MS03-Method of Statement For Booster & Transfer Pump
MS03-Method of Statement For Booster & Transfer Pump
MS03-Method of Statement For Booster & Transfer Pump
CONSULTANT:
ABDULLA SAEED AMER HAMAD
ECG
ALNEYADI
MAIN CONTRACTOR: MEP CONTRACTOR:
ARABTEC CONTRACTING AIRTECHNIC
PROJECT:
AL BARSHA HOTEL, PLOT 3739355, DUABI, UAE
Method of Statement Title :
CONTENTS
3.0 Operation
4.0 Responsibilities
5.0 Equipment
7.0 Checklist
1.1 This method statement aims to discuss and specify the detailed requirements and
comprehensive procedures for the installation of booster pump and transfer pumps.
- Al Barsha Hotel
- Volume III / Part B / Div 23 / Sec 221123.13 Booster Pumps
- Volume III / Part B / Div 23 / Sec 221123.15 Circulation Pumps
_ Volume III / Part B / Div 23 / Sec 221329 Submersible Pumps
2. Location of Activity:
3. Operation:
a. Materials
All pumps equipments as per approved capacity, Type and Field submittal.
Pumps shall be protected from mechanical damage and climatic condition during transport
and while stored at site.
c. Installation (General) :
In General
1. All pumps equipments shall be located and installed as per approved shop drawings.
2. It is to be ensured also that all pump equipment foundations as per design/lay-out have
been completed prior to setting and installation.
3. Support packaged pumps using the vibration control devices (Anti- Vibration Pads &
Flexible connectors).
Booster Pump Set Installation
Booster pump consists of 2D + 1 S arrangement with common suction header and
discharge header, isolating valve fixed on the suction and discharge side of each
pump ,Check valves on discharge side of each pump, pressure gauge and pressure
switch fixed on discharge header, control panel and pressure vessel .All assembled
on a common steel base frame
All Booster Pump set shall be complete as shown in detailed drawing with
duty/stand-by units as to be installed with a pre-wired control panel.
All Parts of the Pump set shall be as per the standard approved as mentioned in
supplier nameplates & capacity.
Pumps should be placed in a well ventilated room to ensure adequate cooling g of
the pumps motors.Kepp a clearance of 50cm-100cm from all sides.
Also, a diaphragm pressure vessel & devices are installed as per standard as
mentioned in material submittal. In which the “Demand Pressure” interfacing is
ensured through the setting of pressure switch, wherein the minimum (Cut-in
Pressure) and maximum (Cut-off Pressure) is met within the pumping system.
Arrows on the pump base show the direction of flow of water through the pumps.
Pipe connection shall made as per the direction for both suction and discharge.
The pipe connected to the pumps shall be of adequate size.
To avoid resonance flexible connectors should be fitted with suction and discharge.
All connections to the water distribution piping network shall be isolated with the
provision of flexible connectors to ensure that no vibrations are transmitted due top
the pump action.
The pumps should be placed on plane solid surface (concrete floor or foundation )
using vibration absorption pad.
All Valves and accessories pertaining to the pump equipments (such as gauges etc.)
are accessible for any operator’s interventions.
To prevent the pump from dry running floats switch shall be installed in the water
tank.
Pump should also follow the BMS point list.
Submersible pump consists of duty standby pump with guide rail ,lifting
chain,control panel.
Drill mounting hole s for the guide rail bracket on the side of the pit and fasten the
guide rail with two screws
.Place the auto coupling base unit on the bottom of the pit .
Use a plum line to establish the correct positioning.
Assemble discharge line in a generally accepted procedure and without the line to
distortion or tension.
Install gate valve and check valve separately on each pump discharge line.
Insert the guide rail into the auto-coupling base unit and adjust the length of the rail
accurately to the guide rail bracket
Unscrew the provisionally fastened guide rail bracket, fit it on top of the guide rail
and finally fasten it firmly to the pit wall.
Clean out debris from the pit before lowering the pump.
Fit the guide claw to the discharge port of the pump. Then slide the guide claw
down the guide rail and lower the pump into the pit by means of chain provided.
Install float switch as per the approved scheme.
Make sure that all cable entries are water tight and no joints inside the pit.
All field wiring and control panel connection to be completed before startup.
4. Responsibilities:
4.1.1. To ensure that all the preparation and application works are carried out according
to the Contract Specification.
4.1.2. To ensure that the progress of works is carried out according to the planned
program and as per the approved Method Statement.
4.1.3. To ensure that all the equipments and materials required executing the work are
available according to the planned construction program.
4.1.4. To ensure that latest approved shop drawings are to be used for the installation
4.1.5. To coordinate with the Main Contractor MEP Coordinator & Safety Officer for a
safe and proper execution of the works.
4.1.7. To monitor the progress of work in relation with the work program and report to
the Construction Manager.
4.2.2. To ensure the quality of materials arriving into the site are in good condition as
per the supplier’s recommendation & with the accordance to the project
specification.
4.2.3. To ensure that latest approved shop drawings are to be used for the installation.
4.2.4. To ensure the quality of the site installations & all should be accordance with the
approved shop drawings, as per the company & main contractor policy
requirements for the satisfaction of customer’s specification.
4.2.5. To ensure that all the work inspection request and material inspection request are
to be followed up & approved by the engineers, to raised and maintain all the
WIR, MIR, Test reports and properly documented.
4.2.6. To carry out the testing and commissioning procedure, and to complies with the
specification.
4.2.7. To ensure that all the certificates, country of origin, International standard shall
be verified.
4.3.1. The foreman will carry out his duties by maintaining continuous coordination with
the Site Engineer on daily basis and ensure proper distribution of the workforce in
the required and planned locations.
4.3.2. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties properly.
4.3.3. To ensure in consultation with the Site Engineer that the manpower involved in
the works are moving as agreed and planned for the work.
4.3.4. To ensure that the daily work is progressing as planned and as advised by the Site
Engineer of any requirement for additional resources.
4.3.5. To control disposal of waste materials according to the instructions received from
the Site Engineer.
4.3.6. To ensure full coordination with the Safety Officer to maintain safe working and
proper housekeeping of the site, following the approved safety measures and
further ensure that all his working team are aware of the same to prevent accident
and losses.
4.3.7. To inform the Site Engineer, QA/QC Engineer of the areas ready for inspection.
General tools and equipments that will be engaged for the Installation of water supply valves
and accessories shall consist but not limited to the following:
Chain Block
Straight Level
Adjustable Wrench
Box Wrench Set
Drilling Machine
Filler Gauge (for Pumps shaft alignment)
7. Check List:
Strictly followed as per the manufacturer’s Health & Safety recommendations for handling and use of
the materials. Ensure that all involved personnel shall be aware of the same.
__________________
ENG.MAGDY BADR
PROJECT MANAGER
AIRTECHNIC A/C SYSTEM CO.LLC.