Bihar State Building Construction Corporation Ltd.

Project : SC.&ST. RAJKIYA AMBEDKAR RESIDENTIAL


+2 SCHOOL
at
Piplawan, Patna

Internal Drainage Network

Summary of Estimated Cost


(Civil + Carriage )

Sl. Particulars Estimated


No. Amount (Rs.)

1 Cost for Civil Works : 9525063.00

2 Cost carriage : 1227685.00

Total (1 to 2) : Rs. : Rs. 10752748.00

R.O. : Rs. 107.53 Lacs


Bihar State Building Construction Corporation Ltd.

Project : SC.&ST. RAJKIYA AMBEDKAR RESIDENTIAL


+2 SCHOOL
at
Piplawan,Patna

Internal Drainage Network

Estimate of Cost
Civil Works

Items Covered Under BCD-SOR-2020, effective from 01.7.2020


Rate Amount
Sn. Item No. Item Of Work Quantity Unit
(Rs.) (Rs.)

Earthwork in excavation

Earth work in excavation over


areas ( exceeding 30 cm in depth.
1.5 m in
width as well es 10 sqm on plan)
1 2.6.1 including disposal of excavated 3007.13 Cum. 314.9 946,945.24
earth , lead
upto 50 m and lift upto 1.5 m;
disposed earth to be levelled and
neatly
dressed.
All Kinds of soil
PCC
Providing and laying in position
cement concrete of specified
grade
exluding the cost of centring and
shuttering-all work upto plinth
2 4.1.3 level. 1:2:4(1 Cement: 2 coarse 219.11 Cum. 3953.4 866,229.47
sand:4 graded stone aggregate 20
mm
nominal size)

RCC
Providing and laying in position
specified grade of reinforced
cement concrete excluding the
cost of
centring,shuttering,finishing and
reinforcement-All work puto
5.33A.1 + plinth level.1:1:5:3(1 cement: 1.5
3 418.48 Cum. 4854.5 2,031,511.16
5.33B1 coarse sand:3 graded stone
aggregate
20 mm nominal size)

Brickwork

Brick work with bricks of class


designation 100A in foundations
6.1A and plinth in cement mortar 1:6
4 +6.1.14A (1cement:6coarse sand) 334.5 Cum. 5641 1,886,914.50
+6.3A Extra for brick work in
superstructure above plinth level
upto floor V level.
Plaster Work

20 mm cement plaster of mix .


5 13.13.4 717.36 Sqm. 182.9 131,205.14
1:6(1 cement: 6 coarse sand)

Reinforcement for RCC work


including straightening, cutting,
5.22 bending, placing in position and
bonding all complete.
6
TMTC-500
5.22.7A TMTC-500 8mm dia 4500 Kg 70.6 317700
5.22.7B TMTC-500 10mm dia 5200 Kg 69.2 359840
5.22.7C TMTC-500 12mm dia 3650 Kg 67.6 246740

7 13.26 Neat cement punning 717.36 Sqm. 38.9 27905.30

Providing and laying Non Pressure


NP-4 class (Heavy duty) R.C.C.
pipes
including collars/spigot jointed
with stiff mixture of cement
8 19.36.2 800 Metre 3280.6 2,624,480.00
mortar in the
proportion of 1:2 (1 cement : 2
fine sand) including testing of
joints etc.
Complete. 600 mm dia RCC pipe

Total= 9,525,062.82

Sand 387.10 cum 580.04 224,534.84


Local Sand 0.00 cum 232.76
Stone Chips 561.32 cum 1,380.93 775,149.91
Brick 165.24 Thous. 784.06 129,560.92
Total
Carriage= 1,129,245.67
Extra Carriage
Brick 165.24 Thous. 248.56 41,072.80
Cement 242.11 MT 236.95 57,366.96
Total Extra Carriage= 98,439.76
Bihar State Building Construction Corporation Ltd.

Project : SC.&ST. RAJKIYA AMBEDKAR RESIDENTIAL


+2 SCHOOL
at
Piplawan, Patna

Internal Drainage Network

Measurment Sheet
Civil Works

Items Covered Under BCD-SOR-2020, effective from 01.7.2020


Length Breadth Height H/
Sn. Item No. Item Of Work Location Description No. Quantity Unit
L/Dia B Depth

Earthwork in excavation

Earth work in excavation over


areas ( exceeding 30 cm in depth.
1.5 m in
width as well es 10 sqm on plan)
including disposal of excavated For hume pipe 800 2.26 1.32 1 2386.56 Cum.
earth , lead at branch road
1 2.6.1 upto 50 m and lift upto 1.5 m;
disposed earth to be levelled and
neatly For branch IC
dressed. 2.26 2.26 1.62 75 620.57 Cum.
chamber
All Kinds of soil
Total= 3007.13 Cum.

PCC
Providing and laying in position
cement concrete of specified
grade For branch IC
exluding the cost of centring and 2.26 2.26 0.1 75 38.31 Cum.
chamber
2 4.1.3 shuttering-all work upto plinth
level. 1:2:4(1 Cement: 2 coarse
sand:4 graded stone aggregate 20 For hume pipe 800 2.26 0.1 1 180.8 Cum.
mm at branch road
nominal size)
Total= 219.11 Cum.

RCC
Providing and laying in position
specified grade of reinforced
cement concrete excluding the
cost of Below
2.26 2.26 0.2 75 76.61 Cum.
centring,shuttering,finishing and For branch IC Chamber
reinforcement-All work puto chamber
Cover Slab 1.96 1.96 0.2 75 57.62 Cum.
plinth level.1:1:5:3(1 cement: 1.5
coarse sand:3 graded stone
3 5.33A.1 + aggregate For hume pipe Base 800 1.2 0.3 1 288 Cum.
5.33B.1 20 mm nominal size) at branch road

Total (a)= 422.23 Cum.


Deduction
Opening 0.5 0.5 0.2 75 3.75 Cum.
Total(b)= 3.75 Cum.
Total= 418.48 Cum.
Brickwork

Brick work with bricks of class


designation 100A in foundations
6.1A and plinth in cement mortar 1:6
4 +6.1.14A (1cement:6coarse sand)
+6.3A Extra for brick work in Ic Chamber X-Direction 1.96 0.38 1.5 2 2.23 Cum.
superstructure above plinth level Y-Direction 1.96 0.38 1.5 2 2.23 Cum.
upto floor V level. Qty. Of 1 IC chamber= 4.46 Cum.
Qty of 75 IC Chamber= 334.5 Cum.
Total= 334.5 Cum.

Plaster Work

5 13.13.4 20 mm cement plaster of mix . IC Chamber 1.96 1.96 1.22 75 717.36 Sqm.
1:6(1 cement: 6 coarse sand)
Total= 717.36 Sqm.

Reinforcement for RCC work


including straightening, cutting,
5.22
bending, placing in position and
bonding all complete.
6
TMTC-500
5.22.7A TMTC-500 8mm dia 4500 Kg
5.22.7B TMTC-500 10mm dia 5200 Kg
5.22.7C TMTC-500 12mm dia 3650 Kg

7 13.26 Neat cement punning Qty. Same as 13.13.4= 717.36 Sqm.

Providing and laying Non Pressure


NP-4 class (Heavy duty) R.C.C.
pipes
including collars/spigot jointed
with stiff mixture of cement
8 19.36.2 800 1 800 Metre
mortar in the
proportion of 1:2 (1 cement : 2
fine sand) including testing of
joints etc.
Complete. 600 mm dia RCC pipe

Total=
MATERIAL STATEMENT
LOCAL
SAND CEMENT BRICK STONE CHIPS
(cum) (MT) (nos.) (cum) SAND
(cum)
Sand Filling 0.00 0.00 cum
Brick Work (1:6) 89.31 21.07 165243.0 334.50 cum
Brick Soling 0.00 0.00 0.00 sqm
PCC (1:3:6) 102.72 48.19 205.62 219.11 cum
RCC (1:1.5:3) 177.85 167.39 355.71 418.48 cum
RCC (1.1.2) 0.00 0.00 0.00 0.00 cum
20mm C.P. (1:6) 17.21 4.02 717.36 sqm
12mm C.P. (1:6) 0.00 0.00 0.00 sqm
6mm C.P. (1:4) 0.00 0.00 0.00 sqm
Cement punning 1.43 717.36 sqm
387.10 242.11 165243.00 561.32 0.00