Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

DPR Preparation Guideline by NRCD

Download as pdf or txt
Download as pdf or txt
You are on page 1of 47

NATIONAL RIVER CONSERVATION PLAN

CHECK LISTS

FOR

DETAILED PROJECT REPORTS

NATIONAL RIVER CONSERVATION DIRECTORATE


MINISTRY OF ENVIRONMENT & FORESTS
GOVERNMENT OF INDIA
NEW DELHI
2004

1|P age
NATIONAL RIVER CONSERVATION PLAN

CHECKLISTS

S. No. Item

I General guidelines for furnishing information in the checklists

II Check list (General) for all Detailed Project Reports

III Check list for core-scheme components of

III (A) Interception & Diversion Detailed Project Reports &

III (B) Sewage Treatment Plant Detailed Project Reports

IV Checklist for Land Acquisition Detailed Project Reports

V Checklist for Low Cost Sanitation (Community Toilet Complex)


Detailed Project Reports

VI Checklist for Crematoria Detailed Project Reports

VII Checklist for River Front Development Detailed Project Reports

VIII Checklist for Afforestation Detailed Project Reports

IX Checklist for Municipal Solid Waste Management Detailed Project


Reports

X Checklist for Cattleshed & Biogas Plant Detailed Project Reports

2|P age
NATIONAL RIVER CONSERVATION PLAN
GENERAL GUIDELINES FOR FURNISHING INFORMATION
IN THE CHECKLISTS

I. THE CONTEXT AND PURPOSE

The purpose of requesting to furnish the checklists along with the Detailed
Project Report (DPR) of the scheme is essentially aimed at ensuring that all vital
details are included in the proposal. Completeness of information would facilitate
a comprehensive examination of the DPR and thus expediting the processing of
the case. It is therefore not only desirable but essential also to furnish all the
requested details in the DPR and cross check the same with the help of the
checklists to ensure the same.

II. PROCEDURE FOR FILLING UP OF THE CHECKLISTS

1. All the items of the checklist should be completed.

2. Attach separate sheets for explanation, wherever required, with proper


annotation (e.g., in the item 2, if details/information are to be furnished,
please attach s separate sheet with the caption: Information in regard to
item 2 of the checklist).

3. Each DPR is to be attached with the GENERAL checklist as well as


checklist of relevant project/scheme.

4. Incomplete checklists shall not be admissible. Response such as “will be


considered at the time of execution” shall also not be admissible.

5. In the case response is ‘Yes’, page number of the DPR is to be indicated


where the related detail is available.

6. In case the response is ‘Yes’, page/annexure number of each sub-item is


to be indicated categorically.

For example; Detailed Design – page -- to --.


Drawing – Annexure -- to --.
Estimation - page -- to --.

7. Reason/justification wherever applicable should be substantiated on the


basis of actual project and not on the basis of PFR.

3|P age
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST (GENERAL)

FOR

ALL DETAILED PROJECT REPORTS

4|P age
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST (GENERAL) FOR ALL DETAILED PROJECT REPORTS

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether the DPR is properly page numbered and
indexed.
2. Whether the salient features of the DPR have been
provided 1
3. Whether the certificate of concurrence from the
head of the local body in regard to following has
been furnished as annexure:
(a) the proposal and provisions made in the DPR,
and
(b) operation & maintenance (O&M) of the
project after the execution and the proposed
financial/institutional arrangements for sustainable
O&M thereof
4. Whether boundary of the project area/town has
been earmarked clearly on the map
5. Whether the copy of latest approved rates of
labour and material has been provided 2
6. Whether the list of schedule of rates (SOR) has
been annexed with the DPR 3
7. Whether the rates of non scheduled items like
pipes etc. annexed with the DPR 3
8. Whether the copy of budgetary quotation for non
scheduled items like pumps, generators etc.
annexed with DPR 3
9. Whether the calculations for arriving at the rates
for those items consisting of labour and materials
but not covered under Analysis of Rates have been
1
Salient features of the DPR should be attached in the beginning of the DPR in order to have an
idea of the project at a glance.
2
In case latest approved rates are few years old, justification for adopting rate of price escalation
to arrive at current year rates should be mentioned in the DPR and the escalated rates adopted in
the estimates.
3
Please ensure that specification of every item has been mentioned in the estimate.

5|P age
annexed with DPR
10. Whether soil testing report of every specific site
has been annexed with the DPR where provision
for excavation in soil, soft or hard rock has been
made in the DPR
11. Population Projection:
11 Whether the population projection has been
(a) carried out adopting various methods
11 Whether the justification for adopting the specific
(b) method of projected population has been
mentioned in the DPR
11 Whether base year of the project has been adopted
(c) as the year of expected commissioning of the
project 4
12. Whether detailed measurement sheet
(incorporating L, B, H/D columns) for each item
has been annexed immediately next to the abstract
of cost 5 of the particular item in the DPR
13. Whether detailed drawings of the works to verify
the quantity mentioned in the detailed
measurement sheet have been annexed with the
DPR
14 Whether estimate of the State Electricity Board
(a) has been provided in the DPR for power
connection (wherever applicable)
14 Also, whether calculations to arrive at the capacity
(b) of transformer has been furnished in the
TECHNICAL STATEMENT of the DPR
15. Whether duly signed NRCD Proforma (by Project
Manager/Executive Engineer) giving proper
justification for variation from PFR to DPR has
been annexed
16. Whether O&M cost calculations have been
mentioned in the DPR 6
17. Whether Bar Chart/CPM/PERT networks, based
on realistic time schedule of completion of

4
On a realistic basis.
5
Provision for any item in the DPR should not be made on Job/Lump Sum basis. Any provision
made without detailing shall not be considered by the NRCD.
6
NRCD guidelines are to be considered wherever applicable.

-2-
6|P age
different activities, has been annexed with the
DPR
18. Whether the cost of all DPRs is within the cost
approved by the CCEA
19. In the case where proposed cost of the scheme is
exceeding the CCEA approved cost, whether
commitment of the State Govt. to meet additional
cost of the scheme is available
20. Whether it has been ensured that the DPR has
been duly authenticated by the competent officer
of the implementing agency

Signature of Project Manager


/Executive Engineer

-3-

7|P age
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST (CORE-SCHEME COMPONENTS)

FOR

ALL DETAILED PROJECT REPORTS

-4-

8|P age
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR CORE-SCHEME COMPONENT


DETAILED PROJECT REPORTS OF
(B) SEWAGE TREATMENT PLANT SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether the DPR has been prepared on the basis of
detailed survey, investigation & engineering design
2. Whether all technical details of the items provided in
the project have been mentioned in the REPORT of
the DPR
3. Whether in economic/financial analysis, different
I&D proposals have been considered together with
STP (including decentralized STPs) to arrive at the
present one in the DPR 7
4. Whether a technical statement has been attached
which provides matching of different hydraulic levels
of related component of I&D in relation to STP
proposed
5. Whether a letter from the State Pollution Control
Board indicating quantity of treated industrial effluent
from ETPs contributing to discharge of drains/sewers
covered under the project has been attached with the
DPR 8
6. Whether the sewage characteristics (BOD, COD,
Nitrogen, Phosphorous, Chlorides, pH, temperature,
total suspended solids, volatile suspended solids and
faecal coliform) of the drains on a composite basis
have been arrived at after testing as per the CPHEEO
Manual
7. Whether the justification has been provided in the
DPR for higher and lower value of BOD parameter in
a drain 9
8. (a) Whether a detailed note on performance of existing
STP (if considered in the proposal) has been provided
in the DPR 10

7
Please include the analysis in the DPR.
8
Please indicate the name of industries in the DPR and linking it to the city index plan showing
point of contribution of treated effluent into the drain/sewer.
9
BOD of municipal sewage normally varies in range of 150-200 mg/lt.
9|P age
8. (b) Whether reasons for inadequate performance 11 of
existing STP (if considered in the proposal) have been
provided in the DPR
9. (a) Whether the site of the proposed STP has been
located as per that earmarked in the Master Plan of the
town 12
9. (b) Whether the provision of the land for the STP has
been made as per 30 years requirement in the DPR for
Land Acquisition
9. (c) Whether implementing agency has proposed for
stabilization ponds based technology of treatment at
the first instance 13
9. (d) Whether the lay out plan of proposed Ponds (or units
of other technologies) & future addition of the same
has been attached with the DPR
9. (e) Whether the STP capacity, to cater for ten years
requirement, has been adopted
9. (f) Whether modular approach adopted to facilitate “add-
on” units to STP at a future date, whenever required
9. (g) Whether the sewage treatment process has been
adopted on the basis of life cycle cost of different
prevalent technologies (including Karnal technology)
14

9. (h) Whether temperature, elevation and location of the


town has been taken into account while designing the
process of the STP, wherever required
9. (i) Whether detailed process and hydraulic designs
enclosed in DPR for units sizing
9. (j) Whether hydraulic drawing of the STP has been
annexed with the DPR
9. (k) Whether the treated effluent shall conform to the
standards mentioned in the guidelines of the NRCD,
which also includes that of faecal coliform
9. (l) Whether parameters of BOD, COD, TSS & Faecal
Coliform (at inlet & outlet of the STP) have been
indicated in the DPR
10
In the case where the STP is existing in the town and not considered in the proposal,
justification should be provided in the DPR for the same.
11
In case it is so.
12
Please attach the supporting documents with the DPR.
13
If not, a certificate from the Land Acquisition Officer to the effect that land as per requirement
is neither available nor/or it is not possible to change land use pattern at the suitable location for
the purpose needed to be annexed with the DPR.
14
Life cycle cost analysis should include capital cost, capitalized annual O&M cost less revenue
from resource recovery, and land cost. The summary of the analysis shall form an important
component of the DPR.
10 | P a g e
10. Whether contour map of the site has been annexed
with the DPR
11. Whether all items of treatment units (Intake Chamber,
Screen Chamber, Grit Channel along with
proportional flow weir, Conveyance Main from
Distribution Chamber to Primary Pond/Inlet to
Primary Pond, Interconnections, Outlet of the Pond to
Effluent Channel, Effluent Channel etc., in case of
Stabilization Ponds) have been designed as per the
CPHEEO Manual and detailed drawings and
estimates provided in the DPR 15
12. Whether the provision of pretreatment units has been
made as per ultimate year discharge of influent so that
additional modules could be added as per future
requirements
13. Whether the screen channel has been provided with
medium bar screen having clear opening of 20-30 mm
or less to arrest floating materials
14. (a) Whether the embankment top width of the ponds is
1.5 m to suit cost effectiveness
14. (b) Whether the slope of the embankment (in case of
ponds) has been adopted on the basis of soil test
report 16
14. (c) Whether lining of the ponds has been proposed 30cm
above and below the water level to control the erosion
of the surface due to wave action, as arrives through
the NRCD experience
14. (d) Whether lining of the ponds has also been proposed at
the bottom & embankments to check the percolation
to sub-soil water and the justification mentioned in the
DPR 17
14. (e) Whether the excavation and filling of the earth of the
ponds has been proposed to be carried out by adopting
balancing method
14. (f) Whether Inlet & Outlet structure of the Ponds has
been provided as per ‘Design Manual for Waste
Stabilization Ponds in India’ of the NRCD
15. Whether independent estimation & detailed
measurement for ancillary works such as boundary
wall/fencing, approach & internal road, external
electrification, staff quarters (as per the NRCD
guidelines), water supply & campus drainage, site
15
Design & drawings of all civil structures are to be annexed with the DPR.
16
Please attach the copy of the recommendations with the DPR.
17
Please annex the soil report to this effect along with the recommendations with the DPR.
11 | P a g e
development/landscaping etc. has been provided in
the DPR
16. Whether dimensional layout plan of the site showing
plan of the STP, piping, roads, staff quarters,
approach & internal roads, boundary wall/fencing,
external electrification points etc. along with land
marks of surrounding area annexed with the DPR
17. Whether provision for establishment of laboratory for
analysis of important parameters of sewage/river
water has been made in the DPR
18. Whether provision for 6 months O&M of the STP for
stabilization purpose has been made in the DPR
19. (a) Whether possibilities for utilization of treated effluent
for agriculture irrigation, pisciculture, industrial
process use etc. have been explored
19. (b) If so, whether estimated quantities and revenue/year
as resource recovery has been given in the DPR
19. (c) Whether arrangements for storage of bio-gas (in the
case of generation in the treatment process) has been
made
19. (d) If so, whether expected resource recovery has been
proposed in the DPR;
(i) by distributing the bio-gas to the nearby residents,
(ii) through power generation
20. Whether disposal of the treated effluent back in the
river has been made at the point after which it shall
not become the reason for health hazard to the
populace and a detailed note about the same has been
included in the report part
21. Whether it has been mentioned in the DPR that the
tender bid for the implementation of works shall also
include the O&M of the STP for 10 years

Signature of Project Manager


/Executive Engineer

12 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST

FOR

CORE-SCHEME COMPONENTS OF

INTERCEPTION & DIVERSION

AND

SEWAGE TREATMENT PLANT

DETAILED PROJECT REPORTS

13 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR CORE-SCHEME COMPONENT


DETAILED PROJECT REPORTS OF
(A) INTERCEPTION & DIVERSION SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether the DPR has been prepared on the basis
of detailed survey, investigation & engineering
design
2. Whether all technical details of the items
provided in the project have been mentioned in
the REPORT of the DPR 18
3. Whether in economic/financial analysis, different
I&D proposals have been considered together
with STP (including decentralized STPs) to arrive
at the present one in the DPR 19
4. Whether a technical statement has been attached
which provides matching of different hydraulic
levels in relation to STP proposed
5. Whether linkages of this scheme have been
established with other ongoing sewerage schemes
being funded by the Central/State Govt., if
applicable
6. Whether the proposed I&D system has been so
designed to become a part of town’s sewerage
system and sewage treatment facility, whenever
required in future
7. Whether a certificate to the effect that no
municipal sewage shall fall in the river after the
implementation of the proposed project has been
provided in the DPR
8. Whether the details of existing sewerage system
and proposal for its amalgamation with that
proposed in the DPR has been mentioned in
details in the REPORT and accounted for in the

18
e.g., size, type & length of sewer/rising main, duties of the pumps etc.
19
Please include the analysis in the DPR.

-1-
14 | P a g e
TECHNICAL STATEMENT
9. Whether the area earmarked for the project in the
town (in A-3 size paper) showing the location of
the drains outfalling in the river, their names &
catchment area, existing and proposed major
works of the scheme are annexed along with
description of I&D proposal in the REPORT of
the DPR 20
10. (a) Whether present sewage generation in the town
has been obtained on the basis of actual discharge
measurement of each drain carried out for over a
month during dry weather 21
10. (b) Whether sewage interception factor 22 and peak
factor of each drain has been worked out and
indicated in the TECHNICAL STATEMENT of
the DPR
11. (a) Whether the rate of water supply for projection of
sewage generation has been adopted on actual
basis
11. (b) In case where actual rate of water supply is higher
than the norms of the latest CPHEEO Manual,
whether the estimation of sewage based on the
norms of the Manual has been compared with the
actual flow of the sewage and higher of the two
values taken at the time of submission of the
DPR, and has been adjusted at the normative
levels of the Manual when projecting for the
future and indicated in the TECHNICAL
STATEMENT of the DPR
11. (c) Whether projected minimum, average & peak
discharges of each drain (in litres per second-lps
as well as million litres per day-mld), its
interception & peak factors during different
design years along with present sewage flow have
been indicated in the tabular form in the
REPORT & TECHNICAL STATEMENT of the
20
Bigger size map having details are to be annexed with the DRAWING part of the DPR.
21
Please annex the table showing the summary of minimum, average & peak discharges along
with interception & peak factors with the REPORT & TECHNICAL STATEMENT of the DPR.
22
The sewage interception factor of each drain should be worked out on the basis of
contributory population of the catchment area of the drain and water supply rate.

-2-
15 | P a g e
DPR
12. (a) Whether hydraulic design of the proposed sewer
has been annexed with the DPR
12. (b) Whether all the sewers have been checked for
minimum self-cleansing velocity of 0.6 m/s
during average flow conditions, by providing
proper slope
12. (c) Whether flow depth to diameter ratios adopted
while designing sewers
13. Whether basis for selection of gravity
sewer/rising main material has been provided in
the DPR 23
14. Whether existing & proposed sewer plan annexed
with the DPR
15. Whether bedding conditions for different reaches
of the proposed sewer have been designed as per
the CPHEEO Manual and the design annexed
with the DPR
16. Whether silt traps on road side, if required, as
gully pits to avoid silting of sewers have been
provided
17. Whether detailed manhole-to-manhole survey of
existing sewers has been conducted and
provisions for sewer cleaning if required,
accordingly, made in the DPR
18. Whether manhole size & spacing have been
adopted as per the CPHEEO Manual
19. Whether manhole cover preferably of Ferro-
cement have been provided in the sewer
alignment to avoid theft of the same
20. Whether type of subsoil strata up to sewer invert
level, subsoil water table data and type of road
surface over the proposed sewers alignments has
been mentioned in the L-Section of the proposed
sewer
21. (a) Whether sewers are planned to be laid below sub-
soil water table
21. If so, whether justification for the same and the
23
Reference is drawn to Para 6.3 of the Manual on Water Supply & Treatment; May 1999
Edition of the CPHEEO, Ministry of Urban Development in this matter.

-3-
16 | P a g e
(b) precautionary measures to be taken during laying
of sewer has been mentioned in the DPR
22. Whether L-Section of the existing/proposed rising
main annexed with the DPR
23. (a) Whether economical size of the rising main has
arrived at after considering at least 3 diameters of
each of pipe materials of PSC, CI & DI etc. 24
23. (b) Whether the chosen diameter of the rising main
provide at least 0.60 m/s velocity for the base
year average flow
23. (c) Whether surge/water hammer analysis for rising
main has been calculated and mentioned in the
DPR
23. (d) Whether the design of thrust/anchor blocks made
in the DPR
23. (e) Whether rising main accessories, wherever
needed, such as thrust blocks, anchor blocks,
expansion joints, scour/drain valves, air/vacuum
release valves and surge protection devices
provided in the DPR 25
24. In case proposed sewer/rising main is crossing
railway line/Highway & their bridges (wherever
applicable), whether permission of the concerned
organization has been obtained and the copies of
the permission and their estimate for the same
annexed with the DPR
25. (a) Whether re-sectioning/lining of the drain for
protection/training purpose has been restricted to
30 m upstream and 20 m downstream of tapping
arrangement
25. (b) Whether the cross section at various chainage and
L-Section of the drain, in which re-
sectioning/lining is to be done, has been indicated
in the drawing sheet
25. (c) Whether the cross section of the drain has been
designed on the basis of rainfall data of the area

24
MS pipe, due to the corrosive nature of the sewage, is not recommended for sewage
conveyance, except after special treatment.
25
Please mention about them in the REPORT along with reference of page number/item number
of the estimation of the same over here as well.

-4-
17 | P a g e
and accordingly calculations have been shown in
the technical statement of the DPR
26. (a) Whether detailed dimensional drawings of nalla
tapping & allied works (also showing ground
level, bed/invert levels etc.) enclosed
26. (b) Whether nalla tapping works need deforestation
or rehabilitation of people/properties or
encroachments problems? 26
26. (c) If so, whether details and solutions have been
proposed in the DPR
26. (d) Whether arrangements of de-gritting and
screening the diverted flow from the tapping
arrangement, before joining the sewers/pumping
station made
27. (a) Whether the capacity of the sump of the pumping
station has been calculated on the basis of 3.75
Minutes detention period of peak discharge
during the ultimate design year
27. (b) Whether size of sump of the pumping station has
been has been out checked with pump
manufacturer for adequacy and so mentioned in
the DPR
27. (c) Whether scouring depth calculations have been
made to arrive at the depth of the pumping station
foundation, in case river flow shall affect the
structure during normal rainy season 27
27. (d) Whether proposed pumping station houses
submersible pumps
27. (e) In the case of ‘No’ in 27 (d) and where
horizontal/vertical motor driven pumps have been
provided, whether justification for provision of
twin sumps instead of single sump considering
overall costs of alternatives provided in the DPR
27. (f) Whether the calculations to arrive at different
invert levels 28 have been mentioned in the
technical statement of the DPR and shown in the

26
In case there is no such requirement, mention so in the DPR.
27
Scour depth calculation should take into account highest flood flow of the river.
28
(ground level, sump bed, bottom of submergible pump, top of submersible pump, storage top,
incoming sewer etc.)

18 | P a g e
drawing
27. (g) Whether the structural design, drawing &
estimate of sump of the pumping station has been
made the part of the DPR
27. (h) Whether land marks of the surrounding area have
been shown in the layout plan of pumping station
campus
27. (i) In the case where approach road and internal road
has been provided inside the campus of pumping
station, whether layout of the same has been
shown in the layout drawing of the pumping
station
28. (a) Whether the efficiency of the pump adopted,
while calculating the BHP, is in conformity with
the duties of the pumps proposed 29
28. (b) Whether the configuration of the pumps proposed
in each pumping station is in conformity with the
guidelines of the NRCD
28. (c) Whether friction losses inside the pump house as
per proposed installation of pumps have been
calculated and accounted for while calculating
duties of the pump in the DPR
28. (d) Whether the provision for required accessories to
pumping plants has been made
28. (e) Whether the details of specifications of the
control panel, starters, pressure gauge etc. have
been provided in the estimate
28. (f) Whether the size of sluice & reflex valves have
been adopted as per the CPHEEO Manual
28. (g) Whether the details of CI connecting pipes &
specials inside the pump house have been
provided in the DPR and accordingly provisions
made
28. (h) Whether flow measuring instrument provided on
the delivery header of pumping station
29. Whether provision for separate electric feeder
line to pumping stations (to take care of frequent
power failure and voltage fluctuation problem)
from HT line has been made in the DPR
29
Supporting documents are to be attached with the DPR.

19 | P a g e
30. (a) Whether provision for DG set has been made in
the DPR to account for interrupted power supply
30

30. (b) In case provision for DG set has been made in the
DPR, whether the calculations to arrive at the
capacity of the same has been mentioned in the
technical statement
31. (a) Whether the provision for staff quarters made, as
per guidelines of the NRCD, in the DPR
31. (b) Whether the ground for adopting a percentage of
civil construction cost towards water supply &
sanitation and electric fittings has been mentioned
in the DPR 31
32. Whether the provision of control and panel room
made in the DPR as per specifications of the State
Electricity Board 32
33. Whether unit estimates of manholes, gully pits,
ventilating columns, boundary wall, gate with
pillars, chambers etc. have been annexed with the
DPR
34. Whether provision for road restoration has been
made as per CPWD/State PWD/Local Body
norms & rates
35. Whether provision for 6 months trial run cost for
pumping station, after commissioning, has been
made
36. Whether the provision of land for pumping
station including electric sub-station has been
made in the DPR for Land Acquisition, in case it
is not available free of cost
37. (a) Whether the sites chosen for I&D scheme are free
of flooding?
37. (b) If not, reasons for choosing such alignment and
locations and measures, to avoid impact of floods
38. Whether traffic diversion/control arrangements
for public and workers’ safety, arising out of
construction phase of I&D works, have been
covered in the DPR

20 | P a g e
Signature of Project Manager
/Executive Engineer

31 In the case where power supply situation is satisfactory in the town, please attach a certified
copy of statement of the State Electricity Board regarding the same.
32 Please attach a copy with the DPR.
33 Please attach the copy of the specification in support with the DPR.

21 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR CORE-SCHEME COMPONENT


DETAILED PROJECT REPORTS OF
(B) SEWAGE TREATMENT PLANT SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1.Whether the DPR has been prepared on the basis of
detailed survey, investigation & engineering design
2. Whether all technical details of the items provided in
the project have been mentioned in the REPORT of
the DPR
3. Whether in economic/financial analysis, different
I&D proposals have been considered together with
STP (including decentralized STPs) to arrive at the
present one in the DPR 33
4. Whether a technical statement has been attached
which provides matching of different hydraulic levels
of related component of I&D in relation to STP
proposed
5. Whether a letter from the State Pollution Control
Board indicating quantity of treated industrial effluent
from ETPs contributing to discharge of drains/sewers
covered under the project has been attached with the
DPR 34
6. Whether the sewage characteristics (BOD, COD,
Nitrogen, Phosphorous, Chlorides, pH, temperature,
total suspended solids, volatile suspended solids and
faecal coliform) of the drains on a composite basis
have been arrived at after testing as per the CPHEEO
Manual
7. Whether the justification has been provided in the
DPR for higher and lower value of BOD parameter in
a drain 35
8. (a) Whether a detailed note on performance of existing
STP (if considered in the proposal) has been provided
in the DPR 36
33
Please include the analysis in the DPR.
34
Please indicate the name of industries in the DPR and linking it to the city index plan showing
point of contribution of treated effluent into the drain/sewer.
35
BOD of municipal sewage normally varies in range of 150-200 mg/lt.
22 | P a g e
8. (b) Whether reasons for inadequate performance 37 of
existing STP (if considered in the proposal) have been
provided in the DPR
9. (a) Whether the site of the proposed STP has been
located as per that earmarked in the Master Plan of the
town 38
9. (b) Whether the provision of the land for the STP has
been made as per 30 years requirement in the DPR for
Land Acquisition
9. (c) Whether implementing agency has proposed for
stabilization ponds based technology of treatment at
the first instance 39
9. (d) Whether the lay out plan of proposed Ponds (or units
of other technologies) & future addition of the same
has been attached with the DPR
9. (e) Whether the STP capacity, to cater for ten years
requirement, has been adopted
9. (f) Whether modular approach adopted to facilitate “add-
on” units to STP at a future date, whenever required
9. (g) Whether the sewage treatment process has been
adopted on the basis of life cycle cost of different
prevalent technologies (including Karnal technology)
40

9. (h) Whether temperature, elevation and location of the


town has been taken into account while designing the
process of the STP, wherever required
9. (i) Whether detailed process and hydraulic designs
enclosed in DPR for units sizing
9. (j) Whether hydraulic drawing of the STP has been
annexed with the DPR
9. (k) Whether the treated effluent shall conform to the
standards mentioned in the guidelines of the NRCD,
which also includes that of faecal coliform
9. (l) Whether parameters of BOD, COD, TSS & Faecal
Coliform (at inlet & outlet of the STP) have been
indicated in the DPR
36
In the case where the STP is existing in the town and not considered in the proposal,
justification should be provided in the DPR for the same.
37
In case it is so.
38
Please attach the supporting documents with the DPR.
39
If not, a certificate from the Land Acquisition Officer to the effect that land as per requirement
is neither available nor/or it is not possible to change land use pattern at the suitable location for
the purpose needed to be annexed with the DPR.
40
Life cycle cost analysis should include capital cost, capitalized annual O&M cost less revenue
from resource recovery, and land cost. The summary of the analysis shall form an important
component of the DPR.
23 | P a g e
10. Whether contour map of the site has been annexed
with the DPR
11. Whether all items of treatment units (Intake Chamber,
Screen Chamber, Grit Channel along with
proportional flow weir, Conveyance Main from
Distribution Chamber to Primary Pond/Inlet to
Primary Pond, Interconnections, Outlet of the Pond to
Effluent Channel, Effluent Channel etc., in case of
Stabilization Ponds) have been designed as per the
CPHEEO Manual and detailed drawings and
estimates provided in the DPR 41
12. Whether the provision of pretreatment units has been
made as per ultimate year discharge of influent so that
additional modules could be added as per future
requirements
13. Whether the screen channel has been provided with
medium bar screen having clear opening of 20-30 mm
or less to arrest floating materials
14. (a) Whether the embankment top width of the ponds is
1.5 m to suit cost effectiveness
14. (b) Whether the slope of the embankment (in case of
ponds) has been adopted on the basis of soil test
report 42
14. (c) Whether lining of the ponds has been proposed 30cm
above and below the water level to control the erosion
of the surface due to wave action, as arrives through
the NRCD experience
14. (d) Whether lining of the ponds has also been proposed at
the bottom & embankments to check the percolation
to sub-soil water and the justification mentioned in the
DPR 43
14. (e) Whether the excavation and filling of the earth of the
ponds has been proposed to be carried out by adopting
balancing method
14. (f) Whether Inlet & Outlet structure of the Ponds has
been provided as per ‘Design Manual for Waste
Stabilization Ponds in India’ of the NRCD
15. Whether independent estimation & detailed
measurement for ancillary works such as boundary
wall/fencing, approach & internal road, external
electrification, staff quarters (as per the NRCD
guidelines), water supply & campus drainage, site
41
Design & drawings of all civil structures are to be annexed with the DPR.
42
Please attach the copy of the recommendations with the DPR.
43
Please annex the soil report to this effect along with the recommendations with the DPR.
24 | P a g e
development/landscaping etc. has been provided in
the DPR
16. Whether dimensional layout plan of the site showing
plan of the STP, piping, roads, staff quarters,
approach & internal roads, boundary wall/fencing,
external electrification points etc. along with land
marks of surrounding area annexed with the DPR
17. Whether provision for establishment of laboratory for
analysis of important parameters of sewage/river
water has been made in the DPR
18. Whether provision for 6 months O&M of the STP for
stabilization purpose has been made in the DPR
19. (a) Whether possibilities for utilization of treated effluent
for agriculture irrigation, pisciculture, industrial
process use etc. have been explored
19. (b) If so, whether estimated quantities and revenue/year
as resource recovery has been given in the DPR
19. (c) Whether arrangements for storage of bio-gas (in the
case of generation in the treatment process) has been
made
19. (d) If so, whether expected resource recovery has been
proposed in the DPR;
(i) by distributing the bio-gas to the nearby residents,
(ii) through power generation
20. Whether disposal of the treated effluent back in the
river has been made at the point after which it shall
not become the reason for health hazard to the
populace and a detailed note about the same has been
included in the report part
21. Whether it has been mentioned in the DPR that the
tender bid for the implementation of works shall also
include the O&M of the STP for 10 years

Signature of Project Manager


/Executive Engineer

25 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST

FOR

LAND ACQUISITION

DETAILED PROJECT REPORTS

26 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR

DETAILED PROJECT REPORTS OF


LAND ACQUISITION SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether the purpose of land acquisition along with
area in hectare (and cost) of each item has been
mentioned in the DPR
2. Whether the existing & proposed works of I&D and
STP (and other components like LCS, Crematoria)
have been shown in the index plan of the town and
annexed with the DPR
3. Whether location of land proposed to be acquired has
been shown in the index plan of the town 44
4. Whether the revenue map of plots (proposed for
acquisition) enclosed with the DPR
5. Whether layout plan of pumping station/STP or any
other item as per the proposal has been annexed with
the DPR
6. Whether types of present land use for each site
selected has been mentioned in the DPR
7. Whether each site related to schemes proposed in the
DPR is free of flooding and devoid of hard rock
formation
8. Whether it has been ensured that each site (in item 7
above) is free of litigation and/or encroachment
9. Whether letter of the Land Acquisition Officer
specifying land cost, registration charges etc. (on the
basis of which cost of land per hectare adopted) has
been enclosed with the DPR
10. Whether the consent letter of the owner of the land to
the effect of its transfer to the implementing agency
has been attached with the DPR, in the case where
land is available free of cost 45
11. Whether different year design flows on the basis of
44
Land for I&D and STP works should be proposed for acquisition on the basis of 30 years
requirement, as per the NRCD guidelines.
45
It is to be complied with in those cases also where the owner is the local body.

27 | P a g e
population projection, rate of water supply,
interception factor etc. has been mentioned in a
tabular form in the DPR
12. Whether the sewage treatment process has been
adopted on the basis of life cycle cost of different
prevalent technologies (including Karnal technology)
13. Whether time taken in each activity of the acquisition
has been mentioned in the DPR
14. Whether start of work of each item of I&D and STP is
matching with date of possession of land for the
purpose
15. (a) Whether trial pits/ bore-whole data and other relevant
investigation/surveys 46 carried out at the proposed
sites
15. (b) If so, whether details of soil bearing capacity and
other technical data enclosed with the DPR

Signature of Project Manager


/Executive Engineer

46
It would be needed for design of relevant items of works.

28 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST

FOR

LOW COST SANITATION (COMMUNITY TOILET COMPLEX)

DETAILED PROJECT REPORTS

29 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR

DETAILED PROJECT REPORTS OF


LOW COST SANITATION (COMMUNITY TOILET COMPLEX)
SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1.Whether identification and marking of space used
for open defecation on city index plan has been
annexed with the DPR
2. Whether location of each of existing LCS units in
the town along with their present condition 47 and
O&M arrangements, level of utilization during last
one year have mentioned in the REPORT of the
DPR and the location shown in the index plan of
the town
3. Whether details of activities already taken up by
the local body or the Social Welfare Department
& other State Govt. agency have been indicated in
the DPR
4. Whether proposed LCS units in the town have
been mentioned in the DPR and shown in the
index plan of the town
5. Whether basis for selection of location of each
proposed LCS unit, its seating capacity (on the
basis of expected number of users) has been
mentioned in the DPR 48
6. Whether renovation of existing LCS units or
increasing its capacity, if applicable/required, has
been provided in the DPR
7. (a) Whether the copy of the consent letter of the
owner of the land has been attached with the DPR,
in the case where land is available free of cost 49
47
Please indicate number of seats against each existing LCS also.
48
LCS/Community toilets of 10, 15 and 20 seat capacity may be provided depending upon the
space and number of expected users.
49
It is to be complied with in those cases also where the owner is the local body.

30 | P a g e
7. (b) In the case where land is to be purchased, whether
provision for it has been made in the Land
Acquisition DPR
7. (c) In case land is to be purchased, whether the type
of present land use for each proposed unit has
been mentioned in tabular form in the DPR
8. Whether layout plan of each LCS complex along
with land marks of surrounding area has been
annexed with the DPR
9. Whether detailed drawing of LCS complex has
been annexed
10. Whether soil test report of those sites, where
foundation of the building is to be laid in soil
other than normal soil, has been annexed with the
DPR 50
11. (a) Whether the proposed LCS unit has been
connected to the nearest sewer and provision made
accordingly
11. (b) In the case where sewer is not available nearby
and septic tank provided, whether cost comparison
of both alternatives for each case mentioned in the
DPR
12. Whether size of the soak pit & septic tank is in
conformity with the seating capacity of the LCS
unit and its design annexed with the DPR
13. Whether provision for proper lighting of the LCS
complex made in the DPR
14. Whether provision for boundary wall along with
gate, if applicable, has been made in the DPR
15. Whether provision for adequate number of urinals,
located outside the front part of the building, has
been made in the DPR
16. Whether provision for adequate water supply by
municipal main, shallow depth tubewell or jet
pump (as per the site conditions) has been made
17. Whether estimate of State Electricity Board for
power connection for each LCS unit has been
annexed with the DPR

50
Please attach the report with the DPR.

31 | P a g e
18. Whether proper size of water storage tank and its
basis, as per requirement of the LCS unit, has been
provided in the DPR
19. Whether the calculations to arrive at the O&M
cost has been annexed with the DPR
20. (a) Whether envisaged resource recovery (on the
basis of user’s payment) has been mentioned in
the DPR
20. (b) Whether institutional mechanism for proper O&M
of the proposed LCS units has been mentioned in
the DPR

Signature of Project Manager


/Executive Engineer

32 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST

FOR

CREMATORIA

DETAILED PROJECT REPORTS

33 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR

DETAILED PROJECT REPORTS OF


CREMATORIA SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether a note on existing cremation ghats of
the town, mode of cremation, number & type
of crematoria installed at each ghat, their
condition at present, their level of utilization
etc. has been provided in the DPR 51
2. In the case where electric/wood based
crematoria have been established under GAP
or NRAP in the town, whether performance
and acceptance of different type of crematoria
has been indicated in the DPR
3. Whether number & type of crematoria
approved at PFR stage has been mentioned
4. Whether the justification for proposing
Electric Crematoria in place of Improved
Wood Crematoria (in case Improved Wood
Crematoria approved by CCEA) has been
mentioned in the report 52
5. Whether number of cremation taking place
during the last 5 years as per the records at the
particular ghat/site proposed for the town has
been mentioned in the DPR
6. In the case where improved wood crematoria
have been proposed in the town, whether
design with latest modification/improvement
based on the study on those installed under
Ganga Action Plan and NRAP has been
adopted in the DPR in order to conserve more
wood
51
Location of existing cremation ghats is to be shown on city index plan.
52
Electric Crematoria should be proposed in those towns only where its acceptability and
subsequent utilization is anticipated.

34 | P a g e
7. Whether the justification of proposing the
number of cremation beds/units at the
particular ghat/site proposed of the town has
been mentioned in the DPR
8. Whether the location of the crematoria has
been marked on the city index plan
9. (a) Whether the land for crematoria is available
free of cost 53
9. (b) In the case where land is to be purchased,
whether the provision for same has been made
in the DPR for Land Acquisition
10. Whether basis for sizing of furnace hall,
waiting hall, office, caretaker room, electric
switch room, generator room etc. (in case of
electric crematoria) has been mentioned in the
DPR
11. Whether justification for providing mortuary
room, record room (in case of electric
crematoria) has been provided in the DPR
12. Whether the basis for selected size of water
storage tank has been mentioned in the DPR
13. Whether the provision of the tube-well for
water supply has been made as per
requirement and sub-soil water strata at the
site 54
14. Whether plan of the site showing the lay-
out/location of the crematoria building, roads,
boundary wall/gate, external lighting etc.
along with landmarks of surrounding area has
been annexed with the DPR
15. Whether detailed drawing of the crematoria
building/shed has been annexed
16. Whether the calculations to arrive at the
capacities of the transformer & generator (in
case of electric crematoria) have been shown
in the DPR

53
In the case where land is available free of cost, letter of the owner of the land for the same is
to be annexed with the DPR
54
In order to limit the O&M cost.

35 | P a g e
17. Whether the height of the chimney proposed
for dispersal of gases is 9 meters (in case of
electric crematoria) 55
18. Whether the provision for land development
and landscaping, if provided, has been made
as per detailed survey and actual site
requirements
19. Whether institutional mechanism for proper
O&M of the proposed crematoria has been
mentioned in the DPR

Signature of Project Manager


/Executive Engineer
55
Height of the chimney is to be adopted taking into consideration the surrounding area of the
location of the site, so that the dispersed gases do not affect the environment of nearby residents.

36 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST

FOR

RIVER FRONT DEVELOPMENT

DETAILED PROJECT REPORTS

37 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR

DETAILED PROJECT REPORTS OF


RIVER FRONT DEVELOPMENT SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether justification for proposing river front
development for a town has been mentioned in the DPR
2. Whether identification of improvements required in
each bathing ghats has been indicated in the DPR
3. Whether the basis for adopting a particular length of
river front development has been mentioned in the DPR
4. Whether location of proposed development of river
front has been shown in the city index plan
5. Whether the DPR has been prepared in consultation
with the Irrigation Department of the State (on items
relevant to the Irrigation Department) and the copy of
their approval annexed with the DPR
6. In the case where illumination has been proposed in the
area, whether illumination points have been earmarked
on the layout plan of the works
7. Whether detailed design, drawing and estimation of all
the items (wherever applicable) has been provided in
the DPR

Signature of Project Manager


/Executive Engineer

38 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST

FOR

AFFORESTATION

DETAILED PROJECT REPORTS

39 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR

DETAILED PROJECT REPORTS OF



AFFORESTATION SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether layout plan of the area proposed for plantation
annexed with the DPR
2. Whether the provisions of trees has been made for
block plantation
3. Whether the provision of planting avenue/aesthetic/
environment friendly 56 trees has been made along the
boundary walls of the STP and pumping station
4. Whether provision for dense foliage plantation around
pumping station, STP has been made in the DPR
5. Whether plantation of revenue earning trees has been
made, as resource recovery, in the area of STP meant
for future expansion
6. Whether appropriate mechanism for maintenance &
protection of plantation for a period of three years has
been indicated in the DPR

Signature of Project Manager


/Executive Engineer


The afforestation schemes are prepared for planting trees in the NRCP work schemes of
Interception & Diversion, Sewage Treatment Plant, Low Cost Sanitation Complex (or
Community Toilet Complex), River Front Development & crematoria in order to improve the
aesthetics of the project area.
56
e.g., Neem etc.

40 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST

FOR

MUNICIPAL SOLID WASTE MANAGEMENT

DETAILED PROJECT REPORTS

41 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST FOR

DETAILED PROJECT REPORTS OF


MUNICPAL SOLID WASTE MANAGEMENT SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether link establishing municipal solid waste vis-
à-vis pollution of the river has been established in the
DPR
2. Whether the provision to regulate the management
and handling of the municipal solid wastes covering
collection, segregation, storage, transportation,
processing and disposal of municipal solid wastes
has been made as per the Municipal Solid Wastes
(Management and Handling) Rules, 2000 of the
Ministry of Environment & Forests
3. Whether an undertaking of the local body to the
effect that bio-medical waste and hazardous waste
will be managed separately from the Municipal Solid
Waste as per the Bio-Medical (Management and
Handling) Rules, 1998 & the Hazardous Waste
(Management and Handling) Rules, 1989
respectively has been attached with the DPR
4. Whether proposal has been prepared on the basis of
decentralized management as a measure of economy
and justified in the REPORT of the DPR
5. Whether the scheme caters to for present requirement
of solid waste generation and management
6. Whether a study, to assess the present actual
generation of the municipal waste in the town, has
been carried out and accordingly mentioned in the
DPR 57
7. Whether a provision for segregation of bio-
degradable & non-bio-degradable waste at the point
of collection has been made in the DPR
8. Whether appropriate technologies for waste
processing & disposal facilities have been considered

57
Please attach a copy of the Study with the DPR.

42 | P a g e
9. (a) Whether an assessment of the assets required for the
scheme has been undertaken for the whole town 58
9. (b) Whether detailed estimation of the assets to be
created has been made in the DPR
9. (c) Whether unit estimates of each construction item and
its drawing has been annexed with the DPR
10. (a) Whether the provision for the land for 30 years has
been made in the DPR for Land Acquisition, in case
it is not available free of cost
10. (b) Whether the consent letter of the owner of the land to
the effect of its transfer to the implementing agency
has been attached with the DPR, in the case where
land (for 30 years requirement) is available free of
cost 59
10. (c) Whether land for disposal is located in such a way
that it shall not affect the health of the residents of
the town 60
10. (d) Whether the proposed land is located in Non-flood
prone area and easily accessible during rains
11. Whether the location 61 and layout plan of the land
proposed for processing & disposal has been annexed

58
Please specify and justify in the DPR.
59
It is to be complied with in those cases also where the owner is the local body.
60
Please justify in the REPORT of the DPR.
61
On the city index plan.

43 | P a g e
NATIONAL RIVER CONSERVATION PLAN

CHECK LIST

FOR

CATTLESHED AND BIOGAS PLANTS

DETAILED PROJECT REPORTS


NATIONAL RIVER CONSERVATION PLAN

44 | P a g e
CHECK LIST FOR

DETAILED PROJECT REPORTS OF



CATTLESHED AND BIOGAS PLANTS SCHEMES

S. No. Question Response (Please √)


Yes Page If No,
No. reasons
thereof
1. Whether the purpose of construction of cattle shed in
reference to river pollution abatement has been
justified in the DPR
2. Whether quantification details of dairy waste have
been provided in the DPR
3. Whether present location of dairy & disposal points
of dairy waste have been given in the REPORT of
the DPR and marked on the city index plan 61
4. Whether the resolution by the local body to the effect
that it agrees with the proposal made in the DPR &
that the assets created for the purpose would not
remained unutilized has been indicated in the DPR 61
5. Whether the copy of the consent letters of the diary
owners who shall be displaced has been attached
with the DPR (to avoid litigation etc. and delay in
implementation)
6. Whether the number of the sheds and its capacity has
been adopted on the basis of present number of cattle
population in the town 61
7. Whether proposed location of the cattle shed has
been marked on the city index plan
8. In the case where land is available free of cost,
whether consent letter of the owner of the land for
the same is annexed with the DPR
9. In the case where land is to be purchased, whether
provision for the same has been made in the DPR for
Land Acquisition
10. (a) Whether the basis for arriving at the capacity of
biogas plant has been given in the DPR
10. (b) Whether detailed drawing of the biogas plant has
been annexed with the DPR
10. (c) Whether revenue generation through utilization of
biogas generated is envisaged, if yes, whether it has
been mentioned in the DPR
45 | P a g e
12. Whether a note on feasibility, planning & marketing
strategy for resource recovery by ways of recycling,
energy generation, sale of manure and reclaiming the
dumping site has been included in the REPORT of
the DPR

Signature of Project Manager


/Executive Engineer

11. Whether other alternatives like steel trusses with


GI/Asbestos sheets for cattle shed, as an alternative
to concrete structure, have also been considered 61
12. Whether the basis for adopting the layout plan of the
cattle shed and provision of related sub-items has
been given in the DPR
13. Whether the details & basis of estimate of cartage of
required materials have been given in the DPR

Signature of Project Manager


/Executive Engineer

46 | P a g e
47 | P a g e

You might also like