Electrical Summit 2023

High Voltage Transmission O & M


Innovation Technology Development
in Modern Electricity

Presented by:

ROFIUL HUDA
AMN DAL HAR RING UIT JBB

July 16th, 2023


Curriculum Vitae

Data Pribadi 3thn 1thn 6mo AMN Dal Har Ring


Supervisor Jargi
JE Jargi Bid. Hartrans UIT JBB
GI Karet Lama
❑ Speaker-Forum Transmisi UIT JBB ❑ Speaker-Electrical Summit,
GI Karet Lama
❑ Expert Proteksi P3B JB ❑ Rangers Hartrans
❑ Millennial Substation, SIGIKAMA
❑ Local Coach OPI ❑ Tim HV Test & VLF
❑ Tim rekomisioning UFR PLN UIW Sulbagsel
❑ Tim TVOSP Minggu ke-4

2009 - 2012 2012 - 2018 2018 - 2019 2019 - 2021 Jan 23 - present

JE Har Proteksi Pegawai Tugas Belajar, Cumlaude


Nama : Rofiul Huda
ULTG Pulogadung Institut Teknologi Bandung
❑ Tim rekom CBF GITET Grati ❑ TU Graz, Austria
NIP : 9109038P3B
❑ Tim rekom DFR P3B JB ❑ ICHVEPS International Conference
TTL : Blitar, 08 April 1991 ❑ Ketua TWMT 2015 & 2017

Pendidikan : S2 Teknik Tenaga listrik 6thn ❑ Key Opinion Leader


2thn
Karya Inovasi Achievement
“Strong engineer who consistently takes
the most challenging projects, builds 1. Alat uji injeksi arus untuk stability relai trafo GIS, 2016 1. Gold Medal Inhub Rusia & Silver Medal MTE Malaysia, 2022
exceptional teams, and drives significant 2. SMART Relai (sistem monitoring & remote transfer data 2. Lulusan Terbaik PTB PLN-ITB Batch 9, 2021
O&M, experience for 13 years in high relai), 2017 3. National English Olympiad Competition, 2017
voltage, protection also diagnosis to 3. Closing circuit supervisi (CCS) sebagai inisiate relai
4. Juara 3 pegawai pilihan UITJBB, 2017
enhance the reliability of electrical grid” autoreclose, 2018
5. Duta PLN UITJBB, 2016

2 rofi91.blogspot.co.id
Outline
Transmission System Overview
Overview of UIT JBB, total assets and
asset growth

HV Transmission and Transformation


Verticality Online Monitoring,
Transmission Platform Development

Issues and strategy


Experience Sharing, innovation and future
strategic
Transmission System Overview
01
Overview of Electricity Chain Business and
its transformation

4
Transmission and Transformation

“PLN UIT JBB memiliki bidang usaha utama jasa penyaluran tenaga listrik dari pembangkit ke distribusi dan pelanggan
di wilayah DKI Jakarta, Provinsi Banten dan sebagian Provinsi Jawa Barat dengan cara pengoperasian dan
pemeliharaan instalasi penyaluran tenaga listrik “
Modern Grid (Smart Grid)

▪ Bi-Directional power flow

▪ Extensive communication
▪ More inverters in the grid
▪ More green energy
▪ Dynamic pricing
▪ Demand response
▪ Use of Non-Conventional
Instrument Transformers

Source: CLP, “Smart Grid,” Hongkong. website: https://www.clp.com.hk/

www.pln.co.i |
d
VISI PLN
KOMPETENSI INTI PLN UIT JBB

VISI Menjadi Perusahaan Listrik Terkemuka se-Asia Tenggara


PLN dan #1 Pilihan Pelanggan untuk Solusi Energi.

KOMPETENSI INTI PLN UIT JBB

Memiliki kemampuan dalam pengelolaan bisnis penyaluran ketenagalistrikan di wilayah DKI


Jakarta, Provinsi Banten dan sebagian Provinsi Jawa Barat dengan memastikan efisiensi dan
efektifitas dalam mendukung keandalan, ketersediaan dan keterpeliharaan aset transmisi
yang aman dan ramah lingkungan.
Di masa depan, kompetensi PLN UIT JBB adalah mengembangkan infrastruktur penyaluran
ketenagalistrikan dengan mengadaptasi transformasi digital

www.pln.co.id 7
|
PERAN PLN UIT JBB
untuk mewujudkan Visi PLN
“Menjadi Perusahaan Listrik Terkemuka se-Asia
Tenggara
dan #1 Pilihan Pelanggan untuk Solusi Energi” Terkemuka se-Asia
Perusahaan Listrik Tenggara
PLN UIT JBB mendukung upaya
perusahaan untuk memiliki bisnis utama PLN UIT JBB mendukung upaya
berupa penyediaan tenaga listrik dengan perusahaan untuk mampu
mengelola bisnis penyaluran tenaga menyediakan penyaluran tenaga listrik
listrik di wilayah DKI Jakarta, Banten dan di wilayah DKI Jakarta, Banten dan
sebagian Jawa Barat untuk mendukung sebagian Jawa Barat dengan standar
keberlanjutan industri ketenagalistrikan kualitas pelayanan kelas dunia
di Indonesia. sehingga menjadikan Indonesia sebagai
pilihan investasi utama di Asia
Tenggara.
#1 Pilihan
Solusi Energi
Pelanggan
PLN UIT JBB mendukung upaya perusahaan untuk
dapat memberikan nilai kepada pelanggan berupa PLN UIT JBB mendukung perusahaan agar
solusi terhadap setiap permasalahan terkait menjadi pilihan utama pelanggan di wilayah
penyaluran tenaga listrik di wilayah DKI Jakarta, DKI Jakarta, Banten dan sebagian Jawa Barat
Banten dan sebagian Jawa Barat untuk karena kualitas dan pelayanan penyaluran
mengantisipasi berbagai peluang dan tantangan tenaga listrik yang diberikan sehingga
usaha serta konsisten dalam pengembangan konsumen menjadi loyal.
standar kerja.
www.pln.co.id 8
|
MISI PLN UIT JBB
(Sesuai Peraturan Direksi No. 0086.P/DIR/2022)

1
Melakukan Pengembangan dan Pengelolaan Aset.

2
Melakukan Pengendalian Investasi dan Logistik Transmisi.

3
Melaksanakan Operasi dan Pemeliharaan Aset Transmisi.

4 Mengelola sumber daya dan aset perusahaan secara


efisien, efektif dan sinergis untuk menjamin pengelolaan
usaha secara optimal dan memenuhi Keselamatan,
Kesehatan Kerja, Lingkungan dan Keamanan serta prinsip
tata kelola perusahaan yang baik (Good Corporate
Governance).

www.pln.co.id 9
|
SEJARAH SINGKAT PLN UIT JBB

1995-2009 ... 2015 2016 2017 2018 2021 ... 2022

PLN P3B Jawa Bali PLN TJBB PLN UIT JBB PLN UIT JBB
Penetapan Organisasi Perubahan Pertama Susunan Organisasi Reorganisasi sesuai
sesuai KEPDIR sesuai PERDIR sesuai PERDIR PERDIR
093.K/023/DIR/1995 0093.P/DIR/2016 0137.P/DIR/2018 0280.P/DIR/2022
tgl 2 Okt 1995 dan tgl 4 Mar 2016 tgl 6 Jun 2018 Tgl 12 Des 2022
Struktur terbaru PLN P3B Jawa Bali (3 Bidang menjadi PLN TJBB ▪ TJBB > UIT JBB
PLN UIT JBB
KEPDIR 4 Bidang) ▪ APP > UPT
Reorganisasi dari PLN Perubahan Kedua Reorganisasi sesuai
SK 259.K/DIR/2009 tgl ▪ Penambahan Layer
P3B Jawa Bali sesuai sesuai PERDIR PERDIR
23 Okt 2009 dan Jumlah ULTG.
PERDIR 0044.P/DIR/2017 0050.P/DIR/2021
▪ Bid KSA > Bid Keu &
018.P/DIR/2015 tgl 9 Jun 2017 tgl 12 Mar 2021
Bid SDMU.
tgl 31 Agt 2015 (Tidak meliputi Bid Keu dan SDM &
▪ K3L dan Pengadaan
pengembangan aset) Umum (SDMU),
menjadi Biro.
menjadi Bid Keu, Kom
& Umum (KKU)

www.pln.co.id
|
WILAYAH KERJA PLN UIT JBB
SRLYRU SLIRA
LBE
SRLYA
PENDO

UPT CAWANG UPT DURIKOSAMBI


PENI
Muara Tawar
KPOSKO PLTGU CLGON
UPT PULOGADUNG
▪ ULTG CAWANG
UPT DURIKOSAMBI
▪ ULTG DURIKOSAMBI
ALNDO PRIOK
MTSUI TLKGA MKRLMA PRTBR PRTMR
CLGRU
LNTAR SPTBR PSKBR TGBRU MKRBR PRBRT

▪ ULTG GANDUL ▪ ULTG CIKUPA


CLGON KDSPI
SPTAN MAXIM KBSRH BDKMY PLPBR
SDJYA GJTGL MRNDA
BLRJ7 GRGOL PLMPG
PSKMS

▪ ULTG TANGERANG
JAWA7 PINKA DNMGT GRGBR

▪ ULTG TANGERANG
NBLRJ KMYRN KLPGD
JTAKE MGBSR HRPIN
MNA CKRBR KTPNG
CKUPA TOSAN PGSAN JGC
BLRJA ANCOL
SPMIL TGLMACKRNG WHANA PLGD SNTER

SELATAN
KDL

KOTA
KRWTU CKNDE GSHRI GMBRU PKRNG
INDFR DKSBI ANGKE KBSRH MGRAI
IKPP LSTEL ALSTR KARET BKASI
SRANG MLNUM DKSB7 KBJRK BDKML KRBRU GDPLA
PLYPR CLDUG
ASAHI SGS KBGAN SBUDI TNTGI PGLGN SMRCN
GMS CBTAT RAKUN
NSYAN DKTAS TRSNA
CURUG ULJMI SNYAN RAWAM PDKLP
DRTGA MPBRU PLMAS

UPT CILEGON
PTKGN

UPT PULOGADUNG
PCAM BNTR2
CNSRI
DNYSA CWANGMPDUA MNTUR Tambun
GORDA TGKSA LEGOK BNTRO GNDUL AGP
CIPNG
LKNG2 SPONG CRNDU
▪ ULTG CILEGON ▪ ULTG PULOGADUNG
Poncol
MDERN LKON7 BSD ATSRI
LKONG PNDAH KMANG
ANYER

▪ ULTG SURALAYA ▪ ULTG KARET


DPKRU GDRIA JTWRG
KOPO
MNSRU
RKBTRU
UPT CAWANG DEPOK CRCAS JTRGN
PLTU LBUAN
SAKETI
RGKOT
CMGIS

CIBNG
CBBUR
ITP
▪ ULTG RANGKAS ▪ ULTG BEKASI
SEMEN CB
BUNAR CLGSI

UPT CILEGON KRCAK


KDBDK

Saguling

Tasik
MALINGPING
BAYAH

PRATU

Ket:
UPT : Unit Pelaksana Transmisi
Gardu Induk 500 kV Saluran Transmisi 500 kV

Gardu Induk 150 kV Saluran Transmisi 150 kV

Gardu Induk 70 kV Saluran Transmisi 70 kV

*) Data Aset Per Juni 2023


http://bit.ly/Dashboard-UITJBB www.pln.co.id 11
|
OVERVIEW ASET PLN UIT JBB
171
Gardu Induk
Substations
586,69 KMS
Saluran Transmisi
Kabel
Transmission Cable
Transmission Line Transformers
500 kV : 1.105,28 kms
150 kV : 2.551,75 kms 408 UNIT 500/150 kV : 30 Units
Aset PLN 150/70 kV : 0 Units
70 kV : 0 kms Trafo Tenaga
UITJBB 150/20 kV : 378 Units
Transformers
70/20 kV : 0 Unit

3.070,34 KMS
Saluran Transmisi
Udara
Transmission Overhead Line
37.150 MVA
Kapasitas Trafo
Tenaga
Transformers Capacity
*) Data Aset Per Juni 2023
http://bit.ly/Dashboard-UITJBB www.pln.co.id 12
|
Transmission System Overview
Asset Profile of 22nd JMCC Members
EVN NPT - VIETNAM
Substation : 179 Unit SESB - SABAH
Transformer Capacity : 112,675 MVA SEB - SARAWAK
Circuits Length : 28,679 Kmc Substation : 47 Unit Substation : 49 Unit
Unit of Transformer : 371 Units Transformer Capacity : 13,586 MVA Circuits Length : 3,301.94 Kmc
Peak Demand : Circuits Length : 5,109.57 Kmc Unit of Transformer : 110 Units
Unit of Transformer : 111 Units Peak Demand : 1,032.06 MW
Peak Demand : 4,398 MW
EGAT - THAILAND
Substation : 234 Unit
Transformer Capacity : 135,882 MVA PLN - INDONESIA
Circuits Length : 38,546.30 Kmc
Substation : 984 Unit
Unit of Transformer : 820 Units
Transformer Capacity : 150,319 MVA
Peak Demand : 32,254.5 MW
Circuits Length : 59,190.65 Kmc
Unit of Transformer : 2053 Units
Peak Demand : 39,515.91 MW

TNB - MALAYSIA
Substation : 473 Unit
Transformer Capacity : 130,770 MVA
Circuits Length : 24,146 Kmc
Unit of Transformer : 1349 Units
Peak Demand : 19,183 MW
13
PROFIL SDM PLN UIT JBB

913 170
(84%) TOTAL (16%)
1083

Laki-laki Wanita

*) Data Yan HC Per 30 Juni 2023


www.pln.co.id 14
|
In the Transformation Program, PLN initiated 29 Breakthrough Projects
covering all business lines, with 21 of them including Digital Breakthrough

Strategic Goals Strategic Enabler

Lean Organization & People Technology Advancement


1 Digital Power 6 Optimize Primary Energy
17 Organization 19 Digitally Enabled
Plant 7 Anti Blackout
2 Digital Procurement Structure Execution Machine
Streamline Subsidiary/
3 Digitally Enabled Distribution 22 Advance Metering Infrastructure
4
Excellence
Dispatch Optimization 24 Centralized Planning Holding-Sub Holding
27 Material Return and Warehouse 18 Zero Accident
5 Investment Prioritization
28
Inventory
(Short Term and Long
Integrated Supply Chain Excellence
Term)

Green Innovative Financial Sustainability National Development


8 RJP 2019-2024 (5GW) Implementation 1 Billing & Collect on Regulatory, Sector
1 21 Digitalization of 20
9 12 Optimization Structure, and
Launch Green Boosters Centralized Payment
Fiber Optics Rollout Tarif Optimization
10 Launch Large Scale Renewables 13 29 Environmental,
23 Local Content
25 Carbon Neutral 2060 Electric Vehicles Infrastructure Social, and
14 (TKDN)
Governance
Captive Power

Customer Focus
15 PLN Mobile 16 Yantek
Optimization Legend: Digital Breakthrough
Relaunch
HV Transmission Assessment Challenges
Current Conductor, Jumper Conductor, Midspan compression
Carrying joint

Insulation Insulator, air insulation, ROW


Primary
Elbow iron member, Paint/galvanized pole, chimney,
Structure
tower yard, bolt nut, connection plate, stub

OPGW box joint, insulator fitting, insulator bond,


Subsystem Junction
sealing end

GSW, OPGW, arching horn, TLA, ACD, aviation lamp,


Protection
repair sleeve, armour rod span
Secondary
Tower information pallet, climbing stone,boundary
Monitoring
stake
1. Main Component

2. Supporting Component

3.
Environment

Figure OHL Transmission and its


Environment
www.pln.co.id 16
|
Transmission System Challenges
02
Problem & obstacle during operation and
maintenance

17
Experience Sharing
Transmission Lines Failure due to Tree Falls
Event 1 Event 2
❑ 150 kV transmission lines ❑ 150 kV transmission lines
Lopana – Otam routes Kasongan – Sudan &
(North Sulawesi province) Kasongan – Parenggean
❑ Type of conductor ACSR routes (West Kalimantan
240/40 mm2 province)
❑ Failure event at May 18th ❑ Type of conductor ACSR
2021, 13:12 WITA 2x240/40 mm2
❑ Energy not served 591.89 ❑ Failure event at October 11th
MWh (There were 13 2022, 22:25 WITA
substations missing ❑ Energy not served 1148.908
voltage) MWh (There were 6
❑ Facts & findings : broken 3 substations missing voltage)
phase conductors and ❑ Facts & findings : live
tower bent due to tree falls conductor connected to
outside ROW (span of ground by broken OPGW due
tower no 178-179) to tree falls outside ROW
(span of tower no 221-222)
18
Experience Sharing
Transmission Lines Failure due to Tree Falls
T/L 150 kV Lopana – Otam Interruption event

❑ Heavy rain in the area (Sinsingon Village, North


Sulawesi) causing landslides and some trees
fell
❑ Fallen Trees hit the lines, thus resulted in
T.179 broken conductor, broken ground wire, broken
Suspensio
n cross arms and twisted tower body

◄ Line Line 2
❑ This disruption caused several power plants
1 ► trip so the frequency of the system dropped
Landslides
Point
and caused the UFLS and island operation
defense scheme work (3 islands).
❑ The total substations that lost voltage were 13
Substations with Energy Not Served (ENS) of
591,891.99 kWh.
T.177
Suspensio ❑ System recovery taken 6 hours 42 minutes
n
T.178 T.179 (Trip at 13:12 WITA, all load normal at 19:55
Tensio Suspensio
n n T.180 WITA)
Tensio
n T.181
◄◄ Tensio Otam ►►
Lopana n 19
Kerawanan Aset Tower Transmisi

Pelaksanaan Assessment pada aset dengan metode konvensional


menjadi kendala dan keterbatasan antara lain:
1. Data saat pengukuran
2. Data trending memerlukan biaya, waktu dan tenaga
3. Perlu keahlian khusus dalam mengoperasikan alat
4. Sangat dimungkinkan perbedaan hasil pengukuran karena
mengandalkan pengamatan visual

www.pln.co.id 20
|
Riwayat Konduktor Putus ACSR, HTLS
SUTT 150 kV Bintaro-Serpong #2 (HVCRC) SUTET 500 kV Lengkong-Gandul #1 (ACCC)
Operasi: 17 Oktober 2017 (usia: + 3 Thn) Operasi: 21 Maret 2019 (usia: + 2 Thn)
Gangguan: 17 September 2020 (Putus) Gangguan: 14 Februari 2022 (Putus)
Baturaja - Bukit Kemuning
Riwayat Putus Saat Rekonduktoring: SUTT 150 kV Keramatwatu-Serang
Lahat - Bukit Asam - SUTT 150 kV Keramatwatu-Serang, 2016 (ACCC)
- SUTET 500 kV Suralaya-Balaraja, 2019 Operasi: Tahun 2016 (usia: < 1 Thn)
Gangguan: 23 Oktober 2016 (Putus)

SUTET 500 kV Lengkong-Balaraja #2 (ACCC)


Operasi: 25 Agustus 2019 (usia: < 1 Thn)
Gangguan: 24 September 2019 (Putus)

Bintaro - Serpong
Gandul - Lengkong Mandirancan-New Ujungberung

Keramatwatu - Serang Mranggen - Incomer

Suralaya - Balaraja
Gilimanuk - Celukan Bawang

Lengkong - Balaraja Kamojang-Darajat

Cibinong - Sentul - Bogor Baru

www.pln.co.id 21
|
RCPS Konduktor Putus ACSR, HTLS

Penyebab konduktor putus


❏ Proses pemasangan tidak sesuai Prosedur
❏ Pengurangan Dimensi material Reinforce Steel
❏ Crimping / Press Desk kurang rapat / tekanan
kurang tinggi
❏ Terjadinya HotSpot karena Umur atau Polutan
❏ Terkisisnya Steel Wire sehingga membentuk
ujung runcing

Panjang Crimping kurang


Reinforce stell tekanan potensi
bekas di hotspot
gerinda

www.pln.co.id 22
|
Case in Indonesia

Broken conductor during 2017-2022 Causes of broken conductor 2017-2022

Causes

Mid span Joint deterioration Broken of the Clamp


Dead clamp deterioration Broken of the jumper
Loose of spacer

● For the past 6 years, 18 times have been counted as disturbances caused by broken conductors in the PLN UIT JBT
area.
● One of the causes of broken conductors is caused by physical deterioration of the conductor due to loose spacers
● On August 31, 2022 at SUTET Mandirancan-New Ujungberung span T.143-144, it was discovered that a fault occurred
due to a broken conductor which was thought to be due to mechanical stress on the conductor due to the loose
spacer.
www.pln.co.id 31
|
Transmission Asset Population (Conductor HTLS)

Number of failures:
10

kmc kmc kmc

Number of failures:
2

www.pln.co.id 31
|
Case in Malaysia

www.pln.co.id 31
|
Field Finding Facts

● The broken conductor is not


located in the junction
Rabu, 31 Agustus 2022 at 08.57 WIB
SUTET Mandirancan - New ● The condition of the midspan
Ujungberung broke in Phasa S joint in good condition indicates
Span T.143-144 that the joint condition is in
good condition

www.pln.co.id 32
|
Event Analysis
The spacer is loose so there is a minor
cross

Anomaly conditions are not monitored by officers

The condition of the There is an influence of load current and


spacer is broken at wind conditions
the hook and there
are defects on the
surface of the
aluminum conductor Conditions that continue continuously
causing degradation of mechanical strength
and resulting in the conductor breaking

www.pln.co.id 34
|
Cases

16 April 2022. 500 kV Mae Moh - Tha Tako T.134/1 - 134/2 31 August 2022. 500 kV Mandirancan - New
Ujungberung T.143-144

❑ Spacer failure can lead to conductor failure


❑ It is needed to assess the condition of the spacer periodically especially on
the flat terrain due to the continuous wind movement

www.pln.co.id
|
Improvement Opportunities
03
Verticality Online Monitoring System

29
VENOM
Verticality Online Monitoring System
DATA KONTINYU
Alat monitoring kondisi kemiringan tower secara realtime Mendapatkan data secara
sekaligus sebagai Early Warning System terhadap kondisi kontinyu sehingga kondisi

01
tower dapat terpantau
tower Transmisi

02
EFISIENSI
Efisiensi waktu, tenaga dan
biaya

EARLY WARNING SYSTEM


KEMUDAHAN ASESMEN DAN DIAGNOSA Media informasi awal
Asesmen dan diagnose dapat segera engetahui
kondisi asset dan merencanakan tinak lanjut
03
www.pln.co.id
|
Tahapan Proses

Pembuatan desain verticality Online


Monitoring System

Menghubungkan node dengan


server

Membuat algoritma Early Warning


System (EWS)

Pengujian Fungsi atau komisioning Blok Diagram Node dan Power Suplai VENOM

www.pln.co.id
|
Kajian Literatur

UAV Lidar2, Algoritma Revised Improved Differential Synthetic


Aperture Radar interferometry (DINSAR)3, 2D Image and 3D Point
Cloud4, menggunakan FOTOMNG system5

Tower's movement monitoring system (TEMONS), PDKT


(Peringatan Dini Kemiringan Tower) dan TOWER Assistant
(Menghindari Gangguan Binatang dan Monitoring Kondisi Tower)

*PT PLN (Persero) REGIONAL JAMALI, “Pedoman Pemeliharaan Peralatan Penyaluran Tenaga Listrik PT PLN (Persero) di www.pln.co.id
Regional Jawa Madura Bali
|
Milestone

2020 Des’21 Jan’22 Okt’22 2022

Pemasangan Pemasangan Pemasangan Pemasangan


Perancangan
V.1 V.2 V.3 V.4

• Identifikasi
Masalah
• Perumusan
alternatif-altern
atif solusi
• Pembuatan
flowchart dan
perancangan
hardware

www.pln.co.id
|
Desain

www.pln.co.id
|
DESAIN

1. Modul Sensor Arus dan Tegangan


2. Modul Inclinometer
3. Main Controller
4. Modul GPS
5. Modul 4G LTE
6. Baterai dan BMS (Baterai Management System)
7. Regulator Step Up
8. Power Module Control
9. Solar Panel

www.pln.co.id
|
Tampilan Website VENOM (http://venom-uitjbb.id)

Waktu dan Tanggal Akses Web


Monitoring All Gateway dan Node
Node dan Gateway pin point
Menu Monitoring Grafik
Chart View
Grafik

www.pln.co.id
|
Implementasi

19 LOKASI :
-500 kV Tasikmalaya – Depok
-150 kV Cilegon Baru - Posco
-150 kV Pucam – Modern
-Gardu Induk Bayah
-150 kV Pelabuhan Ratu – Bayah
-150 kV Kebon Agung - Sutami
-150 kV Sutami –Wlingi
-150 kV Lembursitu – Cianjur
-150 kV Ungaran – Wleri
-150 kV Lembursitu - Cianjur

www.pln.co.id
|
Dokumentasi Pemasangan

www.pln.co.id
|
Early Warning System

1. “VENOM” dapat diimplementasikan pada semua tower transmisi


khususnya yang memiliki issu akan kondisi pondasi tower atau kondisi
geografis dimana tower berdiri

2. Dapat diimplementasikan sebagai dasar untuk pengambilan keputusan


selanjutnya terkait dengan perkuatan / relokasi tower pada perencanaan
Anggaran Investasi (AI)

3. Bisa menjadi satu kesatuan bagian dari konstruksi/pembangunan tower

www.pln.co.id
|
Kalibrasi dan Hasil Uji

KALIBRASI IP 65

www.pln.co.id
|
Improvement Opportunities
04
Thermal Inspection Using Drone

41
Population & Inspection Frequency

Type of drones DJI Phantom 4 DJI Phantom 4 Pro DJI M300, Mavic 2 DJI M210, Mavic DJI M300, DJI M210,DJI
V1, DJI Phantom 4 Zoom, Mavic 2 2E, Phantom 4 Pro Mavic 2, Mavic M300,DJI M600,
Pro V2, DJI Mavic 2 Enterprise 3, Phantom 4, Mavic Mini 2,
Zoom, Mavic 3 Advanced, Phantom Mavic2 Zoom Mavic Pro,Mavic 2
4, Phantom 4-RTK Pro, Mavic Air 2,
Mini 2, Mavic 2
Zoom, Drone
Inspire 2,
Phantom 3 Pro,
Phantom 4 Pro
V2.0, Inspire 1
Pro

Frequency 2 years (handheld) 5 years & 6 monthly 2 times/year 3 year 5 years 2 times/year
(Line Crossing) - (drone/handheld) (drone/handheld) (handheld) (drone/handheld)
Handheld Every year for
important line
(helicopter)

www.pln.co.id
|
Comparison

Thermal Handheld & Drone Operation Photos - 275kV DJI M210 & Mavic 2 Operation Photos - 275kV
Similajau-Murum Junction L1, T54 Similajau-Murum Junction L1, T100

34.1°C
29.6°C

deviation 4.5° more accurate result

FLIR T620 DJI M210 + Zenmuse XT DJI M210 + Zenmuse XT DJI Mavic 2 Enterprise
Advanced
Optimal distance :
Handheld: 40-50 m
drone : 2.5 - 3 m Thermal Inspection using Drone has advantages on its easiness, price, visual close up and long range

www.pln.co.id
|
Comparison

Drone Handheld

useful in difficullt access / terrain &long range Access Depend on the access & limited distance

25 minutes Battery 2 battery/day

Bigger, smaller drone less acuracy Small, easy to carry


Size

Cheaper Price More expensive

www.pln.co.id
|
Emissivity & Solar Heating

Low emissivity objects Solar heating

Example: Example:

emissivity value for:


Aluminium (unoxidized) = 0.07 - 0.2
Aluminium (oxidized) = 0.1 - 0.4
Steel (galvanized, new) = 0.23
Steel (galvanized, old) = 0.88
Stainless Steel (polished) = 0.08
Stainless Steel (weathered) = 0.85

Unreliable readings caused by thermal reflections Surface heating by direct sunlight gives false analysis
(low emissivity = higher reflection)
Mitigation: Mitigation:
Adjusting the emissivity based different object / materials Performing the inspection at early morning or late evening / night
where solar heating on the surface is significantly reduced

The Emissivity and solar heat affect the readings of the thermal inspection

www.pln.co.id
|
Thermal Condition

SESB TNB EVNNPT SEB EGAT PLN


10°-20° <10° <15° <10° <10° <10°
Schedule repair Monitoring No action No Action No action No action
Medium
10°-20° 15°-75° 10°-24.9° 10°-35° 10°-25°
Schedule repair Monitor & Monitor 3 months Monitor & Repeat at high
<70 days Schedule repair Schedule repair Load
<3 month, if the
21°-30° 21°-30° 25°-50° 35°-75° 25°-50°
line is high load,
Schedule repair Schedule repair Schedule repair < Monitor & Repair < 3 months
repair
High <28 days 1 month Schedule repair
immediately
ASAP
>30° >30° >75° >50° 50°-70°
Schedule repair Immediately Repair Repair <7 days Repair < 1 month
Very High action < 7 days Immediately
>75° >70°
Repair Repair
Immediately immediately <3
days

www.pln.co.id
|
Commissioning & Frequency of inspection

Commissioning Visual Visual Visual Visual Torque& Visual


Visual

Inspection
Sighting 4 months monthly Yearly yearly weekly
Climb Up - conditional 5 years years
UAV - monthly - conditional conditional
Action for anomaly replace replace replace replace Mechanical& repair/
elastomer replace
test

www.pln.co.id
|
Improvement Opportunities
05
Broken Conductor Preventive Action

48
Rekomendasi Assessment Konduktor

Rekomendasi Assessment Konduktor usia > 30


tahun (potensi mengandong andongan rendah
jika dibebani tinggi):
1. Uji elektris
2. Uji mekanis
3. Uji konstruksi pilinan
4. Ranging meter
5. Pengukuran tahanan midspan joint
6. Performance test

www.pln.co.id
|
Commissioning & Assessment Method

Special Technique No HTLS No No No No No


for commissioning

Another test during Contact


commissioning resistance
test

Assessment Thermal Thermal Thermal Thermal Thermal


Method X-ray

www.pln.co.id
|
Preventive Action Konduktor Putus ACSR & HTLS

01 Assessment X-Ray Inspeksi Thermal Drone Metode X-Ray


• tanpa mengurani stress
mekanik pada inti core

02 Inspeksi thermal Drone


• Thermal Inspection
menggunakan Drone
memiliki keunggulan Optimal distance :
kemudahan, harga, visual
Handheld: 40-50 m
close up dan jarak jauh
drone : 2.5 - 3 m

03 Pemasangan spacer
pengapit dan atau Pemasangan Spacer Pengapit pada Midspant Joint
reinforcment wedge
jarak 1 meter di kanan & kiri
midspant joint

04 Pengukuran thermovisi
midspant joint dan
junction seuai kepdir 520
atau pada saat kondisi
beroperasi 1 ruas penghantar

www.pln.co.id
|
Improvement Opportunities
06
Security Monitoring System

52
Case: AI algorithms proactively identify risks and improve inspection
efficiency(Transmission line)

23 Huawei Proprietary - Restricted Distribution


Improvement Opportunities
07
Inspection and its Platform

54
Overview New Srintami
▪ GP melakukan inspeksi di tower ▪ LW melakukan inspeksi di tower
▪ Formulir inspeksi bersifat umum (general) NEW ??? (jam awal inspeksi = jam check in)
▪ Data disimpan di tower yang sama ▪ Formulir inspeksi memunculkan checklist sesuai
▪ Data tegakan susah divalidasi peralatan yang ada
▪ Lock Inspeksi minimal 10 menit [1]
▪ LW menyusuri jalur transmisi dan absen check
poin data ROW pada jalur tersebut
▪ Data inspeksi hanya bisa disimpan setelah LW
tiba di tower berikutnya
▪ Pengaturan jadwal inspeksi tower sesuai SLA[2]
Ground Patrol
Line Walker

▪ Sinkronisasi online dengan opsi backlog


▪ LW tetap berkoordinasi dengan Gardu Induk jika terkendala sinyal
setiap minggu dengan fitur COC ▪ KDAV, hasil inspeksi dan Otomatisasi SLA

▪ GP melaporkan ke Gardu Induk tiap minggu ▪ Data inspeksi diupload dengan trigger sinkronisasi dari
▪ Sinkronisasi Data SRINTAMI Mobile ke SRINTAMI Gardu SRINTAMI Gardu
▪ Sinkronisasi sekaligus menjadi nilai absensi GP ▪ Data KDAV GP dan hasil inspeksi

www.pln.co.id 10
|
OVERVIEW NEW SRINTAMI

www.pln.co.id
|
NEW SRINTAMI MOBILE

Fitur dan Fungsi New SRINTAMI Mobile:

Inspeksi Line Walker

Validasi Koordinator LW & PLN

Absensi Online

Tracking Online

Push Notification

Content Amplification

NEW SRINTAMI MOBILE

www.pln.co.id 11
|
NEW SRINTAMI MOBILE

Fitur dan Fungsi New SRINTAMI Mobile:


Inspeksi Line Walker

Validasi Koordinator LW & PLN

Absensi Online

Tracking Online

Push Notification

Content Amplification

www.pln.co.id 12
|
NEW SRINTAMI MOBILE

Fitur dan Fungsi New SRINTAMI


Mobile:
Inspeksi Line Walker

Validasi KLW & PLN

Absensi Online

Tracking Online

Push Notification
VALIDASI

Content Amplification

www.pln.co.id 13
|
NEW SRINTAMI MOBILE

Fitur dan Fungsi New SRINTAMI


Mobile:
Inspeksi Line Walker

Validasi KLW & PLN

Absensi Online

Tracking Online

Push Notification

Content Amplification

www.pln.co.id 14
|
NEW SRINTAMI MOBILE

Fitur dan Fungsi New SRINTAMI


Mobile:
Inspeksi Line Walker

Validasi KLW & PLN

Absensi Online

ROW Online Tracking

Push Notification

Content Amplification

www.pln.co.id 15
|
NEW SRINTAMI MOBILE

Fitur dan Fungsi New SRINTAMI


Mobile:
Inspeksi Line Walker

Validasi KLW & PLN

Absensi Online

Tracking Online

Push Notification

Content Amplification

www.pln.co.id 16
|
NEW SRINTAMI MOBILE

Fitur dan Fungsi New SRINTAMI


Mobile:
Inspeksi Line Walker

Validasi KLW & PLN

Absensi Online

Tracking Online

Push Notification

Content Amplification

www.pln.co.id 17
|
NEW SRINTAMI WEB

Fitur dan Fungsi New SRINTAMI Web:

Vegetation Data

Informasi Pemeliharaan ROW

Anomali Peralatan Jaringan

Line Walker Tracking MAP

NEW SRINTAMI WEB

www.pln.co.id 18
|
NEW SRINTAMI WEB

Fitur dan Fungsi New SRINTAMI Web:

Vegetation Data

Informasi Pemeliharaan ROW

Anomali Peralatan Jaringan

Line Walker Tracking MAP

www.pln.co.id 19
|
NEW SRINTAMI WEB

Fitur dan Fungsi New SRINTAMI Web:

Vegetation Data

Informasi Pemeliharaan ROW

Anomali Peralatan Jaringan

Line Walker Tracking MAP

www.pln.co.id 20
|
NEW SRINTAMI WEB

Fitur dan Fungsi New SRINTAMI Web:

Vegetation Data

Informasi Pemeliharaan ROW

Anomali Peralatan Jaringan

Line Walker Tracking MAP

www.pln.co.id 21
|
NEW SRINTAMI WEB

Fitur dan Fungsi New SRINTAMI Web:

Vegetation Data

Informasi Pemeliharaan ROW

Anomali Peralatan Jaringan

Line Walker Tracking MAP

www.pln.co.id 22
|
Maintenance Strategy

www.pln.co.id
|
Maintenance Strategy
LEVEL 1 PER WEEK
GROUND
Monitoring
PATROL
PER THREE MONTH

PART OF CLIMB UP CREW PER 2 or YEARS


MAINTENANCE 10
COMPONENTS
LEVEL 2 MAINTENANCE
THERMOVISION SIDATO and
Measuring CREW 19
Other
PUNCTURE TEST COMPONENTS
Record
ASSESSMENT OF
SYSTEM
LEVEL 3 THREATS & GROUNDING RESISTANT
Assesment EVALUATION OF SRINTAMI
COMPONENTS RANGING METER
System
OBJECT
INSULATION 4 COMPONENTS THREATS
(IN ROW) AS
CURRENT CARRYING 4 COMPONENTS
Ground
ASSESSMENT MONITORING 3 COMPONENTS COMPONENTS Patrol
MAINTENANCE TO OBSERVE
PROCESS
OF Inspection
COMPONENTS JUNCTION 5 COMPONENTS
Method
Visually
PROTECTION 17 COMPONENTS

STRUCTURE 7 COMPONENTS CHIMNEY


AVALANCHE
ADOPTED
FOUNDATION COMPONENTS OF FOUNDATION TO
ASSESSMENT SRINTAMI RIVER FLOW
OF THREATS
ENVIRONMENT COMPONENTS OF ENVIRONMENT

IMPLEMENTED BY COLLABORATION THIRD THIRD PARTY OR TYPE OF CHECK LIST PERIODIC INSIDENTAL
PARTY & INTERNAL INTERNAL CHECK LIST CHECK LIST

www.pln.co.id
|
“The Biggest Part of Digital
Transformation Is Not About Technology.
It is Changing The Way We Think.”

Terima Kasih