This document provides a checklist for commissioning a Neutral Earthing Resistor (NER). The 11-item checklist includes steps like visual inspections, checking nameplate data against specifications, testing insulation and circuits, measuring resistor values, and cleaning. Upon completion, the checklist is to be signed by representatives from the Commissioning and Testing department and any contracting companies involved.
This document provides a checklist for commissioning a Neutral Earthing Resistor (NER). The 11-item checklist includes steps like visual inspections, checking nameplate data against specifications, testing insulation and circuits, measuring resistor values, and cleaning. Upon completion, the checklist is to be signed by representatives from the Commissioning and Testing department and any contracting companies involved.
This document provides a checklist for commissioning a Neutral Earthing Resistor (NER). The 11-item checklist includes steps like visual inspections, checking nameplate data against specifications, testing insulation and circuits, measuring resistor values, and cleaning. Upon completion, the checklist is to be signed by representatives from the Commissioning and Testing department and any contracting companies involved.
This document provides a checklist for commissioning a Neutral Earthing Resistor (NER). The 11-item checklist includes steps like visual inspections, checking nameplate data against specifications, testing insulation and circuits, measuring resistor values, and cleaning. Upon completion, the checklist is to be signed by representatives from the Commissioning and Testing department and any contracting companies involved.
CL-NG-6460-002-022 Check List of Neutral Earthing Resistor (NER) Commissioning Page Number: 1 of 2
1.0 Equipment General Data and Information
Substation Bay/Panel Equipment Serial No
2.0 Check List of NER Commissioning and Testing
Item Description Done Remarks
1. Visual inspection for any insulator broken.
2. Check nameplate and data. Check the value of resistance and current ratings against 3. the specifications. Checks that the earthing with solderless connectors and suitable for termination of copper conductor of size 240 mm2 for 40 kA and below. 4. Check the grounding resistance of the enclosure earth terminal and resistor earth terminal. Confirm the continuity and tightness of the Bolt & Nut.
Check the resistor rated for 5 Seconds unless specified in
5. data schedule.
6. Test associated NCT & power cable.
Main circuits Resistance measurement test at ambient
temperature. The resistor provided in the NER panel/box 7. shall be measured (after disconnecting the leads) and it should match with the name plate.
8. Insulation resistance measurement test at 5kV DC
Cleaning of all internal as well as external to NER before
9. energization.
Check that the enclosure earth terminal and resistor earth
10. terminal are separate to allow the possibility of disconnection during testing. Archiving System Website: http://AMAS NATIONAL GRID
Title: Index Number:
CL-NG-6460-002-018 Checklist for Commissioning of Oil-Immersed Power Transformer Page Number: 2 of 2
Check if heater circuit is provided, it cutoff automatically,
11. when Transformer is in service and cut in automatically, when transformer is taken out of service.