282109-F-WaveOne Delhi
282109-F-WaveOne Delhi
282109-F-WaveOne Delhi
One
A Story of TransfEr GirdErs
By Anantha Chittur, P.E., S.E., and Steven M. Baldridge, P.E., S.E.
Basement construction.
26 STRUCTURE magazine
checks for deformation com-
patibility of the slab-column
gravity system. Shear walls
at the cores provided lateral
force resistance.
The design is in accordance
with India’s National Building
Code (NBC) and other appli-
cable local codes. Due to the
building’s height and unique
geometry, a wind tunnel
study was conducted to deter-
mine the structural loads and
occupant comfort.
S E P T E M B E R 2 0 21 27
extending between Levels 14 and 15. The total length
of the transfer girder on Level 14 is 310 feet.
The building’s characteristic rectangular aper-
ture measures 200 feet by 103 feet and extends
between Levels 15 and 32. The aperture is framed
at the top by offices between Levels 32 and 41.
The top of the building steps up from one end
of the building to the other. The structure above
the aperture is supported by three profiled post-
tensioned girders that span 112 feet between each
tower. These sizeable concrete transfer girders were
partly conceived due to the contractor’s desire to
use a tried and tested construction methodology
Aperture transfer girder. instead of introducing structural steel trusses. The
contractor’s message to the design team was, “No
the slabs. The conventional practice was to consider the concrete Discovery Channel stuff, please.” However, the concrete option
clear cover of 1⅜ inches to the post-tensioning duct even though came with its own challenges from transfer girders that are 3.3
the tendons are grouted and are often higher in the duct at mid- to 5 feet wide and constructed at 200 feet in the air. Due to the
span. BASE collaborated with the PT supplier to determine the immense weight of the three transfer girders and the associated
elevation of the tendon within the duct, thereby gaining valuable formwork requirements, the girders were shaped to reduce overall
drape in the tendon profile while still meeting the clear cover weight such that it was 20.5 feet deep in the middle to maximize
intent of the code. drape and stiffness for the 112-foot span and 15 feet at the ends
to satisfy shear requirements. Despite the shape optimization, the
weight of wet concrete during placement would be problematic.
Transfer Girders Galore BASE worked with the contractor and PT supplier to construct
At Level 4 of the podium, above three levels of retail, the floor area the beam in two segments with a horizontal construction joint with
was allocated for cinemas that required 56 feet by 84 feet of double- layered tendons that could be independently stressed. Once stressed,
height, column-free space for each of the five cinemas. This could tendons in the lower half were designed to support the weight of the
only be achieved through a five-span shallow post-tensioned transfer upper half during construction. Tendons in the second half were
girder that spanned 56 feet while supporting seven levels of parking, profiled such that maximum drape was utilized for final loading.
one level of office, and one level of outdoor amenities. A portion of The overall process was done in six stages: three bottom segments
the office tower also hovered above the cinemas, requiring a different and three top segments.
strategy to transfer the tower columns.
The limited height available over the cinemas required a double
transfer beam to support the office tower columns spanning between
Conclusion
Levels 15 and 41. This was achieved by introducing one-story-deep A 2 million square foot high-rise project with multiple occupancies
transfer girders between Levels 14 and 15 and using the transfer beam often comes with many challenges that require creative engineer-
over the cinemas to only support the podium loads. ing solutions and close collaboration with the architect and other
Due to the unique nature and length of the 280-foot multi-span consultants. Post-tensioning often helps to simplify many of these
transfer girder over the cinemas that were required along two problems by allowing for the removal, transfer, and shift-
column lines, the design team collaborated with the PT supplier ing of columns and allowing slabs to span longer where
to stress the tendons outside the cross-section of the girder. This required, giving the architect the desired flexibility.■
facilitated pour strips and allowed the entire girder to be con-
structed simultaneously while also providing intermediate stressing
to minimize post-tensioning losses. The external stressing strategy Anantha Chittur is a Senior Associate at BASE and is based in its Chicago
is often used in bridges but is not very common in buildings. BASE office. (achittur@baseengr.com)
worked closely with the PT contractor and formwork subcontrac- Steven M. Baldridge is President at BASE and is based in its Honolulu
tor to minimize the number of reshoring levels by continuing office. (sb@baseengr.com)
the column removed in the cinemas as a low-strength sacrificial
column supporting the transfer girder. This strategy enabled the
early removal of beam formwork and three levels of reshoring Project Team
below the transfer girder.
Owner: Wave Infratech
Due to the zero lot line construction, the parking ramps are integrated
Structural Engineer of Record: BASE
within the building footprint. Two octagonal spiral ramps, one on
Architect of Record: Nostri Architects
each side of the building, provide vertical circulation for the parking
Design Architect: BBG-BBGM
levels. The ramps stop at the underside of Level 13 with 27 levels
General Contractor: Leighton-Infra Joint Venture
above it. Like the columns transferred over the cinemas, the tower
Wind Tunnel Consultant: RWDI
columns above the ramp are supported on 6-foot-deep transfer girders
28 STRUCTURE magazine