Variance Analysis
Outline
▪ Materiality and Trends
▪ Types of Variance in Project Management
▪ Exception Plan
▪ Material Variances in Projects
▪ Labour Variances in Projects
Readings
▪ PMBOK-7, pages 100-101, 113, 177, 182 & 252
▪ Drury, Chapter 17
▪ Lecture Notes
1
MEhsanSaeed 2
1
‘Materiality’ and ‘Trends’ in Variance Analysis
‘Materiality’ refers to the impact of Variance. When calculating Variances,
materiality needs consideration
▪ An Unfavourable Variance of Rs 1.00 on a brick planned at Rs 9.00 isn't a big deal if
the quantity required is small but would add significantly to the material cost if the
quantity required is for the entire house
▪ A Favourable Variance of Rs 2,000 on a geyser is not significant but a Rs 10
Favourable Variance on a bag of cement is
▪ Time spent on Variance Analysis should be proportional to the effect of the Variance
on the Project Baselines; no need being penny wise
‘Trends’ are an important consideration in Variance Analysis
▪ Control actions based on Point-in-time (Singular) Variances need caution; Variance
Trends over time enable better Control actions
▪ A Negative Variance over time of say Rs 9, 10, 11, 8 and 11 is indicative of a steady
trend of increasing costs and, if large enough to be material, merits investigation
followed by a suitable Control action
MEhsanSaeed 3
A. Estimated to Planned
B. Planned to Actual
C. Estimated to Actual
MEhsanSaeed 4
2
A. Estimated to Planned Variance
Variance between what was Estimated for the Project, based on the
estimation techniques or expert opinion, and what emerged upon
Planning
• Occurs in situations where projects are quoted based on best
guesses and ball park figures, by a group who will not actually
execute the work. Detailed planning, however, results in different
figures
• Reasons for such a Variance: new processes, technology, laws, taxes
etc introduced since the initial estimates, or a flawed estimate, or
excessive delay between initiation & planning
• If the variance is significantly Unfavourable, the whole Business
Case or the Feasibility Study for the Project would need review, or
the Project might be shelved
MEhsanSaeed 5
Variance between what was Planned for the Project and how it is
actually working out
• Yields Progress of the Project
• Most widely used in Project Management as EVA and various types
of Variance Analyses like Material Rate & Usage Variance, Labour
Rate & Efficiency Variance etc
• Reasons for such a Variance: change in material and labour costs,
taxes, force majeure, scope creep, progressive elaboration etc
• If the variance is significantly Unfavourable, the situation is
controlled through Preventive or Corrective Actions, or Defect
Repairs, or in the worst case scenario, Rework
MEhsanSaeed 6
3
Planned/Estimated & Actual Spending
3,500
Threshold crossed.
Formulate and Implement
3,000 the Exception Plan
2,500
Cost Baseline
+10% Threshold/Tolerance
2,000 Actual Spending
Spending
MEhsanSaeed
1,500
1,000
Exception Plan An agreed-upon set of Corrective
Actions to be taken if a threshold or forecast is
500 crossed. Usually done at a Stakeholder meeting.
Agreed Plan is implemented and followed through to
determine if it is working.
0
0 5 10 15 Time 20 25 30 35 7
Variance between what was Estimated for the Project and how it is
actually working out
• Applies to Projects which are started intuitively, without a plan or
relying mostly on the Business Case or Feasibility Study
• Also applies to Procurement Contracts where Bids differ significantly
from the Quotations; if so, the corrective action may warrant
change of vendors, processes, materials, contractual stipulations,
etc.
MEhsanSaeed 8
4
Variances & Risk Temperament
Variance often rooted in Risk Temperament of the Estimator or Planner:
6 6
6 Ideally: A, B, C ≈ 0
Planned 5
Actual
5 5
A B C
Estimated Estimated
4 4 4
C A B
Actual 3
Planned
3 3
1 1 1
0 0 0
Category 1 Category 2 Category 1 Category 2 Category 1 Category 2
A. Estimated to Planned
B. Planned to Actual
C. Estimated to Actual
MEhsanSaeed 9
Variance Analysis
of Changes in
Direct Material & Labour Costs
on Projects
MEhsanSaeed
10
10
5
Estimating Activity Resources & Costs
PLANNING EXECUTING
Create and
WBS MONITORING & CONTROL
• Scope Baseline
Define
Activities
• Activity List
Estimate
Activity
Resources
• Resource Requirements Control
Estimate Resources
Costs
• Actual Resources Utilised
• Cost Estimates
Determine Control
Budget Costs
VARIANCE
• Cost BL ANALYSIS • Actual Costs
• Project Budget
(CV, CPI, EAC, VAC, ETC, TCPI)
MEhsanSaeed 11
11
12
6
Variance Analysis an Interplay of Rates & Quantities
MUV
Actual Quantity Used: Actual Quantity of material used for
the activity; eg 900 bags of cement
MRV
MEhsanSaeed 13
13
Upon multiplication, units in numerators & denominators must cancel each other
except the Quantity units; eg, SQ (cft) of timber for 10 houses, 12 doors per house,
𝑑𝑜𝑜𝑟𝑠 𝑐𝑓𝑡
2 cft timber per door = 10 houses x 12 ℎ𝑜𝑢𝑠𝑒 x 2 𝑑𝑜𝑜𝑟 = 240 cft
MEhsanSaeed 14
14
7
Working out Standard Effort (SE)
• In Direct Labour Variance, the SE is used in place of SQ
• Effort is basically ‘How Many Resources & for How Long’. It is the product of
number of Resources and Duration for which they are employed
• HR Effort For HR, Effort is measured in Man-Hours, Man-Days, Man-Weeks
& so on, as follows:
One Man-Hour (MH) = One Man working for One Hour
One Man-Day (MD) = One Man working for One Day (8 Hrs) ∴ One MD=8 MH
One Man-Week (MW)= One Man working for One Week (40 hrs or 5 days,
@ 8 hrs per day, or as planned in the Project Calendar)
Examples:
Men Period Effort Effort Men-Period
40 5 hrs 200 MH
80 MH 10-8H, 5-16H, 2-40H etc
13 20 days 260 MD, 2,080 MH
4 3 weeks 12 MW, 60 MD, 480 MH 20-1D, 10-2D, 5-4D, 4-5D,
20 MD
4-1W, 2-2W, etc
MEhsanSaeed 15
15
1. Formula based:
MRV = ∑AQx(SR-AR) = AQ1x(SR-AR1) + AQ2x(SR-AR2) + AQ3x(SR-AR3) + …
MUV = SRx(SQ-AQ)
OE = MRV+MUV
2. Template Based:
Material Purchased Material Used
Actual Qty Actual Qty Actual Qty Std Qty
x x x x
Actual Rate Std Rate Std Rate Std Rate
MRV MUV
MEhsanSaeed
OE
16
8
17
Variance Analysis (Material) … 1/3 …Using Formulae
Material Cement: On a certain construction project, first slab with a volume of 6000
cft has been poured. For this activity, the standard quantities and rates for cement
were: 17.6 bags per 100 cft; Rs 400 per bag. 1200 bags were purchased @ Rs 500
per bag from one source and 200 bags @ Rs 450 from another. On completion of
pouring, 250 bags remained in the store. Carry out Variance Analysis (find MRV,
MUV and Overall Effect on Project Cost Performance).
MUV = SRx(SQ-AQ)
AQ2 purchased= 200 bags = 400x(1056-1150) = -37,600
AR2 = Rs 450/bag
Overall Material Cost Variance = MRV+MUV
AQ used = 1200+200-250 = 1150 bags = (-130,000)+(-37,600) = -167,600
17
18
Variance Analysis (Material) … 2/3 …Using Template
Material Cement: On a certain construction project, first slab with a volume of 6000
cft has been poured. For this activity, the standard quantities and rates for cement
were: 17.6 bags per 100 cft; Rs 400 per bag. 1200 bags were purchased @ Rs 500
per bag from one source and 200 bags @ Rs 450 from another. On completion of
pouring, 250 bags remained in the store. Carry out Variance Analysis (find MRV,
MUV and Overall Effect on Project Cost Performance).
Material Purchased Material Used
SQ = 17.6 bags x 6000 cft
100 cft Actual Qty Actual Qty Actual Qty Std Qty
= 1056 bags x x x x
Actual Rate Std Rate Std Rate Std Rate
SR = Rs 400/bag 200 1200 bags 200+1200 bags 1150 bags 1056 bags
x + x x x x
AQ1 purchased= 1200 bags Rs 450 500 /bag Rs 400/bag Rs 400/bag Rs 400/bag
AR1 = Rs 500/bag = Rs 90,000+600,000 =Rs 560,000 =Rs 460,000 =Rs 422,400
MRV MUV
AQ2 purchased= 200 bags
AR2 = Rs 450/bag Rs 130,000 (U) Rs 37,600 (U)
Overall Material Cost Variance
AQ used = 1200+200-250 Rs 167,600 (U)
= 1150 bags
18
9
19
Variance Analysis (Material) … 3/3 … Simplistic Approach
Material Cement: On a certain construction project, first slab with a volume of 6000
cft has been poured. For this activity, the standard quantities and rates for cement
were: 17.6 bags per 100 cft; Rs 400 per bag. 1200 bags were purchased @ Rs 500
per bag from one source and 200 bags @ Rs 450 from another. On completion of
pouring, 250 bags remained in the store. Carry out Variance Analysis (find MRV,
MUV and Overall Effect on Project Cost Performance).
Material Labour
Standard Quantity (SQ) Standard Effort (SE)
Actual Quantity (AQ) Actual Effort (AE)
Standard Rate (SR) Standard Labour Rate (SLR)
Actual Rate (AR) Actual Labour Rate (ALR)
Material Rate Variance (MRV) Labour Rate Variance (LRV)
Material Usage Variance (MUV) Labour Efficiency Variance (LEV)
20
10
Variance Analysis (Material) → Variance Analysis (Labour) … 21
2/2
Material Labour
Formula Formula:
MRV = ∑AQx(SR-AR) LRV = ∑AEx(SLR-ALR)
MUV = SRx(SQ-AQ) LEV = SLRx(SE-AE)
OE = MRV+MUV OE = LRV+LEV
Template Template
Material Purchased Material Used Manpower Hired Manpower Employed
Actual Qty Actual Qty Actual Qty Std Qty Act Effort Act Effort Act Effort Std Effort
x x x x x x x x
Actual Rate Std Rate Std Rate Std Rate ALR SLR SLR SLR
MRV MUV LRV LEV
OE OE
21
22
Variance Analysis (Direct Labour) … 1/3 …Using Formulae
On a certain construction project, HR Assignment Plan assigned 200 unskilled
workers (USW), on a particular activity, for 100 days, on a daily wage of Rs 500. Due
to countrywide shortage and escalating inflation no USW was available for less than
Rs 600 per day, and only 190 USWs could be made available. The activity actually
took 80 days to complete. Carry out Variance Analysis
SLR = Rs 500/day/USW
LEV = SLRx(SE-AE)
= 500x(20,000-15,200) = 2,400,000
AE = 190 USW x 80 days
= Rs 15,200 man-days
Overall Labour Cost Variance
ALR = Rs 600/day/USW = LRV+LEV
= (-1,520,000)+(2,400,000) = 880,000
22
11
23
Variance Analysis (Direct Labour) … 2/3 …Using Template
On a certain construction project, HR Assignment Plan assigned 200 unskilled
workers (USW), on a particular activity, for 100 days, on a daily wage of Rs 500. Due
to countrywide shortage and escalating inflation no USW was available for less than
Rs 600 per day, and only 190 USWs could be made available. The activity actually
took 80 days to complete. Carry out Variance Analysis
Rs 880,000 (F)
23
24
Variance Analysis (Direct Labour) … 3/3 … Simplistic Approach
On a certain construction project, HR Assignment Plan assigned 200 unskilled
workers (USW), on a particular activity, for 100 days, on a daily wage of Rs 500. Due
to countrywide shortage and escalating inflation no USW was available for less than
Rs 600 per day, and only 190 USWs could be made available. The activity actually
took 80 days to complete. Carry out Variance Analysis
24
12
More Examples
using
the Simplistic Approach
+
Some Unsolved Examples
MEhsanSaeed
25
25
26
Example 1
Work Package (WP) Scope: Aluminium Windows with Single Pane Glass
20 houses, 10 windows/house, 48 sq ft/window
Standard Rate for WP Costing: Rs 500 per sq ft
After the project started, the Scope was changed to have double glazed (double
paned) windows for better habitability. Resultantly, the rate escalated to Rs 800/sq ft.
To Control Costs, one window was deleted from each house as one room was to be
converted into a store. Carry out Variance Analysis
SQ = 20 houses x 10 windows/house x Planned Material Cost (BL Cost)
48 sq ft/window = 9,600 sq ft = SR x SQ
= Rs 500/sq ft x 9,600 sq ft = Rs 4,800,000
SR = Rs 500/sq ft
Actual Material Cost
= Σ(AR x AQ) - (UU x SR)
AQ = 20 houses x 9 windows/house x = Rs 800/sq ft x 8,640 sq ft = Rs 6,912,000
48 sq ft/window = 8,640 sq ft
26
13
27
Example 2
Material Paint Putty: On a certain construction project of 22 houses, putty base is to
be applied on internal walls after plaster. Area of Internal Walls is 8,000 sq ft per
house. Putty coverage is 5 kg per 100 sq ft wall area. Putty comes in 40-kg drums for
which the Standard Rate is Rs 12,000 per drum. 120 drums of putty are purchased @
Rs 11,500 per drum and 80 drums @ Rs 13,000 per drum. On completion of the
activity, 7 drums of putty remain unused. Carry out Variance Analysis
28
Example 3
The HR planned for a 120-day long project are 20 skilled workers @ Rs 3,000 per day
and 100 unskilled workers @ Rs 1,500 per day. During project execution, 15 skilled
workers and 75 unskilled workers were actually provided @ Rs 3,100 per day and Rs
1,600 per day respectively. The skilled workers worked on the project for 140 days and
the unskilled workers for 150 days. Carry out Variance Analysis for Labour Costs
28
14
Example 4 (Unsolved)
Project & Scope: Lay terrazzo (marble chips) flooring in a housing project of 140
houses. Flooring requirement in each house unit is 5,000 sq ft.
Standard Rates & Quantities: Terrazzo comes in bags of 50 kg @ Rs 2,000 per bag. 1.5
kg covers 1 sq ft area.
Standard Labour Rates & Effort: The company estimates 40 man-days of work in each
housing unit and labour cost @ Rs 1,000 per day per worker (per man-day)
Actual Materials: The company procures 12,000 bags of terrazzo @ Rs 2,060 per bag
from one source and 8,000 bags @ Rs 2,100 per bag from another source. 500 bags of
terrazzo is already available ex-stock which was purchased @ Rs 1,800 per bag.
Actual Labour: The company hires 50 workers on T&M contract @ Rs 1,200 per man-
day.
Project Completion: The project completes in 90 days, with 200 bags of terrazzo
unused.
MEhsanSaeed 29
29
Example 5 (Unsolved)
A flooring company wins a project to lay tiles on the flooring in a housing project of 19
houses. Flooring requirement in each house is 2,000 sq ft.
100 units of tiles cost Rs 8,000, and 2 units cover 1 sq ft of floor.
The company procures 45,000 units of tiles @ Rs 7,000 per 100-units from one source,
and 40,000 units @ Rs 9,500 per 100-units from another source. At the end of the
project, 1,000 units of tiles remains unused.
Find the financial effect of this effect on the Cost Baseline.
MEhsanSaeed 30