Genie Switch Gear
Genie Switch Gear
Genie Switch Gear
page
general general description introduction weights and dimensions storage installation floor preparation connection of panels connection of busbars installation of pilot cables connection main cable connection busend cable box connection operation operation of switch - main operation of switch - earth operation of circuit breaker - main operation of circuit breaker - earth operation of busbar earthing switch cable testing main cable phase live indication operation of pocket terminal accessing VTs disconnection of V.T.s commissioning introduction physical checks HV. withstand test test voltages test connection maintenance SF6 gas endurance characteristics product support 2 2 2 3 4 4 5 8 9 10 10 11 12 12 12 13 14 14 15 16 16 17 18 19 19 19 19 20 20 21 22 23 23
MERLIN GERIN
introduction These instructions cover all operations concerning handling, installation, operation and maintenance of the Genie range of equipment.
the range comprises:s CB2 200A circuit breaker s CB6 630A circuit breaker s CB12 1250A circuit breaker s BS6 630A bus section s BS12 1250A bus section s SW6 630A switch s SWE busbar earthing switch The equipment is suitable for indoor use only. It is therefore necessary to protect the equipment from the environment before and during erection/commissioning. Should the busbar chamber or cable box become exposed to the elements, they should be thoroughly cleaned prior to energising. weights and dimensions
unit(s)
circuit breaker/switch
circuit extended bus-section breaker/switch circuit breaker (with busbar VT) (with busbar VT)
h w d
MERLIN GERIN
note:
lifting chains/ropes should be positioned @1800mm and 1650mm from lifting points, as shown.
note:
lifting chains/ropes should be positioned @1800mm and 1650mm from lifting points, as shown.
0m
0m
180
'F'
important
during lifting of the unit all four lifting points must be used. lifting bars are fixed to unit using existing fixings (marked'F') tightened to a torque value of 10Nm(7.4Ib/ft). new fixings and seals must be used to re-secure the facia after lifting, tighten to a torque value of 5.4Nm(4Ib/ft).
important
during lifting of the unit all four lifting points must be used. lifting bars are fixed to unit using existing fixings (marked'F') tightened to a torque value of 10Nm(7.4lb/ft). new fixings and seals must be used to re-secure the facia after lifting, tighten to a torque value of 5.4Nm(4lb/ft).
180
165 0mm
'F'
'F' 'F'
m 0m 165
LIFTING POINTS
LIFTING POINTS
LIFTING POINTS
LIFTING POINTS
offloading
All units are delivered on pallets (secured by 2 x M8 screws and nuts). The units can be off loaded by forklift truck or by using a lifting kit consisting of 2 lifting bars and can be off loaded using an overhead crane (see above diagrams).
storage
These units are designed for indoor use and must not be left outdoors. They should be stored in a warm, dry switchroom and protected against dust and debris.
ancillary kits
Ancillary kits containing busbars, dyscon boots, glands, screws etc. are supplied loose with each unit or fastened to the panel or secured in the cable box.
MERLIN GERIN
floor preparation
698
41
70
The units can be directly bolted to the concrete floor by use of 2 x 10mm rawlbolts for single width panels or 4 x 10mm rawlbolts for bus-section and extended circuit breaker panels. The floor tolerance is 1mm over 1 metre.
Where it is not possible to guarantee that the floor is within the specified tolerance, we strongly recommend the use of foundation channels, i.e. Unistrut P3270 or similar.
note: the floor must be 1mm below the top of the Unistrut
access holes
4 MERLIN GERIN
connection of panels
Remove pilot cable box (if fitted) . To remove undo the 9 x M6 screws and nuts along the top and rear of the busbar chamber. Place the pilot cable box on the top of the low voltage cabinet. (Approximate weight of pilot cable box is 10kg.)
Remove the busbar chamber top and rear cover plate. To remove undo the 10 x M6 captive screws along the top and rear of the busbar chamber cover.
With the busbar chamber cover removed,bolt the panel busbar chamber flanges together using 10 x m6 screws and nuts via the flange holes along the lower and front edges. Repeat until all panels within the switchboard have been installed and bolted together.
MERLIN GERIN
MERLIN GERIN
Ensure all insulation and chambers are clean and free from debris. To complete the installation, tighten all floor fixings, replace all covers, and components removed
FACIA
UPRIGHT
BUSBAR CHAMBER
Fit the busbar chamber end covers using 20 x M6 fixing screws, nuts and washers.
note: access is required via the busbar chamber top access plates.
M10 HEX HEAD BOLT M10 WASHERS M10 LOCK NUT REAR EARTH BAR CONNECTOR
MERLIN GERIN
Busbar torque 54Nm Ensure that the environment is clean and dry.
Clean dyscon boots and bushings. Apply DC4, Dow Corning silicon grease to boots. Fit busbars into boots as shown above.
refer to accessory kit instructions for full details note: it is recommended prior to refitting busbar chamber covers that the busbars are tested - see page 20 for typical tests
INSULATION
Busbar torque 54Nm Ensure that the environment is clean and dry.
Clean dyscon boots and bushings. Apply DC4, Dow Corning silicon grease to boots. Fit busbars into boots as shown above.
note: it is recommended prior to refitting busbar chamber covers that the busbars are tested - see page 20 for typical tests. Please consult us regarding additional tests which may be required for this busbar system.
MERLIN GERIN
installation of pilot cables through pilot cable box standard arrangement optional
Remove the pilot cable box cover by unscrewing the 4 x M6 screws. Pilot cables can be installed from above or below using pre-punched gland plates with various sized electrical knock-outs.
Remove the pilot cable box cover by unscrewing the 2 x M6 screws. Pilot cables can be installed from above or below using individual sliding gland plates or by drilling the single sliding plate, as shown.
MERLIN GERIN
All units are fitted with dry type cable boxes suitable for accepting heat shrink or cold fit termination kits. Accessory kits containing gland plates etc are available. Cable termination torque = 54NM
note: red phase bushing is on rear left of unit. note: ensure that cable is supported by gland plate before placing on bushings.
10
MERLIN GERIN
MERLIN GERIN
11
Check that the gas indicator is in the green healthy condition. Check the facia diagram for the service condition. Remove padlocks if fitted. Move select to main switch position.
Insert handle as shown and pull down firmly until the switch closes. The selector lever will be locked into the main switch position.
Fit padlock into the handle socket padlock bracket if required. To open, rotate the handle through 180 and reverse the procedure.
Check that the gas indicator is in the green healthy condition. Check the facia diagram for the service condition. Remove padlocks if fitted. With the switch in the open position, move the selector lever to earth switch position.
Insert handle as shown and pull down firmly until the switch closes. The selector will be locked in the earth switch position.
Fit padlock into the handle socket padlock bracket if required. To open, rotate the handle through 180 and reverse the procedure.
12
MERLIN GERIN
Check that the gas indicator is in the green healthy condition. Check the facia diagram for the service condition. Remove padlocks if fitted. Move select to main circuit breaker position. Insert handle as shown and pull down firmly to charge springs.
Pull down on lever firmly.The selector will be locked into the main circuit breaker position. Fit padlock into the circuit breaker closed in service position if required.
To store an additional charge on the springs, rotate the handle through 180 and insert as shown. Move handle up to reset and earth off position.
The handle can then be reversed once more and pulled down to store an additional charge. See indicator flag on top of unit.
To open the circuit breaker press the push circuit breaker off button. Fit padlock into the circuit breaker open position if required.
MERLIN GERIN
13
Check that the gas indicator is in the green healthy condition. Check the facia diagram for the service condition. Remove padlocks if fitted. With the circuit breaker in the open position, move the selector lever to earth switch position. Insert handle as shown and pull down firmly to charge springs.
Pull down on lever firmly to close to the earth on position. The selector will be locked in the earth position.
Fit padlock into the handle socket padlock bracket position if required. To open rotate the handle through 180 and insert and move handle up to reset and earth off position.
note: the circuit breaker off button will not operate.
Check that the gas indicator is in the green healthy condition. Check the facia diagram for the service condition. Remove padlocks if fitted.
Insert handle as shown and pull down firmly until the switch closes.
Fit padlock into the handle socket padlock bracket position if required. To open rotate the handle through 180 and reverse the procedure.
important note: the busbar earthing switch should only be operated when the busbars are de-energised.
14
MERLIN GERIN
Ensure that the main earth switch is earth on. This will open the key way. Push in and rotate test access key cover lever 90 clockwise and remove cover.
Insert test access key into the key way (as shown). Push lever in and rotate 90 anti-clockwise. The test access key can be padlocked in position if required.
Remove the earth star points as shown to provide access for cable testing. The test access key will be locked in position until the earth star point is firmly replaced. Reverse the procedure to return to service condition.
note : ensure cables are discharged before touching bushings.
MERLIN GERIN
15
16
MERLIN GERIN
accessing VTs
important note: before accessing VTs (during commissioning or replacing fuses) ensure that the main earth switch is padlocked in the earth on position. If the unit is a bus-section ensure that the bars are earthed or completely isolated. See page 12 for operation instructions.
Remove the lower circuit breaker front cover access panel for access to solid link and fused type connection.
isolation of VTs
Ensure that the main switch is in the Earth On position
Open VT cover on lower front of unit and remove racking handle from its storage position. Insert the racking handle into the top position of the slot. Turn in an anti-clockwise direction as far as it will go and remove handle. The VTs are now disconnected. The handle can now be replaced in the VT cover flap and this can be closed and the panel can be returned to service condition. To re-connect the VTs, the above procedure should be reversed remembering to ensure that the main switch is in the Earth ON position.
in service isolated
MERLIN GERIN
17
Pull back the VT insulating boot and loosen the VT connection using a 6mm allen key as shown.
Grasp the grey fuse tube and push up until the bottom is clear of the black insulation boot.
Remove the fuse completely from the unit to disconnect the VT.
18
MERLIN GERIN
commissioning
All equipment is subject to stringent quality and operational checks prior to despatch, however it is the owners responsibility to ensure that commissioning tests have been completed to IEC60694. The following is a resume of these tests.
physical checks
Remove all packaging and transit labels from the equipment. Check the data plate details against the specification. Check the operation of the switches/circuit breaker, test access and various interlocks.
functional checks
Check operation of auxiliary switch contacts and remote indication in accordance with the schematic diagram. Confirm the phase relationship of the neon indicator sockets. Check the pick up voltage of auxiliary coils if fitted. Closing coils should operate between 85% and 110% of the rated voltage. Opening coils should operate between 70% and 110% of the rated voltage.
note: all voltages should be applied instantaneously unless otherwise specified
B2 Y2 R2
R1
MERLIN GERIN
Y1
B1
19
test voltages
frequency (Hz) 50 50 50 50
duration (minutes) 1 (AC) 15 (DC) 1 (AC) 15 (DC) 1 (AC) 15 (DC) 1 (AC) 15 (DC)
test number 1 2 3 4 5 6
earthed terminals frame B, frame R, frame Y, frame R2, Y2, B2, frame R1, Y1, B1, frame
The following tests should also be carried out. If additional information and/or assistance is required please consult us. - primary injection - secondary injection - CT spill test - CT polarity test - relay secondary injection - relay timing and functionality tests
20
MERLIN GERIN
Routine maintenance will depend on the conditions to which the unit is subjected and to the relevant codes and practice. Periodic inspection of the
substation and equipment will be necessary to establish the conditions to which the units are subjected to.
mechanism housing
no attention no attention
ideal conditions
environmental conditions
Unit installed and commissioned in accordance with the manufacturers instructions Indoors, completely protected from the weather. Humidity below 40% and no dripping water. Minimal dust and air circulation. Ambient temperature between -5oC and +40oC. No contact with any chemical agents (eg. salt). No infestation of any animal life (eg. insects). No contact with any plant life (eg. mould). No earth movements. No damage to the unit of any kind.
operational conditions
No mal-operation of any kind. No abnormally high number of operations - refer to the graph. No abnormally high number of faults - refer to the graph. No over-voltage or over-current (above rating).
standard conditions
environmental conditions
Unit installed and commissioned in accordance with the manufacturers conditions. Humidity below 60%. Unit may be indoors or outdoors within enclosures, but must not be subjected to regular extremes of weather eg. heavy rain storms, dust storms, heavy snow and ice, flooding, temperature cycles greater than 40oC or less than -5oC, dense coastal fog or acid rain. No regular or thick covering of debris. No contact with any chemical agents (eg. salt). No infestation of animal or plant life. No earth movements. No damage to the unit of any kind.
operational conditions
No mal-operation of any kind. No abnormally high number of operations - refer to the graph. No abnormally high number of faults - refer to the graph. No over-voltage or over-current (above rating).
aggressive conditions
Any environmental or operational conditions which do not satisfy either of the above two descriptions must be deemed aggressive.
note: local legislation may dictate maintenance be carried out with greater frequency, irrespective of site conditions. Please contact your local Merlin Gerin representative for further details.
MERLIN GERIN
21
maintenance
general operation Check that the gas indicator is in the green zone. For circuit breaker panels check the electrical protection system. Check the operation of the unit and all mechanical interlocks.
housing Check all external fixings, labels and earth connections are present and tight. Check inside the MV cable box, busbar system LV cabinet and pilot cable box for heavy deposits of dust, ingress of water or contamination by animal or plant life. Clean the units thoroughly and touch up paint work as necessary.
leakage of SF6
If the gas pressure indicator needle is within the red zone or in the extremely unlikely event of a gas leak contact your local Merlin Gerin office immediately.
mechanism
In the unlikely event of a mechanism failure, please contact Schneider Services.
22
MERLIN GERIN
Endurance Characteristics
NUMBER OF OPERATIONS
MERLIN GERIN
23
Expertise
Schneider Electric
Merlin Gerin Medium Voltage, 123 Jack Lane, Leeds LS10 1BS Tel: 0113 290 3500 Fax: 0113 290 3710 Internet address: http://www.schneider.co.uk