4. DRAINAGE SYSTEM
Supply, installation, testing and commissioning of complete drainage system (UPVC) for Lulu
hypermarket area including Soil, Waste, Kitchen & Vent piping , Sanitary fixtures in toilets & office
spaces, Installation of kitchen sinks & hand wash basins with all accessories in Kitchen Preparation
areas, Stainless steel channel gratings inside preparation and ablution rooms, Channel gratings in loading
and unloading area, Floor trap & Floor cleanout covers, C-type Grease interceptors/Mechanical Grease
trap with lifting station if applicable, Sand & Oil interceptors etc. Drainage requirements in hypermarket
area shall be as per LULU Concept design layouts, Project specification & local Authority regulations.
REV-00 P.O Box: 4048, Y-Tower, Abu Dhabi, U.A.E - Tel: 02 4140900/Fax: 02 6411105 Page 1 of 2
www.lulugroupinternational.com
PROJECT DEVELOPMENT DEPARTMENT Date: 10-08-2023
5. LPG/SNG SYSTEM
Supply, installation, testing and commissioning of complete LPG/SNG system for hypermarket
including LPG/SNG piping, valves, regulators, detectors, safety devices, meters, accessories etc., shall
be as per the M/s LULU Concept design drawings, project specification & local Authority regulations.
Note:
1. ADM, ADSSC, ADDC, ADCD and any other authority or third-party approvals related to complete
project shall be under developer scope.
2. The final technical details, ratings and quantities shall be followed as per final design from MEP design
consultant.
3. Developer has to arrange technical meetings with the project consultant and Lulu Team before finalizing
the design of the project and shall be as per the Lulu design requirements.