Reduction of The Hydrogen Content in The Continuous Casting of Steel
Reduction of The Hydrogen Content in The Continuous Casting of Steel
Reduction of The Hydrogen Content in The Continuous Casting of Steel
S. R. Bragana*, J. M. Hohemberger, J. Vicenzi, C. M. Marques, T. Basegio, A. N. C. Lima, C.P. Bergmann Laboratrio de Cermicos da Universidade Federal do Rio Grande do Sul LACER/UFRGS Abstract. It is well known that the presence of dissolved hydrogen in cast steel can cause defects that appear in hot rolling and forging of steel parts with heavy sections, and also contributes to the formation of internal cracks and blowholes during the solidification of the liquid steel. These problems are especially important in the continuous casting process. So, hydrogen levels must be kept at a minimum in this process. The aim of this work is to investigate possible sources of hydrogen, focusing on the materials that are in contact with the liquid steel during casting. The tundish refractory lining, shrouding tube, tundish covering agents, and casting powders were analyzed. The results showed that not only the control of humidity content in those materials is critical, but the phase transformations that the materials suffer during the casting process are important as well.
1. Introduction
The formation of internal cracks during hot rolling and forging of steel parts with heavy sections as a consequence of dissolved hydrogen within cast steel is know since 1930. More recently, it was realized that certain amounts of hydrogen in the liquid steel contribute to the formation of pinholes and blowholes during steel solidification, what can lead to serious problems, especially in continuous casting process (Stone, 1990). According to H. Johnson (1988), some of these problems are embrittlement, delayed fracture, stress corrosion cracking, exfoliation, and environment-assisted cracking. The damage mechanism can be attributed to the solubility behavior of hydrogen in steel, since its solubility in liquid steel is higher than in solid steel. During solidification, the trapped hydrogen can diffuse, increasing the internal pressure within the material. If the hydrogen content is high enough, this pressure can exceed the mechanical strength of the steel and cause cracks to appear. Since the formation of defects depends on the hydrogen content, it is directly related to the steel production process, part thickness and cooling conditions. Several mechanisms and sources can lead to the increase of hydrogen content during processing of liquid steel. Theoretically, hydrogen has some solubility in the slag, but it is only significant if the degassing operation (VAD) is not correctly performed. Hydrogen can be originated from refractory in two different ways: from their intrinsic humidity or from organic addictives. The possible sources of hydrogen can be summarized as follows (Lachmund, 2000; Jha, 2003; Presern, 1992):
a. b. c. d. e. f.
Environmental air (air humidity) Tundish refractory lining Pouring ceramic shrouding tube Tundish slag Casting powder or fluxes Other refractory materials used in the tundish (barriers, levees, etc).
_____________________________
*
To whom all correspondence should be addressed. Address: LACER/UFRGS Av. Osvaldo Aranha, 99/705, Porto Alegre-RS Brazil 90035-190 E-mail: saulorb@ufrgs.br
Lachmund et al. (2000) concluded that the main source of hydrogen during BOF process with continuous casting is the refractory lining and the shrouding tube, with little contribution from other sources. Therefore, preheating of the shrouding tube and control of the chemical composition of the refractory lining would be possible solutions to decrease hydrogen pick up. Care must be taken when adding materials containing free CaO in their composition, as pointed out by K.N. Jha (2003), because it easily reacts with water, according to the well know lime hydration reaction:
Hence, late additions of lime-containing materials must be avoided, and this raw material should be always kept in sealed packages. The authors explained also the capacity of water retention by the slag, which is higher when the basicity increases (because of higher amounts of CaO). In their experiments, the reduction in basicity was used as to measure the reduction in hydrogen pick up caused by the diffusion trough the metal/slag interface. In this work the objective was to evaluate the materials used in the tundish of steel continuous casting in a local company. They produce high alloy steels from scrap, which is melted in EAF oven and vacuum degassed (VAD). The probable hydrogen sources were analyzed, aiming to generate useful information that could be used to minimize hydrogen absorption within the steel, changing procedures and/or materials. In order to achieve that, the hydrogen content in steel was measured at different process steps, in such a way that it was possible to identify in which step the increase in hydrogen is higher. After that, the refractories were evaluated by means of thermal analysis techniques, and the gases released by the tundish refractories, because of heating, were simultaneously analyzed.
The mineralogical composition of these materials was determined by means of X ray diffraction. Differential thermal analyses with simultaneous analyses of the gases (H2, H2O, CO2) were also conducted.
3. Results
3.1 Hydrogen content measurements Figure 1 shows the hydrogen contents in steel, measured in ladle and tundish. For comparison reasons, measurements were taken in the ladle at different moments of its first run. The graph shows that the hydrogen content is higher in the tundish when compared to the ladle. Such difference is more significant for steel poured in the tundish at the first stage of the run. In this case, the tundish was just assembled and came from right after pre-heating. This was, hence, its first run, with new lining and fresh slag. Considering mean values, the hydrogen pick up at the tundish in relation to the ladle is about 1.2 ppm. At the end of the pouring process, the hydrogen content is only 0.5 ppm higher than the initial value at the ladle. Therefore, it can be inferred that the tundish materials are hydrogen sources, contributing to a higher hydrogen pick up in the steel when compared to the steel in the ladle.
Fig. 1. Hydrogen contents in steel in ladle and tundish, considering a new tundish (first run after assembly).
3.2 Drying and Heating Figure 2 shows the results obtained from temperature measurements made by two thermocouples that were inserted into the wearing refractory, according to the scheme showed in Figure 3. Two heating steps occur in the tundish. At the first one, drying (removal of molding water) and cure of the resins, which are used to bond the particles, are carried out. At this initial stage the temperature measured at about 10 mm inside the refractory almost reach 100C, which would be high enough to remove water from surface pores. At the second step, when the tundish is heated up before steel pouring, the results showed that the temperatures that are reached are insufficient to the complete removal of the structural water, since these temperatures oscillated between 260C to 450C. The differences observed between the thermocouples can be attributed to the differences in the distance
from the gas burner used for heating, and to some variations in refractory thickness where the thermocouples were inserted as well. In this case, both factors contribute to a higher temperature measured by thermocouple 1. From these observations, it can be concluded that these materials can cause an increase in steel hydrogen content.
Fig. 2. Drying (D) at 300C (flame temperature) and heating (H) at 1100C (flame temperature). Thermocouples T1 and T2 inserted 10 mm into the refractory.
Fig. 3. Location of the thermocouples used to measure temperatures during tundish drying and heating.
3.3 Materials Characterization and Evaluation of the Gases Released from Tundish Refractory. The results of thermal analysis (thermogravimetry and differential thermal analysis), as well as the analysis of the gases (H2, H2O, CO2), of refractory materials, shrouding tube e fluxes present in the tundish are shown in Figures 4, 5, and 6.
Fig. 4. Simultaneous thermal analysis (DTA and TG) and analysis of the gases released at the heating of the wearing lining DM.
Fig. 5. Simultaneous thermal analysis (DTA and TG) and analysis of the gases released at the heating of the wearing lining JM.
Fig. 6. Simultaneous thermal analysis (DTA and TG) and analysis of the gases released at the heating of the fluxes.
Considering all analyzed materials, only the wearing refractory and the flux showed a peak of water and/or hydrogen release. The highest hydrogen content was found in the flux, which would potentially contribute to a higher absorption of hydrogen by the steel. The weight loss peak and the endothermic peak within the temperature range of 400C and 500C can be observed in the graphs showed in Figure 6. This temperature range would be characteristic of the decomposition of substances accompanied by structural water releasing. To confirm such hypothesis, the mineralogical composition of the flux was analyzed, as can be seen in Figure 7.
Fig. 7. Powder XRD curve of tundish slag compounds (flux), showing the presence of calcium compounds, including a hydrated phase: Ca(OH)2.
Based on these investigations and on the obtained results, it can be inferred that the flux contains compounds (as showed in Figure 7) that lead to releasing of H2O and H2 during its heating until a temperature of about 560C (Figure 6). Therefore, the flux can potentially contribute to the increase in the hydrogen content in steel, since it is added in the tundish just before the beginning of the continuous casting process.
4. Conclusions
The results obtained from the characterization of the materials involved in the continuous casting process showed that the permanent refractories and the shrouding tube have little contribution to the H2 absorption by the steel. The wearing refractories, however, can release hydrogen; so, control of the drying and heating process is recommendable in order to guarantee total elimination of the H2O/H2 sources. The used flux had great H2 releasing potential, since it is composed by hydrated phases that are decomposed during heating, releasing water. The estimated water content in the flux is about 8 %. Since the amount of flux added in the process is about 120 kg, it could release up to 9.6 kg of H2O. This result explains the increase of hydrogen content in steel in the tundish, and it is confirmed by the increase in the hydrogen content in the first runs and its decrease in subsequent runs. In the later ones, the flux would be calcined and inert regarding to hydrogen release.
References
Jha, K.N., Sardar, M.K., Chakraborty, N.N S. (2003). Hydrogen control during steel making for medium carbon wheels, Scandinavan Journal of Metallurgy, 32. Johnson, H. (1988). Hydrogen in iron. Metall. Transc. B, v. 19, 10. Lachmund, H., Schwinn, V., Jungblunt, A. (2000). Heavy plate production: demand on hydrogen control, Ironmaking and Steelmaking, 27, 5. Presern, V. (1992). Recent trends and the future of vacuum in steel making, Vacuum, 43, 5-7. Stone, R. P., Plessers, J., Turkdogan, E. T. (1990). Accuracy of Determining Hydrogen Content of Liquid Steel with the Hydris System. German chem. Con..