Column & column

c) Beam & Column

d) Other

10. Minimum thickness of member can be used with 8mm butt weld

a) 10 mm

b) 8 mm

c) 20 mm

d) 6 mm

11. Steel grade used in (H) beams, Waler beam and struts is

None of the above

All of the above

355 N/mm2

275 N/mm2

12. Which one of the following section has a correct steel bar arrangement
13. Choose the correct Shear Diagram of the following loading condition

14. Choose the correct Shear Diagram of the following loading condition
15. Minimum depth of pile head inside the pile cap

a) 150 mm

b) 100 mm

c) 50 mm

d) 75 mm

16. In secant piles minimum overlap for the piles

a) 150 mm

b) 100 mm

c) 50 mm

d) 75 mm

17. The minimum overlap splice for pile reinforcement

60pile dia

50pile dia

45pile dia

45pile dia

18. As per DM circular 141, maximum shoring deflection under design loads as per following

a) 30mm if spacing between the shoring and road is more than 5m

b) 50mm if spacing between the shoring and road is more than 5m

c) 10mm if spacing between the shoring and road is more than 5m

d) 20mm if spacing between the shoring and road is more than 5m

19. As per DM circular 141, soldier piles shoring system without tie anchors can be used

when excavation depth does not exceed a distance of


a) 8 m

b) 6 m

c) 4 m

d) 5 m

20. As per DM141 circular, the minimum angle for open excavation is

a) 60°

b) 30°

c) 15°

d) 40°

21. As per DM circular 141, which shoring system is recommended

a) Secant

b) Contiguous

c) None

d) Soldier

22. The level of shoring RC piles for the road should be below G.L by

a) 1 m

b) 1.5 m

c) 2 m

d) None

23. IF the bolts are located outside the flanges of UC column, then the connection is

a) Flushing

b) Fixed
c) Hinge

d) None

24. Materials used in between of H and I beam of soldier pile

a) Concrete

b) Timber

c) Steel

d) All of the above