Annexure I
Annexure I
Annexure I
Sub: Minor fabrication works in fired heater overhead pipelines in SGTF – reg.
Sl.
Approx Unit Rate Total cost
Description of work Unit
No Qty (Rs) (Rs)
1. Cutting & dismantling of existing carbon steel
piping.
Measurement shall be taken, as-built drawings shall be
prepared and approval of Engineer in Charge shall be
obtained before dismantling.
Dismantling of existing pipe lines at various heights by
gas cutting, cold cutting including fittings; elbows,
insulation etc along with structural pipe supports as
Inch meter 325
saddles, shoes, anchors, clamps, valves etc., and safely
transporting to salvage yard/warehouse. Supply of tools
& tackles and arrangement for transportation etc are in
the scope of contractor.
All essential safety features for workman such as safety
belts, safety shoes, hand gloves, helmets, height passes,
height permit, hot work permit etc., are to be provided
by the contractor.
2. Fabrication of carbon steel pipe by butt welding.
Work includes fabrication of CS pipes as per as-built
isometric drawing. Fabricate the pipeline/spool as per
approved drawing. Conducting the liquid penetrate test,
hydro testing of lines as per specifications/isometric
drawing.
Supply of cleaner, penetrate, developer, grinding wheel,
welding rod, welding machine, wire brush and
equipment for hydro test etc., are in the scope of Inch dia 233
contractor. In case of failure of joints during testing
same shall be rectified without any additional cost and
re-conduct the test. The entire inspection tests are in the
scope of contractor.
All essential safety features for workman such as safety
belts, safety shoes, hand gloves, helmets, height passes,
height permit, hot work permit etc., are to be provided
by the contractor.
3. Fabrication of IBR carbon steel pipe by butt Inch dia 150
welding.
Work includes fabrication of CS pipes as per as-built
isometric drawing. Fabricate the pipeline/spool as per
approved drawing. Conducting the liquid penetrate test,
hydro testing of lines as per specifications/isometric
drawing.
Supply of cleaner, penetrate, developer, grinding wheel,
welding rod, welding machine, wire brush and
equipment for hydro test etc., are in the scope of
contractor. In case of failure of joints during testing
same shall be rectified without any additional cost and
re-conduct the test. The entire inspection tests are in the
scope of contractor.
Welding shall be done by IBR qualified welder only
Sl.
Approx Unit Rate Total cost
Description of work Unit
No Qty (Rs) (Rs)
and IBR pipes/fitting/valves/flanges etc. only shall be
used wherever IBR requirement exists.
All essential safety features for workman such as safety
belts, safety shoes, hand gloves, helmets, height passes,
height permit, hot work permit etc., are to be provided
by the contractor.
4. Fabrication of carbon steel pipe by fillet welding.
Work includes fabrication of CS pipes as per as-built
isometric drawing. Fabricate the pipeline/spool as per
approved drawing. Conducting the liquid penetrate test,
hydro testing of lines as per specifications/isometric
drawing.
Supply of cleaner, penetrate, developer, grinding wheel,
welding rod, welding machine, wire brush and
equipment for hydro test etc., are in the scope of
Inch dia 120
contractor. In case of failure of joints during testing
same shall be rectified without any additional cost and
re-conduct the test. The entire inspection tests are in the
scope of contractor.
All essential safety features for workman such as safety
belts, safety shoes, hand gloves, helmets, height passes,
height permit, hot work permit etc., are to be provided
by the contractor.
Note: All quoted rates are inclusive of all taxes & GST (12%)
Rupees…………………………………………………………………………………………………
………………..………………………………………………………………only