Vivek Kumar 2nd RA Bill
Vivek Kumar 2nd RA Bill
Vivek Kumar 2nd RA Bill
Construction
NAME OF WORK : CHIPLUN RIVER BRIDGE
Contractor - V3 CONTRACTORS R A Bill No - 2
Billing Period - 18/03/2023 To 31/05/2023
Item No. Discription Certified Qnty Unit Rate Certified Amt
Cummulative Previous Present Cummulative Previous Present
1 Steel cutting bending binding 59.92 0.00 59.92 MT 6000.00 359520.00 0.00 359520.00
2 Shuttering MS & PLY 1097.55 0.00 1097.554 Sqm 250.00 274388.50 0.00 274388.50
3 Concreting without bucket 935.82 0.00 935.819 Cum 200.00 187163.80 0.00 187163.80
Concreting with bucket 161.74 0.00 161.735 Cum 250.00 40433.75 0.00 40433.75
Dewatering & Foundation
4 173.88 0.00 173.880 Cum 100.00 17388.00 0.00 17388.00
cleaning
5 Curring 347.18 0.00 347.175 Cum 25.00 8679.38 0.00 8679.38
6 Material Shifting 65.48 0.00 65.483 MT 350.00 22919.05 0.00 22919.05
7 Lime powder marking 201.60 0.00 201.600 RMT 2.00 403.20 0.00 403.20
8 PCC 56.76 0.00 56.755 Cum 200.00 11351.00 0.00 11351.00
9 Levelling & Dressing 579.60 0.00 579.600 Sqm 0.00 0.00 0.00 0.00
10 Cement cutting 2620.00 0.00 2620.000 Nos 23.00 60260.00 0.00 60260.00
11 Admixture filling 1889.00 0.00 1889.000 Ltr 10.00 18890.00 0.00 18890.00
12 Shuttering Making 181.97 0.00 181.966 Sqm 0.00 0.00 0.00 0.00
13 Department Labours 310.00 0.00 310.00 Nos 450.00 139500.00 0.00 139500.00
14 Department Mason 62.00 0.00 62.00 Nos 650.00 40300.00 0.00 40300.00
TOTAL AMOUNT - A 1181195 0.00 1181197
Bar
Total Total
Shape of Dia of Length of Nos of weight
Item No. Discription of item Span Length of weight of
bar bar cutting Cutting pre
this item this item
RMT
Steel Previous paid Quantity 0.00
Pier P-09
1- Bottom Main Bar 150 C/C 20 6.00 78.00 468.00 2.470 1155.96
2- Bottom Distribution Bar 150 C/C 20 12.00 33.00 396.00 2.470 978.12
3- Top Main bar 150 C/C 10 6.80 60.00 408.00 0.617 251.74
4- Top distribution Bar 150 C/C 10 15.00 25.00 375.00 0.617 231.38
5- Face Bar - 10 34.20 5.00 171.00 0.617 105.51
6- Vertical-1 150 C/C 20 8.50 71.00 603.50 2.470 1490.65
7- Vertical-2 150 C/C 20 8.50 71.00 603.50 2.470 1490.65
8- Master ring upto 1.5 M Above Raft 150 C/C 12 24.00 16.00 383.97 0.889 341.35
9- Outer ring 1.5 M Above footing till top 200 C/C 10 23.07 20.00 461.36 0.617 284.66
10- Link Bars upto 1.5 M Above raft 150 C/C 10 1.30 600.00 780.00 0.617 481.26
11- Chair Bar - 20 4.00 18.00 72.00 2.470 177.84
12- Link Bars 1.5 M Above footing till top 150 C/C 10 1.30 540.00 702.00 0.617 433.13
Pier P-11
1- Bottom Main Bar 20 6.00 78.00 468.00 2.470 1155.96
2- Bottom Distribution Bar 150 C/C 20 12.00 33.00 396.00 2.470 978.12
3- Top Main bar 150 C/C 10 6.80 60.00 408.00 0.617 251.74
4- Top distribution Bar 150 C/C 10 15.00 25.00 375.00 0.617 231.38
5- Face Bar - 10 34.20 5.00 171.00 0.617 105.51
6- Vertical-1 150 C/C 20 8.00 71.00 568.00 2.470 1402.96
7- Vertical-2 150 C/C 20 8.00 71.00 568.00 2.470 1402.96
8- Master ring upto 1.5 M Above Raft 150 C/C 12 24.00 16.00 383.97 0.889 341.35
9- Outer ring 1.5 M Above footing till top 200 C/C 10 23.07 17.00 392.16 0.617 241.96
10- Link Bars upto 1.5 M Above raft 150 C/C 10 1.30 600.00 780.00 0.617 481.26
11- Link Bars 1.5 M Above footing till top 150 C/C 10 1.30 510.00 663.00 0.617 409.07
12- Chair Bar - 20 4.00 18.00 72.00 2.470 177.84
Pier P-10
1- Bottom Main Bar 150 C/C 20 6.00 78.00 468.00 2.470 1155.96
2- Bottom Distribution Bar 150 C/C 20 12.00 33.00 396.00 2.470 978.12
3- Top Main bar 150 C/C 10 6.80 60.00 408.00 0.617 251.74
4- Top distribution Bar 150 C/C 10 15.00 25.00 375.00 0.617 231.38
5- Face Bar - 10 34.20 5.00 171.00 0.617 105.51
6- Vertical-1 150 C/C 20 8.74 71.00 620.54 2.470 1532.73
7- Vertical-2 150 C/C 20 8.74 71.00 620.54 2.470 1532.73
8- Chair Bar - 20 4.00 18.00 72.00 2.470 177.84
9- Master ring upto 1.5 M Above Raft 150 C/C 12 23.17 16.00 370.69 0.889 329.54
10- Outer ring 1.5 M Above footing till
top 200 C/C 10 23.07 17.00 392.16 0.617 241.96
11- Link Bars upto 1.5 M Above raft 150 C/C 10 1.30 660.00 858.00 0.617 529.39
12- Link Bars 1.5 M Above footing till top 150 C/C 10 1.30 520.00 676.00 0.617 417.09
Pier P-12
1- Bottom Main Bar 150 C/C 20 6.00 78.00 468.00 2.470 1155.96
2- Bottom Distribution Bar 150 C/C 20 12.00 33.00 396.00 2.470 978.12
3- Top Main bar 150 C/C 10 6.80 60.00 408.00 0.617 251.74
4- Top distribution Bar 150 C/C 10 15.00 25.00 375.00 0.617 231.38
5- Face Bar - 10 34.20 5.00 171.00 0.617 105.51
6- Vertical-1 150 C/C 20 8.70 71.00 617.70 2.470 1525.72
7- Vertical-2 150 C/C 20 8.70 71.00 617.70 2.470 1525.72
8- Master ring upto 1.5 M Above Raft 150 C/C 12 23.17 16.00 370.69 0.889 329.54
9- Outer ring 1.5 M Above footing till top 200 C/C 10 23.07 17.00 392.16 0.617 241.96
10- Link Bars upto 1.5 M Above raft 150 C/C 10 1.30 600.00 780.00 0.617 481.26
11- Link Bars 1.5 M Above footing till top 150 C/C 10 1.30 510.00 663.00 0.617 409.07
12- Chair Bar - 20 4.00 18.00 72.00 2.470 177.84
Pier P-13
1- Bottom Main Bar 150 C/C 20 6.00 78.00 468.00 2.470 1155.96
2- Bottom Distribution Bar 150 C/C 20 12.00 33.00 396.00 2.470 978.12
3- Top Main bar 150 C/C 10 6.80 60.00 408.00 0.617 251.74
4- Top distribution Bar 150 C/C 10 15.00 25.00 375.00 0.617 231.38
5- Face Bar - 10 34.20 5.00 171.00 0.617 105.51
6- Vertical-1 150 C/C 20 8.75 71.00 621.25 2.470 1534.49
7- Vertical-2 150 C/C 20 8.75 71.00 621.25 2.470 1534.49
8- Master ring upto 1.5 M Above Raft 150 C/C 12 23.17 16.00 370.69 0.889 329.54
9- Outer ring 1.5 M Above footing till top 200 C/C 10 23.07 17.00 392.16 0.617 241.96
10- Link Bars upto 1.5 M Above raft 150 C/C 10 1.30 660.00 858.00 0.617 529.39
11- Link Bars 1.5 M Above footing till top 150 C/C 10 1.30 530.00 689.00 0.617 425.11
12- Chair Bar - 20 4.00 18.00 72.00 2.470 177.84
Pier P-8
1- Bottom Main Bar 150 C/C 20 6.00 78.00 468.00 2.470 1155.96
2- Bottom Distribution Bar 150 C/C 20 12.00 33.00 396.00 2.470 978.12
3- Top Main bar 150 C/C 10 6.80 60.00 408.00 0.617 251.74
4- Top distribution Bar 150 C/C 10 15.00 25.00 375.00 0.617 231.38
5- Face Bar - 10 34.20 5.00 171.00 0.617 105.51
6- Vertical-1 150 C/C 20 9.27 71.00 658.17 2.470 1625.68
7- Vertical-2 150 C/C 20 9.27 71.00 658.17 2.470 1625.68
8- Master ring upto 1.5 M Above Raft 150 C/C 12 23.17 16.00 370.69 0.889 329.54
9- Outer ring 1.5 M Above footing till top 200 C/C 10 23.07 20.00 461.36 0.617 284.66
10- Link Bars upto 1.5 M Above raft 150 C/C 10 1.30 660.00 858.00 0.617 529.39
11- Link Bars 1.5 M Above footing till top 150 C/C 10 1.30 600.00 780.00 0.617 481.26
12- Chair Bar - 20 4.00 18.00 72.00 2.470 177.84
Pier P-7
1- Bottom Main Bar 150 C/C 20 6.00 78.00 468.00 2.470 1155.96
2- Bottom Distribution Bar 150 C/C 20 12.00 33.00 396.00 2.470 978.12
3- Top Main bar 150 C/C 10 6.80 60.00 408.00 0.617 251.74
4- Top distribution Bar 150 C/C 10 15.00 25.00 375.00 0.617 231.38
5- Face Bar - 10 34.20 5.00 171.00 0.617 105.51
6- Vertical-1 150 C/C 20 6.50 71.00 461.50 2.470 1139.91
7- Vertical-2 150 C/C 20 5.50 71.00 390.50 2.470 964.54
8- Master ring upto 1.5 M Above Raft 150 C/C 12 23.17 16.00 370.69 0.889 329.54
9- Outer ring 1.5 M Above footing till top 200 C/C 10 23.07 0.00 0.00 0.617 0.00
10- Link Bars upto 1.5 M Above raft 150 C/C 10 1.30 660.00 858.00 0.617 529.39
11- Link Bars 1.5 M Above footing till top 150 C/C 10 1.30 0.00 0.00 0.617 0.00
12- Chair Bar - 20 4.00 18.00 72.00 2.470 177.84
Pier P-6
1- Bottom Main Bar 150 C/C 20 6.00 78.00 468.00 2.470 1155.96
2- Bottom Distribution Bar 150 C/C 20 12.00 33.00 396.00 2.470 978.12
3- Top Main bar 150 C/C 10 6.80 60.00 408.00 0.617 251.74
4- Top distribution Bar 150 C/C 10 15.00 25.00 375.00 0.617 231.38
5- Face Bar - 10 34.20 5.00 171.00 0.617 105.51
6- Vertical-1 150 C/C 20 6.50 71.00 461.50 2.470 1139.91
7- Vertical-2 150 C/C 20 5.50 71.00 390.50 2.470 964.54
8- Master ring upto 1.5 M Above Raft 150 C/C 12 23.17 16.00 370.69 0.889 329.54
9- Outer ring 1.5 M Above footing till top 200 C/C 10 23.07 0.00 0.00 0.617 0.00
10- Link Bars upto 1.5 M Above raft 150 C/C 10 1.30 660.00 858.00 0.617 529.39
11- Link Bars 1.5 M Above footing till top 150 C/C 10 1.30 0.00 0.00 0.617 0.00
12- Chair Bar - 20 4.00 18.00 72.00 2.470 177.84
Total
Item No. Discription of item Unit Nos Width Depth Qnty
length
Shuttering Previous paid Quantity = 0.000
Pier P-09
Raft
Longer side Sqm 2 11.80 1.500 0.00 35.400
Shorter Side Sqm 2 5.00 1.50 0.00 15.000
Vertical both side Sqm 2 9.00 4.500 0.00 81.000
Vertical both side Round Sqm 1 3.77 4.50 0.00 16.956
Pier P-10
Raft
Longer side Sqm 2 11.80 1.500 0.00 35.400
Shorter Side Sqm 2 5.00 1.50 0.00 15.000
Vertical both side Sqm 2 9.00 4.880 0.00 87.840
Vertical both side Round Sqm 1 3.77 4.88 0.00 18.388
Pier P-11
Raft
Longer side Sqm 2 11.80 1.500 0.00 35.400
Shorter Side Sqm 2 5.00 1.50 0.00 15.000
Vertical both side Sqm 2 9.00 4.660 0.00 83.880
Vertical both side Round Sqm 1 3.77 4.66 0.00 17.559
Pier P-12
Raft
Longer side Sqm 2 11.80 1.500 0.00 35.400
Shorter Side Sqm 2 5.00 1.50 0.00 15.000
Vertical both side Sqm 2 9.00 4.810 0.00 86.580
Vertical both side Round Sqm 1 3.77 4.81 0.00 18.124
Pier P-13
Raft
Longer side Sqm 2 11.80 1.500 0.00 35.400
Shorter Side Sqm 2 5.00 1.50 0.00 15.000
Vertical both side Sqm 2 9.00 4.900 0.00 88.200
Vertical both side Round Sqm 1 3.77 4.90 0.00 18.463
Pier P-08
Raft
Longer side Sqm 2 11.80 1.500 0.00 35.400
Shorter Side Sqm 2 5.00 1.50 0.00 15.000
Vertical both side Sqm 2 9.00 5.350 0.00 96.300
Vertical both side Round Sqm 1 3.77 5.35 0.00 20.159
Pier P-07
Raft
Longer side Sqm 2 11.80 1.500 0.00 35.400
Shorter Side Sqm 2 5.00 1.50 0.00 15.000
Vertical both side Sqm 2 9.00 1.700 0.00 30.600
Vertical both side Round Sqm 1 3.77 1.70 0.00 6.406
Pier P-06
Raft
Longer side Sqm 2 11.80 1.500 0.00 35.400
Shorter Side Sqm 2 5.00 1.50 0.00 15.000
Vertical both side Sqm 2 9.00 0.000 0.00 0.000
Vertical both side Round Sqm 1 3.77 0.00 0.00 0.000
Pier P-12 CAP
Longer side Sqm 2 12.50 0.800 0.00 19.992
Shorter Side Sqm 2 2.44 0.80 0.00 3.907
Total
Item No. Discription of item Unit Nos Width Depth Qnty
length
Dewatering & Foundation 0.000
Previous paid Quantity =
Cleaning
Pier P-09 Cum 1 7.00 0.30 13.80 28.980
Pier P-10 Cum 1 7.00 0.30 13.80 28.980
Pier P-11 Cum 1 7.00 0.30 13.80 28.980
Pier P-12 Cum 1 7.00 0.30 13.80 28.980
Pier P-13 Cum 1 7.00 0.30 13.80 28.980
Pier P-08 Cum 1 7.00 0.30 13.80 28.980
Total Quantity = 173.880
Previous paid Quantity = 0.000
Net payable Quantity = 173.880
Total
Item No. Discription of item Unit Nos Width Depth Qnty
length
Curring Previous paid Quantity = 0.000
Pier P-11
1.20 4.660 9.00 50.328
Pier Lift upto Cap Bottom Cum 1
1.13 4.66 5.268
Pier P-12
1.20 4.810 9.00 51.948
Pier Lift upto Cap Bottom Cum 1
1.13 4.81 5.437
Pier P-09
1.20 4.500 9.00 48.600
Pier Lift upto Cap Bottom M-35 Cum 1
1.13 4.50 5.087
Pier P-10
1.20 4.880 9.00 52.704
Pier Lift upto Cap Bottom M-35 Cum 1
1.13 4.88 5.516
Pier P-13
1.20 4.900 9.00 52.920
Pier Lift upto Cap Bottom M-35 Cum 1
1.13 4.90 5.539
Pier P-08
1.20 5.350 9.00 57.780
Pier Lift upto Cap Bottom M-35 Cum 1
1.13 5.35 6.048
Total Quantity = 347.175
Previous paid Quantity = 0.000
Net payable Quantity = 347.175
Weight
Item No. Discription of item Unit Nos Qnty
per Nos
Material Shifting Previous paid Quantity = 0.000
MS Plates 600 MM x 1500 MM MT 114.00 0.04 4.560
Props 2 M x 3 M MT 50.00 0.02 1.000
Steel MT - - 59.923
Total Quantity = 65.483
Previous paid Quantity = 0.000
Net payable Quantity = 65.483
Total
Item No. Discription of item Unit Nos Width Depth Qnty
length
Levelling & Dressing Previous paid Quantity = 0.000
Pier P-09 Sqm 1 7.00 - 13.80 96.600
Pier P-10 Sqm 1 7.00 - 13.80 96.600
Pier P-11 Sqm 1 7.00 - 13.80 96.600
Pier P-12 Sqm 1 7.00 - 13.80 96.600
Pier P-13 Sqm 1 7.00 - 13.80 96.600
Pier P-08 Sqm 1 7.00 - 13.80 96.600
Total Quantity = 579.600
Previous paid Quantity = 0.000
Net payable Quantity = 579.600
Cement Loading in Concrete
Qnty
Mixter
Pier P-11 Including PCC , Raft ,
1 1056
Lifts , Anullar filling
Pier P-12 Including PCC , Raft ,
2 767
Lifts , Anullar filling
Pier P-13 Including PCC , Raft ,
3 322
Lifts , Anullar filling
Pier P-10 Including PCC , Raft ,
4 165
Lifts , Anullar filling
Pier P-08 Including PCC , Raft ,
5 310
Lifts , Anullar filling
Total Quantity = 2620.000
Previous paid Quantity = 0.000
Net payable Quantity = 2620.000
Department Labours
Previous paid Quantity = 0 0
Date
3/18/2023 14 Ideal
3/19/2023 14 Ideal
3/20/2023 14 Ideal
3/22/2023 3 Pole fixing for compound
3/23/2023 2 Pole fixing for compound
3/24/2023 2 General work at site
3/25/2023 0 2 Referance point marking & general work
3/26/2023 13 Material unloading and general work at site
3/27/2023 0 14 Shed making for labours
3/28/2023 0 20 Ideal , No work at site
3/29/2023 0 20 Ideal , No work at site
Shed making for cement godown , making connection
3/30/2023 0 20
for pump & curring motor , halogen . Etc
3/31/2023 0 20 Ideal , No work at site
4/1/2023 0
4/2/2023 0
making connection for pump , curring motar & general
4/3/2023 2
work
making connection for pump , curring motar & general
4/4/2023 2
work
making connection for pump , curring motar & general
4/5/2023 3
work
4/6/2023 22 Ideal , No work at site
4/7/2023 9 Cement loading in mixer & general work
4/8/2023 7 Store room cleaning , cover block making etc
4/9/2023 4 Cement loading in mixer & general work
4/10/2023 4 Cement loading in mixer & general work
4/11/2023 0
4/12/2023 10 Cement loading in mixer & general work
4/13/2023 9 Stone pitching , annullar filling , & cement loading
4/14/2023 11 Cement loading in mixer & general work
4/15/2023 5 Cement loading in mixer & general work
making connection for pump , curring motar & general
4/16/2023 2
work
4/17/2023 9 Stone pitching , annullar filling , & cement loading
4/18/2023 22 Ideal , No work at site
4/19/2023 12 Ideal , No work at site
4/22/2023 1 Survey work
Making connection of dewatering pump ,halogen ,
4/28/2023 1 0
vibrator & etc
Making connection of dewatering pump ,halogen ,
4/29/2023 1
vibrator & etc
Filling water in concrete mixer & connection of
5/2/2023 1
vibrator , pump
5/3/2023 5 Labour ideal due to hydra by company
5/6/2023 14 0 Ideal , No scope of work at site by company
5/9/2023 4 9 Depatment work & Ideal
5/11/2023 11 5 Ideal , No scope of work at site by company
5/12/2023 14 Ideal , No scope of work at site by company
Filling water in concrete mixer & connection of
5/17/2023 1
vibrator , pump
5/19/2023 6 Steel rectifying and general work at site
5/20/2023 3 Steel rectifying and general work at site
5/27/2023 1 Survey work
5/29/2023 1 2 Survey work
5/30/2023 62 1 Survey work
Total Quantity = 62 310
Previous paid Quantity = 0.00 0.00
Net payable Quantity = 62.00 310.00