Standard Specification For Roadworks Hold Witness Points July 2020
Standard Specification For Roadworks Hold Witness Points July 2020
Standard Specification For Roadworks Hold Witness Points July 2020
SCHEDULES
HOLD POINTS
WITNESS POINTS
STANDARD SPECIFICATION FOR ROADWORKS
V 4.2 – July 2020
SCHEDULES
HOLD POINTS
WITNESS POINTS
PROJECT INFORMATION
Project Number; . . . . . . . . . . . . . . . .
RFT Number; . . . . . . . . . . . . . . . . . .
Project title;
.............................................................
.............................................................
.............................................................
Superintendent;
Name; . . . . . . . . . . . . . . . . . . . . . . . . . .
Phone number; . . . . . . . . . . . . . . . . . . .
Name; . . . . . . . . . . . . . . . . . . . . . . . .
Phone number; . . . . . . . . . . . . . . . . . . .
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
01 MISCELLANEOUS PROVISIONS
VOLATILE SUBSTANCES MANAGEMENT
Provide details of the volatile substances proposed to be
brought in to the area(s) subject to Volatile Substance Abuse 10 &
1.7
Management Plan(s) and provide details of the proposed 11
methods for complying with the requirements of any applicable
Volatile Substance Abuse Management Plan(s).
PERMITS TO ACCESS LAND FOR WORKS ON ROADS
The Contractor must provide documentary evidence of having
been granted the required permission(s) to;
enter the land which is the site(s) of the works, and
to enter any other lands for ancillary activities related to 1.8 11
the works, and
carry out the works and works related activities.
Do not enter the land until this evidence has been received by
the Superintendent
PERMITS TO ACCESS LAND FOR WORKS ON ROADS
Provide documented advice on sites to which surplus materials
will be taken. Provide documentary evidence of permits, from 1.8 11
the entity/entities with jurisdiction over those sites, for the
dumping of surplus materials at those sites.
CAMP SITE/COMPOUND/WORKSHOP
Provide a copy of written permission from the owner or lessee 1.9 12
of the land permitting establishment and operation of a camp
site, compound and/or workshop, before commencing works.
FOOD PREPARATION FACILITIES
Provide a copy of proof of registration with DoH of any camp 1.9.1 12
food preparation area in accordance with the Food Act 2004.
EFFLUENT
Provide a copy of written approval from Department of Health 1.9.3 12
(DoH) for any proposed on-site effluent disposal system,
before commencing works.
EFFLUENT
Where the use of septic tanks or portable toilets is not
1.9.3 12
reasonable or practical, pit toilets may be used, but this
requires the prior written approval of the Superintendent.
REHABILITATION
Obtain approval from the Superintendent for the completed 1.9.4 12
rehabilitation of the camp site/compound/workshop before final
demobilisation.
OPERATION OF EXTRACTION AREAS
13 &
LIMIT OF EXCAVATION 1.11.5
14
Obtain Superintendent approval to exceed 1ha pit size.
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
EXPLOSIVES
Obtain approval from Superintendent before commencing 1.12 15
blasting operations.
WORK HEALTH AND SAFETY MANAGEMENT PLAN
If the Act requires it, provide a Work Health and Safety
Management Plan within 14 calendar days of award of the 1.14.2 16
contract. Do not commence works until the Superintendent has
advised that the Work Health and Safety Management Plan may
be used.
WORK ON RAILWAY SITES
17 &
Do not commence work until the work plan has been approved 1.16
18
by the owner and operator of the rail system.
WORK NEAR TRAFFIC COUNTING STATIONS
Prior to commencing any excavation, boring of holes, blasting,
rock breaking, soil compaction or similar activity in the vicinity of 1.17 18
traffic counter station detector loops, obtain the location of the
cables from the Department, Transport Planning Division, Data
Contracts Officer and pay all fees.
AS CONSTRUCTED INFORMATION
Provision of As Constructed information is a condition precedent 1.23 19
to Practical Completion.
CONTRACTOR’S SUBMISSIONS
Provide copies of permits, and approvals, for works, and
associated activities, proposed to be carried out in areas not in 1.27 23
the road reserve before commencing any proposed works, and
activities.
02 PROVISION FOR TRAFFIC
SUBMISSION OF TRAFFIC MANAGEMENT PLAN
Submit the Traffic Management Plan (TMP), with the Traffic
Guidance Schemes.
For contracts where audits of traffic control measures are
required:
- Do not commence implementing traffic control
measures until the TMP has been audited by a
Panel Period Audit Consultant and found to be
suitable.
- Do not commence the works until the TMP has been
audited by a Panel Period Audit Consultant and 2.6.2 29
found to be suitable.
For contracts where audits of traffic control measures are not
required:
- Do not commence implementing traffic control
measures until the TMP has been appraised by
DIPL Road Operations and found to be suitable for
use.
- Do not commence the works until the TMP has been
appraised by DIPL Road Operations and found to be
suitable for use.
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
REINFORCEMENT
Do not place concrete until the reinforcement has been 11.3.6 139
inspected by the Superintendent.
PLACING OF CONCRETE
Provide verification that all constituent materials, formwork,
falsework, reinforcement, and environmental conditions comply 11.6.3 140
with all requirements. Do not cast any concrete without that
verification.
EXISTING SERVICES
Obtain the Superintendent's approval before altering the line or 11.8 142
level of existing services.
12 DRAINAGE WORKS
PRECAST REINFORCED CONCRETE BOX CULVERTS
Provide drawings showing complete reinforcement and
dimensions with tolerances and obtain the Superintendent’s
approval prior to fabricating any units. Provide manufacturer’s
certification that the provided culverts comply with the
applicable sections of AS 5100.5 and with AS 1597. Certify 12.5.3 146
that the design is reflected accurately by the shop drawings
and that the design is adequate to resist all specified loads and
the soil loads pertaining to the site.
Provide a table of construction axle loads versus minimum
required cover for each box culvert size.
CONSTRUCTION OF CULVERTS AND STRUCTURES -
SETTING OUT
12.6.1 147
Obtain the Superintendent's approval for the setting out before
construction.
CONSTRUCTION OF CULVERTS AND STRUCTURES -
BACKFILL
Do not place backfill against any in-situ concrete structure until 12.6.10 149
the concrete has attained 80% characteristic strength and
approval has been given.
INLET AND OUTLET STRUCTURES AND MAINTENANCE
HOLES - LAYING AND BACKFILLING
12.11.5 150
Obtain Superintendent's approval of the pipe installation before
backfilling.
13 PROTECTION WORKS
GROUTED STONE PITCHING
13.5.2 155
Obtain Superintendent's approval before grouting.
14 ROAD FURNITURE AND TRAFFIC CONTROL DEVICES
FLEXIBLE GUIDE POSTS - SAMPLES
Provide a sample flexible guide post from each batch
14.6.4 164
purchased for this contract for inspection and approval before
installing any posts.
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
01 MISCELLANEOUS PROVISIONS
CRUSHING OR SCREENING
Provide documentary evidence of the certification that the
plant is fit for use issued by a competent person. Provide
documentary evidence of that person’s skills and qualifications 1.11.3 13
which indicate their competence as defined in the NT Work
Safe Bulletin cited above. This evidence is to be provided
within 2 weeks of the award of the contract.
SAFETY OFFICER
Appoint a Safety Officer and notify the Superintendent of the
Safety Officer’s name, and contact details, including an after-
1.14.1 16
hours contact phone number.
Ensure the Safety Officer is capable and available at all times
as required.
CONTROL STATION CHECK SURVEY
Where results exceed the quoted tolerance notify the 1.21 19
Superintendent and obtain directions.
AS CONSTRUCTED INFORMATION
Provide As Constructed drawings for all of the works.
Show co-ordinate dimensions where applicable.
Show design levels and as constructed levels on
the as constructed drawings. Clearly identify on
the as constructed drawings which levels are
design levels and which levels are as
constructed levels.
Clearly show set-out on the as constructed
drawings. Show both design set-out and as
constructed set-out. Show clearly which is design 19 &
1.23
and which is as constructed. 20
Refer to the specific deliverables in the NTG
Technical Drawings Part 1 - Requirements for
Technical Records Management document,
which is accessible via
https://dipl.nt.gov.au/infrastructure/technical-
standards-guidelines-and-
specifications/technical-records .
Drawings without changes shall be described as "As
Constructed - No Changes" in the amendment description
column.
AS CONSTRUCTED INFORMATION
19 &
Before the work commences provide a proposed procedure 1.23
20
for recording and submitting the amended drawings.
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
08 SPRAY SEALING
SAMPLING OF BINDER - COLLECTION OF SAMPLES
Take samples from the point of delivery on transfer from the
bulker to the sprayer or as directed. Where transfer is for 8.9.5 110
works in the urban area or for small works ensure that
conformance testing is ordered and samples are taken at the
point of transfer from bulker to sprayer.
SPRAYING
Give the Superintendent 48 hours notice of intention to spray 8.13 112
bitumen.
PREPARATION FOR SPRAYER RUN
Record the volume and temperature of the sprayer contents
before each run, while sprayer is on level ground. Dip Sprayer
Tank before and after each sprayer run. Record the dip 8.13.4 113
readings, and the temperature of the sprayer contents at the
time the dip was done. Provide copies of records of Sprayer
Tank dips and temperatures of tank contents within one day of
the completion of a day’s work.
PREPARATION FOR SPRAYER RUN
8.13.4 113
Allow visual inspection when requested.
PREPARATION FOR SPRAYER RUN
Check that the spray bar is at the correct height before 8.13.4 113
spraying begins.
SPRAYSHEETS
Supply spraysheets (paper or electronic formats are 8.18.1 117
acceptable) to the Superintendent at the end of each day’s
production.
09 DENSE GRADED ASPHALT
BITUMINOUS BINDER
Demonstrate that the binder used for asphalt manufacture has 9.5.4 122
been handled according to these requirements.
SURFACE PREPARATION - NEW CONSTRUCTION
Give the Superintendent not less than 24 hours notice of the 9.7.1 124
location and scheduled commencement time of surface
preparation works.
SPREADING - GENERAL
Give at least 24 hours notice before commencement of 9.10.1 126
asphalt material spreading.
LAYING PATTERN
Provide a construction program and paving plan at least 7 9.10.4 127
working days prior to commencement of works. Paving plans
must be confirmed prior to the commencement of each shift.
COMPACTION TEMPERATURES
The Contractor must advise the Superintendent of 9.11.2 128
temperature limits relating to compaction.
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
10 SLURRY SURFACING
COMMENCEMENT OF WORK
Give the Superintendent at least 7 days notice of the date and 10.3 132
time of the commencement of work.
RECORDS
Forward a copy of the slurry surfacing Daily Record Sheet to 10.13 137
the Superintendent daily.
11 MISCELLANEOUS CONCRETE WORKS
FORMWORK
Do not place concrete until the formwork has been inspected 11.6.2 140
by the Superintendent.
PLACING OF CONCRETE
Give the Superintendent sufficient notice so that inspection 11.6.3 140
may be made before and during pouring concrete.
12 DRAINAGE WORKS
PRECAST REINFORCED CONCRETE BOX CULVERTS
12.5.3 146
Give the Superintendent notice prior to casting concrete.
EXCAVATION
Excavate unsuitable material below specified level if directed 12.6.2 147
by the Superintendent.
CONNECTION TO EXISTING SYSTEMS
Advise the Superintendent within 2 days when cleaning out is 12.6.9 148
completed.
BACKFILL
Notify the Superintendent before backfilling where holes or 12.6.10 149
fissures occur in rock trenches.
INLET AND OUTLET CHANNELS
Advise the Superintendent within 2 days when cleaning out is 12.8 149
completed.
END WALLS
Advise the Superintendent within 2 days of when cleaning out 12.11.6 150
is completed.
14 ROAD FURNITURE AND TRAFFIC CONTROL DEVICES
TACTILE GROUND SURFACE INDICATORS
Provide a 5 year warranty for the materials used, and for the
devices installed as tactile ground surface indicators. Provide 14.4 161
a 5 year warranty for the workmanship for the installation of
the tactile ground surface indicators. Both warranties to be in
the name of the Principal.
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
SECTION
INITIALS
PAGE
DATE
CLAUSE TITLE
COATING
Provide copies of specifications for application of protective
coatings from the manufacturers of the products used. Provide 22.13.2 231
copies of manufacturers’ product technical data sheets for all
products used.
COATING DEFECTS
This compatibility between marker and coating is to be
confirmed by the coating manufacturer. Provide written 22.13.7 232
evidence of this compatibility if requested by the
Superintendent.
CONTRACTOR RECORDS
Maintain written records of the work so that complete
traceability of all work and materials provided under this
Specification is maintained. Use the relevant sections of
AS 3894.10, AS 3894.11 & AS 3894.12 QA report forms as a
basis of this record keeping format for all protective coating
work under this contract. Use AS 3894.13 and AS 3894.14, in 22.16 233
addition to the preceding Australian Standards, for structural
steel work coated under this contract.
Maintain these reports on a daily basis. Submit them to the
Superintendent when requested, or, if not specifically
requested, at least weekly.
FILM THICKNESS
Provide and operate wet film and dry film thickness gauges of
approved types to ensure the correct thickness of each coat 22.16.1 233
and the full system is achieved. Provide details of the gauges
proposed for use.