Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
6 a. Fire Pump room shall be enclosed with fire rated walls as per NFPA 101 and
approved Civil Defence drawings (Pls. see c.)
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
7 II. Sprinkler head inside the elevator pit shall be mounted not more than 24
inches (600mm) above the elevator pit (Tapping point. Ref. dwg. FF-114)
III. Sprinkler heads cover plates shall not be painted and free of dirt
At Mosque and Administration - During inspection, it has been noticed some
escutcheon plates was painted and some imbedded with majoon/putty.
Client: Consultant: Contractor
QCDD Compliance Photos
7 III. Sprinkler heads cover plates shall not be painted and free of dirt
At Mosque and Administration - During inspection, it has been noticed some
escutcheon plates was painted and some imbedded with majoon/putty.
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
9b.ii - Each fire hydrant shall be provided isolation gate valve. Ref. drwg. FF-102
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
10a. Initiating devices inside the protected room did not activate.
Note: Manual release did not activate during test for the MDF Room (2nd floor).
Client: Consultant: Contractor
QCDD Compliance Photos
15a. Using Emergency Power Supply System (EPSS) for ventilation fans failed
during testing.
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
15b - Justify the ventilation system at the fire pump room shall be supply and
exhaust. (Ref. drwg AC34-101)
Client: Consultant: Contractor
QCDD Compliance Photos
16a. Using Emergency Power Supply System (EPSS) for smoke control fans failed
during testing
Client: Consultant: Contractor
QCDD Compliance Photos
16b - Duct smoke detector shall be provided to shut down fans upon activation
Duct detector did not shutdown fans during testing.
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
17d - Identification marking of fans and outlets/inlets shall be provided (e.g. “Fresh
Air Supply”/ “Exhaust Air”)
- Ref. drwg. AC1-501-1& 2- (Fire Mode Operation and miscellaneous features) for
validation on next schedule of inspection.
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
Client: Consultant: Contractor
QCDD Compliance Photos
20 - An illuminating approved exit sign shall be installed in accordance with Civil Defence approved
drawings and NFPA 101
Illuminated Directional and Exit signs shall be visible from 30 meters