Farmers
Farmers
Farmers
Province of Samar
Municipality of Basey
oOo
PROGRAM OF WORKS
DETAILED ESTIMATE
I. Earth Works
V = 0.3m x 9m x 12m
= 32.4 cu.m.
35 cu.m. Filling materials ₱ 1,200.00 ₱ 42,000.00
8 cu.m. Back filling 350.00 2,800.00
1 lot Temporary materials 4,000.00 4,000.00
₱ 48,800.00
b. Labor 19,520.00
Direct Cost: ₱ 68,320.00
Indirect Cost:
Contingencies ₱ 8,198.40
Constructor's Profit ₱ 6,832.00
Vat ₱ 4,167.52
Total Cost ₱ 87,517.92
Unit Cost ₱ 2,701.17 cu.m.
VII. Ceiling
a.Materials
113 pcs. 2"x2"x12' good lumber (lawaan) ₱ 180.00 ₱ 20,340.00
44 shts. 1/4x4x8 marine plywood 650.00 28,600.00
5 kgs. 3" CWN 80.00 400.00
10 kgs. 2.5" CWN 80.00 800.00
3 kg. 1" CWN 80.00 240.00
1 lit Stikwel 240.00 240.00
1.5 gal Polituf 1,200.00 1,800.00
₱ 52,420.00
c.1. Labor ₱ 20,968.00
Direct Cost: ₱ 73,388.00
Indirect Cost:
Contingencies ₱ 8,806.56
Constructor's Profit ₱ 7,338.80
Vat ₱ 4,476.67
Total Cost ₱ 94,010.03
Unit Cost ₱ 94,010.03 /lot
VIII. Painting
a.Materials
10 bags Skim coat ₱ 1,000.00 ₱ 10,000.00
10 pcs. #100 1'x1' sand paper 50.00 500.00
20 pcs. #80 1'x1' sand paper 65.00 1,300.00
8 gals. Flat latex 750.00 6,000.00
6 gals. Semi-gloss latex 850.00 5,100.00
2 gals. Semi-gloss enamel 900.00 1,800.00
6 gals. Flat enamel 800.00 4,800.00
1 tin Latex color green 800.00 800.00
3 gals. Concrete neutralizer 400.00 1,200.00
3 pcs. 7" Roller brush 200.00 600.00
6 pcs. 4" roller brush 150.00 900.00
2 pcs. Paint brush 2" 50.00 100.00
2 pcs. Paint brush 3" 100.00 200.00
1 gal. Easy tite 1,000.00 1,000.00
₱ 34,300.00
c.1. Labor ₱ 13,720.00
Direct Cost: ₱ 48,020.00
Indirect Cost:
Contingencies ₱ 5,762.40
Constructor's Profit ₱ 4,802.00
Vat ₱ 2,929.22
Total Cost ₱ 61,513.62
Unit Cost ₱ 61,513.62 /lot
IX. Electrical
a. materials
2 rolls Mole flex ₱ 1,400.00 ₱ 2,800.00
17 pcs. Utility box 35.00 595.00
8 pcs. Junction box 35.00 280.00
₱ 3,675.00
b. Labor ₱ 1,470.00
Direct Cost: ₱ 5,145.00
Indirect Cost:
Contingencies ₱ 617.40
Constructor's Profit ₱ 514.50
Vat ₱ 313.85
Total Cost ₱ 6,590.75
Unit Cost ₱ 6,590.75 /lot
Approved by:
Technical Personnel
Percent
Item No. Scope of Work (Direct Cost) Quantity Unit Unit Price Total Amount
Weight
Approved by: