500kV Nokhar Substation DAILY PROGRESS REPORT Dated:-02-4-2023

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

500kV Nokhar Substation

DAILY PROGRESS REPORT Dated:- 02-4-2023


Sr. Till To Completed
Description Activity Unit Total Today Previous Remarks/Bottlenecks
No Date %
Switch Yard
1 Clearing & Grubbing Sqm 25500.00 510 23970.0 24480.0 96.00% In progress
(Filling Area)
Sample Prepration
2 Water - 100.00% Completed
for water testing
Switch Yard Inspection of Control
1 - 100.00% Completed
(Filling Area) Points
Next Day Plan Dated:- 03-4-2023
Sr.
Description Activity Time Remarks/Bottlenecks
No

1 Switch Yard Clearing & Grubbing 8:00AM

Excvation for
2 Switch Yard 10:00AM
Foundation
Sr.
Description Machinery Quantity Remarks/Bottlenecks
No
1 Loader 1
2 Tractor Trolley 3
3
4
5

Sr.
Description Manpower Quantity Remarks/Bottlenecks
No
1 Site Manger 1
2 Construction Manger 1
3 Site Engineer 1
4 Surveyor 1
5 Assistant Surveyor 2
6 Accountant 1
7 Driver 3
8 StoreKeeper 1
9 Forman 2
10 Labor `15
11
12