DPR Preparation Guideline by NRCD
DPR Preparation Guideline by NRCD
DPR Preparation Guideline by NRCD
CHECK LISTS
FOR
1|P age
NATIONAL RIVER CONSERVATION PLAN
CHECKLISTS
S. No. Item
2|P age
NATIONAL RIVER CONSERVATION PLAN
GENERAL GUIDELINES FOR FURNISHING INFORMATION
IN THE CHECKLISTS
The purpose of requesting to furnish the checklists along with the Detailed
Project Report (DPR) of the scheme is essentially aimed at ensuring that all vital
details are included in the proposal. Completeness of information would facilitate
a comprehensive examination of the DPR and thus expediting the processing of
the case. It is therefore not only desirable but essential also to furnish all the
requested details in the DPR and cross check the same with the help of the
checklists to ensure the same.
3|P age
NATIONAL RIVER CONSERVATION PLAN
FOR
4|P age
NATIONAL RIVER CONSERVATION PLAN
5|P age
annexed with DPR
10. Whether soil testing report of every specific site
has been annexed with the DPR where provision
for excavation in soil, soft or hard rock has been
made in the DPR
11. Population Projection:
11 Whether the population projection has been
(a) carried out adopting various methods
11 Whether the justification for adopting the specific
(b) method of projected population has been
mentioned in the DPR
11 Whether base year of the project has been adopted
(c) as the year of expected commissioning of the
project 4
12. Whether detailed measurement sheet
(incorporating L, B, H/D columns) for each item
has been annexed immediately next to the abstract
of cost 5 of the particular item in the DPR
13. Whether detailed drawings of the works to verify
the quantity mentioned in the detailed
measurement sheet have been annexed with the
DPR
14 Whether estimate of the State Electricity Board
(a) has been provided in the DPR for power
connection (wherever applicable)
14 Also, whether calculations to arrive at the capacity
(b) of transformer has been furnished in the
TECHNICAL STATEMENT of the DPR
15. Whether duly signed NRCD Proforma (by Project
Manager/Executive Engineer) giving proper
justification for variation from PFR to DPR has
been annexed
16. Whether O&M cost calculations have been
mentioned in the DPR 6
17. Whether Bar Chart/CPM/PERT networks, based
on realistic time schedule of completion of
4
On a realistic basis.
5
Provision for any item in the DPR should not be made on Job/Lump Sum basis. Any provision
made without detailing shall not be considered by the NRCD.
6
NRCD guidelines are to be considered wherever applicable.
-2-
6|P age
different activities, has been annexed with the
DPR
18. Whether the cost of all DPRs is within the cost
approved by the CCEA
19. In the case where proposed cost of the scheme is
exceeding the CCEA approved cost, whether
commitment of the State Govt. to meet additional
cost of the scheme is available
20. Whether it has been ensured that the DPR has
been duly authenticated by the competent officer
of the implementing agency
-3-
7|P age
NATIONAL RIVER CONSERVATION PLAN
FOR
-4-
8|P age
NATIONAL RIVER CONSERVATION PLAN
7
Please include the analysis in the DPR.
8
Please indicate the name of industries in the DPR and linking it to the city index plan showing
point of contribution of treated effluent into the drain/sewer.
9
BOD of municipal sewage normally varies in range of 150-200 mg/lt.
9|P age
8. (b) Whether reasons for inadequate performance 11 of
existing STP (if considered in the proposal) have been
provided in the DPR
9. (a) Whether the site of the proposed STP has been
located as per that earmarked in the Master Plan of the
town 12
9. (b) Whether the provision of the land for the STP has
been made as per 30 years requirement in the DPR for
Land Acquisition
9. (c) Whether implementing agency has proposed for
stabilization ponds based technology of treatment at
the first instance 13
9. (d) Whether the lay out plan of proposed Ponds (or units
of other technologies) & future addition of the same
has been attached with the DPR
9. (e) Whether the STP capacity, to cater for ten years
requirement, has been adopted
9. (f) Whether modular approach adopted to facilitate “add-
on” units to STP at a future date, whenever required
9. (g) Whether the sewage treatment process has been
adopted on the basis of life cycle cost of different
prevalent technologies (including Karnal technology)
14
12 | P a g e
NATIONAL RIVER CONSERVATION PLAN
CHECK LIST
FOR
CORE-SCHEME COMPONENTS OF
AND
13 | P a g e
NATIONAL RIVER CONSERVATION PLAN
18
e.g., size, type & length of sewer/rising main, duties of the pumps etc.
19
Please include the analysis in the DPR.
-1-
14 | P a g e
TECHNICAL STATEMENT
9. Whether the area earmarked for the project in the
town (in A-3 size paper) showing the location of
the drains outfalling in the river, their names &
catchment area, existing and proposed major
works of the scheme are annexed along with
description of I&D proposal in the REPORT of
the DPR 20
10. (a) Whether present sewage generation in the town
has been obtained on the basis of actual discharge
measurement of each drain carried out for over a
month during dry weather 21
10. (b) Whether sewage interception factor 22 and peak
factor of each drain has been worked out and
indicated in the TECHNICAL STATEMENT of
the DPR
11. (a) Whether the rate of water supply for projection of
sewage generation has been adopted on actual
basis
11. (b) In case where actual rate of water supply is higher
than the norms of the latest CPHEEO Manual,
whether the estimation of sewage based on the
norms of the Manual has been compared with the
actual flow of the sewage and higher of the two
values taken at the time of submission of the
DPR, and has been adjusted at the normative
levels of the Manual when projecting for the
future and indicated in the TECHNICAL
STATEMENT of the DPR
11. (c) Whether projected minimum, average & peak
discharges of each drain (in litres per second-lps
as well as million litres per day-mld), its
interception & peak factors during different
design years along with present sewage flow have
been indicated in the tabular form in the
REPORT & TECHNICAL STATEMENT of the
20
Bigger size map having details are to be annexed with the DRAWING part of the DPR.
21
Please annex the table showing the summary of minimum, average & peak discharges along
with interception & peak factors with the REPORT & TECHNICAL STATEMENT of the DPR.
22
The sewage interception factor of each drain should be worked out on the basis of
contributory population of the catchment area of the drain and water supply rate.
-2-
15 | P a g e
DPR
12. (a) Whether hydraulic design of the proposed sewer
has been annexed with the DPR
12. (b) Whether all the sewers have been checked for
minimum self-cleansing velocity of 0.6 m/s
during average flow conditions, by providing
proper slope
12. (c) Whether flow depth to diameter ratios adopted
while designing sewers
13. Whether basis for selection of gravity
sewer/rising main material has been provided in
the DPR 23
14. Whether existing & proposed sewer plan annexed
with the DPR
15. Whether bedding conditions for different reaches
of the proposed sewer have been designed as per
the CPHEEO Manual and the design annexed
with the DPR
16. Whether silt traps on road side, if required, as
gully pits to avoid silting of sewers have been
provided
17. Whether detailed manhole-to-manhole survey of
existing sewers has been conducted and
provisions for sewer cleaning if required,
accordingly, made in the DPR
18. Whether manhole size & spacing have been
adopted as per the CPHEEO Manual
19. Whether manhole cover preferably of Ferro-
cement have been provided in the sewer
alignment to avoid theft of the same
20. Whether type of subsoil strata up to sewer invert
level, subsoil water table data and type of road
surface over the proposed sewers alignments has
been mentioned in the L-Section of the proposed
sewer
21. (a) Whether sewers are planned to be laid below sub-
soil water table
21. If so, whether justification for the same and the
23
Reference is drawn to Para 6.3 of the Manual on Water Supply & Treatment; May 1999
Edition of the CPHEEO, Ministry of Urban Development in this matter.
-3-
16 | P a g e
(b) precautionary measures to be taken during laying
of sewer has been mentioned in the DPR
22. Whether L-Section of the existing/proposed rising
main annexed with the DPR
23. (a) Whether economical size of the rising main has
arrived at after considering at least 3 diameters of
each of pipe materials of PSC, CI & DI etc. 24
23. (b) Whether the chosen diameter of the rising main
provide at least 0.60 m/s velocity for the base
year average flow
23. (c) Whether surge/water hammer analysis for rising
main has been calculated and mentioned in the
DPR
23. (d) Whether the design of thrust/anchor blocks made
in the DPR
23. (e) Whether rising main accessories, wherever
needed, such as thrust blocks, anchor blocks,
expansion joints, scour/drain valves, air/vacuum
release valves and surge protection devices
provided in the DPR 25
24. In case proposed sewer/rising main is crossing
railway line/Highway & their bridges (wherever
applicable), whether permission of the concerned
organization has been obtained and the copies of
the permission and their estimate for the same
annexed with the DPR
25. (a) Whether re-sectioning/lining of the drain for
protection/training purpose has been restricted to
30 m upstream and 20 m downstream of tapping
arrangement
25. (b) Whether the cross section at various chainage and
L-Section of the drain, in which re-
sectioning/lining is to be done, has been indicated
in the drawing sheet
25. (c) Whether the cross section of the drain has been
designed on the basis of rainfall data of the area
24
MS pipe, due to the corrosive nature of the sewage, is not recommended for sewage
conveyance, except after special treatment.
25
Please mention about them in the REPORT along with reference of page number/item number
of the estimation of the same over here as well.
-4-
17 | P a g e
and accordingly calculations have been shown in
the technical statement of the DPR
26. (a) Whether detailed dimensional drawings of nalla
tapping & allied works (also showing ground
level, bed/invert levels etc.) enclosed
26. (b) Whether nalla tapping works need deforestation
or rehabilitation of people/properties or
encroachments problems? 26
26. (c) If so, whether details and solutions have been
proposed in the DPR
26. (d) Whether arrangements of de-gritting and
screening the diverted flow from the tapping
arrangement, before joining the sewers/pumping
station made
27. (a) Whether the capacity of the sump of the pumping
station has been calculated on the basis of 3.75
Minutes detention period of peak discharge
during the ultimate design year
27. (b) Whether size of sump of the pumping station has
been has been out checked with pump
manufacturer for adequacy and so mentioned in
the DPR
27. (c) Whether scouring depth calculations have been
made to arrive at the depth of the pumping station
foundation, in case river flow shall affect the
structure during normal rainy season 27
27. (d) Whether proposed pumping station houses
submersible pumps
27. (e) In the case of ‘No’ in 27 (d) and where
horizontal/vertical motor driven pumps have been
provided, whether justification for provision of
twin sumps instead of single sump considering
overall costs of alternatives provided in the DPR
27. (f) Whether the calculations to arrive at different
invert levels 28 have been mentioned in the
technical statement of the DPR and shown in the
26
In case there is no such requirement, mention so in the DPR.
27
Scour depth calculation should take into account highest flood flow of the river.
28
(ground level, sump bed, bottom of submergible pump, top of submersible pump, storage top,
incoming sewer etc.)
18 | P a g e
drawing
27. (g) Whether the structural design, drawing &
estimate of sump of the pumping station has been
made the part of the DPR
27. (h) Whether land marks of the surrounding area have
been shown in the layout plan of pumping station
campus
27. (i) In the case where approach road and internal road
has been provided inside the campus of pumping
station, whether layout of the same has been
shown in the layout drawing of the pumping
station
28. (a) Whether the efficiency of the pump adopted,
while calculating the BHP, is in conformity with
the duties of the pumps proposed 29
28. (b) Whether the configuration of the pumps proposed
in each pumping station is in conformity with the
guidelines of the NRCD
28. (c) Whether friction losses inside the pump house as
per proposed installation of pumps have been
calculated and accounted for while calculating
duties of the pump in the DPR
28. (d) Whether the provision for required accessories to
pumping plants has been made
28. (e) Whether the details of specifications of the
control panel, starters, pressure gauge etc. have
been provided in the estimate
28. (f) Whether the size of sluice & reflex valves have
been adopted as per the CPHEEO Manual
28. (g) Whether the details of CI connecting pipes &
specials inside the pump house have been
provided in the DPR and accordingly provisions
made
28. (h) Whether flow measuring instrument provided on
the delivery header of pumping station
29. Whether provision for separate electric feeder
line to pumping stations (to take care of frequent
power failure and voltage fluctuation problem)
from HT line has been made in the DPR
29
Supporting documents are to be attached with the DPR.
19 | P a g e
30. (a) Whether provision for DG set has been made in
the DPR to account for interrupted power supply
30
30. (b) In case provision for DG set has been made in the
DPR, whether the calculations to arrive at the
capacity of the same has been mentioned in the
technical statement
31. (a) Whether the provision for staff quarters made, as
per guidelines of the NRCD, in the DPR
31. (b) Whether the ground for adopting a percentage of
civil construction cost towards water supply &
sanitation and electric fittings has been mentioned
in the DPR 31
32. Whether the provision of control and panel room
made in the DPR as per specifications of the State
Electricity Board 32
33. Whether unit estimates of manholes, gully pits,
ventilating columns, boundary wall, gate with
pillars, chambers etc. have been annexed with the
DPR
34. Whether provision for road restoration has been
made as per CPWD/State PWD/Local Body
norms & rates
35. Whether provision for 6 months trial run cost for
pumping station, after commissioning, has been
made
36. Whether the provision of land for pumping
station including electric sub-station has been
made in the DPR for Land Acquisition, in case it
is not available free of cost
37. (a) Whether the sites chosen for I&D scheme are free
of flooding?
37. (b) If not, reasons for choosing such alignment and
locations and measures, to avoid impact of floods
38. Whether traffic diversion/control arrangements
for public and workers’ safety, arising out of
construction phase of I&D works, have been
covered in the DPR
20 | P a g e
Signature of Project Manager
/Executive Engineer
31 In the case where power supply situation is satisfactory in the town, please attach a certified
copy of statement of the State Electricity Board regarding the same.
32 Please attach a copy with the DPR.
33 Please attach the copy of the specification in support with the DPR.
21 | P a g e
NATIONAL RIVER CONSERVATION PLAN
25 | P a g e
NATIONAL RIVER CONSERVATION PLAN
CHECK LIST
FOR
LAND ACQUISITION
26 | P a g e
NATIONAL RIVER CONSERVATION PLAN
27 | P a g e
population projection, rate of water supply,
interception factor etc. has been mentioned in a
tabular form in the DPR
12. Whether the sewage treatment process has been
adopted on the basis of life cycle cost of different
prevalent technologies (including Karnal technology)
13. Whether time taken in each activity of the acquisition
has been mentioned in the DPR
14. Whether start of work of each item of I&D and STP is
matching with date of possession of land for the
purpose
15. (a) Whether trial pits/ bore-whole data and other relevant
investigation/surveys 46 carried out at the proposed
sites
15. (b) If so, whether details of soil bearing capacity and
other technical data enclosed with the DPR
46
It would be needed for design of relevant items of works.
28 | P a g e
NATIONAL RIVER CONSERVATION PLAN
CHECK LIST
FOR
29 | P a g e
NATIONAL RIVER CONSERVATION PLAN
30 | P a g e
7. (b) In the case where land is to be purchased, whether
provision for it has been made in the Land
Acquisition DPR
7. (c) In case land is to be purchased, whether the type
of present land use for each proposed unit has
been mentioned in tabular form in the DPR
8. Whether layout plan of each LCS complex along
with land marks of surrounding area has been
annexed with the DPR
9. Whether detailed drawing of LCS complex has
been annexed
10. Whether soil test report of those sites, where
foundation of the building is to be laid in soil
other than normal soil, has been annexed with the
DPR 50
11. (a) Whether the proposed LCS unit has been
connected to the nearest sewer and provision made
accordingly
11. (b) In the case where sewer is not available nearby
and septic tank provided, whether cost comparison
of both alternatives for each case mentioned in the
DPR
12. Whether size of the soak pit & septic tank is in
conformity with the seating capacity of the LCS
unit and its design annexed with the DPR
13. Whether provision for proper lighting of the LCS
complex made in the DPR
14. Whether provision for boundary wall along with
gate, if applicable, has been made in the DPR
15. Whether provision for adequate number of urinals,
located outside the front part of the building, has
been made in the DPR
16. Whether provision for adequate water supply by
municipal main, shallow depth tubewell or jet
pump (as per the site conditions) has been made
17. Whether estimate of State Electricity Board for
power connection for each LCS unit has been
annexed with the DPR
50
Please attach the report with the DPR.
31 | P a g e
18. Whether proper size of water storage tank and its
basis, as per requirement of the LCS unit, has been
provided in the DPR
19. Whether the calculations to arrive at the O&M
cost has been annexed with the DPR
20. (a) Whether envisaged resource recovery (on the
basis of user’s payment) has been mentioned in
the DPR
20. (b) Whether institutional mechanism for proper O&M
of the proposed LCS units has been mentioned in
the DPR
32 | P a g e
NATIONAL RIVER CONSERVATION PLAN
CHECK LIST
FOR
CREMATORIA
33 | P a g e
NATIONAL RIVER CONSERVATION PLAN
34 | P a g e
7. Whether the justification of proposing the
number of cremation beds/units at the
particular ghat/site proposed of the town has
been mentioned in the DPR
8. Whether the location of the crematoria has
been marked on the city index plan
9. (a) Whether the land for crematoria is available
free of cost 53
9. (b) In the case where land is to be purchased,
whether the provision for same has been made
in the DPR for Land Acquisition
10. Whether basis for sizing of furnace hall,
waiting hall, office, caretaker room, electric
switch room, generator room etc. (in case of
electric crematoria) has been mentioned in the
DPR
11. Whether justification for providing mortuary
room, record room (in case of electric
crematoria) has been provided in the DPR
12. Whether the basis for selected size of water
storage tank has been mentioned in the DPR
13. Whether the provision of the tube-well for
water supply has been made as per
requirement and sub-soil water strata at the
site 54
14. Whether plan of the site showing the lay-
out/location of the crematoria building, roads,
boundary wall/gate, external lighting etc.
along with landmarks of surrounding area has
been annexed with the DPR
15. Whether detailed drawing of the crematoria
building/shed has been annexed
16. Whether the calculations to arrive at the
capacities of the transformer & generator (in
case of electric crematoria) have been shown
in the DPR
53
In the case where land is available free of cost, letter of the owner of the land for the same is
to be annexed with the DPR
54
In order to limit the O&M cost.
35 | P a g e
17. Whether the height of the chimney proposed
for dispersal of gases is 9 meters (in case of
electric crematoria) 55
18. Whether the provision for land development
and landscaping, if provided, has been made
as per detailed survey and actual site
requirements
19. Whether institutional mechanism for proper
O&M of the proposed crematoria has been
mentioned in the DPR
36 | P a g e
NATIONAL RIVER CONSERVATION PLAN
CHECK LIST
FOR
37 | P a g e
NATIONAL RIVER CONSERVATION PLAN
38 | P a g e
NATIONAL RIVER CONSERVATION PLAN
CHECK LIST
FOR
AFFORESTATION
39 | P a g e
NATIONAL RIVER CONSERVATION PLAN
∗
The afforestation schemes are prepared for planting trees in the NRCP work schemes of
Interception & Diversion, Sewage Treatment Plant, Low Cost Sanitation Complex (or
Community Toilet Complex), River Front Development & crematoria in order to improve the
aesthetics of the project area.
56
e.g., Neem etc.
40 | P a g e
NATIONAL RIVER CONSERVATION PLAN
CHECK LIST
FOR
41 | P a g e
NATIONAL RIVER CONSERVATION PLAN
57
Please attach a copy of the Study with the DPR.
42 | P a g e
9. (a) Whether an assessment of the assets required for the
scheme has been undertaken for the whole town 58
9. (b) Whether detailed estimation of the assets to be
created has been made in the DPR
9. (c) Whether unit estimates of each construction item and
its drawing has been annexed with the DPR
10. (a) Whether the provision for the land for 30 years has
been made in the DPR for Land Acquisition, in case
it is not available free of cost
10. (b) Whether the consent letter of the owner of the land to
the effect of its transfer to the implementing agency
has been attached with the DPR, in the case where
land (for 30 years requirement) is available free of
cost 59
10. (c) Whether land for disposal is located in such a way
that it shall not affect the health of the residents of
the town 60
10. (d) Whether the proposed land is located in Non-flood
prone area and easily accessible during rains
11. Whether the location 61 and layout plan of the land
proposed for processing & disposal has been annexed
58
Please specify and justify in the DPR.
59
It is to be complied with in those cases also where the owner is the local body.
60
Please justify in the REPORT of the DPR.
61
On the city index plan.
43 | P a g e
NATIONAL RIVER CONSERVATION PLAN
CHECK LIST
FOR
44 | P a g e
CHECK LIST FOR
46 | P a g e
47 | P a g e