2.15. Risk Schedule
2.15. Risk Schedule
2.15. Risk Schedule
Confidential
Duly authorised signatory to sign tenders and contract documents for and on behalf of the tendering entity
Name: Mr. Yago Mijangos Gorozarri Address: Brand Tower, 1st floor Office No. 11
Duly authorised signatory to sign tenders and contract documents for and on behalf of the tendering entity
Info@chinaconstruction.ae
Duly authorised signatory to sign tenders and contract documents for and on behalf of the tendering entity
Name: Mr. Ziad W. Sulaiman Address: Omer lbn Abdulaziz Road, Al Malaz,
P.O. Box 2740 Riyadh 11461, Kingdom
of Saudí Arabia
aalrammah@sajco.com.sa
CONTENTS
1. INTRODUCTION TO THE JV RISK POLICY ....................................... 2
Commercial Manager (CM): heads the Commercial Team where the Risk Manager
is assigned to collaborate and coordinate risk actions within the project focussing on
costs and scheduling. The CM cooperates with the Risk Manager in collecting the
information necessary to identify the risks and monitoring of the risk responses. The
CM is part of the Risk Management Committee.
Risk Owners (RO): have the overall responsibility and authority for treating the
identified risks. Within the project team they would be work package managers. Risk
owners must have the resources necessary to treat their risks and carry out the
following functions:
• Operate within established Risk Management Plan, manuals, processes,
procedures, forms, guidance, tools, and systems
• Provide subject matter expertise for assigned risks to the Project Risk Manager
• Provide input on standards, tools, and methods for managing, treating,
monitoring, and reporting assigned risks
Risk Treatment Owner (RTO): Operates within Project Risk Management Plan and
Policy. The risk treatment owner will be assigned by the Risk Owner by a dedicated
form and
• Monitors and treat specific risks on behalf of (a) risk owner(s);
• Operate within established Risk Management Policy, plans, manuals,
processes procedures, forms, guidance, tools, and systems
• Obtain Risk Owners support and authorization for risks
• Develop timely reports for review and aggregation by Risk Owners.
Risk Management Committee (RMC): The Project Manager, the Risk Manager,
The Commercial Manager, the Risk Owners and Risk Treatment Owners together
form the Risk Management Committee. The Risk Manager invites the members of
the Risk Management Committee to monthly workshops regarding risk management.
Risk identification I A R I R
Risk analysis A R C C
Risk evaluation I A C R
Risk treatment I A I C R C
Communication &
A C A R
Consultation
Workshop Monthly Workshop number of attendees attended the Green >90% Continuous
attendance schedule workshop x 100 Amber 75% - Improvement
Workshop number of attendees invited to 89% Red <
attendance workshop 75%
CONSEQUENCE
1 2 3 4 5
Performance Minimal Minor Unable to Unable to Unable to
consequence consequence achieve a achieve achieve
to objectives to objectives / particular multiple objectives/goals
/ goals goals objective/ goal, objectives/ such that
but remaining goals but minimum
objective goals minimum success cannot
represent better success can be achieved or
than minimum still be claimed
success or achieved or
outcome claimed
Safety
Discomfort No lost time Lost time
Human First aid event Loss of life
or nuisance per OSHA injury or illness injury or
criteria per OSHA illness per
criteria OSHA criteria
Asset Minimal Minor Minor Major Destroyed:
consequence consequence: consequence: consequence asset is
: asset has asset has asset is asset is compromised,
no sign of cosmetic damaged but substantially and un-
physical damage and is repairable damaged but repairable: a
damage repairable repairable total loss
Schedule/Time Minimal Critical path is Critical path is Critical path Critical path
consequence not slipped; not slipped; slips slips and one or
total slack of total slack of more critical
slipped tasks slipped tasks is milestones or
will not impact within 10 days events cannot
critical path in of impacting be met
less than 10 the critical path
days
1 2 3 4 5
Reputational
Questionable Surprise Concern Dissapointing Outrage
Proximity Timeframe
Critical < 1 month
High 1 < months <
Medium 3 < months <
Low > 6 months
5. COMMUNICATION
Formal risk reporting arrangements to the appropriate organizational level must be
established. Risk reports must highlight changed risks and contain relevant and
concise information that can be efficiently assimilated by the reports’ audience.
7. MONITORING
Risk monitoring and control keeping track of the identified risks, residual risks, and
new risks. It also monitors the execution of planned strategies on the identified risks
and evaluates their effectiveness. Risk monitoring and control continues for the life
of the project. The list of project risks changes as the project matures, new risks
develop, or anticipated risks disappear. Risk ratings and prioritization commonly
change during the project lifecycle.
Risk control involves:
• Choosing alternative response strategies
• Implementing a contingency plan
• Taking corrective actions
• Auditing
• Recommending changes if appropriate
• Looking for additional risks
• Risks reassessments
• Creating workarounds
• Updating the risk status
• Re-planning the project, as applicable and
• Closing risks.
DATE 22/03/2022
IDENTIFICATION
Identification Date
Direct Cost/Selling
Risk/Opportunity
Project Phase
Critical Path
Responsible
Finisht Date
Start Date
Risk Code
Location
Risk No.
(R/O)
Price
Chapter Title Description Trigger
LOT 2 - Grout injection compensation in No time extention granted (no variation approved) in case worse geotechnical conditions than expected and more grouting Lack of adjustment
002 R Construction Tunnel L2R2 Tunnel grout injection Yes time. Delay Penalties injection is needed. Delay penalties mechanism for grouting time
Selling Price
LOT2- Ventilation Shafts VS1 and VS2 Due to the lack of geotechnical information in the shafts areas, the selected methodology to perform the shafts could not be the Design status at early stage
008 R Tender Vent Shafts 1&2 L2R8 Ventilation Shafts No Methodology appropiate during tender
DC
LOT 2 - Ventilation Shafts VS1 & VS2 Ventilation Shafts geotechnical conditions worse than expected which could incurr in higher maintenance activities than the Design status at early stage
009 R Construction Vent Shafts 1&2 L2R9 Ventilation Shafts No geotechnical info. standard for the machines involved during tender
DC
010 R Construction Project Staff L2R10 Staff Personnel No LOT 2 - Staff rotation Staff personnel high rotation due to project location Project Location DC
DATE 22/03/2022
IDENTIFICATION
Identification Date
Direct Cost/Selling
Risk/Opportunity
Project Phase
Critical Path
Responsible
Finisht Date
Start Date
Risk Code
Location
Risk No.
(R/O)
Price
Chapter Title Description Trigger
Contractual Non
Confomence. But these
Engineering & Various technical submittals need to submit/obtain approvals from the commence day till 15 days to 30 days . Also all the
023 R Tunnel L2R23 Mobilization Works Yes LOT- 2 Mobilization
Mobilization activities need to complete within 30days (List of activities /submittals included in Annexure A)
activities are not included in DC
Construction mile stones which reduces the
risk.
LOT 3 - Grout injection compensation in No time extention granted (no variation approved) in case worse geotechnical conditions than expected and more grouting Lack of adjustment
025 R Construction Tunnel L3R2 Tunnel grout injection Yes time. Delay Penalties injection is needed. Delay penalties mechanism for grouting time
Selling Price
LOT 3- Ventilation Shaft VS3 Due to the lack of geotechnical information in the shaft areas, the selected methodology to perform the shaft could not be the Design status at early stage
031 R Tender Vent Shaft 3 L3R8 Ventilation Shafts No Methodology appropiate during tender
DC
LOT 3 - Ventilation Shaft VS3 Ventilation Shafts geotechnical conditions worse than expected which could incurr in higher maintenance activities than the Design status at early stage
032 R Construction Vent Shaft 3 L3R9 Ventilation Shafts No geotechnical info. standard for the machines involved during tender
DC
033 R Construction Project Staff L3R10 Staff Personnel No LOT 3 - Staff rotation Staff personnel high rotation due to project location Project Location DC
DATE 22/03/2022
IDENTIFICATION
Identification Date
Direct Cost/Selling
Risk/Opportunity
Project Phase
Critical Path
Responsible
Finisht Date
Start Date
Risk Code
Location
Risk No.
(R/O)
Price
Chapter Title Description Trigger
Contractual Non
Confomence. But these
Engineering & Various technical submittals need to submit/obtain approvals from the commence day till 15 days to 30 days . Also all the
045 R Tunnel L2R22 Mobilization Works Yes LOT- 3 Mobilization
Mobilization activities need to complete within 30days (List of activities /submittals included in Annexure A)
activities are not included in DC
Construction mile stones which reduces the
risk.
LOT 4 - Grout injection compensation in No time extention granted (no variation approved) in case worse geotechnical conditions than expected and more grouting Lack of adjustment
047 R Construction Tunnel L4R2 Tunnel grout injection Yes time. Delay Penalties injection is needed. Delay penalties mechanism for grouting time
Selling Price
LOT 4 - Ventilation Shaft VS4 Due to the lack of geotechnical information in the shaft areas, the selected methodology to perform the shaft could not be the Design status at early stage
053 R Tender Vent Shaft 4 L4R8 Ventilation Shafts No Methodology appropiate during tender
DC
LOT 4 - Ventilation Shaft VS4 Ventilation Shafts geotechnical conditions worse than expected which could incurr in higher maintenance activities than the Design status at early stage
054 R Construction Vent Shaft 4 L4R9 Ventilation Shafts No geotechnical info. standard for the machines involved during tender
DC
055 R Construction Project Staff L4R10 Staff Personnel No LOT 4 - Staff rotation Staff personnel high rotation due to project location Project Location DC
DATE 22/03/2022
IDENTIFICATION
Identification Date
Direct Cost/Selling
Risk/Opportunity
Project Phase
Critical Path
Responsible
Finisht Date
Start Date
Risk Code
Location
Risk No.
(R/O)
Price
Chapter Title Description Trigger
Contractual Non
Confomence. But these
Engineering & Various technical submittals need to submit/obtain approvals from the commence day till 15 days to 30 days . Also all the
067 R Tunnel L2R22 Mobilization Works Yes LOT4 - Mobilization
Mobilization activities need to complete within 30days (List of activities /submittals included in Annexure A)
activities are not included in DC
Construction mile stones which reduces the
risk.
LOT 5 - Grout injection compensation in No time extention granted (no variation approved) in case worse geotechnical conditions than expected and more grouting Lack of adjustment
069 R Construction Tunnel L5R2 Tunnel grout injection Yes time. Delay Penalties injection is needed. Delay penalties mechanism for grouting time
Selling Price
LOT 5 - Ventilation Shaft VS5 Due to the lack of geotechnical information in the shaft areas, the selected methodology to perform the shaft could not be the Design status at early stage
075 R Tender Vent Shaft 5 L5R8 Ventilation Shafts No Methodology appropiate during tender
DC
LOT 5 - Ventilation Shaft VS5 Ventilation Shafts geotechnical conditions worse than expected which could incurr in higher maintenance activities than the Design status at early stage
076 R Construction Vent Shaft 5 L5R9 Ventilation Shafts No geotechnical info. standard for the machines involved during tender
DC
077 R Construction Project Staff L5R10 Staff Personnel No LOT 5 - Staff rotation Staff personnel high rotation due to project location Project Location DC
Mobilisation milestone is very tight to deliver a complete camp for LOT 5 and could lead to extra cost for rental temporary Mobilisation schedule for Lot
085 R Construction Camp lot 5 L5R18 Camp facilities Yes LOT 5 - Camp erection time.
accomodation near the area 5 too tight
DC
DATE 22/03/2022
IDENTIFICATION
Identification Date
Direct Cost/Selling
Risk/Opportunity
Project Phase
Critical Path
Responsible
Finisht Date
Start Date
Risk Code
Location
Risk No.
(R/O)
Price
Chapter Title Description Trigger
DATE 22/03/2022
Response Strategy
ADDITIONAL INFO
Risk/Opportunity
Project Phase
Critical Path
Reputation
Reputation
Reputation
Reputation
Reputation
Reputation
Response and
Risk No.
(R/O)
Time
Time
Time
Time
Time
Time
Cost
Cost
Cost
Cost
Cost
Cost
Title Description Control Action Status
LOT 2 - Delay penalties at tunnel Penalties assumed by not getting performance ratio required to achieve drill&blast
001 R Construction Yes completion milestones in main running tunnels
6 6 4 3 24 18 Accept Active
drill&blast completion
Client acceptance of
LOT 2 - Grout injection variation claims which
No time extention granted (no variation approved) in case worse geotechnical
002 R Construction Yes compensation in time. Delay conditions than expected and more grouting injection is needed. Delay penalties
3 3 5 3 15 9 Mitigate justifies increases in grout 2 2 4 2 8 4 Active
amounts leading in time
Penalties
conssumption
LOT 2 - Delay penalties at first Penalties assumed by not getting performance ratio required to achieve first blast
003 R Construction Yes milestones in main running tunnels
6 6 2 2 12 12 Accept Active
blasts in main tunnel
LOT 2 - Schedule delays for Tight schedule required could lead delays in temporary works installation to achieve the
004 R Construction Yes first blasts milestones
4 4 2 2 8 8 Accept Active
Temporary Works installation
LOT2- Ventilation Shafts VS1 and Due to the lack of geotechnical information in the shafts areas, the selected
008 R Tender No methodology to perform the shafts could not be the appropiate
4 3 12 Accept Active
VS2 Methodology
LOT 2 - Ventilation Shafts VS1 & Ventilation Shafts geotechnical conditions worse than expected which could incurr in
009 R Construction No higher maintenance activities than the standard for the machines involved
4 2 8 Accept Active
VS2 geotechnical info.
Increase staff hiring
010 R Construction No LOT 2 - Staff rotation Staff personnel high rotation due to project location 4 4 16 Mitigate
incentives
4 3 12 Active
011 R Construction No LOT 2 - Inflation rates Inflation rates in the area and plant supplier's countries higher than expected 3 4 12 Accept Active
LOT 2 - Tunnel equipment Tunnel equipment delivery time does not meet the anticipated mobilisation milestones Split equipment supplies
012 R Construction Yes for LOT 2
5 5 25 Mitigate
among various suppliers
5 4 20 Active
delivery
Excavation performace lower than the average expected at the beggining of the
013 R Construction Yes LOT 2 - Learning curve excavation
5 5 4 2 20 10 Accept Active
014 R Construction No LOT 2 - Technical consultant Technical submittals require more technical staff and/or sub-consultants than expected 3 2 6 Accept Active
Even though the programme has tried not to overlap main activities in the tunnel, there Separate main activities in
LOT 2 - Simultaneity factor in
015 R Tender Yes are some activities that could interfere others during the project performance and 4 3 12 Mitigate the tunnel as excavation 4 2 8 Active
tunnel cycles impact the tunnel cycles and lining
LOT 2 - Lack of info about Adit Scarce design information provided about Adit Junctions an associated methodology at
016 R Design Yes this tender stage
5 5 3 3 15 15 Accept Active
Junctions 1&2
Water supply does not meet the requirements for all the Contractor's involved and
017 R Construction No LOT 2 - Water supply other sources have to be found at higher rates
3 2 6 Accept Active
LOT 2 - Drainage trenches Trenches excavation in rock harder than expected and additional resources (plant,
018 R Construction No blasting) needed to achieve the ratios expected
2 3 6 Accept Active
excavation
Additional Geotechnical
LOT 2 - Additional ground
019 R Design No Employer's geotechnical data incomplete and additional information is required 5 3 15 Mitigate campaign from 4 2 8 Active
investigation by the Contractor Contractor's side
Possible floods at the adits 1&2 entrances, VS1&VS2 areas and paved and unpaved
020 R Design No LOT 2 - Flood Risk roads due to the wadis crossing the area
3 3 9 Accept Active
Desgn & Rockbolts Procurement due to non availabilty of drawings, ( Excess qty procurment due
022 R No LOT 2 - Rockbolts Procurement to delivery schedule)
4 3 12 Accept Active
Construction
RISK REGISTER QUALITATIVE SUMMARY VERSION 7
DATE 22/03/2022
Response Strategy
ADDITIONAL INFO
Risk/Opportunity
Project Phase
Critical Path
Reputation
Reputation
Reputation
Reputation
Reputation
Reputation
Response and
Risk No.
(R/O)
Time
Time
Time
Time
Time
Time
Cost
Cost
Cost
Cost
Cost
Cost
Title Description Control Action Status
Various technical submittals need to submit/obtain approvals from the commence day
Engineering &
023 R Yes LOT- 2 Mobilization till 15 days to 30 days . Also all the Mobilization activities need to complete within 5 4 3 3 15 12 Accept Active
Construction 30days (List of activities /submittals included in Annexure A)
LOT 3 - Delay penalties at tunnel Penalties assumed by not getting performance ratio required to achieve drill&blast
024 R Construction Yes completion milestones in main running tunnels
6 6 5 3 30 18 Accept Active
drill&blast completion
Client acceptance of
LOT 3 - Grout injection variation claims which
No time extention granted (no variation approved) in case worse geotechnical
025 R Construction Yes compensation in time. Delay conditions than expected and more grouting injection is needed. Delay penalties
3 3 5 3 15 9 Mitigate justifies increases in grout 2 2 4 2 8 4 Active
amounts leading in time
Penalties
conssumption
LOT 3 - Delay penalties at first Penalties assumed by not getting performance ratio required to achieve first blast
026 R Construction Yes milestones in main running tunnels
6 6 4 2 24 12 Accept Active
blasts in main tunnel
LOT 3 - Schedule delays for Tight schedule required could lead delays in temporary works installation to achieve the
027 R Construction Yes first blasts milestones
4 2 2 2 8 4 Accept Active
Temporary Works installation
LOT 3- Ventilation Shaft VS3 Due to the lack of geotechnical information in the shaft areas, the selected methodology
031 R Tender No to perform the shaft could not be the appropiate
4 3 12 Accept Active
Methodology
LOT 3 - Ventilation Shaft VS3 Ventilation Shafts geotechnical conditions worse than expected which could incurr in
032 R Construction No higher maintenance activities than the standard for the machines involved
4 2 8 Accept Active
geotechnical info.
Increase staff hiring
033 R Construction No LOT 3 - Staff rotation Staff personnel high rotation due to project location 4 4 16 Mitigate
incentives
4 3 12 Active
034 R Construction No LOT 3 - Inflation rates Inflation rates in the area and plant supplier's countries higher than expected 3 4 12 Accept Active
Excavation performace lower than the average expected at the beggining of the
035 R Construction Yes LOT 3 - Learning curve excavation
5 5 4 2 20 10 Accept Active
036 R Construction No LOT 3 - Technical consultant Technical submittals require more technical staff and/or sub-consultants than expected 3 2 6 Accept Active
Even though the programme has tried not to overlap main activities in the tunnel, there Separate main activities in
LOT 3 - Simultaneity factor in
037 R Tender Yes are some activities that could interfere others during the project performance and 4 3 12 Mitigate the tunnel as excavation 4 2 8 Active
tunnel cycles impact the tunnel cycles and lining
LOT 3 - Lack of info about Adit Scarce design information provided about Adit Junctions an associated methodology at
038 R Design Yes this tender stage
5 5 3 3 15 15 Accept Active
Junctions 3&3N
Water supply does not meet the requirements for all the Contractor's involved and
039 R Construction No LOT 3 - Water supply other sources have to be found at higher rates
3 2 6 Accept Active
LOT 3 - Drainage trenches Trenches excavation in rock harder than expected and additional resources (plant,
040 R Construction No blasting) needed to achieve the ratios expected
2 3 6 Accept Active
excavation
Additional Geotechnical
LOT 3 - Additional ground
042 R Design No Employer's geotechnical data incomplete and additional information is required 5 3 15 Mitigate campaign from 4 2 8 Active
investigation by the Contractor Contractor's side
Possible floods at the adits 3&3N entrances, VS3 area and paved and unpaved roads
043 R Design No LOT 3 - Flood Risk due to the wadis crossing the area
3 3 9 Accept Active
Desgn & Rockbolts Procurement due to non availabilty of drawings, ( Excees qty procurment due
044 R No LOT 3 - Rockbolts Procurement - to delivery schedule)
4 3 12 Accept Active
Construction
RISK REGISTER QUALITATIVE SUMMARY VERSION 7
DATE 22/03/2022
Response Strategy
ADDITIONAL INFO
Risk/Opportunity
Project Phase
Critical Path
Reputation
Reputation
Reputation
Reputation
Reputation
Reputation
Response and
Risk No.
(R/O)
Time
Time
Time
Time
Time
Time
Cost
Cost
Cost
Cost
Cost
Cost
Title Description Control Action Status
Various technical submittals need to submit/obtain approvals from the commence day
Engineering &
045 R Yes LOT- 3 Mobilization till 15 days to 30 days . Also all the Mobilization activities need to complete within 5 4 3 3 15 12 Accept Active
Construction 30days (List of activities /submittals included in Annexure A)
LOT 4 - Delay penalties at tunnel Penalties assumed by not getting performance ratio required to achieve drill&blast
046 R Construction Yes completion milestones in main running tunnels
6 6 5 4 30 24 Accept Active
drill&blast completion
Client acceptance of
LOT 4 - Grout injection variation claims which
No time extention granted (no variation approved) in case worse geotechnical
047 R Construction Yes compensation in time. Delay conditions than expected and more grouting injection is needed. Delay penalties
3 4 5 5 15 20 Mitigate justifies increases in grout 2 3 4 4 8 12 Active
amounts leading in time
Penalties
conssumption
LOT 4 - Delay penalties at first Penalties assumed by not getting performance ratio required to achieve first blast
048 R Construction Yes milestones in main running tunnels
6 6 4 3 24 18 Accept Active
blasts in main tunnel
LOT 4 - Schedule delays for Tight schedule required could lead delays in temporary works installation to achieve the
049 R Construction Yes first blasts milestones
4 2 2 2 8 4 Accept Active
Temporary Works installation
LOT 4 - Ventilation Shaft VS4 Due to the lack of geotechnical information in the shaft areas, the selected methodology
053 R Tender No to perform the shaft could not be the appropiate
4 3 12 Accept Active
Methodology
LOT 4 - Ventilation Shaft VS4 Ventilation Shafts geotechnical conditions worse than expected which could incurr in
054 R Construction No higher maintenance activities than the standard for the machines involved
4 1 4 Accept Active
geotechnical info.
Increase staff hiring
055 R Construction No LOT 4 - Staff rotation Staff personnel high rotation due to project location 4 4 16 Mitigate
incentives
3 3 9 Active
056 R Construction No LOT 4 - Inflation rates Inflation rates in the area and plant supplier's countries higher than expected 3 4 12 Accept Active
Excavation performace lower than the average expected at the beggining of the
057 R Construction Yes LOT 4 - Learning curve excavation
5 5 4 2 20 10 Accept Active
058 R Construction No LOT 4 - Technical consultant Technical submittals require more technical staff and/or sub-consultants than expected 3 2 6 Accept Active
Even though the programme has tried not to overlap main activities in the tunnel, there Separate main activities in
LOT 4 - Simultaneity factor in
059 R Tender Yes are some activities that could interfere others during the project performance and 4 3 12 Mitigate the tunnel as excavation 4 2 8 Active
tunnel cycles impact the tunnel cycles and lining
LOT 4 - Lack of info about Adit Scarce design information provided about Adit Junctions an associated methodology at
060 R Design Yes this tender stage
5 5 3 3 15 15 Accept Active
Junctions 4&5
LOT 4 - Drainage trenches Trenches excavation in rock harder than expected and additional resources (plant,
061 R Construction No blasting) needed to achieve the ratios expected
2 3 6 Accept Active
excavation
Water supply is on Contractor's side and due to shortage the cost could be higher than
063 R Construction No LOT 4 - Watter supply the estimated
3 2 6 Accept Active
Additional Geotechnical
LOT 4 - Additional ground
064 R Design No Employer's geotechnical data incomplete and additional information is required 5 3 15 Mitigate campaign from 4 2 8 Active
investigation by the Contractor Contractor's side
Possible floods at the Adits 4&5 entrances, VS4 area and paved and unpaved roads due
065 R Design No LOT 4 - Flood Risk to the wadis crossing the area
3 3 9 Accept Active
Desgn & Rockbolts Procurement due to non availabilty of drawings, ( Excees qty procurment due
066 R No LOT 4 - Rockbolts Procurement - to delivery schedule)
4 3 12 Accept Active
Construction
RISK REGISTER QUALITATIVE SUMMARY VERSION 7
DATE 22/03/2022
Response Strategy
ADDITIONAL INFO
Risk/Opportunity
Project Phase
Critical Path
Reputation
Reputation
Reputation
Reputation
Reputation
Reputation
Response and
Risk No.
(R/O)
Time
Time
Time
Time
Time
Time
Cost
Cost
Cost
Cost
Cost
Cost
Title Description Control Action Status
Various technical submittals need to submit/obtain approvals from the commence day
Engineering &
067 R Yes LOT4 - Mobilization till 15 days to 30 days . Also all the Mobilization activities need to complete within 5 4 3 3 15 12 Accept Active
Construction 30days (List of activities /submittals included in Annexure A)
LOT 5 - Delay penalties at tunnel Penalties assumed by not getting performance ratio required to achieve drill&blast
068 R Construction Yes completion milestones in main running tunnels
6 6 4 3 24 18 Accept Active
drill&blast completion
Client acceptance of
LOT 5 - Grout injection variation claims which
No time extention granted (no variation approved) in case worse geotechnical
069 R Construction Yes compensation in time. Delay conditions than expected and more grouting injection is needed. Delay penalties
3 3 5 4 15 12 Mitigate justifies increases in grout 2 2 4 3 8 6 Active
amounts leading in time
Penalties
conssumption
LOT 5 - Delay penalties at first Penalties assumed by not getting performance ratio required to achieve first blast
070 R Construction Yes milestones in main running tunnels
6 6 2 2 12 12 Accept Active
blasts in main tunnel
LOT 5 - Schedule delays for Tight schedule required could lead delays in temporary works installation to achieve the
071 R Construction Yes first blasts milestones
4 2 2 2 8 4 Accept Active
Temporary Works installation
078 R Construction No LOT 5 - Inflation rates Inflation rates in the area and plant supplier's countries higher than expected 3 4 12 Accept Active
Excavation performace lower than the average expected at the beggining of the
079 R Construction Yes LOT 5 - Learning curve excavation
5 5 4 2 20 10 Accept Active
080 R Construction No LOT 5 - Technical consultant Technical submittals require more technical staff and/or sub-consultants than expected 3 2 6 Accept Active
Even though the programme has tried not to overlap main activities in the tunnel, there Separate main activities in
LOT 5 - Simultaneity factor in
081 R Tender Yes are some activities that could interfere others during the project performance and 4 2 8 Mitigate the tunnel as excavation 4 1 4 Active
tunnel cycles impact the tunnel cycles and lining
LOT 5 - Lack of info about Adit Scarce design information provided about Adit Junctions an associated methodology at
082 R Design Yes this tender stage
5 5 3 3 15 15 Accept Active
Junction 5
LOT 5 - Drainage trenches Trenches excavation in rock harder than expected and additional resources (plant,
083 R Construction No blasting) needed to achieve the ratios expected
2 3 6 Accept Active
excavation
Water supply not easy to find in the area and rates and transportation are higher than
084 R Construction No LOT 5 - Watter supply expected
3 2 6 Accept Active
Search for temporary
Mobilisation milestone is very tight to deliver a complete camp for LOT 5 and could lead
085 R Construction Yes LOT 5 - Camp erection time. to extra cost for rental temporary accomodation near the area
5 5 25 Mitigate accomodation near city of 5 2 10 Active
Tabuk
LOT 5 - Tunnel equipment Tunnel equipment delivery time does not meet the anticipated mobilisation milestones Split equipment supplies
086 R Construction Yes for LOT 5
5 5 25 Mitigate
among various suppliers
5 4 20 Active
delivery
Possible floods at the Adits 6 entrance, VS5 area and paved and unpaved roads due to
088 R Design No LOT 5 - Flood Risk the wadis crossing the area
3 3 9 Accept Active
RISK REGISTER QUALITATIVE SUMMARY VERSION 7
DATE 22/03/2022
Response Strategy
ADDITIONAL INFO
Risk/Opportunity
Project Phase
Critical Path
Reputation
Reputation
Reputation
Reputation
Reputation
Reputation
Response and
Risk No.
(R/O)
Time
Time
Time
Time
Time
Time
Cost
Cost
Cost
Cost
Cost
Cost
Title Description Control Action Status
Desgn & Rockbolts Procurement due to non availabilty of drawings, ( Excees qty procurment due
090 R No LOT 5 - Rockbolts Procurement - to delivery schedule)
4 3 12 Accept Active
Construction
Various technical submittals need to submit/obtain approvals from the commence day
Engineering &
091 R Yes LOT5 - Mobilization till 15 days to 30 days . Also all the Mobilization activities need to complete within 5 4 3 3 15 12 Accept Active
Construction 30days (List of activities /submittals included in Annexure A)
Duly authorised signatory to sign tenders and contract documents for and on behalf of the tendering entity
Name: Mr. Yago Mijangos Address: Brand Tower, 1st floor Office No. 11
Gorozarri Alemam Saud bin Faisal Street 2964,
As Sahafah District,
Riyadh 13321 - 6106,
Kingdom of Saudí Arabia
Position: MENA & Asia Pacific Email: MBPoseA@fcc.es
Managing Director rodolfo.illa@fccco.com
Duly authorised signatory to sign tenders and contract documents for and on behalf of the tendering entity
Duly authorised signatory to sign tenders and contract documents for and on behalf of the tendering entity
Name: Mr. Ziad W. Sulaiman Address: Omer lbn Abdulaziz Road, Al Malaz,
P.O. Box 2740 Riyadh 11461,
Kingdom of Saudí Arabia
Position: Managing Director Email: info@sajco.com.sa
aalrammah@sajco.com.sa
Date: 27-03-2022 Tel: +966 11 4 787005