Filling with Gravel in trenches, sides of foundations and basement with initial lead in
BLDCSTN - layers not exceeding 15cm thick, consolidating each deposited layer by watering and
2-8 4 ramming including all operational, incidental, labour charges, seignorage charges, hire
Page - 18 charges of T & P etc., complete for finished item of work. APSS No.309 & 310
Data for 2015-2016 SSR Amendments to A.P.Revised Standard Data-2009
Unit :6 Cum
a.Labour
Mate Day 0.00 0.00 Day 0.00
Mazdoor(Unskilled) Day 0.31 525.00 Day 162.75
Add area Allowance 40% 162.75 65.10
b. Material
Gravel cum 6.00 511.40 cum 3068.40
Water Charges (Rural)-M-189 (b) Kl 0.01 3231.15 Kl 32.31
3328.56
c) Add 13.615% Overhead& Contracorst profit on
13.615% 3328.56 453.18
a+b
Cost for 6 Cum = (a+b+c+d) 3781.75
Rate per 1 Cum 630.29
Rate per cum Say 630.30
Plain Cement Concrete (1:5:10) proportion (cement: fine aggregate: Coarse aggregate)
using 40mm size Hard Broken Granite (IS383, 1970) machine crushed metal from
approved quarry including cost and conveyance of all materials like cement, sand,
BLDCSTN -
coarse aggregate, water etc. to site, mixing concrete in concrete mixer including , sales
3-7 7
& other taxes on all materials, all operational, incidental, and labour charges such as
Page - 21
laying and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item of work (APSS No. 402) for
Levelling Course and Flooring Bed
Unit : Cum
a.Material
Cement Kg 129.60 4220.00 MT 546.91
Coarse aggregate 40mm Cum 0.90 1833.80 Cum 1650.42
Fine Aggregate (Sand) Cum 0.45 2165.00 Cum 974.25
3171.58
b. Machinery
494.90
c.Labour
Mason 1st Class Day 0.10 630.00 Day 63.00
Mazdoor (Unskilled) Day 1.39 525.00 Day 729.75
Add area Allowance 40% 792.75 317.10
1109.85
Sub-Total :: 4776.33
d. Add 13.615% Overhead&
13.615% 4776.33 650.30
Contractors profit (a+b+c)
Cost for 1 cum (a+b+c+d+e) 5426.63
Rate Per Cum Say 5426.65
Unit : 10Sqm
a.Materials
Base coat in CM(1:6) 16mm
thick
Cement Kg 40.80 4220.00 MT 172.18
Fine Sand (Screened) Cum 0.17 2260.000 Cum 384.20
Top coat in CM(1:4) 4mm
thcik
Cement Kg 14.40 4220.00 MT 60.77
Fine Sand (Screened) Cum 0.04 2260.000 Cum 90.40
707.54
b.Labour
Mason 1st Class Day 0.630 630.00 Day 396.90
Mason 2nd Class Day 1.470 565.00 Day 830.55
Mazdoor (unskilled) Day 3.900 525.00 Day 2047.50
Add area Allowance 40% 3274.95 1309.98
4584.93
Rate per 10 Sqm 5292.47
Brick Masonry in superstructure with CM (1:8) prop with Flyash Cement solid blocks
BLDCSTN- of size 290 x 150 x 140 mm, for manufacturing of flyash solid blocks using flyash of 80
5-17 59 kgs, cement of 15 kgs. Gypsum of 5 kgs. and stone dust with a compresive strength not
Page.35 lessthan 50 kg/sqm including cost and conveyance of all materials, labour charges,
seiniorage charges, scaffolding and curing etc., for Superstructure Walls.
Unit : Cum
a.Material
No of blocks required for one 103.4482759
Nos 104.00 35462.38 1000 3688.09
cum of Masonry
Cement for CM (1:8) Prop Kg 18.00 4220.00 MT 75.96
Sand for CM (1:8) Prop Cum 0.10 2165.00 Cum 216.50
3980.55
b.Labour
Mason 1st Class Day 0.420 630.00 Day 264.60
Mason 2nd Class Day 0.920 565.00 Day 519.80
Mazdoor (Unskilled) Day 2.800 525.00 Day 1470.00
Add area Allowance 40% 2254.40 901.76
3156.16
Rate per Cum 7136.71
Unit : 10Sqm
a.Materials