Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Method Statement For Conduit Installation - Cast in Situ of PVC / Gi / Ms Conduit Pipe For Electrical Works

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

MICROSOFT DATA CENTER, HYD01-K-003 M3SD-K003-GEN-HYD01-E-0001

METHOD STATEMENT FOR CONDUIT Rev: 00


INSTALLATION – CAST IN SITU OF PVC / GI / Date: 26/04/2023
MS CONDUIT FOR ELECTRICAL WORKS

METHOD STATEMENT FOR CONDUIT INSTALLATION – CAST IN SITU


OF PVC / GI / MS CONDUIT PIPE FOR ELECTRICAL WORKS
MICROSOFT DATA CENTER, HYD01-K-003 M3SD-K003-GEN-HYD01-E-0001
METHOD STATEMENT FOR CONDUIT Rev: 00
INSTALLATION – CAST IN SITU OF PVC / GI / Date: 26/04/2023
MS CONDUIT FOR ELECTRICAL WORKS

Table of Content

1. Purpose
2. Scope
3. Legislation and Code of Practice
4. Abbreviations
5. Responsible Personnel on Site
6. Tools & equipment
7. Installation Procedure & Methodology
8. Reference Documents
9. Quality Inspection and Testing
10. Safety
MICROSOFT DATA CENTER, HYD01-K-003 M3SD-K003-GEN-HYD01-E-0001
METHOD STATEMENT FOR CONDUIT Rev: 00
INSTALLATION – CAST IN SITU OF PVC / GI / Date: 26/04/2023
MS CONDUIT FOR ELECTRICAL WORKS

1.0 PURPOSE:
This document describes the method statement for conduit installation which includes MS, GI and
PVC conduits and accessories for any kind of construction project.
Procedure will ensure that all concerned persons are familiar with the sequence of activities,
utilization of resources and execution of the works in compliance with applicable project safety and
quality procedural requirements, project legal documents and specifications.

2.0 SCOPE:
This method statement is intended to outline the activities and the method used for the
installation of electrical conduits and accessories.
All work within the rights-of-way of the standards and specifications will be done in
compliance with requirements issued by authorities.

3.0 LEGISLATION AND CODE OF PRACTICE:


All related codes and standards referenced in the project electrical specifications.

4.0 ABBREVIATIONS:
 MS: Mild Steel
 GI: Galvanized Iron
 PVC: Poly Vinyl Chloride

5.0 RESPONSIBLE PERSONNEL ON SITE:


 Electrical Manager
 Electrical Field Engineer
 Safety Officer
 QA/QC Engineer
 Electrical Supervisor

6.0 TOOLS AND EQUIPMENTS:


 Bending Machine
 Die Set
MICROSOFT DATA CENTER, HYD01-K-003 M3SD-K003-GEN-HYD01-E-0001
METHOD STATEMENT FOR CONDUIT Rev: 00
INSTALLATION – CAST IN SITU OF PVC / GI / Date: 26/04/2023
MS CONDUIT FOR ELECTRICAL WORKS

 Measuring Tape
 Screwdriver
 Chalk Mate Thread
 Oil
 Drill Machine
 Mini Hacksaw Frame with Blade

7.0 INSTALLATION PROCEDURE AND METHODILOGY:


 Ensure the civil people have finished ply/post tension work on the slab.
 Arranged the approved shop drawings for the area of installation.
 Measure and mark-up shuttering for the position of the boxes.
 Fix the boxes on their designated locations. Ensure that the boxes are filled with polystyrene to
prevent cement sediment to accumulate inside the boxes.
 Install in situ conduits as per requirements, tie the conduits into the reinforcing bars. Ensure that
the maximum run of conduit between boxes shall not contain more than three quarters of the
bends. Ensure that the maximum run of conduit between boxes shall not exceed 25m for straight
runs. In any cases that the straight run of conduit will exceed 25m, pull boxes shall be installed.
 Raise Notification for Inspection of conduit installation.
 Ensure that all installed conduits shall be taken care off during concrete pouring time.
 Shutter closing and concreting will commence.

8.0 REFERENCE DOCUMENTS:


 Approved Electrical Shop Drawings
 Approved Material Submittals for Conduits and Boxes
 Approved Material Inspection Report
 Approved Safety Plan
 Approved QA/QC Inspection Plan

9.0 Quality Inspection and Testing


The work area shall be maintained neat and tidy as reasonably practical at all the times.
Executed works in areas where other works are still being carried out shall be protected as per the
contract requirements.
In accordance with the project quality plan, necessary records will be maintained as documentary
evidence of the establishment of this electrical method statement.
MICROSOFT DATA CENTER, HYD01-K-003 M3SD-K003-GEN-HYD01-E-0001
METHOD STATEMENT FOR CONDUIT Rev: 00
INSTALLATION – CAST IN SITU OF PVC / GI / Date: 26/04/2023
MS CONDUIT FOR ELECTRICAL WORKS

All the in-process work shall be monitored for quality of workmanship and installation against
approved shop drawings by the relevant supervisor.

Installation works shall be inspected for conformance to project electrical specifications.

The inspection formats shall be used in accordance with the requirements of the main contractor.

An inspection request for the MS / GI / PVC conduits and boxes shall be submitted one day prior to
the consultant.

10.0 Installation Procedure & Methodology


 All safety precautions shall be followed as per the approved safety plan and procedure. Ensure
all involved persons are aware of the same.
 Tradesmen shall ensure that before leaving their workplaces, it must be clean, tidy and free from
rubbish.

You might also like