WNC 35 16 152 Vol-7.7.20

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

WESTERN RAILWAY

CAO(C)’s office
Churchgate,
Mumbai- 400 020

No.WNC 35/16/152 Vol. I Dated .07.2020.

FA&CAO(C)CCG.

Sub : 109th report of Public Accounts Committee (16thLok Sabha) on the subject
“Accounting of Projects in Indian Railways”.

Ref :1) FA&CAO(G)’s letter No.AJ/PAC/A13005/4139 dt.14.12.2018


2) FC Railways D. O. No.2014-BC-AP-Chap3/12-13/PAC/XVI/109
dt.11.03.20
3) Dy.FA&CAO(C-II)’s letter no. FA/S&C/C&AG report 19 of 2014/PAC date
22.05.2020.
******
In reference to above, Item wise updated status and details of the corrective measures to be
taken, are enclosed for perusal and further necessary action.

A. Position of completion report: - All 36 outstanding Completion Reports, pertain to


Construction Depts.(as pointed out by audit) have since been finalized.

B The position of 44 outstanding completion reports as on 31.03.2018(including 5 as


pointed out in the audit report) All 44 completion report as pointed out by audit has since
been finalized.

D. Incurrence of expenditure in excess of sanctioned estimate: - Out of 70 projects pointed


out by audit, 61 projects have since been regularized and 7 projects remain to be
regularized for excess over estimate. (Annexure -N).

E. Incurrence of expenditure in excess of sanctioned estimate as on 31.03.2020:- In this


regard, the list of 27 excess over expenditure items outstanding as on 31.03.2020 with
targets for regularization is placed as Annexure – “B”. As per instructions, as soon as it
becomes apparent that expenditure is likely to exceed the sanction estimate, revised
estimate is prepared. In some cases, the expenditure remained unsanctioned due to delay
in sanction of revised estimates /completion report. The excess expenditure was incurred to
meet contractual obligations and quantity variation due to site conditions etc. Efforts are
being made for sanction of revised estimates/completion reports so that excess over
estimate is regularize. In this connection instructions have been issued to field office vide
this office letter No. WNC -35/16/152 dt.11.10.2018 to take immediate necessary action to
regularize the excess over sanctioned estimate by making RE/CR.

This has the approval of CAO(C).

(Ajay Singh)
Chief Engineer (C) NE
Incurrence of expenditure in excess of sanctioned estimate (EOE-PAC) Position as on 1.07.2020. (fif. In
thousands) Annexure-N
Amount Month/ Target date
involved
Sr.No. Name of work Remarks DyHOD HOD for closing
as per
Year the case.
POM

Prov. of Up loop at
vaitarna on Virar – Civil sub CR
1 4584 2003-04 DyCE/C/I/CCG CE©C&S  15.08.2020
Surat section of pending
Mumbai division.

Work
completed CR
Vasai Road prov. of
under process.
2 cover over new 266 2006-07 DyCE/C/I/CCG CE©C&S  31.08.20
Excess will be
platform,
regularized in
main CR.

Addition loops at 6
. S&T final bill Dy.CE/C/III/
3 station on Virar – Surat 63169 2009-10 CE©HQ 30.08.2020 
pending. CCG
section

LPL– Augmentation of
Sub CR of
4 BG, AC Coaches POH 51480 2009-10 DyCE/C-I/CCG CE©C&S  31.07.2020
Mech. Pending.
facilities.

RE under
5 GC Neemuch – Ratlam 388329 2007-08 DyCE/C/RTM CE/C/NE  31.08.2020
process

Doubling kalapipal- RE under


6 288389 2007-08 DyCE/C/I/IND CE/C/NE 31.10.2020 
Phanda 6 block station process

Doubling Akodra- RE under


7 121299 2009-10 DyCE/C-I/IND CE/C/NE  31.10.2020
Sujalpur process

TOTAL 917516          
Position of EOE as on 31.03.2020
Amo Mon Target
Sr.
unt th/ date of
Dy.HOD HOD Name of work Remarks
No invol comple
Year
. ved tion

DyCE/C-1/CCG
1 Prov. of Up loop at vaitarna
CE/C/ 2003 Civil sub CR 15.08.2
on Virar – Surat section of 4584
C&S -04 pending 020
Mumbai division. (WC-194)

CC
G
DyCE/C-1/CCG

Work completed CR
under process.
CE/C/ Vasai Road prov. of cover 2006 31.08.2
2 266 Excess will be
C&S over new platform (WC-235) -07 0
regularized in main
CR.

LPL– Augmentation of BG,


DyCE/C- CE/C/ 5148 2009 Sub CR of Mech. 31.07.2
3 AC Coaches POH facilities.
1/CCG C&S 0 -10 Pending. 020
(WC-219)

Civil and Electrical


DyCE/C- CE/ JOS (South) ROB in lieu of 5277 2014 Feb.-
4 sub CRs are
II/CCG C/HQ LC No. 24 & 25 (WC-287) 8 -15 20
pending

DyCE/C- CE/C/ BVI construction of 12- 6979 2015 Final variation & Feb.-
5
I/CCG C&S Meter-wide FOB (WC-337) 4 -16 Final bill pending 20

Addition loops at 6 station on Civil department


DyCE/C/ CE/ Virar – Surat section 6316 2009 file in Vigilance. 30.08.2
6
III/CCG C/HQ 9 -10 S&T final bill 020
(WC 216) pending.

Providing new FOB with


Ramp for physically
DyCE/C CE/ 2015
7 handicapped persons at Vapi 4861 RE under process Sep-20
III/CCG C/HQ -16
Valsad and Billimora (WC-
307)

Audited expenditure
DyCE/C/ CE/C/ Virar ROB in lieu of LC-40 1101 2015 Feb.-
8 awaited from
I/CCG C&S (WC-222) 5 -16 20
VVMC

UDN-JL limited height


DyCE/C CE/ Subways at LCs No. 38, 108, 7321 2018 30.09.2
9 RE under process
III/CCG C/HQ 127, 128, 145, 146, 147 & 2 -19 020
134 (WC-367)

Reply signaling gear with


DyCSTE/ CSTE centralized operation of pt 8 2004 Final bill under Feb.-
10 9578
C/Field ©II sig on D special route at NDB -05 process 20
(WC-214)

CR not submitted
CWM-PL 7152 2002 Feb.-
11   MX retro fitment work by Dy.
& MX 1 -03 20
CEE/MX
DC AC conversion between
DyCEE/ CCG-VR on MLS 1051 2013 Mar.-
12 CEE© CR under process
C/CCG 96 -14 20
(WC-193)
13
DyCE/C- CE/ 2883 2007 31.10.2
Doubling kalapipal-Phanda RE under process
RT 1/IND C/NE 89 -08 020
M
DyCE/C-I/ CE/ 1212 2009 31.10.2
14 Doubling Akodra-Sujalpur RE under process
IND C/NE 99 -10 020
DyCE/C/ CE/ 2016 Feb.-
15 LC 200-201 532 RE under process
RTM C/NC -17 20
DYCE/C/ CE/ 2017 Mar.-
16 LC 231 2887 RE under process
RTM C/NC -18 20

DyCE/C/ CE/ 3883 2007 31.08.2


17 GC Neemuch – Ratlam RE under process
RTM C/NC 29 -08 020

DyCE/C/ CE/ ROB HKH-MHOW at LC- 1081 2014 Mar.-


18 RE under process
RTM C/NC 259 3 -15 20
DyCE/C/ CE/ 2015 Feb.-
19 Dohad workshop POH/MTR 2235 RE under process
RTM C/NC -16 20
DyCE/C/ CE/ 2016 Mar.-
20 LC No. 194 & 195 2079 RE under process
RTM C/NC -17 20
DyCE/C/ CE/ 2364 2018
21 ROB 101 B RE under process  
RTM C/NC 6 -19
DyCE/C/ CE/ 2016 Feb.-
22 Limkheda TSS sub station 9180 RE under process
RTM C/NC -17 20

23
DyCE/C- CPM/ ADI conversion of MG PF 3232 2014 Feb.-
RE under process
I/ADI ADI lines No. 9 & 10 (WC-509) 3 -15 20
A
DI

DyCE/C- CPM/ Additional loop line VG-GIM 3976 2013 Mar.-


24 RE under process
I/ADI ADI 7 stations (WC-150) 0 -14 20

CE/C/
DyCE/C- 5442 2017
25 Surve VG-SUNR RE under process  
III/ADI 83 -18
y
Cost sharing /
details of
DyCE/C- CE/C/ Cost sharing ROB at KIM- 2014 Feb.-
26 8603 expenditure with
II/BRC South Koshamba LC-160 (WC-832) -15 20
State Govt is
pending
Completion
DyCE/C- CE/C AKV-Ralpipla GC work 5608 2013
27 Estimate under Jan.20
II/BRC /South (WC-122) 46 -14
process

SUNR replacement of sig Work completed.


DyCSTE© CSTE 2011
28 equipment by EI(D) route 8492 FVS under finance  
DFC-ADI ©I -12
(WC-343) vetting at CCG

2561
TOTAL      
150