41537TECH Mech
41537TECH Mech
41537TECH Mech
SECTION-A
CMM/MAPS/MM/41537/MANUAL-PO/1291 DT:-
Welding Specification:
1. The tank should be fabricated from steel plate material confirming to IS 2062
Gr-B.
3. Cold bending of steel plate should be done such that no dent marks damage
on the plate.
Welding procedure:
Welders Qualification:
All welding joints should be done by the qualified welders as per ASME
Sec.IX.Relevant performance qualification certificate should be produced for
verification before start of the work at any time during the fabrication of the
tank.
Welding inspection:
Hydrostatic test:
Welding consumables:
2. Butt weld 100% 100% Root pass and 10% Random spot
joints final pass DPT Radiography .10% of
the entire BW joint
length
Welding Procedure/Specification:
Metals : C.S P1 to P1
Position : All
Preheat : Nil
Process:
Procedure for but and fillet welding of carbon steel pipe/fittings with standard
edge preparation by manual metallic arc process using low hydrogen type
covered electrodes.
Mode of Qualification:
Base metal:
Weld able quality carbon steel confirming to the requirements for materials listed
under group P1 of Table Q-11.1 of Section IX of ASME Boiler&Pressure vessel
code.
Electrode characteristics:
Position of welding:
Care of electrodes:
The covered electrodes shall be properly stores in their original sealed containers
in a dry place. Prior to welding, electrodes shall be kept in a baking oven and
heated at 3750C+/-250C for a period of one hour to remove all the moisture and
transferred to the storage oven. The storage oven shall be maintained at 1000C
above ambient temperature. The electrodes shall remain identified until
consumed. Electrodes shall be drawn from the oven for the use only to the
extent of immediate necessity to avoid unnecessary exposure to
atmosphere.Electrdes exposed in the t=field for more than one hour shall be
returned to the drying oven and kept at 1000C for at least 2-hours.All the
electrodes which have been exposed to rain or contaminated with water shall be
discarded. The daily requirement of electrodes shall be carefully assessed and
drawn to avoid more than one rebaking and many heating and cooling cycles.
Cleaning:
Surface for welding shall be cleaned and free from paint, oil, grease,
rust or any other foreign matter. In any event weld metal shall be deposited only
upon bright base metal. Solvent approved by QS to clean the weld groove and its
adjacent area shall be used before welding. Swab used for this purpose shall be
lint free.
Welding Technique:
Tacks are recommended at a spacing of 4”, but not less than three
tacks shall be made.
Tack welds shall either be removed completely when they have served their
purpose, or their starting and stopping ends shall be properly prepared by
grinding or other suitable means so that they may be satisfactorily
incorporated into the final weld.
Tack welds shall be examined visually for defects and if found to be defective,
shall be removed.
d) The root pass shall be completed by manual metallic arc process using
covered electrodes.
e) After root pass the same shall be inspected visually as well as by a
method required by the relevant specification.
If the weld is visible from inside, it shall be inspected for lack of fusion, lack
of penetration, icicles; etc.the internal reinforcement shall not exceed 1.5mm.
h) The width of the head should not exceed three times the core wire diameter,
except for the final pass. The thickness of each pass shall generally about 3mm.
k) The arc should be struck either on a striker plate and carried over the joint, or
in the joint where the metal surface will be fused into the weld.
All traces of slag and flux shall be removed by means of wire brushes or chisels
before successive beads or layers are deposited.
Defects:
Any defect that appears in the weld shall be removed by chipping and grinding.
Whenever arc gouging is permitted grind or file back at least 1.5mm beyond the
deepest indentation before depositing the weld metal. Magnetic particle, liquid
dye penetrant or radiography inspection should be used to check that defect has
been completely removed prior to weld repair.
Description of work:
1. The rubber lining shall be bonded to the substrate. The adhesive system
shall be suitable for the type of rubber & for the service conditions. The
adhesive shall be applied to the primed substrate surface by brush, roller
or spray, any solvent in the adhesive being allowed to evaporate between
the successive coats or subsequent application of lining. The raw rubber
is to be tailored to fit the surface to be lined. Preshrinking and necessary
shall be carried out as first step.
2. The surface of the rubber, which will be lined on the metal, has to be
coated with rubber adhesive solution till it gets tackness. During the same
time the adhesive compound is applied on the prepared & allowed to tack.
Both rubber /metal & rubber / rubber surfaces coated with adhesive
solution shall be allowed to Dry sufficiently to achieve tackness. The type
of end joint shall be strapped Design. This Strapping joint shall be
suitably staggered to get effective smooth surface. The sheets before
laying shall be spark tested to confirm healthiness.
3. Fitting the lining sheets to the surface:
a) Exclusion of air-in the application of lining air shall be allowed to
escape between adjacent layers & metal.
b) Continuity of lining: When fitted all the sheets & strapped joints shall
be free from pinholes & other defects.
iii) Inspection: The contractor has to offer the tank for inspection to
NPCIL/QAI at each of following stages.
1. Surface preparation.
2. Raw material – rubber with test certificate from NCPIL approved
laboratories.
3. Spark test on raw arterial.
4. Laying of joint – no patch permitted.
5. Hot steam vulcanization.
6. Hardness test = Hardness shall be =60 Shore A + or -5.
7. Spark – test after vulcanization to ensure defect free lining.
8. Overall visual.
The outside surface has to be coated with anticorrosive coating of Epigen 4029
of 500micron thick.The complete tank outer surface including pipe spools,
flanges, man hole covers and support pads have to be coated with adequate
bonding and shall have excellent chemical resistance.
The top layer shall be of ultraviolet coating with polyurethane paint of grey
colour.
Surface preparation:
The cleaned surface is to be grit blasted uniformly unit grey –white surface is
formed. Suitable enclosure shall be arranged to contain blast debris.
For Best Result ensure that surface is free from rust,dust,moisture, Oil
and Grease
The contract has to submit Tentative QA plan along with offer and submit full
QAP after receipt of evaluated work order.
QAP shall indicate all stage inspections, acceptance norms and methods of
testing. The QAP will be approved by NPCIL. Contractor has to execute the
works as per approved QAP and procedures.
Specification:
Material Test Certificates shall be submitted. In case of Non-condition with material TC,Check Analysis sh
chemical(except CarbonEquivalent)Analysis.
a)Procedure
b)Performance
03 Dished Ends:
04 Shell
06 Nozzle:
Separate QAP for Rubber Lining shall be submitted after Tank Fabrication
LEGEND:
W - Witness
LPIR -Liquid Penetrant Inspection Report