Abstract Cost For Intake Well & Pontoon
Abstract Cost For Intake Well & Pontoon
Abstract Cost For Intake Well & Pontoon
Total
Sr. No. Description
Amount (Rs.)
1 Resurveyed of Proposed Side 557,500.00
Coffer Dam for Intake Well, 2 Nos of Inspections well & Jack well
2 35,000,000.00
100 m long & 20 m Ht.
3 Dewatering Work during Excavation 16,000,000.00
Cost of Intake well 1 Nos, Inspection well 2 Nos, & Jack well 10 m
4 30,765,957.99
Dia. & 40 m Ht
5 HDD in Hard Rock for Rosepiece I & II (2 Nos.) 6,593,009.00
5 Rosepiece I - 85m MS Pipe @ 900mm Dia. 1,472,836.00
6 Rosepiece II - 15m DI K9 @ 900mm Dia. 799,367.00
7 Rosepiece III - 5m DI K9 @ 900mm Dia. 338,216.00
8 Sluice Gate Valve @ 900mm Dia. - 3 Nos. 3,200,000.00
9 Approach Bridge of 150 m Length 22,500,000.00
10 Mechanical Euipments EOT crane & others 2,500,000.00
Net Cost 119,726,885.99
Contingencies Charges (3% of Project Cost) 3,591,806.58
Grand Cost 123,318,692.57