Drainage
Drainage
Drainage
Estimate of Cost
Civil Works
Earthwork in excavation
RCC
Providing and laying in position
specified grade of reinforced
cement concrete excluding the
cost of
centring,shuttering,finishing and
reinforcement-All work puto
5.33A.1 + plinth level.1:1:5:3(1 cement: 1.5
3 418.48 Cum. 4854.5 2,031,511.16
5.33B1 coarse sand:3 graded stone
aggregate
20 mm nominal size)
Brickwork
Total= 9,525,062.82
Measurment Sheet
Civil Works
Earthwork in excavation
PCC
Providing and laying in position
cement concrete of specified
grade For branch IC
exluding the cost of centring and 2.26 2.26 0.1 75 38.31 Cum.
chamber
2 4.1.3 shuttering-all work upto plinth
level. 1:2:4(1 Cement: 2 coarse
sand:4 graded stone aggregate 20 For hume pipe 800 2.26 0.1 1 180.8 Cum.
mm at branch road
nominal size)
Total= 219.11 Cum.
RCC
Providing and laying in position
specified grade of reinforced
cement concrete excluding the
cost of Below
2.26 2.26 0.2 75 76.61 Cum.
centring,shuttering,finishing and For branch IC Chamber
reinforcement-All work puto chamber
Cover Slab 1.96 1.96 0.2 75 57.62 Cum.
plinth level.1:1:5:3(1 cement: 1.5
coarse sand:3 graded stone
3 5.33A.1 + aggregate For hume pipe Base 800 1.2 0.3 1 288 Cum.
5.33B.1 20 mm nominal size) at branch road
Plaster Work
5 13.13.4 20 mm cement plaster of mix . IC Chamber 1.96 1.96 1.22 75 717.36 Sqm.
1:6(1 cement: 6 coarse sand)
Total= 717.36 Sqm.
Total=
MATERIAL STATEMENT
LOCAL
SAND CEMENT BRICK STONE CHIPS
(cum) (MT) (nos.) (cum) SAND
(cum)
Sand Filling 0.00 0.00 cum
Brick Work (1:6) 89.31 21.07 165243.0 334.50 cum
Brick Soling 0.00 0.00 0.00 sqm
PCC (1:3:6) 102.72 48.19 205.62 219.11 cum
RCC (1:1.5:3) 177.85 167.39 355.71 418.48 cum
RCC (1.1.2) 0.00 0.00 0.00 0.00 cum
20mm C.P. (1:6) 17.21 4.02 717.36 sqm
12mm C.P. (1:6) 0.00 0.00 0.00 sqm
6mm C.P. (1:4) 0.00 0.00 0.00 sqm
Cement punning 1.43 717.36 sqm
387.10 242.11 165243.00 561.32 0.00