Work Order
Work Order
Work Order
To,
Subject: Work Order for Supply, Installation, Testing and Commissioning of Welland Power 660KVA
(Prime Power) & (726KVA Standby Power) Generator System.
Page 1 of 4
AITs and all sorts of Customs Duties, Marin Insurance, LC and
Bank Charges, Loading- Unloading, Carrying costs to the project
site, Dhanmondi, Dhaka-1209 and all other expenditures up to
Installation, Testing, Commissioning of the total system are
included in this price. The Installation, Testing, Commissioning
will be free of cost.
4 Mode of Payment During Work order 30%.
After arrival at Chattaragam Sea Port 20%.
After installation 30%.
After commissioning 10%.
One year after commissioning 10%.
5 Generator Origin UK
6 Country of Assemble UK
7 Commencement of work You should take over the site immediately.
8 Approval You will be required to get an approval of working Drawing
from concern Authority/ Consultant within one week from the
date of getting the work order and having the first installment
payment.
9 Completion of work Total completion period 04 months and 10 days from the time
of manufacturing of DG set in UK factory, carrying upto
Chattagram sea port, sea port to our project site, installation,
testing. Commissioning at our project site 726/A (Old),
86/A(New) Sarmasjid Road, Dhanmondi, Dhaka-1209 from the
date of work order.
10 Additional Work If additional work is required and deemed necessary beyond
the job specified, the concerned signatories shall notify
accordingly.
11 Service 01 [One] year after sell Service against equipment and
workmanship defects with effect from the date of completion
of work at site and commissioning of the system.
12 Warranty Edison Power Bangladesh Ltd. (SECOND PARTY) shall provide
Warranty of equipment’s, Battery and fittings against
Manufacturing defects for a period of 18 months from the date
of shipment or 12 months from the date of Commissioning
whichever falls due first.
13 Maintenance Edison Power Bangladesh Ltd. will carry out free of cost
servicing for 12 (Twelve) months from the date of
Handover, during which time Edison Power Bangladesh
Ltd.will carry out the service of the Generator set and
should attend to the breakdown calls.
14 Penalty If the work is not completed within the time period as
stipulated date of Work Order at para 09, you shall be liable for
a penalty @ 0.01% of total contracted value per day of delay
which shall be realized from your bill [penalty will not exceed
5% of total value]. If there is any delay from the client's end i.e
Power line, Interior work, Change of Design etc Vendor will not
Page 2 of 4
be liable for penalty.
15 Other Conditions a. Your entire job planning and schedule of work should
be framed in such a way that the other tenants of that
site do not feel inconvenient and disturbed due to your
on-going job. Moreover, you must take reasonable care
to store of your materials and continue your job
without hampering other works. In case any problem
arises, you shall resolve the issues in consultation with
the engineer in charge and the Chief Executive Officer.
b. DR. FAZLUL HAQUE COLORECTAL HOSPITAL LTD
reserves the right to cancel the Work Order for not
complying with any conditions of this Work Order and
in such case Company will not be liable to pay any
compensation.
16 Elements of Work Order This work order comprises of
a) 4 pages of this work order,
b) Your last revised Quotation dated: 17.12.2020. Where
your Quoted price was Tk-40,00,000/- (Forty Lac only).
c) Our latest BOQ Dated: September,2020
17 Skilled Work Force During work you must have One skilled DG Engineers, requisite
nos of Skilled Technicians other skilled people at the project
site to complete the work within the stipulated time frame with
skillness and craftsmanship. No delay of work will be allowed.
No unskilled Labor/ Technicians/ Engineers will be allowed.
There must have craftsmanship in your work. Required Duct
made by Steel sheet must be done by definite tools and
machineries. Leak proof test must be done properly.
17 FORCE MAJEURE i. If the delivery, installation, as well as the Project
completion and work under this agreement be
prevented or delayed due to prohibition of law, act of
nature, war, riot, or any other reasonable
unforeseeable circumstances caused beyond the
control of the SECOND PARTY, the SECOND PARTY shall
not be held liable for any delay in the performances of
all or any part of this Contract in connection thereof.
Page 3 of 4
evidenced and reduced to writing, by virtue of a
Supplementary Agreement
Best regards
Page 5 of 4