Chapter 5 Coffer Dam
Chapter 5 Coffer Dam
Chapter 5 Coffer Dam
INTRODUCTION
• Cofferdams are temporary enclosures to keep out water and soil so as to permit dewatering and
construction of the permanent facility (structure) in the dry.
• Removal of the cofferdam must be planned and executed with the same degree of care as its
installation, on a stage-by-stage basis. S heet piles extending below the permanent structure are often
cut off and left in place, since their removal may damage the foundation soils adjacent to the
structure.
• In cofferdam construction, safety is a paramount concern, since workers will be exposed to the
hazard of flooding and collapse.
TYPES OF COFFERDAM:
(a) Earthen cofferdam
(b) Rock-fill cofferdam
(c) Single-walled cofferdam
(d) Double-walled cofferdam
(e) Crib cofferdam
(f) Cellular cofferdam (Circular or diaphragm type)
Crib cofferdam
(f ) Cellular cofferdam:
This type of cofferdam is mostly used for de-watering large areas in places where the depth of
water may be of the order of 18 to 21 m. Cellular cofferdams are mostly used during the
construction of marine structures like dams, locks etc. Cellular cofferdam is made by driving
straight web steel sheet piles, arranged to from a series of inter-connected cells.
(i) Circular type cellular cofferdam.
(ii) Diaphragm type cellular cofferdam.
COFFERDAM COMPONENTS:
• Sheet piling
Sheet piling is a manufactured construction product with a mechanical connection “interlock” at
both ends of the section. These mechanical connections interlock with one another to form a
continuous wall of sheeting.
• Bracing frame
• Concrete seal
The typical cofferdam, such as a bridge pier, consists of sheet piles set around a bracing frame
and driven into the soil sufficiently far to develop vertical and lateral support and to cut off the
flow of soil and, in some cases the flow of water.
5. COFFERDAM CONSTRUCTION SEQUENCE:
For a typical cofferdam, such as for a bridge pier, the construction procedure follow the listed
pattern.
1. Pre-dredge to remove soil or soft sediments and level the area of the cofferdam
4. Set steel sheet piles, starting at all four corners and meeting at the center of each side
5. Drive sheet piles to grade
6. Block between bracing frame and sheets, and provide ties for sheet piles at the top as necessary
7. Excavate inside the grade or slightly below grade, while leaving the cofferdam full of water