Royal Commission For Jubail and Yanbu 021-C19: Document No: Rev. I C - 0 3 3 0 - F - 1 0 2
Royal Commission For Jubail and Yanbu 021-C19: Document No: Rev. I C - 0 3 3 0 - F - 1 0 2
Royal Commission For Jubail and Yanbu 021-C19: Document No: Rev. I C - 0 3 3 0 - F - 1 0 2
Subcontractor:
PROJECT TITLE:
DPS & MMPS FOR SITE DEVELOPMENT OF
UTILITIES FOR BUFFER ZONE
DOCUMENT TITLE:
TABLE OF CONTENTS
1. INTRODUCTION 3
2. ABBREVIATIONS 4
3. SCOPE 5
1. INTRODUCTION
This document provides description for Site Acceptance Test (FAT) to be carried out for
the Instruments and Switch Rack for Lift Stations.
ABB level transmitter, pressure transmitters, level switcher and Flow meter are used in
this project.
The test shall involve Switch rack and instruments functionality tests. All the transmitters
and Switch rack shall be tested as per attached procedure.
2. ABBREVIATIONS
DO Digital Output
AI Analog Input
PS Power Supply
mA Milli Ampere
ET Expansion Terminal
TB Terminal Block
Add Address
ES Engineering Station
OS Operator Station
PG Programming Device
3. SCOPE
The scope of this SAT test is to verify all the instruments and switch rack
are up to the client requirements and shall be grouped into following
phase
CHECK
SN DESCRIPTION REMARKS
PASS FAIL
CLIENT : MARAFIQ
CONTRACTOR : CGC
SUB-CONTRACTOR : VEICO
Functionality CHECK
Start filling the tank with water from zero level and check the following.
CHECK
SN DESCRIPTION REMARKS
PASS FAIL
level.
Stop filling the tank and turn on the power
11 supply of the pumps, the pump shall start run
and check the beacon lamp go off when the level
of the tank go below high high level.
Once the level reach Low level and R2 is on only
12 one duty pump should be running, so check the
duty selector to chose which pump need to be
run on Auto mode.
Check the ODOR removal system Functionality
13
and the ODER Blower is running Auto once the
pumps run, and off once the pumps off.
14 Check the flow water reading coming from the
flow meter (if required)
15
Check the pin stock Functionality
16
Check the Jib crane Functionality
CLIENT : MARAFIQ
CONTRACTOR : CGC
SUB-CONTRACTOR : VEICO
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
CLIENT : MARAFIQ
CONTRACTOR : CGC
SUB-CONTRACTOR : VEICO
ACCEPTANCE CERTIFICATE
We, the undersigned, hereby declare that upon SAT is tests specified in this SAT Document,
and the proper disposition of all properly documented witnessed discrepancies, resulting from
tests specified in this procedure, the system tested & witnessed is functionally acceptable and
ready for the installation at site.
CLIENT : MARAFIQ
CONTRACTOR : CGC
SUB-CONTRACTOR : VEICO