Project: MUMBAI TRANS HARBOUR LINK PROJECT ( Package-2) Construction of 7.

807 Long Bridge Section (Ch 10+380 to Ch 18+187)


MTHL-P2/FQF/62
Across the Mumbai Bay Including Shivaji Nagar Interchange
Employer: Mumbai Metropolitan Region Development Authority Rev: 0

General Consultant: AECOM Asia-PADECO-Dar AL-Handasah-TY Lin International Consortium Date: 23-03-18

Contractor: DAEWOO-TPL Joint Venture

DAILY LABORATORY PROGRAM

DATE:- 07-01-2023

1 Coarse and Fine Aggregates Testing (TIPL & MS Infra) :- Sieve Analysis, Moisture Content, Silt content Testing at Daewoo-TPL-JV QC Lab Ulwe.

2 Concrete :- Unit Weight Testing at QC Lab.

Grade of No. of
Sl. No. Date of casting Structure Date of testing Testing Location
Concrete Cubes

Concrete Cube Compressive Strength 3-Days

1 04-01-2023 S-46 MP-163-164 RHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

2 04-01-2023 S-19 MP-167-168 RHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

3 04-01-2023 S-60 MP-164-165 LHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

JMP-1 (Diaphragm) & MP-252-MJP-3, MJP-3-MJP-6,MJP-6-


4 04-01-2023 Diaphragm & Deck Slab Opening M60 3 07-01-2023 Daewoo TPL JV QC Lab
MJP-9, MJP-9-MJA-2 (Deck Slab Opening)

5 04-01-2023 S-08 MP-166-167 LHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

6 04-01-2023 MP-240-239 Outer LHS (Crash Barrier) Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab

S-75 MP-160-161 RHS (Segment) & AMP-5 (Bearing


7 04-01-2023 Segment & Bearing Pedestal M60 3 07-01-2023 Daewoo TPL JV QC Lab
Pedestal)

8 04-01-2023 S-42 MP-163-164 LHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

MP-199-200 LHS Outer (Crash Barrier) & MP-215-214 LHS


9 04-01-2023 Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab
Outer (Crash Barrier)

10 04-01-2023 MP-172 LHS (Pier Cap) Pier Cap M55 3 07-01-2023 Daewoo TPL JV QC Lab

11 04-01-2023 S-47 MP-154 LHS &S-61 MP-155 LHS (Wet Joint) Wet Joint M60 3 07-01-2023 Daewoo TPL JV QC Lab

Concrete Cube Compressive Strength 7-Days

1 31-12-2022 S-47 MP-154 RHS & S-61 MP-155 RHS (Wet Joint) Wet Joint M60 3 07-01-2023 Daewoo TPL JV QC Lab

2 31-12-2022 S-16 MP-161-162 LHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

S-45 MP-163-164 RHS (Segment) & S-60 MP-159-160 RHS


3 31-12-2022 Segment & Segment Wall M60 3 07-01-2023 Daewoo TPL JV QC Lab
(Segment Wall)

4 31-12-2022 MP-249 RHS (Diaphragm) Diaphragm M60/A10 3 07-01-2023 Daewoo TPL JV QC Lab
ACP-6-ACP-5 LHS Stretch 360 to 389 (Crash Barrier) & MP-
5 31-12-2022 Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab
215-216 LHS Outer (Crash Barrier)
6 31-12-2022 MP-247-248 LHS Median (Crash Barrier) Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab

MP-213-212 LHS Outer (Crash Barrier) & MP-241-240 LHS


7 31-12-2022 Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab
Outer (Crash Barrier)

8 31-12-2022 S-74 MP-160-161 RHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

9 31-12-2022 S-59 MP-164-165 LHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

10 31-12-2022 S-34 MP-168-169 RHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

Concrete Cube Compressive Strength 28-Days

1 10-12-2022 S-61 MP-159-160 RHS (Segment) Segment M60(GGBS) 3 07-01-2023 Daewoo TPL JV QC Lab

2 10-12-2022 S-28 MP-162-163 LHS (Segment) Segment M60(GGBS) 3 07-01-2023 Daewoo TPL JV QC Lab

3 10-12-2022 S-16 MP-186-187 RHS (Segment) Segment M60(GGBS) 3 07-01-2023 Daewoo TPL JV QC Lab

4 10-12-2022 S-01 EJ S02 MP-151 RHS &S-16 MP-152 RHS (Wet Joint) Wet Joint M60(GGBS) 3 07-01-2023 Daewoo TPL JV QC Lab

S-25 MP-162-163 RHS (Segment) & CAP-1 (Seismic


5 10-12-2022 Segment & Seismic Stopper M60 3 07-01-2023 Daewoo TPL JV QC Lab
Stopper)

6 10-12-2022 CAA-1 to CAP-11 (Span Top Slab) Span Top Slab M60 6 07-01-2023 Daewoo TPL JV QC Lab

7 10-12-2022 Haunch at AM Retaining Wall (CH 34.595 to 43.861 BHS) AM Retaining Wall M45 3 07-01-2023 Daewoo TPL JV QC Lab

S-63 MP-165-166 LHS (Segment) & S-45 MP-158-159 RHS


8 10-12-2022 Segment & Segment Wall M60 3 07-01-2023 Daewoo TPL JV QC Lab
(Segment Wall)
MP-206-207 LHS Median (Crash Barrier) & MP-230-229
9 10-12-2022 Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab
LHS Outer (Crash Barrier)
MP-220-219 LHS Outer (Crash Barrier) & MP-231-230 RHS
10 10-12-2022 Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab
Median (Crash Barrier)
MP-216-215 LHS Median (Crash Barrier) & MP-219-220
11 10-12-2022 Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab
LHS Outer (Crash Barier)

12 10-12-2022 MP-159 RHS (Integral Pier Head Segment) Integral Pier Head Segment M60/A10 6 07-01-2023 Daewoo TPL JV QC Lab

13 10-12-2022 MP-183 RHS (Pier Cap Pedestal &ADD) Pier Cap Pedestal &ADD M55 3 07-01-2023 Daewoo TPL JV QC Lab

Concrete Cube Compressive Strength 56-Days

1 12-11-2022 S-40 MP-188-189 LHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

2 12-11-2022 S-20 MP-162-163 LHS (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

S-55 MP-189-190 LHS (Segment) & CAP-4 (Seismic


3 12-11-2022 Segment & Seismic Stopper M60 3 07-01-2023 Daewoo TPL JV QC Lab
Stopper)

4 12-11-2022 MP-210-MP-211 LHS Median (Crash Barrier) Crash Barrier M45 3 07-01-2023 Daewoo TPL JV QC Lab

5 12-11-2022 S-32 MP-163-164 (Segment) Segment M60 3 07-01-2023 Daewoo TPL JV QC Lab

6 12-11-2022 JMP-5 (Diaphragm) Diaphragm M60/A10 3 07-01-2023 Daewoo TPL JV QC Lab

7 12-11-2022 CAP-6 & CAP-7 (Span Bottom Slab & Deviator) Span Bottom Slab & Deviator M60 3 07-01-2023 Daewoo TPL JV QC Lab

8 12-11-2022 MP-155 RHS (Integral Pier Head Segment) Integral Pier Head Segment M60/A10 6 07-01-2023 Daewoo TPL JV QC Lab

9 12-11-2022 MP-173A LHS (3rd Pier Lift) Pier M55 3 07-01-2023 Daewoo TPL JV QC Lab