Power System Reliability Evaluation Considering Cyber-Malfunctions in Substations
Power System Reliability Evaluation Considering Cyber-Malfunctions in Substations
Power System Reliability Evaluation Considering Cyber-Malfunctions in Substations
net/publication/281333089
CITATIONS READS
24 618
2 authors:
Some of the authors of this publication are also working on these related projects:
RELIABILITY ASSESSMENT OF ELECTRIC POWER SYSTEMS USING GENETIC ALGORITHMS View project
All content following this page was uploaded by Hangtian Lei on 02 November 2017.
a r t i c l e i n f o a b s t r a c t
Article history: Protection system failures have been recognized as major causes of expanded outages and thereby affect
Received 22 April 2015 bulk power system reliability. With the rapid progress of smart grid technologies, legacy protection
Received in revised form 3 August 2015 systems with hardwired architecture are being gradually replaced by computer and communication
Accepted 5 August 2015
networks consisting of multi-functional and smart Intelligent Electronic Devices (IEDs). In this paper, a
systematic methodology for considering the effect of cyber-malfunctions in substations on power sys-
Keywords:
tem reliability is proposed by extending the concepts we previously presented. The Roy Billinton Test
Cyber-physical interface matrix
System (RBTS) is extended to include substation protection systems with modern architecture, which
Hidden failure
Protection system
is an important step as a test system like this is currently unavailable. The proposed approach is then
Reliability demonstrated on this test system. The quantitative relationship between switching time and system-
Switching wide energy unavailability is studied. The results of our study clearly indicate the impact of protection
system failures on system-wide reliability indices and signify the importance of accelerating line switch-
ing process. Furthermore, the overall methodology used in this paper provides a tractable and scalable
option for the reliability evaluation of large cyber-physical power systems.
© 2015 Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.epsr.2015.08.010
0378-7796/© 2015 Elsevier B.V. All rights reserved.
H. Lei, C. Singh / Electric Power Systems Research 129 (2015) 160–169 161
reliability terms and tedious mathematical operations were intro- 2.1. Reliability analysis at the substation level
duced in [18,19]. These terms are hardly available from engineering
practice, making it difficult to implement the overall methodology The failure modes of protection systems in terms of basic cyber
in practical applications. Reference [20] proposed a more system- elements and their relationships to transmission line tripping sce-
atic and scalable methodology of performing the overall analysis in narios are analyzed in this stage. The CPIMs, which depict the
a tractable fashion with the use of Cyber-Physical Interface Matrix interdependencies among the failures of physical components due
(CPIM). In [20], a typical substation protection system with detailed to various cyber failure modes, are obtained at the end of this stage.
architecture was designed and analyzed as an example to illus-
trate the procedures of obtaining a CPIM. The steps on how to use 2.2. Reliability evaluation from the system-wide perspective
a CPIM in composite power system reliability evaluation were also
formulated. In this stage, a sequential Monte Carlo simulation is performed
The composite power system displayed in [20] is simple and is on the composite system to obtain system-wide reliability indices.
used for illustration only. The overall methodology with the use of The results of CPIMs obtained in the previous stage are directly
CPIM needs to be further demonstrated with its implementation on utilized in this stage without the necessity of considering protection
a standard test system so that the impact of protection failures on system configuration details. At the end of this stage, system-wide
system-wide reliability indices can be numerically validated. Also, reliability indices, such as Loss of Load Probability (LOLP), Loss of
the scalability of the overall methodology needs further illustration Load Expectation (LOLE), Expected Energy Not Supplied (EENS), and
as this is very important to its application for large power systems. Expected Frequency of Load Curtailment (EFLC), for each bus and
Moreover, the unavailability of standard reliability test systems for the overall system, can be obtained.
containing practical protection features is an obstacle for valida-
tion of the impact of protection failures on system-wide reliability 2.3. System-wide reliability indices
indices. The extension of the Roy Billinton Test System (RBTS) [21]
performed in this paper provides valuable information for develop- The following system-wide reliability indices [7,9,22] are
ing standard reliability test systems including protection features defined and used in this paper.
and will thereby benefit future studies in this area. With these
2.3.1. Loss of load probability (LOLP)
objectives, this paper continues and enhances the work that has Ns H t
i i
been performed in [20]. The remainder of this paper is organized LOLP = (1)
i=1 ttotal
as follows. Section 2 outlines the overall methodology. Section 3
presents the test system configuration and parameters. In Section where,
4, the overall analysis, including the reliability analysis at the sub- Ns is total number of iterations simulated;
station level and the reliability evaluation at the composite system Hi equals 1 if load curtailment occurs in the ith iteration; other-
level, is performed. Also, the results are presented and summarized. wise it equals 0;
The scalability of the overall methodology performed in this paper ti is simulated time in the ith iteration, with the unit of year; and
is illustrated in Section 5. Some major considerations in software ttotal is total simulated time, with the unit of year.
implementation for large power systems are discussed in Section
6. Finally, the conclusions are made in Section 7. 2.3.2. Loss of load expectation (LOLE)
LOLE = LOLP × 8760 (2)
2. Methodology outline and objectives 2.3.3. Expected energy not supplied (EENS)
Ns 8760R t
i i
The cyber-physical interdependencies exist in many aspects of EENS = (3)
i=1 ttotal
power systems, including but not limited to supervisory control,
protection, monitoring, metering, etc. This paper focuses on the with the unit of MWh/year,
aspect of protection since protection hidden failures are recognized where,
as common causes of expanded outages and have significant impact Ns is total number of iterations simulated;
on power system reliability [4–10]. Ri is load curtailment during the ith iteration, with the unit of
In this paper, reliability evaluation is performed in a composite MW;
power system consisting of current-carrying components and pro- ti is simulated time in the ith iteration, with the unit of year; and
tection systems. The Roy Billinton Test System (RBTS) [21] is used ttotal is total simulated time, with the unit of year.
as the test system with extensions at load buses to include detailed
2.3.4. Expected frequency of load curtailment (EFLC)
configuration in terms of protection system elements. Ns Z
i
The size of this system is small to permit reasonable time for EFLC = (4)
i=2 ttotal
extension of cyber part and development of interface matrices but
the configuration of this system is sufficiently detailed to reflect with the unit of (/year),
the actual features of a practical system [22]. The methodology where,
performed in this paper also applies for large systems. For large sys- Ns is total number of iterations simulated;
tems, in spite of more efforts needed in detailed analysis of cyber Zi equals 1 if load curtailment does not happen in the (i − 1)th
failure modes as well as effects on the physical side, the main pro- iteration AND load curtailment happens at the ith iteration; other-
cedures are identical to those performed in this paper. In short, wise it equals 0; and
the selected system is adequate to illustrate the methodology and ttotal is total simulated time, with the unit of year.
extension to larger systems is more mechanical effort rather than
illustrating the validity of the technique. 3. Test system configuration
The overall analysis mainly consists of two stages: (1) reliabil-
ity analysis of protection systems at the substation level and (2) The Roy Billinton Test System (RBTS) [21] is used as the test
reliability evaluation from the system-wide perspective. system in this paper. The single line diagram of the RBTS is shown
162 H. Lei, C. Singh / Electric Power Systems Research 129 (2015) 160–169
G1 G5 ~ Table 3
~ G6
~ Transmission line physical parameters.
Load Load
Bus 3 Bus 4 power flow model is used in case of load curtailment. Therefore,
only the real power data are considered.
5 8
3.1.1. Generation variation
85 MW 40 MW The generators are represented by reliability models with two
states, up and down. The corresponding failure rate and Mean
Load Repair Time (MRT) are obtained from [21] and are tabulated in
Bus 5
20 MW Table 2.
20 MW
3.2. Transmission line data
Fig. 1. Single line diagram of the RBTS.
The transmission line physical parameters and outage data are
Table 1
obtained from [21] and are tabulated in Tables 3 and 4, respectively.
Bus data. A DC optimal power flow model with simplified line parameters
is used in case of load curtailment. Therefore, the line resistance (R)
Bus no. Name in Fig. 1 Peak load (p.u.) Generation capacity (p.u.)
as well as the charging susceptance (B) are not considered in the
1 Generating station 1 0.00 1.10 transmission line model and only the line reactance (X) is provided
2 Generating station 2 0.20 1.30
in Table 3. Furthermore, in the DC optimal power flow model, since
3 Load bus 3 0.85 0
4 Load bus 4 0.40 0 the voltage magnitude at each bus is assumed to be 1.0 p.u., the
5 Load bus 5 0.20 0 current rating for each line shown in Table 3 is numerically equal
6 Load bus 6 0.20 0 to the power rating.
For the transmission line outage data, compared with [21], the
transient outage (normally with duration of less than one minute)
in Fig. 1. The bus, generation, load, and transmission line data are is not considered in this paper. Instead, a new term switching time
also provided in this section. In this paper, 100 MVA and 230 kV are is defined. The switching time for each transmission line, which
used as the base values of power and voltage. is tabulated in Table 4, defines the time needed to switch a line
back to service when this line is tripped due to a protection failure
3.1. Bus, generation, and load data rather than resulting from a primary fault occurs at this line. The
reciprocal of a switching time is called a switching rate and has been
The data for all the buses and generating units are obtained from illustrated in [20].
[21] and are tabulated in Tables 1 and 2, respectively. A DC optimal
Table 4
Table 2 Transmission line outage data.
Generating unit data.
Line no. Buses Permanent outage Outage duration Switching
Unit no. Bus Rating (MW) Failure rate (/year) MRT (h) rate (/year) (h) time (h)
1 1 40 6.0 45
From To
2 1 40 6.0 45
3 1 10 4.0 45 1 1 3 1.5 10.0 4.0
4 1 20 5.0 45 2 2 4 5.0 10.0 4.0
5 2 5 2.0 45 3 1 2 4.0 10.0 4.0
6 2 5 2.0 45 4 3 4 1.0 10.0 4.0
7 2 40 3.0 60 5 3 5 1.0 10.0 4.0
8 2 20 2.4 55 6 1 3 1.5 10.0 4.0
9 2 20 2.4 55 7 2 4 5.0 10.0 4.0
10 2 20 2.4 55 8 4 5 1.0 10.0 4.0
11 2 20 2.4 55 9 5 6 1.0 10.0 4.0
H. Lei, C. Singh / Electric Power Systems Research 129 (2015) 160–169 163
MU MU MU MU MU
3-1 3-2 3-3 5-1 5-2
3-4 3-5
5-3 5-4
MU MU
3-4 3-5 MU MU MU
5-3 5-7 5-4
Load 3
Line 9
Process Bus
Process Bus
MU MU pDOWN = (6)
4-4 4-5
+
Load 4
Table 5
Reliability data for protection system elements.
Process Bus
Element name MTTF (year) Failure rate MRT (h) Repair rate
(/year) (/year)
Line 2 Line 4 Line 7 Line 8 CB 100 0.01 8 1095
Protection Protection Protection Protection
MU 50 0.02 8 1095
Panel Panel Panel Panel
PB 100 0.01 8 1095
Line protection panel 50 0.02 8 1095
Fig. 3. The protection system for bus 4.
164 H. Lei, C. Singh / Electric Power Systems Research 129 (2015) 160–169
Table 6
The cyber-physical interface matrix for bus 3.
Table 7
The consequent event matrix for bus 3.
Table 8
The cyber-physical interface matrix for bus 4.
associated cyber elements are perfectly reliable, then the first case to determine the time of their next transitions. Appropriate
would have probability one while all other cases zero. transition rates should be used according to situations.
Following similar procedures performed above, the complete e. Evaluate system state: Perform the network power flow analysis
Cyber-Physical Interface Matrices (CPIMs) and Consequent Event to assess system operation states. Update reliability indices.
Matrices (CEMs) for buses 3, 4, and 5 are obtained and are shown f. Repeat steps b–e until convergence is achieved.
from Tables 6–11.
In step e, the following DC power flow linear programming
4.2. System-wide reliability evaluation model [33–35] is used with the objective of minimizing total load
Nb
The next event sequential Monte Carlo simulation [32] forms curtailment.Objective: y = Min Ci
the main framework for the reliability evaluation in this stage. The i=1
detailed steps, including illustrations on how to utilize the results subject to:
of a CPIM in the composite system reliability evaluation [20], are
summarized as follows. B̂ + G + C = L
G ≤ Gmax
a. Initialize. C≤L
b. Determine a primary event: Find the minimum time to the next DA ≤ F max
event, update the corresponding element’s state, and update the (10)
total time. −DA ≤ F max
c. Determine consequent events: If the state change in step b indi-
G, C ≥ 0
cates a primary fault occurring at a transmission line, then use
1 = 0
CPIMs and CEMs to determine the consequent events and update
elements’ states accordingly. If a CPIM row corresponding to this 2...Nb unrestricted
transmission line has n consequent events, the probabilities of
these events (p1 , p2 , . . ., pn ) sum up to 1. Draw a random number where,
ranging from 0 to 1. The value of this random number determines Nb is number of buses;
which consequent event is going to happen. It should be noted C is an Nb × 1 vector of bus load curtailments;
that a transmission line connects two substations. Therefore, two Ci is load curtailment at bus i;
random numbers should be drawn independently to determine B̂ is an Nb × Nb augmented node susceptance matrix;
the consequent event at each substation. G is an Nb × 1 vector of bus actual generating power;
d. Effects of switching and repair: For elements whose states have Gmax is an Nb × 1 vector of bus maximum generating availability;
been changed in step b or in step c, draw new random numbers L is an Nb × 1 vector of bus loads;
Table 9
The consequent event matrix for bus 4.
Table 10
The cyber-physical interface matrix for bus 5.
Table 11
The consequent event matrix for bus 5.
Table 14
Table 13 EENS comparison.
Simulated transmission line failure rates.
EENS (MWh/year) (%)
Line no. Failure rate resulting from Failure rate resulting from
primary faults (/year) protection malfunctions If protection systems Considering protection
(/year) are perfectly reliable malfunctions
2. Simulation can be custom coded in more efficient programming The methodology implemented in this paper is scalable and pro-
languages. Custom programs are generally more efficient than vides an option for the reliability evaluation of large cyber-physical
generic ones coded in MATLAB. power systems. For such systems, in spite of more efforts needed
3. Much more efficient methods such as interior point methods can in detailed analysis, the main procedures remain similar to those
be used for linear programming. performed in this paper.
4. Monte Carlo simulation is readily amenable to parallel and dis-
tributed processing environments [36,37] to reduce the CPU Acknowledgments
time.
This paper was made possible by the Power Systems Engineering
It is important to mention that Monte Carlo simulation has Research Center (PSERC) under the grant “Reliability Assessment
already been successfully used for large composite power systems and Modeling of Cyber Enabled Power Systems with Renewable
but without considering the cyber-malfunctions. The contribu- Sources and Energy Storage (T-53)” and by NPRP grant # NPRP
tion of this paper is to develop a methodology to include cyber 7-106-2-053 from the Qatar National Research Fund (a member
induced dependent failures in such Monte Carlo programs. The of Qatar Foundation). The statements made herein are solely the
cyber induced dependent failures can be included in Monte Carlo responsibility of the authors.
simulation by using CPIMs. This does not significantly alter the
number of times linear programming is called for and thus does References
not alter the CPU time much.
[1] R. Billinton, Power system reliability evaluation, Gordon and Breach, New York,
1970.
6.2. Storage of matrices [2] R. Billinton, R.N. Allan, Reliability assessment of large electric power systems,
Kluwer, Boston, 1988.
[3] R. Billinton, W. Li, Reliability assessment of electric power systems using Monte
For a given power system, let m be the total number of rows in Carlo methods, Plenum Press, New York, 1994.
all CPIMs (or CEMs), n be the number of columns in a CPIM (or a [4] A.G. Phadke, J.S. Thorp, Expose hidden failures to prevent cascading outages,
IEEE Comput. Appl. Power 9 (3) (1996) 20–23.
CEM). [5] D.C. Elizondo, J. De La Ree, A.G. Phadke, S. Horowitz, Hidden failures in protec-
The value of m depends on the number of transmission lines. tion systems and their impact on wide-area disturbances, Proceedings of IEEE
The number of transmission lines in an actual power system is typ- power engineering society winter meeting, January/February 2001, vol. 2, pp.
710–714.
ically 1.2–2 times of the number of buses. Each transmission line [6] F. Yang, A.P.S. Meliopoulos, G.J. Cokkinides, Q.B. Dam, Effects of protection sys-
contributes a row in two CPIMs (or CEMs) corresponding to both of tem hidden failures on bulk power system reliability, Proceedings of the 38th
the two buses it connects to. Consider a power system with 1000 IEEE North American power symposium, September 2006, pp. 517–523.
[7] X. Yu, C. Singh, A practical approach for integrated power system vulnerability
buses (substations), which is a typical size of an actual transmission analysis with protection failures, IEEE Trans. Power Syst. 19 (November (4))
grid, it is reasonable to estimate the number of transmission lines (2004) 1811–1820.
as 2000 and thus the value of m is estimated to be 4000. [8] R. Billinton, J. Tatla, Composite generation and transmission system adequacy
evaluation including protection system failure modes, IEEE Trans. Power App.
The value of n is determined by the row with maximum number
Syst. PAS-102 (June (6)) (1983) 1823–1830.
of consequent events, which depends on the transmission line hav- [9] M.C. Bozchalui, M. Sanaye-Pasand, M. Fotuhi-Firuzabad, Composite system reli-
ing maximum number of adjacent lines. Assuming a transmission ability evaluation incorporating protection system failures, Proceedings of the
line has maximum 10 adjacent lines, thus the maximum possi- 2005 IEEE Canadian conference on electrical and computer engineering, May
2005, pp. 486–489.
ble value of n is 210 , which is 1024. Of course, it is possible that [10] K. Jiang, C. Singh, New models and concepts for power system reliability evalua-
a few transmission lines may have more than 10 adjacent lines. tion including protection system failures, IEEE Trans. Power Syst. 26 (November
For such lines, only the 1024 most likely consequent events are (4)) (2011) 1845–1855.
[11] S.H. Horowitz, A.G. Phadke, Power system relaying, 3rd ed., John Wiley & Sons
considered since the remaining consequent events have negligible Ltd, Chichester, West Sussex, UK, 2008.
probabilities. Thus, it is reasonable to estimate n as 1024. [12] J.L. Blackburn, T.J. Domin, Protective relaying: principles and applications, 3rd
Each entry in a CPIM can be stored as a 64-bit double-precision ed., CRC, Boca Raton, FL, USA, 2007.
[13] P.M. Anderson, Power System Protection—Part VI: reliability of protective sys-
floating-point number. Therefore, the total storage space needed tems, McGraw-Hill/IEEE Press, New York, 1999.
for all CPIMs is 8·m·n Bytes, which equals 31.25 MB (32,768,000 [14] B. Kasztenny, J. Whatley, E.A. Udren, J. Burger, D. Finney, M. Adamiak, Unan-
Bytes). swered questions about IEC 61850—what needs to happen to realize the vision?
Presented at the 32nd annual western protective relay conference, Spokane,
Each entry in a CEM is a binary number corresponding to a con- WA, USA, October 2005.
sequent event. For a system with 2000 transmission lines, 2000 bits [15] T. Skeie, S. Johannessen, C. Brunner, Ethernet in substation automation, IEEE
are needed to represent such an event. Thus, each entry uses 250 Control Syst. Mag. 22 (June (3)) (2002) 43–51.
[16] T.S. Sidhu, P.K. Gangadharan, Control and automation of power system substa-
Bytes (2000 bits) and the total storage space needed for all CEMs is
tion using IEC 61850 communication, Proceedings of the 2005 IEEE conference
250·m·n Bytes, which equals 976.5625 MB (1,024,000,000 Bytes). on control applications, August 2005, pp. 1331–1336.
Therefore, the total space needed to store all CPIMs and CEMs is [17] J.D. McDonald, Electric power substations engineering, 3rd ed., CRC, Boca Raton,
estimated to be 1007.8125 MB, which is approximately 0.9842 GB. FL, USA, 2012.
[18] B. Falahati, Y. Fu, L. Wu, Reliability assessment of smart grid considering direct
It is feasible to claim such space on hard drive or Random Access cyber-power interdependencies, IEEE Trans. Smart Grid 3 (September (3))
Memory (RAM). (2012) 1515–1524.
[19] B. Falahati, Y. Fu, Reliability assessment of smart grids considering indirect
cyber-power interdependencies, IEEE Trans. Smart Grid 5 (July (4)) (2014)
1677–1685.
7. Conclusions [20] H. Lei, C. Singh, A. Sprintson, Reliability modeling and analysis of IEC 61850
based substation protection systems, IEEE Trans. Smart Grid 5 (September (5))
In this paper, a systematic reliability evaluation methodol- (2014) 2194–2202.
[21] R. Billinton, S. Kumar, N. Chowdhury, K. Chu, K. Debnath, L. Goel, E. Khan, P.
ogy is implemented in a composite power system consisting of Kos, G. Nourbakhsh, J. Oteng-Adjei, A reliability test system for educational
current-carrying components and protection systems with modern purposes-basic data, IEEE Trans. Power Syst. 4 (August (3)) (1989) 1238–1244.
architecture. The quantitative relationship between switching time [22] A. Sankarakrishnan, R. Billinton, Sequential Monte Carlo simulation for com-
posite power system reliability analysis with time varying loads, IEEE Trans.
and system EENS is also studied. The results clearly indicate the Power Syst. 10 (August (3)) (1995) 1540–1545.
impact of protection failures on system-wide reliability indices and [23] IEEE Committee Report, IEEE reliability test system, IEEE Trans. Power App. and
also signify the importance of accelerating line switching process. Syst. PAS-98 (November/December (6)) (1979) 2047–2054.
H. Lei, C. Singh / Electric Power Systems Research 129 (2015) 160–169 169
[24] T.M. Lindquist, L. Bertling, R. Eriksson, Circuit breaker failure data and [31] P. Ferrari, A. Flammini, S. Rinaldi, G. Prytz, Mixing real time Ethernet traffic
reliability modeling, IET Gener. Transm. Distrib. 2 (November (6)) (2008) on the IEC 61850 process bus, Proceedings of the 9th IEEE international work-
813–820. shop on factory communication systems (WFCS), Lemgo, Germany, May 21–24,
[25] M.G. Kanabar, T.S. Sidhu, Reliability and availability analysis of IEC 61850 based 2012, pp. 153–156.
substation communication architectures, Presented at the IEEE power & energy [32] C. Singh, J. Mitra, Monte Carlo simulation for reliability analysis of emergency
society general meeting, Calgary, AB, Canada, 2009. and standby power systems, Proceedings of the 30th IEEE industry applications
[26] V. Skendzic, I. Ender, G. Zweigle, IEC 61850-9-2 process bus and its impact society conference, Orlando, FL, October 1995, pp. 2290–2295.
on power system protection and control reliability, Schweitzer Engineering [33] C. Singh, J. Mitra, Composite system reliability evaluation using state space
Laboratories, Inc., Pullman, WA, USA, Technical Report, 2007. pruning, IEEE Trans. Power Syst. 12 (February (1)) (1997) 471–479.
[27] K.P. Brand, V. Lohmann, W. Wimmer, Substation automation handbook, utility [34] EPRI, Composite system reliability evaluation methods, Final report on research
automation consulting Lohmann, Bremgarten, Switzerland, 2003. project 2473-10, EPRI EL-5178, June 1987.
[28] M.G. Kanabar, T.S. Sidhu, Performance of IEC 61850-9-2 process bus and cor- [35] J. Mitra, C. Singh, Incorporating the DC load flow model in the decomposition-
rective measure for digital relaying, IEEE Trans. Power Del. 26 (April (2)) (2011) simulation method of multi-area reliability evaluation, IEEE Trans. Power Syst.
725–735. 11 (August (3)) (1996) 1245–1254.
[29] L. Andersson, K.-P. Brand, C. Brunner, W. Wimmer, Reliability investigations [36] N. Gubbala, C. Singh, Models and considerations for parallel implementation of
for SA communication architectures based on IEC 61850, Presented at the IEEE Monte Carlo simulation methods for power system reliability evaluation, IEEE
PowerTech, St. Petersburg, Russia, June 2005. Trans. Power Syst. 10 (May (2)) (1995) 779–787.
[30] A. Apostolov, B. Vandiver, IEC 61850 process bus—principles, applications and [37] C.L.T. Borges, D.M. Falcão, Carlos João, O. Mello, A.C.G. Melo, Composite reliabil-
benefits, Proceedings of the 63rd annual conference on protective relay engi- ity evaluation by sequential Monte Carlo simulation on parallel and distributed
neers, 2010, pp. 1–6. processing environments, IEEE Trans. Power Syst. 16 (May (2)) (2001) 203–209.