Irc Sp 91 2010-印度隧道规范
Irc Sp 91 2010-印度隧道规范
Irc Sp 91 2010-印度隧道规范
GUIDELINES
FOR
ROAD TUNNELS
Published by :
CONTENTS
Page No.
s ection
1. Introduction 1
3. Geo-Technical Investigations 19
4. Structural Design 27
Annex - A Terminology 98
Annex - B Environment Management Plan for Road Tunnels 102
IRC:SP:91-2010
Members
EX-Officio Members
Corresponding Members
ii
p
IRC:SP:91-201 O
1 INTRODUCTION
The Road Tunnels Committee (H-7) of the IRC was constituted in August 2006. The
Personnel of the H-7 Committee are as under:
This is the first time that such guidelines are being prepared for Road Tunnels in
the country by the IRC. Therefore, the Committee in its first meeting held on 18th
Oct, 2006 discussed the scope as suggested by IRC and decided upon various
topics to be taken up by the members. The Committee had several meetings and
prepared a draft for consideration of Highway Specification and Standards (HSS)
Committee. The draft was placed before the Highway Specification and Standards
(HSS) Committee on 1st May, 2010, wherein some comments were offered for
incorporation.
1
IRC:SP:91-2010
The revised draft incorporating the comments of the Highway Specification and Standards
(HSS) Committee was presented before the Council in its 191 st meeting held on 22nd May,
201 Oat Munnar (Kerala). The document after discussion was approved by the Council for
printing as a publication of IRC. The valuable contributions of the members of the Road
Tunnels Committee (H-7) and suggestions of members of Highway Specification and
Standards (HSS) Committee and Council members are hereby acknowledged.
1.1 Tunnels are introduced into the road system in mountainous terrain to negotiate
mountain ranges and reduce the road length. The tunnels may also be introduced to avoid
passage through snow bound areas or pass below sea, creeks and rivers or even to
cross thickly populated urban areas etc. A road tunnel may also be considered in open
country on environmental grounds to protect areas of ecological interest. The fundamental
objective of road tunnel is to ensure safe transit of the road traffic in difficult terrain.
1.2 The decision to introduce a tunnel in a road system largely depends upon
the cost benefit ratio, traffic volume, category of road etc. Cost of Tunnelling is much
more than that of open excavation. The tu nnel cost is mainly dependent on topography,
geology and access. For expressways and high density corridors passing through
mountain ranges the option of tunnel is generally more economical considering life-
cycle cost and overall saving for the traffic using the shorter route.
1.3 The planning, design and construction of a road tunnel is a complex inter-
disciplinary task and requires expertise in different fields. The planning and design involves
site investigation, physical planning, conceptual design and detailed design with due
consideration for construction methods. All these aspects, construction methods, lighting
and ventilation, safety and operation and maintenance are dealt with in further sections.
2
--
IRC:SP:91-2010
• Over ground Tunnels: Ducts constructed over the ground for protecting
roads in landslide/avalanche areas.
2
AREA = 0.905 D
PERIMETER = 3.58 D
0- Section
1
----____--.J J
• Circular Section: Circular sections are structurally the best and are
commonly used for underwater tunnels, tunnels through soft ground
and for tunnels excavated with tunnel boring machines.
3
IRC:SP:91-2010
2
AREA= 0.7860
PERIMETER = 3.14 D
+
Circular Section
2
AREA= 0.8293 o
PERIMETER= 3.267 D
;/
/
/
_/
4
IRC:SP:91-2010
• Egg Shaped Sections: Egg shaped and egglipse sections are best
suited for sewerage tunnels because of their hydraulic properties. They
are also used for road tunnels with high vertical pressure.
T AREA= 0.864 D2
. . . . - - - - -----:,,........--._:
PERJMETER • 3.317 0
1.
1.170
---+-
- 0' -- - -
(NOTE: For classification of tunnels on length basis for Expressways refer para 6.2 of
"Guidelines for Expressways VOL II: DESIGN")
5
IRC:SP:91-2010
6
IRC:SP:91-2010
The starting point of planning of road tunnels is the Traffic Study which identifies the
volume and nature of traffic likely to be generated over the design life of the connecting
road network. The study also identifies the complexion of traffic i.e. number and types
of vehicles likely to use the tunnel and the design speed of traffic. The number of traffic
lanes required to be provided shall be decided, taking into account the outcome of the
traffic study. The need for footpaths/walkways and their widths shall also be decided
at this stage, particularly for urban tunnels. The minimum vertical clearance shall
be decided taking into consideration the local regulations and the height of loaded
vehicles likely to pass through the tunnel. Based on the traffic studies, preliminary
design of ventilation system and tunnel lighting shall be carried out. The preliminary
design of the side drains, which are generally located under the walkways meant for
pedestrians/maintenance personnel, shall also be carried out taking into consideration
the quantity of rainwater/seepage water likely to pass through the drains.
The study of topo-sheets and maps of the area shall be carried out. Possible alternative
accesses to the tunnels shall be conceived, taking into account natural topography of
the area. In populated area, many existing alternative accesses would be available.
From various alternative options the access to be considered shall be one which
causes the least disturbance to existing structures, infrastructure, etc. The alternative
alignments shall be marked on the topo-sheets and maps/drawings. From the contours
longitudinal sections along the alignment shall be prepared and grades and levels of
tunnels and probable locations of tunnel portals plotted thereon.
The topo-sheets and available maps of the area may not be up-to-date and may not
exactly indicate the present position in respect of structures, roads , service lines, etc.
For verification of the actual situation at the site, alternative conceptual layouts shall
be roughly set out at the site and reconnaissance survey of the area shall be carried
out. Salient features of the area and local constraints such as habitation, structures,
power transmission lines, pipelines, local roads etc. shall be noted and marked on
the topo-sheets/drawings. The feasibility of creating access roads for construction
7
IRC:SP:91-2010
work, if not already existing, shall also be examined. Necessary adjustments and
rea lignments in the layout of the conceptual alternatives shall then be made so as to
avoid or minimize disturbance to existing structures, monuments etc.
2.8.1 The geometry of the tunnel is a very important aspect of tunnel design. The
main objective of road tunnel design is to ensure safe transit of traffic for which the
facility is designed, at least cost. The safety of traffic depends upon the geometrics of
tunnel i.e. its cross section, gradients and curvature. Generally a tunnel shall maintain
the same geometrical standards as on the adjoining carriageways in the open air
outside the tunnel. Where geometry is confined, such restriction shall commence at
least 150 m from the entrance of the tunnel along with speed restrictions.
8
p
IRC:SP:91-2010
The cross section of a tunnel mainly depends upon projected traffic volume, provision
of ventilation system (if any), geology of area and provision for pedestrian traffic,
particularly in urban areas. Considering the geotechnical conditions likely to be met
with, the traffic volume and functional requirements as given in Table 1 below, the most
economical section shall be selected. The finished width of a tunnel depends upon the
number of traffic lanes required considering future projected traffic and the number
and width of the footpaths I walkways, kerbs, crash barriers and drains required to be
provided.
The lane width of 3.5 m (3.75 m for Expressways) shall be kept for highway tunnels.
However, for urban areas the lane width may be reduced to 3.2 m and even to
3.0 m for low volume traffic roads. As far as possible the width of traffic lanes and
off-carriageways in road tunnels shall be same as that on the adjoining carriageways
in the open air. If the width of traffic lanes in tunnels is restricted as compared to
the adjoining carriageways in the open air, such restriction shall commence at least
150 m from the entrance of the tunnel along with speed restrictions.
The fi nished height of a tunnel would depend upon the minimum vertical clearance,
which shall not be less than 5.5 m. However for tunnel on road with low traffic volume
it may be reduced as per local regulations and the height of loaded vehicles likely to
pass through the tunnel. Such minimum vertical clearance shall be available over
the full width of the carriageway as mentioned in para 2.8.2. 1 above, irrespective
of the shape of tunnel. Space required above the minimum vertical clearance line
for accommodating tunnel ventilation and lighting fixtures proposed, if any, shall be
provided accordingly, duly considering the shape of tunnel proposed which in turn
depends upon strata met with.
Where tunnel cross sections of especially small dimensions are adopted due to various
constraints, dimensional templates shall be erected outside the portals at the point
of entry so that vehicles larger than the permitted size do not enter and get stuck.
Such templates shall be suitably strengthened to resist impact from over-dimensioned
vehicles without getting damaged, but at the same time not unduly stiff so as to damage
the vehicles excessively.
In case of 'D' shaped tunnels, the geometry of the arch could be semi-circular, segmental
or multi-radius. The segmental or multi-radius arch is flatter and reduces the quantity
9
IRC:SP:91-2010
For tunnels on low volume traffic roads , bi-directional two lane cross-section shall be
adopted . For roads with projected traffic volume exceeding 10,000 vehicles/day/lane,
uni-directional twin tube tunnels each of two-lane, three-lane or at the most four-lane
cross section shall be adopted depending upon volume of projected traffic. In case of
twin tube tunnels the clear distance between the tubes shall be between 0.5 to 2 times
width of tunnel depending on the type of strata, the stresses generated and their effect
on stability.
Taking into account all these factors along with functional requirements as given in
Table 1 below and geotechnical conditions likely to be met with, necessary geometry
of finished section of the tunnels shall be determined.
Short Tunnel
NA --- *** --- --- --- --- --- *** --- --- ---
Up to 500 m
Medium Tunnel
500m to 1500 m
NA Yes Yes Yes Yes --- Yes Yes Yes Yes Yes *
Long Tunnel
NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes *
Above 1500 m
*** Lighting shall be provided for Urban Tunnels and preferably for tunnels longer
than 100 m in Non-urban area.
NA - Not Applicable
• CP - Cross Passage.
10
-
IRC:SP:91-2010
• VN - Ventilation.
• LG - Lighting.
• TE - Telephone at spacing of about 200 m
• FS - Fire Safety - Fire extinguisher at spacing of about 50m
• EG Egress (Such egress shall have minimum dimensions of
2 m x 2.5 m height with adequate ventilation & lighting, and isolation
from main tunnel through fire proof doors)
Note 1: In case of long tunnels, provision of refuge to park at least 6 vehicles along the length of tunnel with one-
lane width, proper informatory signs, transitions and line of sight shall be planned at about 750 m intervals
beyond the leftmost lane.
Note 2: In case of twin tube tunnels, each tunnel tube with uni-directional traffic, cross passages connecting the two
tubes shall be planned at a spacing of about 300 m. In the event of an incidenVaccident in one of the tubes,
the other tube shall be used as an escape and rescue route by diverting the traffic through cross passages to
the extreme right lane of the other tube, so as to dear the tunnel in case of emergencies. The cross passages
shall be at an angle of about 300 to the alignment as shown in sketch below and shall have provision for
one traffic lane, edge strips, crash barriers/kerbs and walkways on either side. In normal conditions cross
passages shall be barricaded.
Note 3: For installation of facilities in expressway tunnels refer Table 6.01 of "Guidelines for Expressways Volume
-ll:DESIGN"
........
................
................
........................
-----------TUNNllLCJINDIU.INB ------------ -- --------~
11
IRC:SP:91-2010
Typical sketches indicating tunnel cross sections for bi-directional and uni-directional
traffic conditions are given below.
_______ T_____ _
CLEARANCE LINE
Ml UM CLEARANCE 5500
CABLE BOX- -
FIRE FIGHTING -i---o
WATERLINE I
FOOTPATH
RAILING FOOTPATH
I CRASH BARRIER RAILING
TOP OF PAVEMENT CRASH BARRIER
DRAIN DRAIN~ ~N PIPE
J
I=
MINIMUM INVERT EXCAVATION IN INVERT
H GIEIDlo-- A •1...1• A -------! DIEI GH
12
IRC:SP:91-2010
R1
MINIMUM I
CLEARANCE 5e;oo
CABLE BOX4--+---" '
FIRE FlGHTING-+---t-- J..I
WATER LINE
WM..t<WAY ON..Y FOR
'\ MAINTENANCE STAFF
'\ RAILING
"'\ ,_
'\
CRASH BARRIER
TOf> OF PAVEMENT
13
IRC:SP:91-2010
CABLE BOX
FIRE FIGHTING
WATER LINE
CLEARANCE 5600 FOOT PA
RAJU NG L
CRASH BARRIER = K
DRAINPIPE DRAIN
=c
bbd._L~~~~~~""""',~r--ir-=
AAVEMEHT
==~~~~~-L.bkJ -B
' INIMUM INVERT EXCAVATION IN INVER1'
HOIEIOJo- A A A
The gradient along the tunnel length shall be very gentle. Steep gradient affects traffic
capacity, resulting in additional emission by vehicles and makes ventilation more
difficult. The tunnel gradients are generally limited to 4-6 percent in short tunnels
and to around 3 percent if length exceeds 500 m. Where steeper gradients become
necessary, the design of the ventilation system shall be done taking into consideration
the effect of steep gradients and possible incidences of fire. Generally a high point
somewhere in the tunnel shall be provided for efficient drainage of seepage water.
The straight alignment is generally preferred. However the straight stretch shall not
be more than 1500 m in case of long tunnels to avoid the effect of monotony and
induction of an unconscious increase in speed. For the same reason last few meters
of the tunnel shall have gentle curve. The curves if provided shall be gentle and meet
the minimum radius requi rements for the design speed of the tunnel. Tunnel alignment
at the ends and open/approach cuts shall merge smoothly with adjoining road in the
open air. In case of twin tube tunnel, crossing of central median shall be planned at
suitable locations at approaches of both tunnels so as to allow emergency services
gain immediate access to either tube and also to send back diverted traffic to proper
traffic lanes.
14
IRC:SP:91-2010
For long tunnels the distance traversed shall be suitably marked so that motorists are
aware of distance covered and remaining distance. This is especially useful in times
of emergencies to give people a clear idea of distances involved in both the directions
for fast egress.
Based on the geometry of the finished tunnel section and the anticipated geotechnical
conditions along the alignment, a preliminary rough assessment of the need, type and
quantum of tunnel supporting systems shall be made. The supporting system shall be
in the form of rock-bolts, shotcrete, steel ribs, forepoling , pipe roofing and concrete
lining, separately or in combination . This preliminary assessment shall be made on
the basis of past experience and supporting systems provided in other tunnels under
similar conditions by engaging services of geotechnical experts. A combination of rock
bolts and steel fibre reinforced shotcrete [SFRS] with or without lattice girder is the
present trend based on cost and time considerations and flexibility in construction.
For rough assessment of cost of different alternatives, data regarding cost of various
construction materials and specialized construction manpower shall be collected.
Data in respect of construction costs in general and costs of similar projects in the
area shall also be collected.
Taking into account data on construction costs, quantum of tunnel excavation and
supporting system and appurtenant works etc. preliminary estimate of the cost shall
be made.
A detailed survey of the tunnel alignment for the selected alternative shall then be
carried out. Drawings showing the longitudinal sections, cross-sections and contour
plans along the tunnel alignment shall be prepared.
15
IRC:SP:91-2010
For designers and constructors of tunnel, the ground through which the tunnel passes
is the construction medium. As described in details, in a subsequent section entitled
"Geotechnical Investigations", realistic geotechnical and geophysical assessment of
the ground through which the tunnel would pass should be made. A detailed geological
mapping shall also be carried out based on the investigations.
Geotechnical information and data should be used to assess the loads that are
likely to be caused on the periphery of the tunnel. Section of the tunnel shall then
be analyzed by empirical and/or numerical methods and need, type and quantum of
necessary supports be determined, as described in detail, in a subsequent section
entitled "Structural Designs".
Taking into account the length, shape, size, tunnel environs and the complexion of the
likely traffic for which the tunnel has been designed, detailed design of the Ventilation
and the Lighting System shall be carried out by experts, as described in detail, in a
subsequent section entitled "Ventilation and Lighting".
2.17 .1 In order to trap rainwater from hill slopes and prevent it from flowing into the
approach cuts and the tunnel, suitable catch water drains shall be provided above the
top of sides of the open/approach cuts and above excavated portals.
2.17 .3 Inside the tunnel, suitable side drains shall be provided behind the kerbs/
crash barriers. Suitable drain pipes going through the kerbs/crash barriers shall be
provided to lead seepage and wash water to the drains. The drains shall be located
below the walkways meant for the pedestrians and maintenance personnel, as
shown in the sketches below. The carriageway shall have suitable camber to facilitate
drainage into the side drains. In case of bi-directional tunnel, the camber shall be
from the centre outwards and in case of uni-directional tunnel from high speed lane
towards low speed lane. The vertical profile shall facilitate self draining of tunnel by
16
IRC:SP:91-2010
providing high point somewhere in the tunnel. However, for long tunnels this may not
be possible and detailed drainage system shall be designed by providing sumps and
combination of self draining and pumping arrangements.
2.17.4 The black topped road surface inside tunnel, generally constructed on rocky
subgrade, gets damaged due to seepage water and creates sever problem for surface
drainage. Hence the pavement inside the tunnel and in approach cuts shall be of high
performance pavement concrete.
CLEAR LIN
DRAIN COVER I
W~AY SLAB
HAND RAILING 1000 HIGH
CLEAR LINE
DRAIN COVER I
W~AYSLAB
l
KERB ~NIMUM
325 DRAIN
WAJJ... RAIN Pl
DRAIN
PAVEMENT
B
~-------'I I F I
Details of Crass Barrier/Kerb with Poothpath Walkway
Provision for installation of tunnel furnishings such as sign boards, fire fighting
arrangement, cable trays for telephone and power lines etc. shall be made in
consultation with relevant local authorities.
2.19 Aesthetics
The tunnel portals and other components shall be suitably designed with particular care
for good aesthetics, pleasing geometry, shapes and proportions, patterns, textures,
colours, etc. For important tunnels, particularly in urban areas, specially designed
internal paneling may be thought of for all internal surfaces, which would be amenable
for easy cleaning, improved acoustics and sound absorption as well as enhanced fi re
resistance. Muck dumping areas shall be suitably dressed to proper stable slopes,
shapes and turfed/landscaped to improve the environment and aesthetics.
17
IRC:SP:91-2010
All necessary statutory clearances and approvals shall be obtained before taking up
construction . These shall include at minimum;
a) Environmental and Forest (if any) clearances,
b) Permission for blasting in the area,
c) License for storage and handling of explosives,
d) Acquisition of right of way,
e) Approvals from Fire authority in case of urban tunnels
f) Clearance from Pollution Control Board
Based on the data on cost of required construction materials, ownership and operation
cost of plant and equipment, cost of manpower, construction technology required to
be used and time required for completion of Tunnelling operations, detailed analysis of
cost of all the items of work should be prepared and total cost shall be analyzed.
Upon completion of all these activities and steps, the project proposal would be ready
for further processing, if any and implementation
18
F
IRC:SP:91-2010
3 GEO-TECHNICAL INVESTIGATIONS
3.1 Site specific geological conditions along a tunnel alignment play a prominent
role in influencing major decisions regarding planning, designing and construction e.g.
• Alignment and portal locations
• Shape of the tunnel
• Tunnel supporting systems
• Minimum distance to be kept between twd tunnels
• Methodology of construction of tunnel including risk assessment
• Construction method and treatment of open cuUslopes
The starting point of all these designs is knowledge in respect of the behavior of
the Tunnelling media-likely to be met with during Tunnelling . It is therefore very
important that appropriate geo-technical investigations are conducted early in the
planning process. The objective of geological investigations is to understand the
history, topography, geology, environmental setting and the engineering properties
of the underlying strata. The geotechnical information regarding nature of ground,
groundwater conditions, engineering and other scientific parameters is essential for
anticipating ground behaviour which is useful to select tunnel shape, size, excavation
method & the support system, and other essential parameters for a cos t and time
effective tunnel design.
For designers and constructors of tunnels, the ground through which the tunnels
pass is the construction medium. It is therefore necessary to have fairly realistic
geotechnical assessment of the construction media and its environment. The most
important consideration is the condition of the ground mass just above crown of the
tunnel (generally for a height of 2 times width of tunnel) and at the level of the tunnel
19
IRC :SP:91-2010
Besides the above, additional data shall be collected during actual construction as
given in para 3.4.
3.3. 1 Collection of available data regarding regional and local geology of the
area
Data regarding General Geology of the project area shall be collected from
a) Site reconnaissance survey to collect information on geological
features .
b) Geological Survey of India and similar organizations of the State
Government,
c) Nearby Engineering Institutions and Engineering Projects' in the
vicinity.
The data collected shall include general idea of in-situ stresses in the ground formations
of the region , which is required for assessment of rock mass quality.
After conceptual alternative alignments of the tunnel have been set out on the ground,
geological mapping of the area should be carried out to observe and to make note
of geological features such as type of strata, existence of outcrops, dip and strike
of strata, discontinuities, folds , faults, ground water regime etc. Taking into account
general geology of the area and the data collected during the study of surface geology,
a preliminary geological map shall be prepared and preliminary assessment of geo-
technical conditions that are likely to be met with, along the alternatives shall be
made. These studies along with other preliminary studies would help in arriving at the
technical feasibility of each alternative, rough cost of each alternative and selection of
preferred alignment for further detailed studies.
20
IRC:SP:91-2010
For realistic gee-technical assessment of the ground , exploratory bores shall be drilled
to a depth of about 5 m below the expected level of invert of the tunnel. The cores shall
be collected from the relevant strata as defined above in para 3.2 above. Boring shall
be carried out using at least NX size coring bits and using double-tube core barrel
in normal situations and triple-tube core barrels in weak rocks, fault zones, shear
zones, crush zones, folded rocks etc. Use of triple tube core barrel helps preventing
mechanical breakage of rock cores due to rough handling .
During boring operations, following observations shall be made and tests shall be
carried out:
1) Rate of penetration in each 1.5 m drill run :
The rate of penetration gives a broad idea about toughness of the
strata.
2) Locations, if any, where rate of penetration changes suddenly:
Sudden change in the rate of penetration indicates change in the type
of strata. If the drill string suddenly drops, it will indicate presence of
hollow joint/cavity or joint with very soft matrix.
3) Quantum of drilling water:
Flow of drilling water going into the drill hole and water flushing out of a
drill hole shall be monitored continuously. Sudden loss of drilling water
indicates presence of open dry joints or fractured zone. Increase in the
rate of drilling water flushing out of a drill hole indicates intersection of
groundwater table. Sudden large increase in the rate of drilling water
flushing out of a drill hole would indicate artesian conditions.
4) Colour of drill water/sludge:
Observing carefully the colour of drill water/sludge coming out from the
borehole is important as it gives idea about the type of strata in which
bore is passing.
21
IRC:SP:91-2010
5) Permeability:
Permeability of rock strata is the amount of flow of water through rock
mass when it is saturated. Generally one permeability test shall be
carried out in each 6 m tier. However, one test shall be carried out in
each 3 m length of the borehole in the relevant strata, using Double
packers and using falling and constant head methods
The drilling data shall be recorded in the proforma given in the
Annex-C.
As soon as core is removed from the core barrel all pieces of core must be immediately
numbered serially, their depths and serial numbers painted on them and their lower ends
marked so as to ensure that all pieces are kept in correct order exactly representing
the depth from which they have been obtained. Lengths of all pieces of core shall be
measured and recorded in the daily drill report. Cores shall be immediately placed in
core boxes made according to standard specification, and all the necessary information
such as the name of the project, location of drill hole, drill meterage, drill hole number,
etc. shall be painted on the box. The cores of some soft and weak rocks disintegrate
on exposure to atmosphere. Cores of such rocks when raised to the surface should
be covered with a thin layer of wax by immediately immersing it in melted wax for
preventing its exposure to atmosphere. Such waxed core remains intact indefinitely
and the rocks in their true form as they occur in-situ are seen in the core and not in the
misleading disintegrated form . The core boxes shall be preserved till three years after
completion of the tunnel and after it is put to use.
22
p
IRC:SP:91-2010
Following tests shall be carried out in a competent laboratory. At least five samples of
each lithological category should be tested. If the lithology indicates that the relevant
ground mass is only of one category, at least a total of ten samples from different
levels shall be tested.
• Unconfined compressive strength and hardness
• Natural and dry density and specific gravity
• Rate of water absorption and porosity
Young's modulus of elasticity
Poisson's ratio
• Tri-axial strength (for structurally disturbed rock formation)
• Petrography - Hand and microscopic petrography
• Tensile strength - (in completely geologically disturbed area)
Sometimes, when a tunnel passes below a high mountain, boring of exploratory holes
to cover the relevant strata becomes impracticable due to the excessive depth of
boreholes. In such a situation as also to gain information in respect of the hidden
geological features along the alignment, geo-technical assessment is carried out by
excavation of tunnels of small cross-section called exploratory drifts. These drifts give
an idea of the nature of strata likely to be met with.
23
IRC:SP:91-2010
Such information collected from drifts, which are at shallow depths from the ground
surface, shall be used only by a Tunnelling expert in association with an experienced
geologist since the behavior of rock masses under small cover in drifts is significantly
different than the behavior of the similar rock masses at higher depths actually
encountered during tunnelling.
3.3.4.3 Seismic methods are the most commonly used methods of geophysical
surveys for engineering investigations. These methods are mainly based on application
of analogies of optical laws to seismic wave propagation. Seismic refraction and
reflection provide engineers and geologists with the most basic geological data
via simple procedures with common equipment. Seismic methods of subsurface
evaluation involve the generation of pulses of energy, usually at the ground surface,
consisting of compression, shear and surface waves that propagate through the
ground and are either reflected back toward the surface, or are refracted at and travel
along lithological boundaries. The wave energy which returns to the surface is picked
up by geophones placed at the ground surface. The geophones convert the wave
24
IRC:SP:91-2010
The usual practice in the field is to apply a direct current or alternating current of low
frequency through two electrodes implanted in the ground and to measure the difference
of potential between two additional electrodes that do not carry current, also implanted
in the ground, a few meters away. The difference in the electrical potential i.e. resistivity
of the ground between the two types of electrodes as above, is measured.
Data collected during planning stage shall be got corroborated by following additional
investigations during actual construction. This will help in revalidating the initial design
or for making any course corrections required .
25
IRC:SP:91-2010
Horizontal bore holes of suitable length shall be drilled at regular intervals at tunnel
faces to gather geological information about strata ahead of the face. This information
shall be used to plan further Tunnelling operations and changes in design, if required .
Adequate advance precautions shall be taken in case large ingress of water is
encountered from the probe hole.
3.4.2 Seismic method as described in para 3.3.4.3 above can also be used for
advance probing by detonating very small explosive charges on the tunnel face and
mapping the reflected/refracted waves to get some idea of the strata ahead.
Study of cores and data collected from surface and subsurface observations shall be
used to evaluate parameters required for the assessment of RMR and Q described in
details in the section titled 'Structural Design'. These indices are useful for assessing
the characteristics of various lithological units. These two parameters are also used
for assessing method of excavation, support requirements , anticipating tunnel
deformations and construction problems.
Lithological Section i.e. longitudinal section along the alignment of the tunnel and its
approach/open cuts s~owing location of the boreholes shall be prepared, incorporating
therein all the relevant data collected during the geo-technical investigations. The
lithological section would give an idea about the spread of different formations
26
IRC:SP:91-2010
along the tunnel alignment, together with expected Rock Mass Rating/Classification
(RMR & Q) to reasonable accuracy. The geophysical information shall be used to
supplement wherever necessary, to prepare a geological L - section of a tunnel.
4 STRUCTURAL DESIGN
4.1 Preamble
The basis or the starting point of all these designs is the assessment of applicable
loads. For arriving at the quantum of these loads, it is necessary to have sufficient
knowledge in respect of the structural properties of the ground likely to be met with
during tunnelling. Such knowledge is obtained by carrying out detailed geological
and geotechnical studies, as set out in the section dealing with 'Geo-technical
Investigations'.
The rock mass through which a tunnel is driven could vary from a strong massive
formation to fissured , jointed and weak formation . Depending on the in-situ stresses
and other characteristics of the formations, the periphery of an underground opening
starts showing signs of deformation. In massive strong formations with low in-situ
stresses, the deformations could be insignificant (less than 1 percent of the excavation
size) needing no supports as against the fissured , jointed and weak formations needing
heavy support.
The tunnel supporting systems are divided into two major categories viz. Immediate
supports and Ultimate supports. The rock mass through which a tunnel is driven
could vary from a strong massive formation to fissured , jointed and weak formation.
Immediate support pressures are small in strong rocks, but high in weak rocks.
The ultimate support pressure is 1.7 times the immediate pressure irrespective of
the rock type. Rock mass rendered with proper immediate flexible supports allows
development of just sufficient deformation and self-adjustment without loosening
the rock mass and results in generation of minimum ultimate pressures. In massive
strong formations with low in-situ stresses, the deformations could be insignificant
needing no supports as against the fissured , jointed and weak formations needing
heavy supports. All methods of tunnel excavation and support systems presently
27
IRC:SP:91-2010
used, allow some degree of deformation in the surrounding rock mass. Present-
day approach is to reinforce the existing rock mass to the extent possible rather
than providing it with stiff ribs with lagging with packing behind. When advanced
construction techniques such as NATM are used, the design scheme and the
construction scheme go closely hand in hand and both have to be developed in a
holistic manner.
This section covers the structural design of immediate as well as ultimate tunnel
supports. As per current practice, immediate supports comprise of rock bolts, plain and
reinforced shotcrete with or without lattice girders embedded in it and ultimate supports
comprise of plain & reinforced shotcrete with or without lattice girders embedded in it.
Concrete lining with or without steel ribs embedded therein are generally used in weak
rocks, where high pressures are developed
4.2.2 The design shall be based on the most adverse combination of probable
load conditions, but shall include only those loads which have reasonable probability
of simultaneous occurrence. The methodology of construction is an important factor
in structural design, particularly in case of soft strata and soils. The loading conditions
vary from construction stage to operation stage & maintenance stage and the design
shall be checked for loading conditions during these stages.
4.2.3 The paras given below in this section pertain to tunnels in rock. The structural
design of tunnels in soft strata and soils is not covered in this section.
28
IRC:SP:91-2010
4.4.2 Method based on Rock Mass Rating [RMR] as set out in Indian Standard
IS 13365 [Part 1]: 1992 and support design base thereon.
29
IRC:SP:91-2010
In this method following gee-mechanical properties are assessed and ratings in the
form of points are allotted as indicated in detail in Appendix-I & II :
I) Strength of intact rock material [MPa]:
This is the same as the Uni-axial compressive strength.
II) Rock Quality Designation [RQD]:
Rock Quality Designation indicates aggregate percentage of intact
pieces of core that are more than 100 mm in length when compared to
the total length of cores.
Ill) Spacing of Discontinuities [m]:
Spacing of discontinuities means spacing between joints.
IV) Condition of Joints:
Condition of joints indicates degree of roughness of joints.
V) Ground Water Condition:
Assessment of ground water condition is made on the basis of quantum
and pressure of ground water in the joints.
VI) Rating adjustment for joint orientations:
Assessment of orientation of joints vis-a-vis direction of tunnel
excavation is made taking into consideration as to how much favourable
is the orientation for tunnelling through.
Rock Mass Rating (RMR) Value is the sum of the ratings as per 'I' to 'V' above. Adjusted
RMR is total of 'I' to 'V' above plus adjustment as per 'VI' above.
Methodology for arriving at the RMR Values is set out in Appendix-II. An example for
determination of RMR is given in Appendix-IV.
4.4.3 Method based on rock mass quality [Q] as set out in Indian Standard
IS 13365 [Part 2]: 1998 and support design based thereon.
In this method following gee-mechanical properties are assessed and rating in the
form of points is allotted as indicated in details in Appendix-Ill:
a) Rock Quality Designation [RQD] :
As defined in 4.4.2 (II)
b) Joint Set Number [Jn] :
'Jn' indicates the number of joint sets
c) Joint Roughness Number [Jr] :
30
IRC:SP:91-2010
Methodology for arriving at the rock mass quality [Q] is set out in Appendix-Ill. An
example for determination of rock mass quality [Q) is given in Appendix-IV.
Various empirical rules have been developed over the years for characterization of the
rock mass. Terzaghi was the first to formulate a rational empirical method classification
for evaluation of rock loads which are used for design of steel supports. Rock mass
assessed by Method based on Rock Mass Rating [RMR] and by Method based
31
IRC:SP:91-2010
on tunnel quality index 'Q' are considered as more realistic as these methods take
into account various variable parameters related to the conditions of the strata. 'Q'
system is more appropriate for tunnels in rock. Both these methods take into account
very similar geo-mechanical properties of rock mass, self supporting capacity of the
periphery of the opening and the reinforcing effect caused by the supporting system.
Since these methods are empirical, they need to be used very carefully and correlated
with past experience.
A) Terzaghi's empirical method for assessment of rock load for design of steel ribs:
Terzaghi's rational empirical method classification for evaluating rock load was
subsequently modified by Deere et al. [1970] and Rose [1982]. Terzaghi's classification
and evaluation of rock loads with subsequent modifications, which is currently in use,
is given in the table below:
Values for type 4, 5 & 6 reduced by Rose by about 50 percent from Tergazhi's values
because water table has little effect on load [Terzaghi 1946, Brekke 1968]
Rock load 'Hp' in feet of rock on roof of support in tunnel with width 'B' [ft] and height
'H' [ft] at depth more than 1.5 [B+H] ; NA- Not Applicable.
Terzaghi's values of rock loads are found to be more conservative today, due to
improvements in Tunnelling technology.
32
IRC:SP:91-2010
33
I RC:SP:91-2010
C) Estimated Support Categories based on Rock Mass Quality 'Q' [After Grimstad
and Barton, 1993 reproduced from Palmstorm and Brooch, 2006]
Barton et al [197 4] have suggested the following Excavation Support Ratio [ESR] for
use in the Estimation of Support [Reinforcement] Categories based on Rock Mass
Quality Q
Estimated Support [Reinforcement] Categories based on Rock Mass Quality 'Q' are
indicated in the following nomogram:
ROCK CLASSES
- ----
G F
-- E 0 c B A
E•oopllonaly EX1Ttmtly Very Very Ext Exe
Poor Fair Good
poor poor poor good good good
100 20
so 11 iD
..
g>
~
7 ':J'
5
E 20 5 3
£ ~
m
3 (/'J
lJ
s 24
"
Cl)
' c;,,ii •
2 'i ,. .~~~' •• 1s
REINFORCEMENT CATEGORIES:
1) Uneupported 6) Fibt• ,..,.,lotcect ~.end bolling. g . 12 cm
2) Spot bollng 7) Fibre rHlbced tho4creta and bolling, 12. 15 cm
3) Systemahc bolling 8) Ftbrtrfflbcect~.> 15cm.
4) Systomalc: bclt.ng, (and unreonlotc«I shotcrete. 4 • 10 cm) rlMl'lb-ced 111>1 ol lhotcrete and boll1ng
S) Fibre rtl"lbrced 1hotcfote and bolllng. 5 • g cm II) Cut ooncrete lining
34
IRC:SP:91-2010
Id An ex,mple of Estimated Support requirements based on the above nomogram is
attached as Appendix-V.
>r An abstract of the recent updating of the Q-charts has been quoted below for the
s bene t of the users, especially considering its utility to replace the conventional cast
concrete tunnel lining even in very poor to exceptionally poor rock masses (Q=1-
0.001 ). The charts are backed by deformation measurements and numerical analysis
bas1 J on static analysis of the support using STAAD software.
A second updating of the Q system for rock mass classification [1st updating by Grimstad
and Barton, 1993] is in progress. In this updating, emphasis has been placed on the
wid• pplication of fibre reinforced sprayed concrete [Sfr], even in the lowest rock mass
quahues and the recent changes in rock support practice and material properties. In
ex ~mely poor rock, where some deformations may be expected, the toughness and the
energy absorption of the sprayed concrete has been taken into considered in the improved
a -support chart. A substantial amount of data from recent projects has been gathered
am.J analyzed. Analytical research has been carried out with respect to the thickness,
spacing and reinforcement of reinforced ribs of sprayed concrete [RRS] as a function
of the load from the rock and the rock mass quality. The basis of the RRS design is the
calculated deformation and bending moment. The analytical calculations are compared
with numerical analysis and deformation measurements in the tunnel. Modem practice
ROCK Cl ASS ES
G F E 0 C B A
....
;~ f
I '
10 100 1000
Rodl•-...llilyQ• &Ql2
Je
ll .l: s JI!
h SRF
RIJNR)RCDIENJ"CATrnORIE'i S)Filn.mfcrood,._rd...,.S.9cm.Slt+8
I) ~ 6)Filnnmtor-l"-n1~~12cm,Sl-+8
i)~~ · 7)Fibre~*-nlbab& 12-ISca,St-tB
l)~ ..... 8 l)n.. .......... . _ > U .. '
4) SJ--.:~ .,.,(""*1 nliacC*-"'lllll ..... Sl-tllJIS+8
(rd.......Ccrood"'-.4-IOan). D(+~ 9)0.--..CCA.
E)lml,Y~nrtln~ilda\'llt•2'-~~P.--.
~ -RR.Swilh61wm r'M•ob.tit•111•~ ............. -...,_(oc>..-.
j--W I 7111 F.m!bm!Clm:lplildslD~lll'lb ldl'-1.tec{tlc ba&(s.ICC b~
35
IRC:SP:91-2010
indicates that RRS may replace traditional cast concrete lining in extremely poor rock.
RRS in shape and support capacity is similar to lattice girders, but are more flexible in
application because RRS is not prefabricated. An improved Q-support chart that gives
derails of RRS in very poor to exceptionally poor rock mass is given below:
Barton et al [1980] have suggested the following formula for estimation of the length
of rock bolts:
0.15 B
L=2+
ESR
where,
Barton et al [1980] have suggested the following formula for estimation of the Maximum
Unsupported Span:
Though the empirical methods described in the foregoing para A to C give guidelines
in the form of provision and spacing of rock bolts, many of them are silent about
the diameter and length of the bolts, grade of shotcrete and size and spacing of rib
supports etc. and have to be decided based on the experience of the designers.
4. 5.1.3.1 The stand-up time is the time duration for which periphery of a tunnel
excavation line is able to stand without 'tunnel supports'. The stand-up time is directly
related to the quality of rock mass. Poorer the rock mass, shorter will be the stand-up
36
IRC:SP:91-2010
time. Stand-up time is also inversely proportional to 'unsupported span'. It explains the
necessity of resorting to multiple heading in case of wide tunnels.
In the direction of tunnel advance, unsupported span is the distance of tunnel face
from the support line. In the transverse direction, unsupported span is the width of the
tunnel opening. Good rock masses permit larger unsupported span whereas poorer
rock mass permit only smaller unsupported span. In other words, a wider tunnel
opening can be left unsupported in good rock mass. The unsupported span is defined
as the shorter of the two distances between,
i) the tunnel face and the line of support nearest to the face and
ii) the excavation width.
In poor rock mass, the distance of the tunnel face from the line of support would be
the unsupported span. In a good rock mass, however, the excavation width will be the
unsupported span.
4.5.1.4 Relation between rock mass rating, stand-up time and unsupported span
This basic inter-relation between the rock mass rating, the stand-up time and the
unsupported span is given by Bieniawski as shown below.
20
ZONE OF IMMEDIATE '
'' ''
15
COLLAPSE.
'
'
'' ' ' ''
E 10 '
z '''
~
(/) ''
6
0 '' ''
'' ''
~0 ' 80
Q,
Q,
::> 2
(/)
z
::>
STAND-UP TI ME. hr
'RMR' is used for estimating 'unsupported span' and 'stand-up time', whereas 'Q' is
used for estimating support pressure and for selecting supporting details as shown in
the nomogram presented at the end of para 4.5.1- C. Thus an inter-relation between
37
IRC:SP:91-2010
'Q' and 'RMR' is used when only 'RMR' and not 'Q' are assessed during geological
investigations. Various inter-relations are shown in the following chart.
Analytical solutions assess support stiffness and maximum support pressure for
concrete/shotcrete, steel ribs , and rock bolts etc. The stresses caused on the
supporting system by the rock mass can be calculated from analytical elastic closed
form solutions. Kirsch 's elastic closed form solution is one of the commonly used
analytical solutions. The closed form solution is restricted to simple geometries and
models, and therefore often of limited practical value. However, it serves as a good
check for the results obtained from numerical analysis.
Various numerical methods are available for stress analysis such as two dimensional
Plane Frame Method, Finite Difference Method, 2D/3D Finite Element Method or other
similar computational/numerical methods for;
Deciding the geometry of excavated periphery of the tunnel
Deciding on the minimum distance between adjacent tunnels
Tunnel support design comprising of shotcrete, lattice girders.steel ribs
and concrete lining based on incremental needs of an advancing face
Apart from methodologies mentioned above, the Observational approach is used when
38
IRC:SP:91-2010
the tunnel behaviour is not known with confidence. This is also called build-as-you-go
approach. The tunnel deformations and support pressures are monitored to develop
a stable support system to stabilize the tunnel. The NATM and the NTM both depend
on this approach with a purpose of ensuring adequacy of support and identifying time
for providing a rigid final support called lining.
The design of steel rib supports aims at estimating bending moment, shear forces and
axial load, which are compared with safe capacities of support system. The design ignores
a very vital factor called 'rock-support interaction'. Without rock-support interaction, the
support is akin to hang in air. This assumption leads to an over-design. This explains
why this empirical tunnel support design has gained popularity the world over.
IS 13365 (Part 2) : 1192 lays down the procedure and methodology for estimation of
Immediate [Short-term] Support Pressures and Ultimate [Long-term] Support Pressures.
As a structural system tunnel linings differ from other structural systems in that their
39
IRC:SP:91-2010
interaction with the surrounding ground is an integral aspect of their behavior, stability
and overall load carrying capacity. The flexibility of the lining to deform under load also
depends on the surrounding ground. This flexibility allows the lining to deform to match
with the surrounding ground, allowing the surrounding ground to mobilize strength and
stabilize. The tunnel lining deformation allows redistribution of the moments by creation
of "hinges" at points of high moment that relieve the moments in the tunnel lining.
The purpose of cast-in-situ concrete linings is to support the ground, provide base for
installation of furnishings and control seepage of ground water. Cast-in-situ concrete
linings are in plain or reinforced concrete, installed some time after the initial ground
support. Cast-in-place concrete linings can take on any desired geometric shape.
While tunnel size and stand up time of the strata dictates the choice between full face
40
IRC:SP:91-2010
or multiple drift excavation, the standup time of strata dictates support installation
activities. The work cycle time involving various activities of construction shall be
monitored as documented in 'Method Statement'.
5.2.1.1 Proper Surveying is very essential for efficient tunnelling. Skilled and
experienced surveyors, appropriate techniques and instruments shall be used.
Otherwise serious consequences, such as deviations in alignment and levels,
excessive or inadequate excavation of the cross-section, reduction in safety due to
adjacent tunnels straying towards each other, excavations of same tunnel from the
two end faces not meeting properly, etc. may result. Contractual problems may also
arise because of poor surveying.
5.2.1.2 Surveying equipments range from the common Level instruments through
Theodolites and Total Stations to advanced Lasers and Profilers. Proper Bench Marks
duly transferred from existing GTS or Project Bench Marks shall be established outside
the tunnel at either end. All traverses shall always be closed and any resulting closing
error should be negligible and be properly distributed. Construction Bench marks shall
also be established at intermediate locations for long tunnels to speed up the surveying.
Such Bench marks shall always be got cross checked independently to ensure
maximum accuracy. Tunnel grade line shall be drawn on excavated side surfaces
using indelible markings or embedded fixtures to facilitate quick ready checks. Check
surveys shall be carried out at regular time/ progress intervals using an independent
agency and with independent instruments and methods. Generally cross sections shall
be generated immediately after excavation using post-survey data and cross-checked
with required sectional area to monitor over-breaks or undercuts, as both these defects
are expensive and difficult to rectify. Such comparisons also enable corrections to
be applied to excavation techniques to minimize further erroneous excavation and
also to avoid dangerous over-excavations. Such comparisons shall also be made
contractually mandatory. All field observations and plots shall be preserved at least till
the completion of the tunnel excavation and lining work. Any corrections requi red in
the alignment due to wrong excavation shall always be made up gradually and as per
approved plans.
Almost all the tunnels have an Open/Approach Cut at each of its ends. The length of
41
IRC:SP:91-2010
open/approach cut depends upon cost of open excavation vs. cost of underground
excavation and cost of protective work involved which depends upon type of strata
met with. In case the cost of protective work becomes very high the option of cut and
cover shall be studied which may be economical in such circumstances. However
the excavation of these approach cuts in any case shall be carried out to stable side
slope and continued till a near vertical stable ground mass, suitable for forming of
excavated portal of the tunnel gets exposed. The locations of portals shall be decided
with reference to rock cover in rocky strata. The minimum cover above tunnel crest
depends upon the type and structure of rock mass, the size and shape of tunnel. The
portals and approaches shall be designed with great care with regard to safety. If need
be, the ground mass in which the excavated portal is to be formed shall be stabilized
by installation of rock bolts, grouting, shotcreting etc. Thereafter, Tunnelling shall
commence carefully by using techniques for advancement of tunnel face, described in
the subsequent paragraphs. In case of mountainous region having very steep vertical
cliffs with valley on other side, the approach to tunnel or sometimes road alignment
itself may have to be planned along cliffs. In such case the option of half tunnel by
partial excavation on hillside with one side remaining uncovered and exposed to valley
side, can be considered if geological formations are favorable. The details about 'Half
Tunnel' are dealt with at the end of this chapter in para 5.6.
Various types of equipment required to tackle different types of strata envisaged shall
be planned for right from the beginning. The tunnel face shall be advanced by carrying
out excavation using techniques and methods suitable for type of strata, stand up time
of the strata, type of machinery available and with due regards to size and shape of
tunnel. The tunnel face can be advanced by two techniques as follows:
• No-Blast Techniques.
• Conventional Technique of Drilling and Blasting.
Most common technique used for advancement of tunnel face, except in soft strata is by
'Drilling and Blasting' and same is dealt with in detail separately in para 5.3 below.
42
IRC:SP:91-2010
d Tunnelling Shields
~
Tunnelling Shields are used for
1
constructing circular or ovular tunnels
through different types of soft ground.
Shield is a rigid steel cylinder. The front
end is in the form of a cutting edge and
fitted with excavation facilities and the
rear end has facilities for removal of
excavation spoils and for installation of
supports inside the tail of the shield. In
Photo of Tunnelling Shield
shield tunnelling, periphery of excavation
is not visible as it is either supported by the shield itself or by tunnel supports. As
the excavation at the face progresses, the shield is pushed forward with the help of
h} draulic jacks which take thrust from the supports at the rear end of the shield. During
forward movement of the shield, the tail end slides past the supports already erected
nside the tail transferring the load of the excavated periphery from the shield to the
supports. Various types of shields such as Compressed Air Shield, Slurry Shield and
Earth Pressure Balancing Shield etc. are available to deal with different soil conditions.
Roadheaders
Another type of machine that can excavate tunnels of any shape is the Roadheader.
It has a hydraulic boom with a rotary cutting head at its front end, a loading device
usually involving a conveyor and a crawler traveling track to move the entire machine.
The boom can be moved up or down and right or left to cover the whole face. The boom
presses the rotating cutting head into the rock face, cuts the rock into small fragments
which drop down to the invert of the tunnel. Collector arms of the machine pull the muck
onto an apron which transfers the muck onto a trailing conveyor for depositing the muck
into muck disposal vehicles. In case
of soft soil tunnels, the roadheaders
operate under the protection of and
inside the shields. Apart from rotating
cutting head, various types of special
function heads are available. For
tunnels having height more than about
One type of machine which can excavate only circular sections through a variety of
strata from hard rock to soft strata and at a considerable speed is the Tunnel Boring
Machine (TBM), which comprises a rotating circular head with several cutters mounted
oni its face. As the cutter head rotates, it presses the cutters into the tunnel face, cuts
rock into small fragments, picks up the dislodged rock fragments with its muck collectors
and drops the fragments onto the head of a trailing conveyor for depositing them into
muck disposal vehicles. The TBM train is scores of meters long and has arrangements
and equipment for drilling of probe holes and grout holes, erection of precast lining
segments and grouting, as well as service equipment such as dewatering pumps,
transformers, hydraulic power units, containers for materials, rest rooms etc.
Splitting Techniques
Where rock cannot be blasted for various reasons such as avoiding noise, vibrations
and surface subsidence, the rock can be split along planes of weaknesses and fissures.
Then the pieces can be separately picked up and removed. There are various methods
available for splitting the rock. Some of them are listed below:
a) Conventional wedging and splitting:
Wedges and feathers are inserted into natural fissures or predrilled
holes and the rock induced to split along the line of wedges, for
subsequent removal.
b) Hydraulic Splitters:
Hydraulic splitters can be inserted in holes pre-drilled in a pattern and
the rock induced to split along the line of holes quickly and noiselessly,
of subsequent removal.
44
IRC:SP:91-2010
These methods are slow and are preferred where use of other techniques is not
feasible.
Immersed Tube/Sunken Tube Tunnels
45
IRC:SP:91-2010
sunk in to place (often into an excavated trench, connected to the elements already in
place, finished and covered up. Immersed/Sunken Tube normally takes off from and
ends into a cut and cover tunnel or bored tunnel constructed up to the edge of water.
Immersed/Sunken Tubes cause least disturbance to marine traffic and are more
resistant to seismic vibrations.
Cut-and-cover Tunnels
Cut-and-cover is a simple method of construction for shallow tunnels.
In the Bottom-up method, a trench is excavated with the help of ground support in
the form of diaphragm walls, sheet piles or intersecting piles etc. and the tunnel is
constructed within. The tunnel may be of in situ concrete, precast concrete, precast
arches, corrugated steel arches etc. The trench is then backfilled with compacted fill
material and the surface is reinstated.
In the Top-down method, initially, a trench is excavated with the help of ground support
in the form of diaphragm walls, sheet piles or intersecting piles etc A shallow excavation
is then made to allow the tunnel roof to be constructed using precast beams or in situ
concrete. The surface is then reinstated except for access openings. This allows early
reinstatement of roadways, services and other surface features. Excavation machinery
is then lowered into the access openings, and the main excavation is carried out under
the permanent tunnel roof, followed by constructing the base slab.
46
IRC:SP:91-2010
(B) Based on the planning contained in the Method Statement and the experience
gained from the previous cycles the charging of the face shall be carried out with the
explosives. Due consideration shall be paid to the charge per series of detonators
and the location of the holes being charged in the face for minimizing the vibrations
and damage to the surrounding rock mass. Charge comprising of designed quantity
of suitable explosives together with a delay detonator of designated delay shall be
inserted into each drill hole. Leading wires of the detonators shall then be connected
to form a circuit and ends of the circuit connected to an electric exploder through hook
up wires. Due safety precautions at the time of charging the face shall be taken. The
face shall be cleared and service lines, equipments withdrawn from the face and shall
be parked at a safe distance of about 70 m from the tunnel face. The other necessary
precautions as prescribed for blasting shall be observed. The exploder shall then be
charged and the circuit fired to blast the explosives. To overlap the activity of 'charging
the holes' and the 'drilling of holes', the use of non-electrical detonators (NONEL) can
also be resorted to. By doing so, the overall cycle time can be reduced at some extra
cost. NONEL is also suitable for safe working in periods of lightening incidence.
(C) For facilitating drilling, charging of blast holes and scaling etc. mobile access
platforms with intermediate deck can be used. Mobile Drilling Jumbos comprising of
hydraulic rock drills mounted on hydraulic booms which can cover full face of a tunnel
are available. A basket mounted on a telescopic hydraulic boom is also provided with
the jumbos for facilitating scaling, charging of blast holes etc.
47
IRC:SP:91-2010
(E) Ventilation: The tunnel face is a dead end and at the same time it is an area
of maximum activity. It therefore becomes necessary to see that the face is properly
ventilated by means of artificial ventilation. Where the excavation is carried out by the
No-blast Techniques, operation of heavy equipment generates a lot of heat, diesel
equipment fumes and increased humidity. Where excavation is carried out by Drilling
and Blasting technique, heat and fumes caused by the blast need to be exhausted out
from the face.
Methods of driving the tunnels by attacking the face depends upon the size and shape
of tunnel, equipments available, the condition of formation, the stand up time of the
strata through which tunnel is passing, the extent to which supports are necessary
and overall economics. Tunnels can be driven by the following methods:
• Full Face Method
• Heading and Benching Method
• Multi-drift Method
• Multi section Method
This method is used when the tunnel is being excavated through stable formations .
Limitation of full face method depends upon the size of the tunnel and capacity of
equipment being used for the job.
48
IRC:SP:91-2010
Heading and Benching method is used when height is more than about 8 m and area
of the face is large and/or when the tunnel is being excavated through not very stable
formations, to enable installation of supports within the available stand-up time.
In this method, the heading and the bench are divided into smaller parts. This method
becomes necessary when the tunnel is being excavated through very poor and unstable
formations, to enable installation of supports within the available short stand-up time.
For wider tunnels in stable formation pilot heading followed by side slashing has to be
resorted to.
Even in the so called compact and hard rock formations, possibility of meeting
jointed and weak and water charged zones can not be totally ruled out. Though the
geotechnical explorations help to gain adequate knowledge of the strata, knowledge
about the condition of the strata immediately ahead becomes absolutely necessary for
safe and efficient Tunnelling through heterogeneous strata. Assessment of the strata
immediately ahead is carried out by drilling probe holes of suitable diameter through
the tunnel face itself. If water starts gushing out through a probe hole, it indicates
presence of ground water ahead and sufficient care shall be exercised. Sudden
increase or decrease in the rate of drilling would give indication of the thickness and
condition of joints and weak zones. This information enables to carry out advance
grouting to seal passages of water and loose joints and be prepared to deal with the
difficulties before actually entering the ground ahead.
It is therefore preferable that assessment of the strata immediately ahead is carried out
by drilling probe holes, on regular basis. In locations where the geological investigations
indicate likely presence of highly jointed and fissured formations such assessment
with advance probing and treatment shall be made mandatory.
5.2.5 Scaling
Immediately after blasting , defuming activity at the face shall be taken up using the
ventilation fans and the ducting system provided. The defuming time will depend upon
49
IRC:SP:91-2010
the type of explosive, quantity of explosive and the ventilation system, etc. Thereafter
the face shall be approached and inspection shall be carried out to see the efficacy
of the blast. The service lines shall then be extended/reinstalled. If found necessary,
water shall be sprinkled on the muck pile created at the face to contain the blasting
fumes. The scaling, which is an operation for knocking down all loose rock fragments
hanging on to the periphery of the Tunnel, shall then be started mechanically or
manually immediately after the blasting fumes are exhausted from the face.
Routine inspection of the periphery of already excavated tunnel shall also be carried
out and loose scales that may have developed because of spalling shall be knocked
down.
The blasting crushes the rock of the tunnel face into small fragments and forms a muck
pile in front of the face. After scaling of the sides and face, the activity of removing
the muck shall be undertaken provided the excavated sides and the face retain
themselves till the muck from the face is removed. Otherwise, the muck pile shall be
spread near the face and temporary support measures be adopted to increase the
stand up time. The muck coming out of excavation at the face shall be removed from
the face with the help of loaders and muck haulage units and led to and disposed off
into the areas designated for muck disposal. In case of long tunnels, deployment of
diesel operated excavators/loaders and dumpers for muck removal be avoided and in
their place electrically/pneumatically operated loaders and battery operated haulage
cars or belt conveyers shall be preferred. For long tunnels rail mounted equipment as
against tyre mounted equipments and conveyers are preferred.
A suitable area in one or more locations, of adequate size to hold the total quantity
of muck expected to be removed from the tunnel with a reasonable height of the pile,
shall be identified and earmarked as Muck Disposal Area. This Area shall be well
accessible from the Tunnel portal(s), connected by a road of appropriate quality. The
muck haulage units carrying the disposal muck from the tunnel shall dump the muck
only within this Area and dozers shali be deployed for spreading the muck uniformly
in layers to permit muck to be stacked safely up to the design height of the pile. In the
process of building up the pile up to the maximum specified height, temporary roads
shall be formed by the dozer(s) to enable the dumpers to reach various locations of
the Muck Disposal Area to spread the muck uniformly. In all the temporary stages
the pile shall be carefully heaped and leveled to avoid unintended and unsafe slides
or collapses of the slopes. Once a particular stack reaches its deigned height, muck
dumping shall be immediately diverted to the next designated pile. The stable slopes
50
IRC:SP:91-2010
of the stack shall be pitched with excavated stones to prevent mud from oozing out
and the slopes shall be finally turfed to make them more stable and prevent erosion
due to run-off water.
It shall be realised that for efficient and safe tunnelling, supports shall be installed as
soon as possible after exposing the face and well within the stand up time.
Plain or Steel Fiber Reinforced Shotcrete, as the name suggests, is
concrete shot over exposed periphery of a tunnel. In case of Tunnelling
through highly weathered and very highly jointed rocks , immediately
after completion of defuming, a layer of Steel Fiber Reinforced
Shotcrete [SFRS] shall be placed on the exposed periphery, to give it
an immediate support and to prevent dilation of the exposed surface
and to extend it's stand up time. This will also make the area safe
for further operations. Even in very stable rock formations, a layer of
shotcrete is provided over exposed periphery to prevent weathering
and dilation of joints.
Rockbolts are provided to stitch together layers of jointed and blocky
formations. Different types of rockbolts such as split-wedge type,
expansion shell type and those grouted with resin or mortar capsules
etc. are available. The choice depends on the type of strata in which
the rockbolts are to be placed. For facilitating installation of rockbolts,
Mobile Access Platforms can be used. Rockbolters comprising of a
51
IRC:SP:91 -2010
hydraulic rock drill mounted on hydraulic boom for drilling and a basket
mounted on a telescopic hydraulic boom for installation are also
available for rockbolting.
• Provision of ribs made of joists or lattice girders is made where exposed
periphery of a tunnel is not capable of standing on its own and needs
active external support. To form a continuous roof, lagging in the form
of steel plates or concrete planks shall be placed over the extrados
of the rib supports and the annular gap between the tunnel periphery
and the lagging shall be tightly packed with backfill concrete. In case
of Lattice Girder Supports, girders shall be embedded in plain concrete
lining or SFR Shotcrete.
Where excavation of the heading is carried out by multi-drift method
i.e. by initially advancing the central drift & followed by widening to
full section of the heading. Arch of the Central Drift shall be supported
using segments of the arch rib and held in place by rock bolts or by
installation of temporary verticals and bottom struts. After completion
of excavation & supporting of the central drift, widening of the central
drift shall be carried on in stages. At this stage, the segments of the
arch ribs already erected in the central drift shall be extended in the
widened section. These extension segments can be held in place by
rock bolts or the other end of these extension pieces shall be made to
rest and fixed onto a wall beam laid on each side of the heading. In
case of Supports fabricated out of steel joists, concrete lagging planks
shall be placed over the extrados of the supports and the annular gap
between the tunnel periphery and the lagging shall be packed with
backfill concrete. In case of Lattice Girder Supports, the girders shall
be embedded in SFR Shotcrete/concrete lining .
Plain or Reinforced Concrete Lining of appropriate thickness shall be
used where exposed periphery of a tunnel is not capable of standing on
its own and needs active external support. The Concrete Lining can be
built from pre-cast segments or can be cast-in-situ. Cast-in-situ lining in
sides and overt of tunnels can be cast together using mobile telescopic
shutters or in separate operations. Invert concrete can be placed
thereafter. Mixed Concrete shall be brought to the placement point in
transit mixers and placed in position with Concrete Pumps. Depending
upon the development of the stresses in the tunnel, suitable time gap
shall be allowed between excavation and lining so as to gain stability of
the excavated section of rock and thus avoid transfer of load to lining.
52
IRC:SP:91-2010
53
IRC:SP:91-2010
functioning of the assembly. The space behind the lining and excavated
periphery of rock is generally filled up with pea gravel, injected with
cement grout and adequate contact for stress transfer from the rock
strata to the lining is ensured.
• In poor rock with limited standup time, forepoling technique is used
to improve/strengthen the strata ahead above the tunnel roof before
advancing the face. Basically an arch-like shell is created ahead of
the tunnel face prior to its excavation, enabling tunnel excavation to be
carried out safely and speedily under a protective arch. Forepoles are
also installed to treat cavity formation and extremely weak geological
material like highly sheared rock mass and even overburden material
like colluvium and river deposits. Forepoling is also useful in situations
where tunnels have to be excavated at shallow depths, or where minimum
disturbance is to be caused to the surface structures, i.e. ground surface
settlements have to be restricted, as for instance in urban areas. Three
different methods of forepoling are commonly used:
i) Roofing Method: Forepoling is carried out by installing steel bars
of required diameter (generally 25 mm, 32 mm and 36 mm). Steel
sections, plates or pipes can also be used instead of rods in poorer
strata. Length of fore poles may vary from 5 m to 12 rn . Spacing is
generally 300 to 500 mm depending upon the geological material to be
treated. Forepoles can be used with or without grouting. Forepoles are
installed outside the tunnel periphery at an angle (with the longitudinal
horizontal centerline of the tunnel) ranging from 5 to 7 degrees up. For
Pipe roofing heavy duty seamless steel pipes are used with or without
perforations to allow grouting to be done through the perforations. Pipe
diameter varies from 89 mm to 100 mm and length may vary from
10 m to 20 m depending upon the site conditions. Pipe jacking or micro
Tunnelling methods can also be used for installing the pipes.
ii) Spiling Method: The Spiling method is a ground improvement technique
where the support structure of a tunnel top sector is installed ahead
of the excavation of the face. Such support mechanism provided by
forepoling technique stabilizes the tunnel face area in both longitudinal
and transverse directions by means of an arch-like reinforced zone
formed primarily by injection. This method can also be used in
conjunction with standard drill-and-blast Tunnelling when severe
fault zones are encountered or wherever extra support structures are
required.
IRC:SP:91-2010
9 Ill
Biggest advantage of the technique is that it can be used in varying ground conditions
and for tunnels of all shapes and reduces surface settlement and is therefore most
suitable for urban Tunnelling through soft ground. However, as the process of jet-
grouting is a high energy process, in shallow tunnels the jet-grouting process may
induce surface settlements that exceed the design requirements.
55
IRC:SP:91-2010
For tunnelling in soft grounds, an approach called 'The New Austrian Tunnelling
Method' (NATM) can be adopted. It was developed between 1957 and 1965 in Austria
and was given its name to distinguish it from the old Austrian tunnelling approach. The
main idea is to use the geological properties of the surrounding rock mass to stabilize
the tunnel itself.
The main idea is to use the geological properties of the surrounding rock mass to
stabilize the tunnel itself. The NATM integrates the principles of the behaviour of rock
masses under the influence of the excavation method and the support system and
monitoring the performance of underground construction during construction . The
NATM is not a set of specific excavation and support techniques. The NATM is a
philosophy where properties of the surrounding rock or soil formations of a tunnel and
the support systems are integrated into an overall ring-like support structure. Thus the
supports and the formations will themselves be part of this supporting structure.
The NATM has since been adopted the world over for a large variety of ground
conditions including rock tunnelling . Based on experience, the philosophy has been
renamed as Norwegian Method of Tunnelling [NMT].
56
IRC:SP:91-2010
Based on the computation of the optimal cross-section, just a thin shotcrete protection
could be adequate. It is applied immediately behind the face, to create a natural load-
bearing ring and therefore to minimize the ground deformation. Additionally, geo-
technical instruments are installed to measure the later deformation of excavation.
Therefore a monitoring of the stress distribution within the ground mass is possible.
This monitoring makes the method very flexible, even at surprising changes of the
geo-mechanical ground mass consistency during the Tunnelling work. Such problems
are not solved only by thick shotcrete, but by using mesh reinforcement/SFRS which
can be combined with steel supports or rock bolts.
The measured rock properties lead to the appropriate tools for tunnel strengthening.
Therefore NATM/NMT is also applied to soft ground excavations and to tunnels in
porous sediments. The flexible NATM/NMT technique enables immediate adjustments
in the construction details, but this requires a flexible contractual system too.
57
IRC:SP:91-2010
5.2.9 Grouting
5.2.9.3 Water control grouting (pregrouting) is done through holes drilled to cover
the zones ahead of the excavated area to arrest seepage of water into the excavated
tunnel. Holes are drilled at an angle to the longitudinal centerline of the tunnel, from all
58
IRC:SP:91-2010
round the periphery of the cross-section. The number of holes and spacing depend on
the circumstances involved. In areas of low seepage, Tunnelling can proceed ahead
of the seepage zone and arresting the seepage can be carried out with suitable lag
behind the excavation face. Length of holes varies from 3 m to 15 m. For arresting
large seepages, careful planning is necessary. It is preferable to carry out such grouting
ahead of excavation i.e. before tunnel face enters such zone. The locations and extent
of grout holes as well as the type of grout and its composition have to be designed
duly considering the various parameters such as exact location of seepage, presence
of porous seams, origin of seepage water, amount of seepage and its pressure, etc.
such grouting is best done using specialized agencies.
5.2.9.4 Contact grouting is done using transverse drilled holes for cast in-situ lining
to fill up the voids caused by shrinkage of concrete or where lining concrete has
not penetrated all excavated areas. Contact grouting is essential where cast in-situ
concrete plugs are required for a tunnel. In the case of precast and installed concrete
lining the cavity behind is normally filled up with pea gravel and grout is injected inside
to consolidate the gravel into concrete. Grouting is also done in conjunction with pipe
roofing to treat cavity formations and as part of forepoling operations.
5.2.9.5 Grout used for these applications is generally neat cement grout. The water-
cement ratio varies from case to case but generally ranges from 1:5 to 0.6. Similarly,
grout pressure will range from less than 1 bar to 15 bars depending on the material
to be grouted and the ground conditions. Care shall be taken to limit the pressures in
areas where possible fracturing of existing strata is dangerous. Pressures are higher
where fracture grouting is required/permissible or for jet grouting. Fine sand is added
to the grout where large cavities have to be filled up. Special grouts are used for
treating seepages, using admixtures such as sodium silicate. Polyurethane Foam
(PUF) is also used often to arrest large seepages. Reference to relevant provisions of
standards covering River Valley Grouting may also be made.
At the end of each excavation cycle, the gee-logging and profile plotting of the
excavated tunnel is very important along with evaluation of the efficiency parameters.
After analyzing this activity, next cycle may be modified to the required extent.
5.2.11 Monitoring
Depending upon the geology of the rock mass during tunnelling, convergence
measurements at the excavated crown and sides may be taken up with the help of
59
IRC:SP:91-2010
multi-point bore hole extensometers or studs and tape extensometers. The cycle of
taking readings will depend upon the convergence observed.
5.3. 1. 1 The drills used for tunnelling are either pneumatically or hydraulically
powered and having either air pusher legs and/or mounted on drilling jumbos. With air
pusher legs it is always advisable to use templates for guiding the direction of drilling.
The drilling jumbos have varying specifications. They can have a simple mounting
arrangement on truck or rail. In most sophisticated type of computerized jumbos
drilling programme is fed in for the total drilling cycle. The choice of drilling system will
depend upon the size, shape and length of tunnelling work at hand as these are the
main factors deciding t0tal economy of the project.
5.3.1.2 For a successful blast, it is most important to initially create a free face that
is required to accommodate the requisite advance of subsequent serial blasts. For
creating a free face (barring the burn cut pattern) it is absolutely necessary to drill the
blast holes in the following manners.
Cut Holes:
These holes are located around the middle of the cut and are drilled at
an inclination of about 60° and are to be blasted first to create free face
for next set of blast holes termed as Cut Spreaders.
• Cut Spreaders:
These are the next set of blast holes having lesser inclination and are
in two or more rings. They are meant to widen the free face created by
blasting of Cut Holes. They are usually 15 to 30 cm deeper than other
holes.
• Cut Easers:
They are drilled almost parallel to the tunnel alignment and are mainly
responsible for the scheduled advance of the face. Number of rings of
these holes depends upon the size of the tunnel.
• Trimmers:
These blast holes are drilled near the periphery to shape up the tunnel
periphery to the requisite section as per the designs and with lighter
charge to avoid excessive over breaking.
60
p
IRC:SP:91-2010
Where drilling is carried out by hand-held rock drills the diameter of hole is minimum
about 28 mm. In case of drilling carried out by mechanical Jumbo the diameter of
holes are large to suit the rock drills. The diameter of holes at deepest point shall be
about 3 mm more than the diameter of cartridge being used.
5.3.1.3 The drilling pattern to be adopted shall ensure minimum over breaks and
shall consume least quantity of explosive per unit volume of excavation. The drilling
pattern depends upon texture and formation of rock, size and shape of tunnel, strength
of explosives and fragmentation required suitable for handling. The following are the
drilling patterns most commonly used for tunnel drivage.
1) Wedge Cut or "V" cut Drilling Pattern: In this pattern horizontal cut
holes are driven around the middle of the face, in an inclined angle of
around 60° to the face towards the centre. Maximum explosive charge
concentration is required at the apex end of the blast holes as they are
to be blasted at the first instant for creation of the free face.
2) Cone/Pyramid/Diamond Cut: This kind of cut is suitable for laminated
rock type which is of sedimentary in nature. It also helps in drivage of
smaller cross-sectional area tunnels so as to break the rock along the
cleavage planes.
3) Burn (Parallel) Cut Holes: The burn cut holes are drilled parallel to the
tunnel advance and perpendicular to the face of the tunnel. Some of
the drilled holes (mostly in the middle section of the face) are holes
of large diameter [say 100 m,m.] or a set of closely spaced holes of
conventional diameter [46 to 56 mm] and are left as dummy holes
without any explosive charge, so that they act as free face for the
heavily charged blast holes around. Specific Geometrical relationship
in between the diameter of dummy holes and spacing in between
dummy holes and charged blast holes is required to be maintained for
the given rock in order to create the free face.
With Burn or Parallel holes cut possible advance per round is longer as compared to
than that with angular cut holes. Success of Burn or Parallel Hole Cut depends upon
accuracy in keeping the holes parallel. This requirement and requirement of holes of
large diameter or a set of closely spaced holes of conventional diameter calls for use
of drilling Jumbos.
5.3.2 Blasting
61
IRC:SP:91-2010
the detonator leads are not rubbed or damaged in the process. The wooden tamping
rod of sufficient and requisite length shall be used for the purpose. The stemming
material ideally could be of mud cakes or preferably pneumatic charge locks.
5. 3. 2. 2 Choice of explosives
The best choices for the blasting operations are the emulsion explosives produced by
intimate and homogeneous mixer of oxidizer and fuel. Basically emulsion explosives
consist of micro droplets of super saturated oxidizer solution in oil matrix. They are
in the form of water-in-oil emulsion. The various advantages associated with use of
emulsion explosives are as below;
Emulsion explosives are much better water resistant than water gel
slurry or ANFO. This is because the oil-phase envelops the water
phase.
• They are safer to handle, store and use because of their relative
insensitivity to detonation by friction, impact or fire.
• Due to the oxidizer drop-let size (0.2 to 10 micron) they have higher
value of Velocity of Detonation (VOD) which can tackle the toughest
rock conditions very effectively and that too with out compromising on
safety standards.
• Since emulsion explosives are more oxygen balanced they generate
minimum noxious fumes and very less smoke. This in turn can reduce
the ventilation time after the blasts and further can shorten the cycle
time of operations. Liquid emulsion explosives are pumpable and
charging time can be cut down.
Normally, the consumption of explosives in tunnel blasting is much more than that
required for open cut, basically because in case of open cut blasting, existing free
face is available whereas in tunnel blasting it has to be created. For road tunnels, the
Specific Charge or the Powder Factor is normally around 1.2 kg/cum of in-situ rock
on an average. However, this requirement of explosives may vary from site to site
depending on the geological strata involved and the cross section of the opening.
Selection of delays in initiation system and timings shall be such as to create a free
face effectively by moving out the broken rock mass so much that the rock volume
after swell from subsequent blasts must be accommodated. For this the fracturing and
62
IRC:SP:91-2010
breaking time of the rock and time required for spreading out cracks in the rocks is
to be studied . It, basically, all depends on condition of rock. In hard and brittle rocks
the speed of developing cracks is faster than that in softer rocks . This rock breaking
speed can vary from 1-3 millisecond time per meter. But the ejection speed of rock
after the blast may vary from 20-30 m per second i.e.20-30 mm per milli-seconds. So
it can be understood that for a 4 m long blast holes the broken rock takes about 300-
400 milli-seconds for complete removal from the face . Precisely, for this reason long
delays (half-second, 300 to 500 milli-seconds) are preferred for tunnel blasting. The
short (ab out 50 milli-second) delays can be used in baby-cut and cut holes as they can
provide the requisite initial shattering effect for rock breaking and forming a free face
tor easer and trimmers. The advantages of delay detonators are;
• Better fragmentation ,
• Reduced secondary blasting,
• More uniformity in size of fragmentation,
• Important advantage is more holes can be fired in a single blast with
less vibrations, concussion and noise.
The available initiation systems are either Shock Tube system or Combination of
Millisecond and Half second electric delays. In shock tube system precise calculation
of the requisite delay intervals is possible whereas, in case of electric delays there are
always short comings in respect to the delay timings because of permitted tolerance.
These days, Electronic Detonators ("E"Dets) are available for precision timings.
5. 3.2.6 Misfires
Misfire can be defined as a blast hole that has not fired during designated blasting
operation owing to following causes.
• Due to manufacturing defects.
• Due to desensitization of explosives.
• Due to faulty connections or faulty blast designs.
Due to negligence in following laid down rules & regulations.
• Due to prevailing Geological conditions.
• Due to circumstantial conditions like water bearing strata
For dealing with misfires relevant IS codes and explosive rules shall be followed.
63
IRC:SP:91-2010
5. 3. 2. 7 Controlled blasting
The concept of controlled blasting as applied to tunnel blasting is for minimizing over
breaks and has many advantages like:
1) Less damage to peripheral rock,
2) Reduced requirement of support system,
3) Safer tunnel operation in general ,
4) Reduced requirement of scaling,
5) Reduction in over breaks.
In order to reduce the cracking or damage to the strata at the periphery it is advisable
to use "Air-Column Method" which can minimize the redia l vector component of blast
induced ground vibrations. This method consists of inserting in to the blast hole an
inert spacing device of a length about four times of the diameter of the blast hole prior
to charging of first explosive cartridge. This leaves requisite air gap in between the
explosive cartridge and the end of the blast hole. With this method a plain straight
tunnel face can be secured for next drilling cycle with out any cracks.
Efficiency of blasting shall be routinely assessed by tabu lating Pull, Specific Charge,
Specific Drilling, Detonator or Hole Factor, Blast-induced damage and Overbreak/
Underbreak against the values assumed during planning.
Non-structural works inside road tunnels involve construction of Side Drains, Walkways,
Crash Barriers, Kerbs and Road Carriageway, which can be taken up simultaneously
with the other works.
64
IRC:SP:91-2010
Telephone Stations, Signage and Centralised Monitoring System such as CCTV etc.
Furnishings can be conveniently installed after completion of the Road Carriageway
work.
5.6 Half Tunnels
5.6.1 Feasibility
For construction of roads in precipitous mountains, half tunnels can be built-in the
difficult terrains, like vertical hills/cliffs to minimize the excavation quantity as well as
time and cost. Half tunnels shall be constructed in selected patches of roads if rock
formation is suitable. A comparative techno-economic study between half tunnel and
a full face road tunnel shall be made.
There is not much similarity between half tunnels and tunnels. While tunnels are
possible to be constructed in any kind of strata, half tunnels may be possible only with
65
IRC:SP:91-2010
vi) Joint planes i.e. bedding shall be horizontal to sub-horizontal and shall
be favorable for half tunnelling.
vii) Joint spacing shall be more than 3 m.
viii) Joint planes should be undulating rough and tight.
ix) Joints should be free from clay filling , shearing or fault.
Having decided about the location of a half tunnel, the sequence of construction shall
be as under:
1) The formation level between the two points of the road shall be marked
to asses required height of cut.
66
IRC:SP:91-2010
67
IRC:SP:91-2010
NATVRALHILLSLOPE 1----------....,...-----''----------
TRACER PATH
(THE FIRST ACTIVITY OF
EXCAVATION)
1.S
111BENCH
2.0
2nd BENCH
3rd BENCH
·.,
5lh BENCH
TCRETE ·1SFRS
68
IRC:SP:91-2010
only after an approved Quality Assurance programme and an approved Quality
Control Programme are in place for each activity. While the QA system ensures the
establishment of appropriate procedures and systems for ensuring the necessary
q ality, the QC system ensures that the establish Systems are duly adhered to.
5 7.2 In the Design stage the QA/QC systems shall cover, at minimum, proper
e tablishment of the required objectives, laying down of proper procedures for the
design, following established methods, deployment of competent and capable people,
the setting up of a suitable monitoring and supervision system, etc for the design
activities.
5.7.3 In the Construction stage, the QA/QC systems shall cover, at minimum,
the laying down of appropriate construction procedures, checks on the qualities of
the personnel, machines and the materials deployed in the works and suitable tests
on the completed structure. All processes involved in the construction on and off the
site shall be duly covered. Preparation of detailed Construction Method Statement
n advance and strict adherence to the same are essential to ensure good Quality
Practice.
5. 7.4 The Project Quality Plan covering the above at various stages shall be
prepared by the concerned agencies and got approved by competent authority. Such
systems shall be duly followed by all concern during the Design and the Construction
stages.
5. 7.5 Wherever relevant, existing National Standards and where they are
deficient, the relevant international Standards or Good Engineering Practices shall
be adopted while drafting the QA/ QC systems. The Reference Numbers of such
standards referred shall be duly listed in the relevant Manuals for ready reference.
69
IRC:SP:91-2010
All the agencies involved in the construction of tunnels shall ensure that all applicable
rules and regulations are duly complied with in strict conformity with the spirit and
body of such regulations.
Since each underground project has its own peculiarities and special features in view
of topography, rock features, etc, it is very essential for each tunnel project to carry out
a comprehensive Risk Analysis of the particular project and evolve a Project Safety
Plan (PSP). While the agencies concerned may adopt the standard provisions of their
respective organisations, it is essential to have a project-specific safety plan, which
is fully relevant to the particular site. The PSP shall be prepared by the concerned
construction agency and got approved from the competent authority. The PSP shall
address all site-specific issues and tackle all the risk elements identified .
70
IRC:SP:91-2010
lagging and back-packing I grouting and permanent concrete lining. The most complex
su ports are the provision of umbrella tubes used along with forepoling and grouting
3
te hniques. The size and shape of the underground installations shall be conducive to
srife and smooth operations.
Apart from this all operations connected with the construction of tunnels shall be
analysed and appropriate safety precautions taken through the implementation of the
PSP.
All personnel entering the tunnel during construction shall wear all applicable Personal
Protective Equipment (PPE). The PPE shall comprise, at minimum, Safety Helmet,
safety (hard) shoes, tight clothing with no loose ends and jackets/clothing with reflective
stripes. Additional PPE such as goggles, gloves, dust masks, helmet lamps, etc shall
also be adopted wherever conditions so warrant.
A proper access control system should be in place to have a clear idea at all times
on the identity of all personnel who are inside the underground installations in case
any accident take place and rescue operations are to be launched. It is also essential
to keep track of all equipment inside the tunnel. It is common to issue token to all
concerned personnel and make them deposit the tokens while entering the tunnel and
retrieving the same on exiting.
6.2.4 Signage
The contractor's personnel shall practise all standard safety systems. These wou ld
include at minimum, safety induction (initial training in basics of Safety) and training
(routine training) exercises, medical screening of personnel for working inside tunnels,
system of permits for simultaneous operations in various locations, pep talks (regular
talks to workmen before they commence work on importance of safety and how
necessary it is for them to observe safety regulations for their own welfare) and tool box
71
IRC:SP:91-2010
talks (specific safety instructions at the site in the specific area of work for the workmen),
talks on specific operations to be carried out on the day, safety walkabouts(general
safety observance checks carried out by safety stewards by going around the site
and checking observance of the various safety regulations.etc), safety audits, safety
reviews and mock drills.
Only wet drilling shall be permitted. Drilling shall not be resumed after blasts have
been fired until a thorough examination has been made by blasting foreman (head
blaster) to make sure that there are no misfired charges, which the drill may strike. All
holes shall be of slightly greater diameter than the diameter of cartridges of explosives
used. A drill, pick or bore shall not be inserted in butts of old holes even if examination
fails to disclose explosives. Separate holes shall be so drilled as to be nowhere less
than 30 cm clear distance away from the previous hole. Charging of drilled holes and
drilling shall not be carried out simultaneously in the same area, unless Nonel type of
detonators are used and adequate precautions have been taken.
All explosives shall be handled and used with care either by or under the direction of
competent persons and following the Indian Explosive Act, 1884, Explosive Rules,
1983, and IS 4081 - 1967 Safety code for blasting and related drilling operations.
Explosives and detonators shall be placed in separate insulated carriers whether
carried by persons or conveyed mechanically and an attendant shall ride with the
explosives being conveyed mechanically on slopes in shafts or in underground work
areas. For carrying explosives mechanically, prior permission of Chief Inspector of
Explosives shall be obtained. Insulated containers, used for carrying explosives or
detonators shall be of approved manufacturer and shall be provided with suitable
non-conductive carrying device, such as rubber, leather or canvas handle or a strap.
Explosives and detonators shall be brought to the working places in separate, tight,
well insulated containers , and kept in the containers until removed for placement in
drill holes. If drill holes are not ready, they shall be stored in locked box type magazines
72
IRC:SP:91-2010
located at a safe distance of at least 170 m from the working space. No person other
than a shot firer shall carry any priming cartridges into a shaft, in which the sinking is
in progress. No such cartridge shall be so carried except in a thick felt bag or other
container sufficient to protect it from shock.
Electric firing shall be done by an approved method . All drilling equipment and
personnel not engaged on loading shall be removed from the site before loading of
holes starts. Loading of a round shall be completed by the crew starting the work of
loading. Firing of round shall be the responsibility of the blasting foreman . Only clay
sticks or pneumatic air locks shall be used for separation of charge/stemming of the
holes.
Before use each and every electric detonator shall be tested for a positive test with the
help of an ohmmeter. Before shot firing , the circuit shall be tested for insulation and for
continuity. Before a shot is fired in an underground working place due warning shall be
given to persons within 330 m in all directions and every entrance to the place where
a shot is about to be fired shall be guarded so as to prevent any person, not having
received warning from placing himself in dangerous proximity to the shot.
In case an exploder is used the revolving handle of the exploder shall be in the custody
of the blasting foreman to prevent anybody else firing the shot when the blasting
foreman and other persons are inside. Stray currents may cause accidents while
loading and utmost care shall he taken in removing all faults from electrical circuits.
Electric power, light and other circuits in the vicinity within 70 m of the loading points
shall be switched off after charging the explosive and before the blasting operation
starts. Power supply is to be switched on only after the blasted area has been properly
inspected by the blasting foreman for misfires. All tracks, airlines and vent pipes shall
be kept properly grounded. The heading shall be properly lighted with the electric
floodlights before and after blasting.
Immediately after a blast has been fired , the firing line shall be disconnected from
the blasting machine or other source of power. When at least 5 minutes have passed
after the blast was fired , a careful inspection of the face shall be made by the blaster
to determine if all charges have been exploded, Electric blasting misfires shall not
be examined for at least 15 minutes after failure to explode. Other persons shall not
be allowed to return to the area of blast until an ALL CLEAR' signal is given by the
blasting foreman .
73
IRC:SP:91-2010
All wires shall be carefully traced and search made for any exploded cartridge by the
man-in-charge of the blasting operation. Sufficient time shall be given for the fumes to
clear before permitting the labour to work for mucking operations.
6.3.4 Misfires
Misfired holes shall be dealt with by the blaster preferably by the same person who
had done the charging operations. If broken wires, faulty connections, or short-circuits
are determined as the cause of a misfire, the proper re pairs shall be made, the firing
line reconnected and the charge fired. This shall be done, however, only after a careful
inspection has been made of burdens remaining in such holes and no hole shall be
fired when the burden has been dangerously weakened by other shots. The charge
of explosives from a misfired hole shall not be drilled, bored or picked out. Misfired
charges, tamped with solid material, shall be detonated by a safe approved method.
The stemming shall be floated out by the use of water or air jet from hose until the
hole has been opened to within 60 cm off the charge , and the water shall be pumped
out or siphoned off and the new charge placed and detonated. Whenever this method
is not practicable, a new hole shall be drilled 30 cm deep and spaced not nearer than
60 cm, shall be loaded and detonated. A careful search shall be made of the unexploded
material in the debris of the second charge.
It is essential to carry out proper scaling operations after each blast to remove all the
loose rock pieces and guard against rock falls . Many accidents in tunnelling result
from rock falls than any other cause. Careful and frequent inspection of walls and
roofs as well as of tunnel supports shall be carried out. Thorough scaling of loose
rocks at all weak spots is the best preventive against rock falls . Periodic inspection of
unsupported sections of the tunnel from a travelling scaling platform shall be carried
out for locating weak spots. Supported sections shall also be inspected regularly to
make sure that the weakness of the formation has not spread beyond the supports.
Loosened rock shall be supported/ removed forthwith. All supports shall be checked
occasionally to make sure that there is no member under distress. All scaling platforms
shall be equipped with safe ladders.
Following the basic philosophy elucidated in the earlier section, design and installation
of appropriate supports within the stand-up time for the particular type of rock is the
most important steps to ensure proper safety for all personnel inside the tunnels.
•
IRC:SP:91-2010
Special watch shall be maintained for uncontrolled collapse of the face or adjacent
areas, sliding in of muck and water, etc.
Ventilation shall be carried out in tunnels to make the working space safe for workers
by keeping the air fresh and by eliminating harmful and obnoxious dust, explosive
fumes, exhaust from operating equipment, particularly diesel-operated equipment,
and other gases. Mechanical ventilation shall be adopted where necessary to force
the 'air in or exhaust the air out from the working face to the portal through ducts.
Externally located fans operate in forced ventilation and induced ventilation modes
to supply air through rigid or more commonly, flexible ducts. Intermediate booster
fans ensure better supply for longer ducts. Venti lation is also necessary to ensure
temperatures of not more than 4°C dry and 29°C wet at the working place. Ventilation
shall be properly designed considering the tunnel topography and emission levels
inside. The volume of air required generally depends on length of heading, size of
tunnel, type and amount of explosives used , frequency of blasting, and temperature
and humidity. Where the temperature is high or heavy blasting is resorted to suitably
augmented volume of air shall be provided.
It is important to be alert all the time for the presence of toxic gases in underground works
and appropriate instrumentation should be provided to keep track of the ambient air
quality at all times. Proper records should be maintained of specific measurements of air
quality at regular intervals throughout the day after blasts or major rockfalls. Particularly
after each blasting for underground rock excavation, the ventilation measures should
be set in place quickly and effectively for de-fuming and personnel should be allowed
to enter only after establishing that the air quality is sufficiently acceptable. In certain
regions geothermal conditions prevail and cooled air should be supplied to enable safe
and comfortable working conditions. In any case appropriate well designed ventilation
systems shou Id be put in place to ensure proper ambient conditions.
Air Quality Testing - The tests shall be carried out once every 24 hours but in any
case after every blast or a major rock-fall. In case any of the gases are detected to
have crossed the threshold value indicated therein, the workmen shall be withdrawn
immediately till the percentage is brought down well below the threshold value by
improving the ventilation or by other effective measures.
Apart from ventilation, Noise is another factor which is problematic in underground work.
Sufficient steps should be taken to reduce the noise levels to acceptable limits and
Workmen and visitors should be asked to wear ear plugs/muffs, etc where required .
75
IRC:SP:91 -2010
6.5 Lighting
Adequate lighting shall be provided at the face and at any other point where work is
in progress and at equipment installations such as pumps, fans and transformers.
A minimum of 50 lux shall be provided at tunnel and shaft headings during drilling,
mucking and scaling. When mucking is done by tipping wagons running on trolley
tracks a minimum of 30 lux shall be provided for efficient and safe working . The lighting
in general in any area inside the tunnel or outside an approach road . etc. shall not be
less than 10 lux.
Emergency lights (battery operated) shall be installed at the working faces and at
intervals along the tunnel to help escape of workmen in case of accidents. All
supervisors and gang-mates shall be provided with cap lamps or hand torches. It shall
be ensured that at least one cap lamp or hand torch is provided for every batch of
10 people. Any obstruction, such as drill carriages, other jumbos and drilling and
mucking zones in the tunnel shall be well lighted. Hand lamps shall be equipped with
strong cover of glass or other transparent material, dust and waterproof, and equipped
with a strong guard over the cover. The exterior of all hand lamp sockets shall be non-
metallic.
Irrespective of length and bends in the tunnel, arrangements shall be made for
transmitting of warning signals by any one of the following means: (a) By electrically
operated bells, operated by battery/dry cells with the bell placed outside the tunnel and
the position of the switch shifting with the progress of the tunnelling work. The position
of the operating switch although temporary shall be so chosen as to ensure proper
accessibility and easy identification. (b) By the use of field (magnet type) telephone.
For tunnel lengths up to 100 m, only one of the systems mentioned above may be
adequate whereas in tunnels of length more than 100 m at least two systems shall be
installed with the wires running along opposite sides of the tunnel, if practicable.
76
IRC:SP:91-2010
Closed Circuit TVs are often deployed to keep a continuous watch on underground
installations from the Control Room on top.
6. 7.1 General
All combustible materials like rubbish shall be continuously removed from such areas
where flammable liquids are stored, handled and processed. All spills of flammable
liquids shall be cleared up immediately. Containers of flammable liquid shall be tightly
capped. All waste and combustible rubbish shall be removed at least daily from the
tunnel.
Fire Incidence Detection Systems should be able to detect the fire very early in
its development and also accurately locate the position of the fire. The degree of
accuracy depends on the type of active fire safety systems that may be installed in the
tunnel. It is recommended that fire-fighting equipment such as hydrants, hose reels
and extinguishers are strategically located within the tunnel. Fire extinguishers and
fire-bu ckets appropriate to the hazard shall be conveniently located and identified.
The electrical installations should be carefully designed and executed and regular tests
should be carried out to ensure safe conditions and emergency cut-off procedures.
Electricity leakage monitoring systems should be in place.
All parts of the electrical installation shall have all conductors and contact areas of
adequate current carrying capacity and characteristics for the work they may be called
upon to do and all joints in conductors shall be properly soldered or otherwise efficiently
made. They shall be so constructed, installed and maintained as to prevent danger
of fire, external exposition and electric shock, be of adequate mechanical strength to
withstand working conditions underground, be not liable to be damaged by water, dust
or electrical, thermal or chemica l action, to which they may be subjected, be efficiently
insulated or have all bare live parts enclosed or otherwise protected, and be installed
at such a location that dumpers or wagons do not come in contact with the same.
On the occurrence of a fire caused by any electrical apparatus or a fire liable to affect
77
IRC:SP:91-2010
any electrical installation: the supply of electricity should be cut off from such apparatus
or installation as soon as practicable, and the fire shall be attacked and reported to
the nearest available supervisor. As far as practicable, combustible material shall not
be used in the construction of any room or recess containing electrical apparatus. No
flammable material shall be stored in rooms, recesses or compartments containing
electrical apparatus.
Adequate fire extinguishing equipment suitable for use on live parts shall be kept
ready for immediate use in or near any room , recess or compartment containing such
parts as will be readily accessible safely for use in case of emergency. This equipment
shall be inspected at least once in a month.
6.8 Housekeeping
6.8.1 General
Only the materials required for work in progress shall be kept inside the tunnel. All other
materials shall be removed from inside the tunnel. Sufficient width of the formation as
even as possible and without any obstacles shall be created to enable the workers to
get out of the tunnel quickly in case there is any collapse or any other mishap inside
the tunnel.
Transport of Material: Vehicles carrying pipe, rail and timber shall be properly loaded
for safe passage through the tunnel. The load shall be kept within the side limits for the
vehicle as loads projecting over the sides are dangerous to men working in the tunnel.
For transportation of wide loads special care shall be ensured in the operation of the
vehicles with prior warning to the workmen along the tunnel to ensure a safe journey.
Transport of Employees: A safe and smooth walkway system shall be provided for
employees, suitable separated from vehicular roads by guard railing. For transportation
of employees by vehicles proper safety precautions shall be taken.
All water and air pipes as well as electrical cable shall be arranged along the sides of
the tunnel, duly supported at regular intervals and in a systematic and neat fashion.
78
IRC:SP:91-2010
A study of boring data and geological formations shall be made to have an indication
of locations, where water can be expected. Water inflow may be reduced or even
entirely stopped by grouting of the wet seams. A wet area covering more than a single
seam shall be sealed off by installing a suitable section of concrete lining. In case of a
steady flow of water from the roof or side of the tunnel the flow shall be deflected down
the sides to sumps by metal shields. The number of pumps provided at site shall be
50 percent more than the requirements calculated on the basis of the estimated
pumping needs, or at least one number, whichever is more. In case of steeply inclined
tunnels steps shall be provided for quick exit in case of failure of haulage. Gutters
and sumps shall be kept clean. Suitable arrangement shall be made to indicate the
position of sumps in case tunnel invert is flooded.
An Emergency management Plan shall be part of the approved Project Safety Plan
and shall be well communicated to all working personnel and well displayed at the
site. Emergency Rescue Measures should be drawn up to take care of various
possible contingencies. It would also be advisable to provide safe rooms in deep
installations where people can take shelter for a few hours in case of an emergency.
Buried large diameter pipe lines leading to outside can be provided to offer a medium
for communication and feeding in air supply in case of any collapses and blockages of
the entrance to underground installations.
Ventilation is the process of expelling stagnant air and introducing fresh air in an
enclosed space. In road tunnels almost all the vehicles using the tunnel are internal
combustion engines. During their travel, these vehicles go on releasing a continuous
stream of obnoxious exhaust fumes and smoke. These fumes and smoke escape into
the atmosphere in case of an open road. However, inside a tunnel, these exhaust
79
IRC:SP:91-2010
fumes and smoke collect and keep on hanging near the roof. If a tunnel is not properly
ventilated, increase in concentration of the exhaust fumes and smoke results in
reduced visibility and slowing down of traffic and discomfort to the vehicle users. The
main intention of ventilation is to create user-friendly healthy environment inside a
tunnel.
Internal combustion engines used for powering most of the vehicles plying on roads
are either of spark-ignition type or of compression ignition type. Each of these types
generates obnoxious exhaust fumes and smoke with different characteristics. Major
constituents of these obnoxious exhaust fumes and smoke are carbon monoxide,
carbon dioxide, oxides of nitrogen and sulphur dioxide. In addition to these components,
spark-ignition type engines also emit un-burnt hydrocarbons to a very small extent.
Carbon monoxide [CO] is an odorless toxic gas which when inhaled
combines readily with blood hemoglobin in preference to oxygen,
reduces oxygen carrying capacity of the blood and shows toxic effects
which could be fatal after long exposure. The process gets reversed
upon timely exposure to fresh air.
Carbon Dioxide [C0 2] is toxic only at very high levels of concentration
which are well above those found in vehicular traffic tunnels.
Oxides of Nitrogen are of two types viz. Nitric Oxide [NO] and Nitrogen
Dioxide [N0 2]. These oxides unite with water and form nitrous and nitric
acid in the lungs and destroy the functioning of lungs.
Sulphur Dioxide [S02] forms sulphuric acid and causes toxic effects.
However, S02 is a very small component of vehicular emissions.
Hydrocarbons are also a very small component of vehicular
emissions.
80
IRC:SP:91-2010
Quantum of fresh air required to be introduced into a tunnel will depend on all the
factors mentioned under 7.1.2 to 7 .1.5 above and the permitted levels of the pollutants.
For the purpose of design, the 'Traffic Model' should therefore be carefully developed
on these considerations
81
IRC:SP:91-2010
7. 1. 7. 1 Natural ventilation
Natural Ventilation is caused by movement of air due to chimney stack effect created
by the difference in level between two portals of a tunnel. Difference between the
ambient temperature at the two portals and wind also plays a part in creating natural
draft. Piston effect created by the vehicular traffic creates additional draft.
Normally for tunnels shorter than 500 m. in length, natural ventilation is enough.
Exception would be urban tunnels with heavy traffic volume having possibility of
congestion during peak hours where provision of mechanical ventilation becomes
necessary. Another exception is tunnels longer than 500 m. having very low traffic
volume.
Where technically feasible , provision of a vertical shaft near about the centre of a
tunnel would effectively improve natural ventilation because of additional chimney
stack effect created by it. If such a shaft is fitted with an exhaust fan , the chimney
stack effect will not be affected by change in atmospheric conditions.
In case of all tunnels more that 500 m. in length, Mechanical System of Ventilation
should be provided unless the traffic volume is very low.
82
IRC:SP:91-2010
In Transverse system inlet and exhaust ducts are provided along the whole length of
a tunnel either at ground level or around crown of the tunnel. Fresh air flowing through
the inlet duct is uniformly released at various points along the length of the tunnel and
foul air is uniformly sucked into the exhaust duct at various points along the length of
the tunnel. Thus the system is linear only to the extent of travel of air from an inlet port
to the nearest exhaust port. This system is most useful for tunnels with bi-directional
traffic. In Semi transverse system only fresh air is supplied through the ducts but in
Fully transverse system fresh air is supplied as well as foul air is sucked through
independent ducts as shown in sketches given below:
Jet Fans & Carneaux at every 100 m Intermediate ceiling & Extracters
Intermediate ceiling in the central part and Jet fans at the entrances
83
IRC:SP:91-2010
TIJNNEL
""\iII II
I\__
D
VENTILATION DUCTS
S~filllGING LEVEL
WALKWAY
........-+-·-- .. ' }1 1
SUPPLY OF
COllCIElt l't.YDIENT ~ ~· FRESH AIR
~::-=...... .., ~
SUCTION BY EXHAUST/FANS
84
IRC:SP:91-2010
Three types offans are used mainly for tunnel ventilation. They are axial flow, centrifugal
flow and propeller fans. The choice depends on flow and pressure characteristics to
match the ventilation needs.
A tunnel is a linear enclosed space, covered by ground all around. Thus even in broad
daylight or in a moonlit night, space inside a tunnel is always dark.
Purpose of a Road Tunnel is to create a user-friendly facility for smooth, efficient and
speedy movement of road traffic. None of these purposes would be met if a tunnel is
dark. Though vehicles would move with their own lights on , speed of traffic would get
red uced . It would create congestion and movement could be in fits and starts.
It is, therefore, necessary to create a well lit environment in side a road tunnel. The
environment should be comfortable to human eyes and should make driving easy.
Such environment is created by provision of various forms of Tunnel Lighting. The
choice wou Id depend on the shape, size and length of the tunnel . Provision of adequate
lighting helps the motorists avoid using bright head lights which could blind the motorists
coming from opposite direction in bidirectional tunnels. Also, some people experience
claustrophobia (fear of enclosed spaces) and good lighting helps alleviate this fear to
some extent.
85
IRC:SP:91-2010
suitably designed lighting conditions at the entry and exit areas of the
tunnel and the portion of the tunnel in between these areas.
Access Zone
Threshold Zone
It is the first zone next to the entrance to a tunnel. In the Threshold Zone,
the intensity of lighting is gradually adjusted from that outside the entrance
to that in the beginning of the transition zone.
Transition Zone
It is the zone next to the Threshold Zone. In the Transition Zone, the intensity
of lighting is gradually adjusted to that in the Interior Zone.
Interior Zone
86
IRC:SP:91-2010
It is the zone beyond the Interior Zone and between/before the exit portal of
the tunnel. In the Exit zone, the intensity of lighting is gradually adjusted to
that in the portion just beyond the Exit Portal.
Since requirement of intensity in the Threshold, Transit and Exit Zones during day time
is different than that during night time, required intensity can be achieved by putting
the luminaries in two different circuits. Alternatively, luminaries that can give variable
output by use of dimmers can also be used.
Tunnel lighting has to be highly reliable. Tunnel lighting is required round the clock. It
is therefore necessary to install and maintain a 100 percent back-up system.
7.2.5 Maintenance
The amount of maintenance required would depend on where the tunnel is located,
the type and volume of traffic it is required to handle, quality of ventilation and the size
and grade of the tunnel itself.
The luminary units should be sealed so as to prevent entry of water from water sprays,
dust and smoke. The luminaries have to be cleaned frequently to clear dust and soot
that may collect on their outer surface. Proper routine maintenance programme should
be conceived and implemented.
Instead of waiting for the luminaries to fail before replacement, systematic replacement
and renewal programme should be conceived and implemented.
87
IRC:SP:91-2010
8.1 Introduction
The over all aim of operation and maintenance of a road tunnel shall be to maintain
a specified level of safety for the road users, with an optimal level of expenditure and
without adverse environmental effect. Decisions at the design stage as regards the
tunnel geometry, tunnel shape, maintenance access, type and extent of the plant and
equipment installed, and their configuration in operation, have a significant bearing
on the overall Operation and Maintenance aspects. Therefore, the maintenance shall
be planned and performed in such a way that the operational assumptions made at
the design stage remain validated throughout the long operational life of the road
tunnel. The Operation and Maintenance activities of the road tunnel shall be planned
to achieve the following objectives:
a) Safety of the road users
b) Ensuring free flow of traffic
c) Operational economy
d) Dealing with abnormal situations
Normal tunnel operation shall provide for maintenance of the structure, equipments
and installations, manning of control rooms , inspection and examination of vehicles .
The operating manuals for various activities, plants and equipment, overall
maintenance schedules shall be prepared in detail and shall be made available
to the operating staff. The overall scheme shall make provision for the periodical
replacement and improvement of equipment and installations, maintaining
appropriate stock of spare parts and special tools. Actions for imparting training
to operating staff, updating of techniques and updating of O&M manuals shall be
taken from time to time.
Preparation for dealing with accidents and abnormalities which have a greater impact
for tunnel due to the confined space and restricted access as compared to road in
open area shall be given special importance. Abnormal operational situations call for
a command structure to deal with the situation and deployment of rescue vehicles,
ambulances, signal system, communication facilities and fire fighting equipments.
88
IRC:SP:91-2010
b) Maintenance of tunnel:
Maintenance of tunnel covers preventive maintenance as well as
corrective maintenance as enumerated below;
• Preventive maintenance is the one which keeps the systems in a
good and safe condition preventing an operational breakdown. Pre-
ventive maintenance is safer, more effective and more economic
than maintenance based on repairing faults or damage. Without
preventive maintenance, the systems could become unsafe and/
or could only be brought back to a safe condition at high cost. The
preventive maintenance of tunnel covers routine periodic-based
maintenance as well as condition-based maintenance.
89
IRC:SP:91-2010
Preventive
Maintenanc Correc tive
Mainte n a nce
Inspection
C alend ar O peratio n Postpo~ment Imm ediate
based Time besed possible repair
Maintenanc Maint enance
Meas uremenV
Ass e s sment
Ad1ustment I
Overhauling
E valuation o f
entire s ystem
Evaluetlon
of system Repair I condition
condition replaceme nt
90
IRC:SP:91-2010
91
IRC:SP:91-2010
Pedestrians on carriageway
Animals in tunnel
iii) Weather hazards:
Fog
High winds
Dazzle from the Sun particularly for East - West alignment
Flood
Snow
iv) Human hazards: (vehicle occupants, operator and emergency ser-
vice staff)
Panic under stress,
Lack of knowledge (procedures, equipment, location, etc.),
Disregard towards instructions and advice,
Jamming communication channels,
Injury during rescue ,
Vandalism,
Terrorist activity.
The strategies for dealing with the various incidences shall be decided
taking into consideration available resources, procedures laid down in
the manuals and communications requirements of the various parties
involved and the needs of the road user. Response strategies shall
deal with the initial occurrence of a situation and also with any resulting
developments, as for example, a breakdown in a tunnel may lead to
initial local queuing which may further lead to traffic jam on the road for
long duration.
8.3.1 The authority responsible for operation and maintenance of the road on
which tunnel/s is constructed shall establish a separate organizational structure for
operation and maintenance of the tunnel/s. The operational organization shall be
responsible for the operation and maintenance, fire fighting and rescue procedures, as
well as traffic control operation. The operational organization shall also be responsible
for preparing and updating procedures, manuals, specifications, etc.
92
IRC:SP:91-2010
8.4 Documentation
In order to achieve the appropriate standards for the operation and maintenance of
tunnels it is essential that the operating manuals for equipment, maintenance schedules
etc. shall be prepared and shall be readily available for reference of the concern staff
of the operational organization. The manuals shall contain procedures to address a
whole range of scenarios. Each procedure shall contain a number of instructions to
be undertaken, each of which initiates an action in one of the manuals. The individual
manuals might cover the following aspects:
i) Administration manual
The administration manual contains personnel registers including the
competence, skills and training records for individuals. It shall clearly
93
IRC:SP:91-2010
94
IRC:SP:91-2010
in the maintenance and inspection manual. The manual shall also list
the regulations that apply to maintenance work, like for instance:
• During hours with heavy traffic;
• If nuisance is caused to others (e.g. acceptable noise levels during the
night hours, smoke and dust regulations , etc);
• Night time work;
• Traffic regulations; etc.
vi) Safety Manual
This manual shall include all the procedures and instructions that are
to be followed in operation and maintenance of tunnel.
8.5.1 Tunnel maintenance activities both planned and unplanned shall be carried
out by proper traffic management. The tunnel shall be equipped in such a way that
as many maintenance operations as possible can be carried out off-site in work shop
or other places where it is not necessary to interference with traffic flow in any way.
To plan maintenance and operation that affect vehicle traffic, as these may be cause
of accidents involving user of the tunnel or the workers operating the maintenance
equipments, certain precautions as enumerated below shall be taken for safety of
traffic as well as maintenance staff.
• Maintenance staff working in the tunnel shall be protected from errant
vehicles entering into the tunnel. For that purpose warning signs shall
be posted at appropriate location and one driving lane shall be closed
completely by barriers and providing proper warning signage/signals
well in advance for safety of coming traffic.
• The closer of lane shall be indicated before the road enters tunnel.
Variable messages, traffic signs, barriers shall be used for the
purpose.
• In twin tube tunnel one tube can be closed for maintenance while
temporarily bi-directional traffic flow allowed in other tube.
8.5.2 Safety equipments that shall be readi ly available in Tunnel are listed
below:
Supervision and alarm equipments:
• CCTV
• IDS (incident detection system)
95
IRC:SP:91-2010
• emergency telephones
• fire alarms
• automatic fire detectors
• instruments for measuring visibility
• instruments for measuring gas concentrations
• sensors for doors, alarm boxes
• devices for detecting vehicle height
• Emergency power UPS
Escape routes and communication:
• emergency doors
• radio transmission
• com munication equipment
public address system
• escape route signs
smoke-free escape routes
• emergency lighting
• variable message signs
Traffic regulation equipments:
Lane signals
• Blinking red light
Variable text signs
Barriers
• Emergency Road Sign
Fire fighting equipments:
• hand-operated fire extinguishers
• fire hydrants
• water reservoir
• fire-hose coil with supply
sprinkler (if used)
• closed drainage system
• fire engines (if owned)
96
1RC:SP:91-2010
Depending upon the importance of the tunnel, length of the tunnel some restrictions
and additional facilities as enumerated below shall be considered.
For safety reasons speed limit within road tunnel may be imposed taking into
consideration geometric design of the tunnel. Generally speed within tunnel is
marginally lower as compared to speed on open road.
97
IRC:SP:91-2010
Annux-A
(Clause 1.4)
TERMINOLOGY
Adit: A tunnel driven from the surface to create additional working faces for the main
tunnel or for access, ventilation, or emergency evacuation.
Controlled Blasting: Blasting operation carried out to keep vibrations within specified
limits and to prevent uncontrolled flying away of rock fragments .
Cover: The perpendicular distance to nearest ground surface from periphery of the
tunnel.
Drift: A near horizontal tunnel of a small cross-section and short length driven either
from surface or from underground face for exploration or any purpose.
Drill Jumbo: A rail or tyre mounted equipment on which one or more drill booms are
mounted to facilitate faster deployment of the drills.
Drilling Pattern: An arrangement showing location, direction and depth of the blast
holes to be drilled into the face of tunnel.
Egress: A small parallel tunnel/passage or adit leading to outside open space for
emergency escape of people.
98
IRC:SP:91-2010
explosive substance having explosive power equal to or greater than black powder.
Forepole : Steel rods/sections, pointed boards or pipes driven in the roof ahead of the
face prior to excavation. Grouted pipe forepoles are used as Spiles.
Full face excavation: Excavation of the face of tunnel carried out in one operation
instead of by 'Heading and Benching' or 'Multi-drifting'.
Half Tunnel : Tunnel section on steep hill slope with one side remaining uncovered
and exposed on the valley side.
Heading and Benching : A Tunnelling method in which 'Heading' i.e. the top section
(generally up to around springing level) is excavated first, followed by 'Benching' i.e.
removal of lower portion.
Look-out: The angle with respect to the centerline of a tunnel at which the
peripheral holes are required to be drilled so as to provide adequate space for drilling
equipment.
Minimum Excavation Line: The line within which no unexcavated material of any kind
is permitted to remain . This line could vary along the length of the tunnel depending
upon strata.
Mucking: The operation of removal of excavated material and haulage for disposal.
NATM : New Austrian Tunnelling Method (NATM) is a philosophy, which takes into
account inherent properties of the rock mass and suggests methods and supporting
measures for the newly exposed rock mass in conjunction with continuous
monitoring.
99
IRC:SP:91 -2010
Overbreak: The portion excavated/dislodged beyond the desired excavation line i.e.
'Payline'. This could be due to natural/geological reasons or faulty workmanship.
Pay Line: An assumed line (beyond minimum excavation line) as specified in the
contract which governs payment of items of work.
Probe Holes: Holes of suitable diameter and length drilled into the face or around the
tunnel for assessment of the strata.
Q: Rock Mass Quality Index based on geomechanical properties of the rock mass
used in the empirical "NGI - Q" system for rock mass classification for design of ground
supports in under ground works.
RMR: Rock Mass Rating based on geomechanical properties of the rock mass used
in the empirical "CSIR - RMR" system for rock mass classification for design of ground
supports in under ground works.
Shaft: A linear well like excavation/structure, usually vertical but may be at angles up
to 60° from vertical.
Shotcrete: Plain or Fiber Reinforced Concrete (with small size aggregates) shot i.e.
sprayed on any surface.
Specific Drilling : Quantum of drilling expressed in meters per cubic meter of rock
excavated in an excavation cycle.
Squeezing Rock: A type of rock mass condition in which the rock mass has time
dependent plastic deformation when exposed.
Stand-up-Time: Time duration for which newly exposed periphery of a tunnel is able
to stand on its own without exhibiting significant deformation/distress .
100
IRC:SP:91-2010
stemming: Inert material packed near the open end of a blast hole to lock the explosive
charge in place.
Tunnel Lining: Concrete, Shotcrete or any other material installed over exposed
surface.
Tunnel Portals
Excavated Portal: Entrance location where the 'open/approach cut' ends
and full tunnel section starts.
Tunnel Portal: A facade structure surrounding tunnel opening and extending
upto adjacent sides of 'Open/Approach Cut', constructed in front of the
excavated portal. Where constructed at the end of 'Cut and Cover' portion,
it is termed as 'False Portal'.
Tunnel Support: Shotcrete, Steel ribs, Rock bolts/anchors or Tunnel lining placed to
support the excavated periphery of a tunnel.
Working Face: Blind end inside a tunnel from where next 'working cycle' starts.
101
:;o
Annex-B ()
Implementation Supervision
1) Transport of Heavy equipments (above Source to Contractor Engineer's Random checks Visual inspection
construction machinery 15-20 tonnes), crawler-mounted construction Representative record
-Damage to road machinery and steel wheel sites
surface mounted rollers shall be mobilized
to construction site without causing
any hazardous condition and any
~ damage to network roads enroute
0
N to site. Such heavy equipments
shall be preferably mobilized on
multi-axial heavy trucks.
2) Construction traffic - Movement of tunnel construction Network Contractor Engineer's Routine Visual Inspection
A • Damage to network machinery shall not cause damage roads used Representative inspection record
roads to network roads and shall always for the
be maintained in good condition. construction
B • Compliance to road The driver shall be trained At all Contractor Engineer's Monthly/ No incident or
safety rules regarding traffic rules, safer driving construction Representative Random checks accident record with
practice, road courtesies etc. sites traffic police and in the
Copies of valid driving license shall driving license
be furnished.
1
Sr. Environmental Mitigation Measure Location Responsibility Supervision Performance
No. Issue Frequency Indicator
Implementation Supervision
c- Large Volume of Mass movement of vehicle in and At all the Contractor Engineer's Fortnightly/ Visual inspection,
Construction Traffic out of construction site such as roads Representative Random checks plan of vehicular
debris removal vehicles, machinery used for movement, record
and material transportation construction of the transport
vehicles, RMC Trucks, etc. shall vehicles and the
be preferably planned during non- transport network
peak hours. Movement of vehicles roads.
through congested roads, narrow
lanes having sharp turning radius
~
shall be avoided and instead
0
(..V alternate road networks available
shall be preferred. All Over-
Dimensioned cargo/ elements
projecting out and beyond the
truck outline shall be flagged
with red flags in the day time and
with red lamps in the night time.
Assistance from traffic Police shall
be sought wherever required
D - Damage to road Vehicles exiting from construction At all the Contractor Engineer's Weekly/Random Visual inspection of
surface site on to public roads shall have roads Representative checks the public roads
their tyres washed to remove all used for
;:u
mud clinging to tyre surface construction ()
(f)
:9
co
~
I
N
0
~
0
;::o
()
(./}
\)
Sr · 1Environmental
No. Issue
I Mitigation Measure I
Location
I Responsibility
I Supervision
Frequency
Performance
Indicator
c.o
_..
I
"'
0_..
1 0
Implementation Supervision
3) I Parking I
construction Parking shall be in such a way
that traffic flow along the road is
At all the
roads
Contractor Engineer's Weekly/Random Visual inspection
Representative checks
vehicles record of the transport
not hampered. Heavy machinery used for roads and Parking
equipment or parts thereof which construction places
are suspended or held aloft by the and parking
use of slings, hoists or jacks shall be areas
blocked or cribbed to prevent falling
or shifting. Bulldozers, scraper
blades, Loaded buckets, dump
__...
0
~ I I I
bodies and similar equipments of
construction machinery parked
outside the project site or in areas
of considerable public movement
and near children playing area,
shall be fully lowered or blocked.
All controls shall be in neutral
position and motors/Engines
stopped and parking brakes set.
4) I Air Pollutants Construction site should be At all Contractor Engineer's Weekly Visual inspection
Emissions adequately watered periodically to construction Representative record of dust cloud
Air pollutant emissions minimize fugitive dust generation. sites at the site, sprinkling
are regulated under frequency
Rule 115 of CMV Rules,
2000.
1
Sr . Environmental Mitigation Measure Location Responsibility Supervision Performance
No. Issue Frequency Indicator
Implementation Supervision
All trucks/dumpers carrying Source to Contractor Engineer's Weekly Visual inspection
construction material prone to construction Representative record of dust cloud
create dust pollution should be sites at the site, sprinkling
covered during transportation. frequency.
All equipmenUvehicles should be At project Contractor Engineer's Quarterly Equipment
kept in good state of repairs. sites Representative maintenance records
to be maintained
~
0 All vehicles registered under At project Contractor Engineer Quarterly A copy of Pollution
01
Central Motor Vehicle Rules, 2000 sites Under Control (PUC)
shall have valid certificate issue certificate.
by authorized agency throughout
their deployment period at
construction site. A Separate or
master register of vehicle's shall
be maintained at construction site
office containing details of vehicles
under deployment and a copy of
PUC certificates
;:o
()
'ch
"'{)
(0
.....
I
"'.....
0
0
;u
()
u,
-0
S r · 1Environmental Mitigation Measure location Responsibility Supervision Performance co
~
No. Issue Frequency Indicator I
tv
0
Implementation Supervision ~
5) Noise Emissions All in-built noise-silencing device At construction I Contractor Engineer's Monthly Noise monitoring
such as silencers and mufflers sites Representative report generated
shall be maintained and any from any equipment,
Under Environment defective device shall be promptly Vehicle or machinery
(Protection) Rules, 1986 replaced. Equipment's shall be
maintained as per manufacturers
(Schedule VI, Part E)
guidelines to reduce tonal
the noise generation components, frequency
standards applicable for modulations or impulses, which
will increase the annoying effect
construction equipment,
of any noise, generated.
->.
0
machinery and vehicles.
CJ)
Implementation Supervision
Implementation Supervision N
I
0
~
have fallen off from the dumpers 0
during transit.
Before commencing the muck
stacking operations, a retaining
wall of suitable design shall be
constructed for a suitable height
to retain the muck and prevent 11
from spreading out to undesirable
locations, particularly in slopes
to prevent the muck from sliding
down to the river or valley or to
~
any undesirable locations The
0 retaining wall shall have sufficient
co
weep holes to drain out water
retained in the muck arising from
atmospheric precipitations, etc
so as to preserve the safety of
the stack as well as to collect
the muck-contaminated water in
collection pits. Ring drains shall be
constructed all-round the retaining
walls to collect the drain water and
conduct the same to collection
pits from where it shall be led off
to holding ponds. Contaminated
water shall not be allowed to
drain out of the Muck Disposal
Area without treatment. . Suitable
landscaping shall be done
1
Sr. Environmental Mitigation Measure Location Responsibility Supervision Performance
No. Issue Frequency Indicator
Implementation Supervision
over the muck piles for better
aesthetics and for proper
preservation of the slopes/pile.
8) Labour Camps, Health Construction of labour camps shall At construction Contractor Engineer's At start of work Visual inspection,
and hygiene be located away from the nearest sites Representative & Monthly Records
habitation to avoid conflicts and thereafter
stress over infrastructures facility
The contractor shall provide, erect
& maintain necessary temporary
...... living accommodation, ancillary
0
<.O facilities such as toilet blocks,
potable water supply, canteen etc.
as per standards set by various
acts (Labour Act 1951) Contract
Labour Act 1970, Construction
Worker Act 1996. Construction
Workers Rules 1998.
Annex-C
(Clause 3.3.3.3)
CORE LOG-I
Client: Drill Hole No. 1 Date:
Site:
Operator Name: TopR.L- __m _ _ Diameter of bore (mm):- 100 & Nx.
'E
c
~
8 ._
Q) - E
0 u
'E
0
Q)
713
~ .~
20...
Q)
:S
-~
-o_
E E
o -
~
0
~ ~*'
u - 0 u u - .Ero :t:: Q) Q) = c
:::J
er: 0 CJ)
z Q) ~ 0
.Q. :f§ 0 u > ~ 0 Petrographic
=c
0
z
Q)
u -0
..c >
-0
Q) Q)
u
a:: LL -0 co .~
_o... 8 o~ Remarks
-~ Description
0
~
0
(ij
-~
(f)
a. -oi 0E
c Q)
~ er:
Q)
a::
0
:S
Ol
cQ)
-o LU
Q)
._
2
c
._
Q)
~
-
O>
c
~>
Q)
-...,
ro
c
·5
Q)
._
0
u
Q)
er:
~
0
~ c
u Ol
0 ·-
er: :g
0
<l;
(_)
_J ~ _J
(.)
1 2 3 4 5 6 7 8 9 10 11 12
0.00 OVER
to BURDEN
2.00
2.00 1 to4 21 1 2 J H • 42 NIL All joints are Total drill water
to 2 5 J H stained with loss throughout
3.50 3 5 J H iron oxide the length of
4 9 J H and calcium the bore drilled.
carbonate
3.50 5 to 99 5 29 J v 66 49 From P.No. • R.L. to be
to 15 6 13 J H 1to96 calculated &
5.00 7 11 J 45' porphyritic Filled
8 2 J v basalt with
9 2 J v green infillings
10 6
11 10
12 6
13 10
14 6
15 4 J v
5.00 16 to 10 16 10 J H 68 23
to 30 2 17 6 J H
6.50 18 5 J 80'
19 3 J H
20 7 J 45'
21 3 J v
Note: The information filled above is typical for guidence J - Joint, V - Vertical joint, H -
Horizontal joint.
111
IRC:SP:91-2010
Annex-D
(Clause 3.4.3)
TUNNEL INSTRUMENTATION
Convergence Measurement
The measuring points shall consist of the convergence bolts made of stainless steel
pins mounted on a short reinforcing bar grouted into predrilled hole.
The tape extensometer with steel tape of a low thermal coefficient shall be set between
the opposite convergence bolts. The convergence shall be read on a digital gauge
with a resolution of 0.01 mm.
The convergence bolts shall be installed within the heading zone after the installation
112
IRC:SP:91-2010
of supports. At the beginning, the measurement shall be carried out daily. Later, weekly
readings shall be taken for several months up to the cessation of any movement but
latest when the placing of the concrete lining commences.
The convergence measuring tape and the digital gauge shall be calibrated on their
corresponding calibration devices before and after each measurement. Digital readout
shall be in metric units.
11 3
IRC:SP:91-2010
114
IRC:SP:91-2010
115
IRC:SP:91-2010
Appendix-I
(Clause 4.4.2)
1. Characteristics of Rock
Table 1 Weathering
Fresh Rock fresh, crystals bright, few joints may show slight staining. Rock rings under hammer if
crystalline.
Very slight Rock generally fresh, joints stained, some joints may show clay if open crystals in broken face
show bright. Rock rings under hammer if crystalline.
Slight Rock generally fresh-joints stained and discolouration extends into rock up to 25 mm. Open joints
contain clay. In granitoid rocks some occasionally feldspar crystals are dull and discoloured.
Crystaline rocks ring under hammer.
Moderate Significant portions of rock show discolouration and weathering effects. In granitoid rocks must
feldspar are dull and discoloured; same show clayey. Rock has dull sound under hammer and
shows significant loss of strength as compared with fresh rock.
Moderately All rock except quartz discoloured or stained. In granitoid rocks all feldspars dull and discoloured
Severe and majority show Kaolinization. Rock shows severe loss of strength and can be excavated with
geologist's pick. Rock goes "clink" when struck (Saprolite).
Severe All rock except quartz discoloured or stained. Rock "Fabric" clear and evident but reduce in
strength to strong soil. In granitoid rocks all feldspars Kaolinized to some extent. Some fragments
of strong rock usually left (Saprolite).
Very Severe All rock except quartz discoloured or stained. Rock "Fabric" discernible but mass effectively
reduced to "soil" with only fragments of strong rock remaining.
Complete Rock reduced to "soil". Rock "fabric" not discernible or discernible only in small scattered locations.
Quartz may be present as dyke or stringers.
116
IRC:SP:91 -2010
117
IRC:SP:91-2010
118
IRC:SP:91-2010
Appendix-II
(Clause 4.4.2)
DATA SHEET FOR GEOMECHANICAL CLASSIFICATION OF ROCK MASSES
AND ASSESSMENT OF ROCK MASS RATING (RMR) (AFTER BIENIAWSKI 1989)
119
IRC:SP:91-2010
Appendix-Ill
(Clause 4.4.3)
DATA SHEET FOR GEOMECHANICAL CLASSIFICATION
OF ROCK MASSES FOR
ASSESSMENT OF TUNNELLING QUALITY INDEX " "
(AFTER BARTON ET AL 1974)
Q-system for rock mass classification (Barton)
Q = ROD 0 Jr 0 Jw (EQ 1)
Jn Ja SRF
1) Rock Quality DesiQnation RQO
A Verv Poor 0-25
B Poor 25-50
c Fair 50- 75
D Good 75-90
E Excellent 90-100
Note: i) Where RQD is reported or measured ass 10 (including 0), a nominal value of 10 is used to evaluate Q.
ii) RQD interval of 5, i.e., 100,95,90,etc., are sufficiently accurate.
21 Joint Set Number Jn
A Massive, no or few joints 0.5 -1
B One joint set 2
c One ioint set plus random ioints 3
D Two ioint set 4
E Two ioint set plus random ioints 6
F Three joint set 9
G Three joint set plus random 101nts 12
H Four or more ioint sets heavilv jointed 15
J Crushed rock earthlike 20
Note: i) For intersections, use ( 3.0 x J0 ). (ii) For portals, use ( 2.0 x J0 ).
121
IRC:SP:91-2010
123
IRC:SP:91-2010
APPENDIX-IV
(Clause 4.4.2)
EXAMPLE OF DETERMINATION OF 'RMR' & 'Q' VALUES & SUPPORT
REQUIREMENTS
(Refer IS 13365: Part 1 & 2, 1992)
A proposed Irrigation Project involves construction of two 'D' shaped parallel tunnels,
each about 690 m. long connecting two reservoirs. The alignment of the tunnels is
almost in N S Direction. Width of each Tunnel is 11 m. wide with semi-circular roof.
Clear gap between the two tunnels is 33 m. The tunnels are to be excavated by
Conventional method of Drilling and Blasting.
Local Geology:
Geological Mapping along the proposed alignment indicated that the alignment is
covered thin layer of soil and scree material underlain y moderately weathered to
fresh Charnockite and Gneiss.
Sub-surface Exploration:
Lithological Longitudinal Section along the alignment indicated that Entry Channel will
have to be constructed from Ch. 30 m to Ch. 60 m and Exit Channel from Ch. 750 m to
Ch. 790 m Thus the tunnel is expected to stretch between Ch. 60 m. and Ch. 750 m.
Engineering Properties of the Rock Mass at the Tunnel were expected to be generally
as follows:
Particulars Value
Unit Weight of Rock Mass 2400 kg./cum.
Specific Gravity 3.1515
Uniaxial Compressive Strength 108.9 MPa
Tensile Strength [Brazilian Test] 13.71 MPa
Modulus of Elasticity 21 .27 GPa
Poisson's Ratio 0.1963
Angle of Friction 43°
Porosity 0.79%
Average Vertical Stress at Tunnel Grade 3.6 MPa
124
IRC:SP:91-2010
In order to arrive at preliminary characterization of the rock mass, the tunnel length
was divided in three reaches as follows:
From Ch. m. To Ch. m. Lenath m. Particulars
60.00 90.00 30.00 Inside Entrv Portal
90.00 720.00 630.00 Inner Tunnel
720.00 750.00 30.00 Inside Exit Portal
Rock Mass Characterization of the tunnel medium has been carried out as per ' RMR '
- Rock Mass Rating [Bieniawski] and' Q "-Rock Mass Quality [Barton]. The mechanics
of arriving at the 'RMR' and 'Q' is indicated in the following Tables
125
;a
Appendix-V ()
(Clause 4.5.1 (c) (f)
-u
(6
SUPPORTS IN THE TUNNEL -"
I
N
Immediate Immediate Immediate Roof Immediate Support for Ultimate Roof & Side Support for 0
-"
Roof Support for Roof Support for Support for 18 m. Benching 18 m. [Full] Section 0
Average Category of 6 m. Wide HeadinQ 12 m. I 2/3 rd l Width !Full] Width
RMR&Q Support Rock Bolt Shotcrete Rock Bolt Shotcrete Rock Bolt Shotcrete Rock Bolt Shotcrete MB 200 Rib Support
Pattern Thickness Pattern Thickness Pattern Thickness Pattern Thickness
m mm m mm m mm m mm mm
20 [ 0.07] Immediate 1.5 x 1.5 100
20 r 0.011 Immediate 1.5x1 .5 150
20 f 0.01 J Immediate 1.S x 1.S 1SO 1.S x 1.S 1SO
20 [ 0.071 Ultimate Placed at 500 mm Spacing &
Embedded in 350 mm. thick M 20
Concrete CoverinQ full Overt & Invert
....... 30 I 0.211 Immediate 1.S x 1.S 100
N 30 [ 0.21] Immediate 1.5 x 1.5 150
(j')
30 [ 0.21] Immediate 1.5 x 1.5 150 1.5 x 1.5 150
30 [ 0.21 ] Ultimate
40 I 0.64 J Immediate 2.0 x 2.0 100
40 r0.64 I Immediate 2.0 x 2.0 150
40 r o.64 J Immediate 2.0 x 2.0 150 2.0 x 2.0 1SO
40 [ 0.64 J Ultimate
so I 2.00 I Immediate 2.0 x 2.0 50
so I 2.001 Immediate 2.0 x 2.0 100
so r 2.001 Immediate 2.0 x 2.0 100 2.0 x 2.0 100
so I 2.00 I Ultimate
60 [ 6.00 l Immediate Spot Nil
60 r6.oo 1 Immediate Spot 100
60 l 6.oo I Immediate 2.5 x 2.5 100 2.S x 2.S 100
60 r 6.00 I Ultimate
IRC:SP:91-2010
CODES OF PRACTICE/ACTS/RULES
IS 4081 1986 Safety Code for Blasting and other related Blasting Operations.
IS 823 1964 Code of Practice for Manual Metal Arc Welding of Mild Steel.
IS 816 1969 Code of Practice for Manual Metal Arc Welding for General
Construction in Mild Steel.
127
IRC:SP:91-2010
IS 817 1966 Code of Practice for Training and Testing of Metal Arc Welder
[Revised] .
IS 800 2007 Code of Practice for Use of Structural Steel in General Building
Construction.
IS 13365 1992 Quantitative Classification Systems for Rock Mass (Part 1 & 2)
PIARC Guidelines
Report of PIRAC Committee on Good Practice for the Operation and Maintenance of
Road Tunnels (CS) -2005
128
. ··:.""'
1:
J