1.0 INTRODUCTION
CSD engineer/technician shall mark the items which has been checked and tested
during SAS–Substation Automation System check at the site using this check list.
2.0 RESPONSIBILITIES
CSD engineer/technician is responsible for marking any checked or tested item mentioned
in the above mentioned work instructions by applying this check list, sign the completed
check list and follow the fling system procedure.