A 196120 in Direkt
A 196120 in Direkt
A 196120 in Direkt
T$0, ITPA3L-,
OPEIK~ AO s~tjQr5 AfJI0 MS THESIS p
O12T0MIPJTIOOZ P o,
0 CO V rJiC I rL)C
C.. S. PFRFORIING ORG. REPORT NUMBER
9. PERFORMING ORGANIZATION NAME AND ADDRESS 10. PROGRAM ELEMENT. PROJECT. TASK ;..
AREA & WORK UNIT NUMBERS •
AFIT STUDENT AT: GEoA &I\JMCTof
188 ,Y
II. CONTROLLING OFFICE NAME AND ADDRESS 12. REPORT DATE
1988
13. NUMBER OF PAGES
14. MONITORING AGENCY NAME & ADDRESS(If different from Controlling Office) 15. SECURITY CLASS. (of this report) ,
AFIT/NR
Wright-Patterson AFB OH 45433-6583 UNCLASSIFIED
IS. DECL ASSI FICATION/DOWNGRADING
SCHEDULE .
17. DISTRIBUTION STATEMENT (of the abstract entered in Block 20, If different from Report)
SAME AS REPORT
,P
20. ABSTRACT (Continue on reverse side it necessary and Identify by block number)
ATTACHED
4, -. r . ,
By
A thesis submitted to
The Faculty of
May 1988
Thesis directed by
K---
'
John Cibinic, Jr.
Professor of Law
* 1f
I,-/
" I
PREFACE
The views expressed herein are solely those of the author and
PREFACE
INTRODUCTION 1
I. Equitable Adjustments 7
A. Defining Cost 12
B. Cost Accounting Standards (CAS) 13
C. The Cost Principles 14
D. Measurement of Cost 15
E. Accounting Systems 16
F. Allocation of Costs 17
1. Direct Costs 17
2. Indirect Costs 18
3. Classification of Costs as Direct or Indirect 18
4. Process of Allocating Indirect Costs To Cost
Objectives 20
a. Indirect Cost Groupings 20
(i) Cost Principles 20
(ii) Common Indirect Cost Groupings 22
b. Distribution Base 23
c. Base Period 24
d. Indirect Cost Rates 26
V. How Volume Affects Costs 26
A. Absorption Costing 30
1. In General -30
2. Absorption Costing for Financial Reporting Purposes 31
B. Full Costing 32
C. Direct Costing 32
ii
VII. Allowability Under the Cost Principles 33
A. Reasonableness 34
1. Burden of Proof 34
2. Determining Reasonableness of Indirect Costs 35
B. Generally Accepted Accounting Principles 35
C. Terms of the Contract 36
1. Advance Agreements 36
2. Limiting Clauses 37
D. Limitations Set Forth in FAR Subpart 31.2 38
E Accounting for Unallowable Costs 38
1. Unallowable Costs Included in Indirect Cost
Groupings 39 U.
iii
B. Entitlement to Unabsorbed and Extended Overhead 60
1. Unabsorbed Overhead 61
2. Entitlement Where Delay Does Not Ultimately Reduce
the Contractors Distribution Base 62
3. Extended Overhead 63
4. The Rationale Supporting Extended Overhead as a
Separate Basis of Recovery 67
5. Entitlement Under Various FAR Clauses 69
C. Measuring Unabsorbed Overhead 71
1. A Parade of Formulas 71
2. The Eichleay Formula 72
a. Background -- ----- 72
b. The Eichleay Formula 76
c. Criticisms of Eichleay 76
d. Alternative to Formulas Such as Eichleay 83
(i) Unabsorbed Overhead 83
(ii) Extended Overhead 84
3. Getting the Boards and Courts to Accept Alternatives
to Eichleay 85
a. Overcoming Capital Electric and Savoy
Construction 85
b. Contractually Establishing the Method of Recovering
Unabsorbed Overhead 88
4. Preventing Double Recovery of Unabsorbed Overhead 90
a. Percentage Markup on Direct Cost 90
b. Direct Recovery of Normally Fixed Indirect Costs 92
D. Unabsorbed Overhead in the Context of a Termination for
Convenience 92
I.Termination Settlements 93
A. Objective 93
B. Complex Nature of Termination Settlements 94
iv
-- T ._
CHAPTER 5 CONSISTENCY
V
II. Application of the Consistency Requirement 143
A. Classifying Costs as Direct or Indirect 144
1. Overcharging Results from Inconsistent Classification
of Costs as Direct or Indirect 145
2. "Costs Incurred for the Same Purpose in Like
Circumstances" 147
a. CAS 402 Guidance 147
(i) Costs Incurred for the Same Purpose 148
(ii) Costs Incurred in Like Circumstances -150
b. Decisions of the Boards and Courts 151
(i) One of Several Cost Objectives Requires More of
an Indirect Costs than Other Cost Objectives 152
(ii) Direct Cost Functions Performed by an Employee
or officer Whose Salary Is Normally Charged
Indirectly 153
B. Assignment of Costs to Indirect Cost Groupings 155
C. Distribution of Costs to the Several Cost Objectives 156
D. Base Period Selection 157
CONCLUSION 173
FOOTNOTES 176
Vi
I|
INTRODUCTION
/A
overhead.
2I
.. 'WOW,
or1U
particularly when a markup for indirect costs is also
permitted.
Principles. -4 / -
1
fixed indirect costs although the event necessitating the
ft
3
equitable adjustment does not cause the contractor to incur
available.
4
direct recovery is a consistent accounting practice and
5
.5
convenience.
.5
6
CHAPTER 1
I. EQUITABLE ADJUSTMENTS
technological advances.
7
performance of a construction contract, the contractor is
Government contracting.
.- . . .. .. .. .. .~ .
'equitable adjustment' refers to a legal concept of returning
Government. 1 1
9
- - a~a .YW . .. .
an equitable adjustment.
GOVERNMENT
10
of preparing the termination settlement proposal." 18 What a
fairly for the work done and the preparations made for the
reassessed 22
opportunity cost.
A. Defining Cost 2 5
12
WmI~~ ~ ,'C~A ~ ~ r - *, * ~ .
procurement regulations and the Government accounting texts
The CAS are included in the FAR at Subpart 30.3. They apply
are:
13
a. CAS 401, Consistency in Estimating, Accumulating, and
Reporting Costs;
b. CAS 402, Consistency in Allocating Costs Incurred for
the Same Purpose;
c. CAS 403, Allocation of Home Office Expenses to
Segments;
d. CAS 406, Cost Accounting Period;
e. CAS 410, Allocation of Business Unit General and
Administrative Expenses to Final Cost Objectives;
f. CAS 418, Allocation of Direct and Indirect Costs.
The CAS listed above are general standards. The CAS also
(B&P).41
14
'I
determining costs under terminated contracts; 4 3 and for
4
pricing changes and other contract modifications. 4
D. Measurement of Cost
cost objectives.
".0 'Al
1.i
E. Accounting Systems
by a change.
16
L
Because many estimates and allocations are involved in every
51
cost system, 'true' costs exist only in theory."
F. Allocation of Costs
the contract; (b) benefits both the contract and other work,
1. Direct Costs
benefited. 58 In a
directly to the cost objective
17
Ai. - K... t . A- . - h - . 8 4:,V . :
labor."60
2. indirect Costs
18
5 4
- ' m. p'J 5 x ' --' |;c~ .... .. -. S '% .'% ' * . . .. - .
in indirect cost groupings. 6 6 This preference for direct
not only meet the criteria established for direct costs, but
this reason, both the Cost Principles and CAS 402 permit
19
an indirect cost. However, when telephone costs are material
Objectives
20
which the grouping is to be allocated. The base
should be selected so as to permit allocation of the
grouping on the basis of the benefits accruing to the
several cost objectives. 7 4 When substantially the
same results can be achieved through less precise
methods, the number and composition of cost groupings
should be governed by practical considerations and
should not unduly complicate the allocation. 7 5
21
YA-
|WA
22(
22
23
should be allocated a share of the cost in proportion to the
purposes.97
c. Base Period
24
A short cost period might be subject to seasonal
variations, and thus yield cost allocation rates which
do not accurately reflect the normal operations of the
contractor's business. Cost recovery would then vary
greatly, although the contractor's operations might
have remained at a constant level. On the other hand,
long cost periods could attenuate the relationship
between.the indirect costs and the direct costs which
generated them, especially when a significant change
in the contractor's operations occurs. 9 9
CAS 406 provides the criteria and guidance for base periods
longer than one year may be used, their use may distort the
25
_w . .. . .. Ar Ur S
d. Indirect Cost Rates
or $600.
J.
26
Ak.-
impact" on a contractor, the relationship between volume and
change.
below.
(1) Variable Costs. "Variable costs change proportionately
Costs are fixed only in the short run; over time all costs
27
,~ ~A J(177"-7'~
.A'. . V .5 #.,VV, Ir.' TV * c -'0, -- -
fixed costs. "[They] are fixed over some range of output and
available. 1 1 6
Examples include electricity and telephone
costs.
regression. 1 1 8 4
28
B. Contribution Marqin and Breakeven Point
29
-. . . . . . . .Ja.
A. AbsorDtion Costina
1. In General
the term "full costing" will mean the product costing method
30
Re r.
2. Absorption Costing For Financial RePortina Purposes
purposes. 1 2 4
costs."
31
B. Full costina,
C. Direct Costina
32
costs.
134
"allowable" costs in any billing, claim or proposal.
allowable:136
(1) Reasonableness;
(2) Allocability; .
33 .
,%
The CAS and allocability have already been discussed. 1 3 7 The
A. Reasonableness
question. "139
1. Burden of Proof,
agree otherwise.142
34
hi-
2. Determinina Reasonableness of Indirect Costs
categories. "144
35
I).
An additional problem is the large number of sources of
1. Advance Aareements
36
A A-' AP MM
independent research and development (IR&D) and bid and
2. Limitina Clauses
37
p
in amount.
_n
38
1. Unallowable Costs Included in Indirect Cost
Groupinas
from which they benefit (if they are given a free ride),
benefits received.167
39 A
a -PA(v
CHAPTER 2
caused by a change.
40
- ~ ~ . A-%. %
The following process normally is used to determine the
costs of the change, (3) direct and indirect costs are added
41
two groups: (1) estimates concerning how the change will
are available.
42
...... ......
amount of litigation has been generated by contractors who
deletion.178
43
rate is not applied automatically to change orders. The FAR
-A'
cost rate and the amount of direct costs are agreed upon. A
44
- . -' < , $; - , C . aJ. S -. - - - -;
45
direct costs; and (4) the indirect cost rate is multiplied by
46
V,
Some board decisions state that the standard markup for
1 9 4
overhead on construction contracts is 10%, other board
1 9 5
I
decisions that the standard markup is 15%. The 10% rate
47
recover overhead, commission, and profit on changed work
performed by subcontractors, and (3) establish which costs
48
volume projections may lead to "over" or "under" recovery of
indirect costs.
Example:
follows:
Distribution Base
Direct Costs (10 million units X $2 per unit) $20 million
49
projected rate (150%) in costing the change results in the
CONTRACTOR WHOLE?
50
The Court of Claims has stated that the objective of an
2 1 1 --to
equitable adjustment is "to keep a contractor whole"
"leave the contractor in the same financial condition as it
2 12
would have been if the change order had not been issued."
Costina
that the contractor has not been made whole. 2 1 7 Using full
made "whole."
51
-:Z k,
Assume instead the change decreased the contractor's costs of
$1500.
fixed costs.
52
additional work required by the change takes the place of
"other work" that could have been priced to permit recovery
(1) Full costing is the costing method used when the original
53
probably led to the assumption that its use would be
amount for fixed overhead, and thus, may be priced much lower
54
Principles require that indirect costs be allocated "on the
means is that the direct costs of the changed work will not
costs.
for the changed work, had the changed work been the subject
55
she would have been in but for the tort, the focus is on the
areas. -225
I'
56
,..J
',p
CHAPTER 3
UNABSORBED OVERHEAD
until a time when labor and material prices are higher, (2)
rehandling of materials.
571
or complete, may occur before performance begins, in the
1. Unabsorbed Overhead
58
A&Jt
is involved here is a lower contract allocation base
(or none at all if the contract work has stopped) in a
situation in which indirect costs continue but no
other work is substituted for the contract work not
performed during the delay period. 2 2 9
unabsorbed overhead.
2. Extended Overhead
59
S
Boards and commentators frequently comment that "extended
costs would have been incurred had the contract not been
difficulties.
60
.II _J"
1. Unabsorbed Overhead
have had the delay not occurred. Profit for the accounting
overhead.
and courts generally have required proof that the delay "
61
2. Entitlement Where Delay Does Not Ultimately Reduce
62
3A
3. Extended Overhead
office costs than it would have had the delay not occurred.
63
contract more than originally anticipated. Confusion exists
64
VW
is a contra-t cost, (2) the allocation is based on the
have included more home office costs in its bid had it known
would have kept the contractor from increasing its bid even
65
-W. - *..&. - I . .. -
66
overhead was denied. 2 5 7 However, the reversal in Savoy
contract performance.
67
contrast, as a concept applicable only to manufacturers. 2 6 0
work.
68
out construction contractors for this special remedy is
69
Work clause, 2 6 9 Changes clause, 2 7 0 Differing Site Conditions
27 2
clause, 2 7 1 and Termination for Convenience clause.
70
C. Measuring Unabsorbed Overhead
ell
1. A Parade of Formulas
formula in much the same way that other increased costs are
a. Backaround
For over 25 years, boards and courts have used the Eichleay
71I
~Sa~
~ SI/~b ~ 1. ~ ~ * *~~SS ~ - ~
overhead costs. Other formulas have been used, but the
unabsorbed overhead.288
72
the Federal Circuit to decide whether extended overhead was
73
I' U 3; L . 5. .9:. .--. .*L 6_ , .-., . .- - ... .. .. .. .J*
issue.
the Court of Appeals for the Federal Circuit has endorsed the
74
4'
It is in recognition of these failings that certain
Boards seem to have withdrawn from their earlier
endorsements of the Eichleay principle. Even the
majority opinion in Capital Electric, above, appears
to be inviting litigants, in an appropriate case to ,
have the Court of Appeals conduct an en banc review
3 01
of the Eichleay approach.
States.,303
1
(.... ........
75
'S
c. Criticisms of Eichleav4
costs.
76
'A
contract billings distribution base is simply a cost of
the Eichleay formula and examine home office costs and other
,',
.
'F"
calculated, prior to use of the formula, to identify and
contract does not mean that the contractor's work force was
78
,e
replacement contract. The Government contract is then
79 .
..............................
' ...
summer months. Which members of a contractor's work force
and which equipment items are idled often depend on when the
80
occurs. 3 2 1 However, fixed indirect costs are less subject
,-I
81
8 1 "U
U- ~ *.--..,..
The difference between the amount of recovery under the
overhead for each day of delay, rather than the $311 it did
3 27
recover under the Eichleay formula.
sparingly, if at all.
82
.~ *%
~.%
' .:d
-.. '%- .. **4.\~.,
~ ~ ~
the credit due the Government when work is deleted from a
32 9
contract.
distribution base.
adjustments330
83
performance prior to the delay. The reasonableness of the
circumstances.
84
,I
Alternatives to Eichleav U.
Instead, the Court based its decision upon the formula's long
86
".%
the per diem rate because the contractor's books were
344
unavailable for audit.
87
shall be upon the contractor to establish that such cost is
Unabsorbed Overhead
read:
88
Eichleay and modifications thereof are not acceptable
measures of unabsorbed overhead and therefore will not
be used for this purpose.
89
percentage markup on direct costs incurred during the delay
In almost all cases where this issue has been raised, the
percentage markup on direct costs has been either denied or
overhead.356
90
performed during the delay; specifically, the delayed
the direct costs of this substituted work would not have been
occurred.
91
A ,C,%$ 'p
during the delay period and unabsorbed overhead constitutes
for Convenience
92
yei
CHAPTER 4
I. TERMINATION SETTLEMENTS
A. Obi ctive
93
!'
- i .. - - - ' ,J ... . .. r-v j vw
times.
94
cost more to perform as a result of the partial termination
are:
The answers are often fact specific and depend in part on the
95
L .. .' '4 . - , . % . . W. iJ p -.. .- S. rr:wjr ..
terminated work are recovered, for the most part, in the same
'V
'V N!VV' ~~~
96
V'
V
B. Direct Charaina of Costs Normall? Treated as
Indirect Costs
terminated contract.
Costs
9N
•.'
I
contract and show that they have not already been recovered V
98
2. Indirect Costs Not Specifically Permitted as Direct
Costs.
99
3. Consistency Issues Raised by Direct Charging of
number of questions:
to ensure that the contractor does not recover the cost both
CAS9?
Under the Cost Principles and CAS 402, "[n]o final cost
100
charged indirectly.
charging.
101
( .~r - C - I
! i
Without exception, the commentators believe that some direct
change" approach is consistent with CAS 402 and and the Cost
102
V
pool.
CAS 402 and FAR 31.203(a) state that indirect costs "shall
103
included as a direct cost of that or any other final cost
cost pool are costs "incurred for the same purpose in like
the indirect cost grouping are not "costs incurred for the
contract and removes the direct charge from its indirect cost
104
)1
I
terminated contract.
105
it is not used as a distribution base (i.e., burdened with
C. Subcontractor Claims
106
'*N' ~ N%
~ 'N~ItdNV'
~ ' ~ N,
RJ% ' N '~ . ** -~~ - -~.-'. -
allocated shall exclude the same and similar costs
claimed directly or indirectly as settlement
expenses.414
107
,~%-% ~ I V N, V.
normal practice to include subcontract costs in its direct
office overhead. Thus, the Board did not allow the full
D. Unabsorbed Overhead
108
unabsorbed overhead where delay is contractor caused. 4 2 5 In
addressed.
109
SA
&Qnk r
E. Accountinq Records
110I
While the FAR specifically states that contractors are not
F. Cost Principles
111 1
the Cost Principles may have less effect in determining
The FAR supports the position that the Cost Principles need
112
G. General Limits on Recovery of Indirect Costs
113
% . d, ,
i/t
114
%. N
d%
not result in double recovery (that the cost was removed from
115
W.4
JU .4L' )* 4 ~ ~ ~
the indirect cost grouping prior to allocation) lies with the
contractor.478
expenses.410
481
(1) Potential double recovery;
costs-483
116
B. Burden of Proof
490
A contractor bears the burden of proving settlement costs.
117
contractor that any future costs incurred for the terminated
record keeping.
118
-w -. -. -. .
available for audit review. 4 9 6 Finally, to ensure that all
Settlement
119
contractor's proof that it incurred such costs, 4 9 9 (2)
a. Reasonableness
120
(whether or not successful) and of contesting the contracting
1I
t
121
2. Costs of Safeguarding, Inventorying. and DisDosinc
of Terminated Inventory
material handling. 5 1 4
122
V. UNABSORBED OVERHEAD AFTER TERMINATION FOR
CONVENIENCE
123
(3) Recovery of unabsorbed overhead is permitted by the
and delay.
124
.
profit it would have made on the terminated work but also the
might have had even less work during the period to absorb
125
proceeded to completion. The question is whether the
Government should, or does, at the time of contracting,
guarantee to the contractor that in the event of contract
overhead would:
126
4rW
I
terminated contract.
5 35
time following termination.
127
.-
. t w ~ ) .. - =_ B.- _=. - °
convenience.536
Contract
128
nonrecurring costs would be recovered in their entirety as
Contract
129
130oS
price of the unterminated portion of the contract. 5 4 7 Note
the fixed indirect costs that would have been absorbed by the
indirect cost rate would have been had the contract not been
from the actual fixed indirect cost rate; and (5) multiply
131
N
[ L. 1 17 C.7 X.
rate was lower than the rate upon which the bid was based the
were higher than they would have been had the contract not
132
AN
a z
have increased had the contract not been partially
accordingly.
i 133
CHAPTER 5
CONSISTENCY
repetitive.
arise. Although the issues are more complex, the courts and
134
S-%r F r
issue, the fact of inconsistency in many instances is
termination settlements.
135
MZ ~ ~ ~ , ~ ~ ~ $ ~
%--* 1
~
1. REQUIREMENT FOR CONSISTENCY
process.
will not have the same cost charged to it more than once.
136
approximate cost rather than to maximize the cost charged to
circumstances.
137
the large number of often conflicting sources of authority
purposes.
require consistency.
138
I
objective. "566
401 and 402. CAS 401 and 402 apply whenever a contract is
8
subject to either full or modified CAS-coverage. 5 6
139
Such changes, however, must be accomplished through
violates CAS 401 when it does not use the same cost
140
.4
.4
contract.
To date, CAS 401 has not played a major role in the pricing
141
b. Cost Accountina Standard 402- -Consistency in
only once and on only one basis to any contract or other cost
142
.-"-.
, . -". " "". "," "," "-" """ , . '" N
-,,?
i""
-'"" '...,i " ,.., ' " , i
established accounting practices will cause an inequitable
consistencly thereafter.
'
The key to applying CAS 402 is understanding what is meant by
143
(3) Distributing indirect cost groupings to the several cost
objectives
144 ,
the contractor's established cost accounting practices until
accounting practices.
indirectly.594
145
generated plus, as an indirect charge, a portion of the
contract.596
146
. . . i . i i -
2. uCosts Incurred for the Same Purpose in Like
Circumstances"
147
cost is not "incurred for the same purpose" or if the
test.
contracts are "costs incurred for the same purpose" and may
148
proposal for a new contract requires a disproportionate
cost. Since the costs are not costs incurred for the same
purpose than general purpose tooling and (2) the fact that
149
This is permissible in that the function performed by the
circumstances.
150
~. ~ .. ~ ~ ~ ~ 9
W-, IlW
F?
evident that the cost was incurred for the same purpose and
1516
contract.613
152
contracts indirect cost resources of which they required more
taken.
effect the purpose for which the cost was incurred. The
153
~ *'~I ~.
.i~-** ~ ~ .~4 . ~
.. - ~* 4,* %**: ~ -b~a
contractor may try to recover part of the person's salary as
154
Applying the functional test case, the Board expressed the
155
V. 50,71-7 VCR
to that determination.
:P
Objectives
156 '
'e I
separate distribution base. 6 2 9 However, doing so is an
63 0
inconsistent accounting practice and is not permissible.
objectives.631
157
5-
F
disallowed.
158 p
contractor's recovery.641
10
159
Y! -".-Y '
-O VV---
160
If a contractor fails to follow its disclosed and/or
Contractors not subject to the CAS can also change their cost
allow.660
161
- - i- -/'- / %i ! -d i I***~
-%\~
i .. .. . .. . . ... ~5- 5,'a.~
- - - - - - - - - - - - T V
Chances
1. CAS-Covered Contracts
162
application of a change in accounting practice, boards and
6 65
courts probably will permit retroactive application.
b. Non-CAS-Covered Contracts
163
accounting practice. 6 6 6 Even so, retroactive application is
164
and cost plus fixed fee contracts. Inequitable distribution
165
The real threat to the contractor from retroactively applying
ADJUSTMENTS
166
J4
reclassify normally indirect costs as direct costs: (1) a
The fact that a change order may have benefited more from a
167
.A j, *UA P 1 L L
accounting practices and results in over recovery. 6 8 5 If
cost rate. 6 8 9 Use of the standard markup has not been deemed
168
1
2. Recovery of Indirect costs During Delay
used for the delay period; one such as method is the Eichleay
69 2
formula.
169
= - - - - -- F 7-7- 7V -- -. -W
170 '
-. - . - . .- .4 - - 4 .
.2
CONVENIENCE
171
Government. 710
172
-.. NF- N.
CONCLUSION
173
, .m % P U,~t % °pp
!~P%
-~ ' ~ h..*- TV T 77 K17 K. , &-
the basis for its recovery has been hindered by its use as a
over 25 years and its use was affirmed in 1984 by the Court
presumptions upon which the formula rests have not been fully
174
2
overhead, one must examine the presumptions upon which the
measurement.
. a-7
FOOTNOTES
1
J. CIBINIC & R. NASH, ADMINISTRATION OF GOVERNMENT CONTRACTS, 267
(2d ed. 1985).
2 FAR
52.243-4.
3 Cibinic
& Nash, supra note 1, at 281.
4
-' Suspension of Work clause, FAR 52.249-10.
5
FAR 52.236-2.
176
&
177
% "_-
of over $100,0000, is at FAR 52.249-2. The termination
clause for cost reimbursement contracts is at FAR 52.249-6.
1 8 Cibinic & Nash, supra note 1, at 773.
1 9 FAR 49.201(a) (emphasis added).
2 0 FAR 31.205-42(b).
21 FAR 31.205-42(g).
2 2 FAR 52.249-2.
2 3 j.
BULLOCH, D. KELLER, & C. VLASHO, ACCOUNTANTS' COST HANDBOOK, A
GUIDE FOR MANAGEMENT ACCOUNTING, 19.12-13 (3d ed. 1983). See
also J. FREMGEN & S. LIAo, THE ALLOCATION OF CORPORATE INDIRECT
COSTS, 19-20 (1981)
178
179
(8) Nondefense contracts and subcontracts awarded to
business units that are not currently performing any
CAS-covered national defense contracts.
(9) Contracts awarded to labor surplus area concerns
pursuant to a labor surplus area set-aside.
(10) Contracts and subcontracts to be executed and
performed entirely outside the United States, its
territories, and possessions.
3 0 FAR30.202-1(b). The contractor must disclose information
sufficient to "(1) establish[] a clear understanding of the
cost accounting practices the contractor intends to follow,
(2) definte] costs charged directly to contracts and
disclos(e] the methods used to make such charges, and (3)
delineat[e] the contractor's methods of distinguishing direct
costs from indirect costs and the basis for allocating costs
to contracts." Department of Defense, DEFENSE CONTRACT AUDIT
MANUAL,8-202a (1983).
31
For contracts subject to full CAS coverage, FAR Subpart
30.3 is incorporated by reference into the contract. See FAR
52.230-3, Cost Accounting Standards clause. For contracts
subject to modified CAS coverage, the contractor is required
to comply with the provisions of FAR 30.401 and 30.402. See £
41
.d.
180
V V.
....... ..
42FAR Part 31, Contract Cost Principles and Procedure.
43
FAR 31.103(b) (3).
44
FAR 31.103(b) (6).
45
FAR 31.201-1.
4 6
Id.
47 See Bedingfield & Rosen, supra note 27, at 5-2; Bulloch,
Keller, & Vlasho, supra note 23, at 21.8; P. FISCHER & W.
FRANK, COST ACCOUNTING, THEORY AND APPLICATION, 6 (1985) . This is
true even though the accounting system may be in compliance
with Generally Accepted Accounting Principles (GAAP).
4 8 Bedingfield
& Rosen, supra note 27, at 14-18.
4 9 Id.
See e.g., National Mfg., ASBCA 18806, 74-1 BCA 10580
at 50,150.
5 0 Bedingfield
& Rosen, supra note 27, at 14-18. See e.g.
Leopold Constr., ASBCA 23,705, 81-2 BCA 15277. Because
contractor's accounting practices did not segregate costs in
a way that permitted actual costs of the change to be
determined, the contractor failed to carry its burden of
proof with respect to additional costs. Therefore, its
recovery was limited to the Government's estimate of
increased cost.
5 1ASPM,
supra note 24, at 3-8.
52A "cost objective" is an activity for which a separate
measurement of cost is desired. Horngren, supra note 25, at
58. FAR 31.001 defines "cost objective" as a "function,
contract, or other work unit for which cost data are desired
and for which provision is made to accumulate and measure the
cost of processes, products, jobs, capitalized projects,
etc."
53
FAR 31.001.
54
FAR 31.201-4.
55
FAR 31.201-1.
181
i. . .
5 6 Bedingfield
& Rosen, supra note 27, at 5-5. Anderson,
supra note 27, at 9-3, defines a direct cost in terms of
traceability. "If the thing (or object), whether tangible or
intangible, represented by a cost is traceable to individual
units of product produced or services performed, the cost is
a direct cost of the product or service; otherwise, the cost
is an indirect cost."
57FAR 31.202(a). A "final cost objective" is a cost
objective that has allocated to it both direct and indirect
costs and, in the contractor's accumulation system, is one of
the final accumulation points. FAR 31.001. A cost can be
"specifically identified" with a particular final cost
objective if (1) the beneficial or causal relationship
between the costs incurrence and the final cost objective is
clear and exclusive, (2) the amount of the cost is readily
and economically measurable, and (3) all other costs incurred
for the same purpose in like circumstances can also be
identified specifically with final cost objectives and
accounted for as direct costs. See Boeing Co., ASBCA 39224,
79-1 BCA 13708 at 67,248-49. Note that the FAR's definition
of "direct cost" differs from the commonly accepted cost
accounting definition of direct cost in its emphasis on
"final cost objectives." Bedingfield & Rosen, supra note 27,
beginning at 8-8, sharply criticize the FAR's definition for
failing to recognize that all costs can be direct costs at
some level; for example, "[a]ll costs are direct costs of a
company taken as a whole." As a practical matter, however,
the definitional difference appears unimportant.
5 8 FAR 31.202(a).
5 9 Bulloch,
Keller, & Vlasho, supra note 23, at 1.13.
60 Id.
6 1 FAR
31.203(a) defines "indirect cost" as any cost not
directly identified with a single, final cost objective, but
identified with two or more final cost objectives or an
intermediate cost objective. Anderson, supra note 27, at 9-3
to 9-4, defines an indirect cost as one which economically
cannot be traced to individual units of product or services.
For Government contracts, the focal point of cost
accumulation is by contract rather than by product.
Therefore, for Government contract purposes, an indirect cost 40
182
7. R I - 6 1 -1
- ' ..- - .-. W% W
183
with the specific objective in mind, leaving as
indirect charges only those where the identification
cannot be made. Indirect costs, therefore, are
residuals. Such a stance is not only in accord with
generally accepted accounting principles, it is also
consistent with the definitions embodied in [FAR
31.202(a)].
Secondly, where the essential task is to determine
the amount of an equitable adjustment flowing from a
changed condition, the terms of the contract clauses
call for a finding of the 'increase or decrease in the
cost of . . . performance of the contract' . . . . In
our view, this necessarily implies a preference for
costing out a change or changed condition in the most
direct manner possible. The alternative to this
approach which consists of lumping all disputed costs
into an overhead pool for allocation hardly seems to
be either a rational or a fair method of arriving at
I
equitable adjustment for specific claims.
6 8 Nash
& Cibinic, supra note 65, at 1457.
6 9 1d.
at 1464-65. Anderson, supra note 27, at 9-4 comments:
"it may not be economically feasible to charge the cost
directly--the costs of record keeping required for direct
charging may exceed the benefits."
184
),'
- ~ v.. r *. . .
,-.. 4 Vd -.A- P rMS 7F-0 -7e . W%
7 2 Bedingfield
& Rosen, supra note 27, at 5-6.
73
Fultz, supra note 71, at 3.
7 4 1n
American International Manufacturing, ASBCA 25816, 84-3
BCA 17698 at 88,286, the Government argued that guard
services benefited more than just the contractor's
-manufacturing operations and therefore should be transferred
*from the service overhead pool to the much larger G&A pool.
The board found against the Government on the facts, but the
case demonstrates that inclusion of a cost in a cost pool
that is not distributed to all cost objectives benefiting
from the cost will result in over allocation to the cost
objectives to which the cost is distributed. Note, it is the
grouping (rather than the individual costs elements in the
grouping) which must bear a beneficial or equitable
relationship with the several cost objectives. See Cyro-
Sonics, Inc., ASBCA 13219, 70-1 BCA 13219 at 38,654.
75
FAR 31.203(b).
7 6 See
Anderson, supra note 27, at 9-14.
185
9
v*.,*, . ~ .~
was unable to establish this as a separate pool for purposes
of pricing adjustments.
78
Horngren, supra note 25, at 515.
79
FAR 31.203(b).
8 OObviously,
a contractor's cost accounting system must be
capable of determining costs for purposes of progress
payments. However, the precision needed to justify progress
payments is significantly less than that needed to justify
compensation under an equitable adjustment or a termination
settlement.
8 1 FAR 31.203(b).
8 2 Bedingfield
& Rosen, supra note 27, at 8-26; ASPM, supra
note 24, at 6-5 to 6-14.
8 3 See
e.g., infra Chapter 2, Parts I.E and F. The standard
markup for indirect costs and clauses limiting recovery of
indirect costs both use the term "overhead" as a synonym for
indirect costs in general.
8 4 See TOUCHE Ross AND CO., GOVERNMENT COST RECOVERY, 36-A (1986) .
851d. See also FAR 30.410-30; Anderson, supra note 27, at
9-6.2.
I
8 6Aseparate CAS has been established for G&A. See FAR
30.410. Another CAS covers "indirect cost." See FAR 30.418.
Note that the CAS apply only to CAS-covered contracts.
87See FAR 30.403. A home office is "[an office responsible
for managing two or more, but not necessarily all, segments
of an organization." FAR 30.403(a)(2). See also Braude and
Kovars, Extended Home Office Overhead, Constr. Briefings, No.
84-6, 1-2 (June 1984).
186
%~.1~ % % ~*af
incidental to the general administration of the
company.
8 8 See FAR 30.403-40.
8 9 Horngren,
supra note 25, at 478-79.
187
several cost objectives." (emphasis added) No mention is
made of any other distribution base. By implication, it is
only when allocation cannot be made on a relative benefit
basis that use of another basis is permissible.
9 5 See
Fultz, supra note 71, at 53; Horngren, supra note 25,
at 516-17.
96See FAR 30.403-40, Allocation of Home Office Expenses to
Segments; FAR 30.410-40, Allocation of Business Unit General
and Administrative Expenses to Final Cost Objectives; and FAR
30.418, Allocation of Direct and Indirect Costs.
97FAR 31.203(b) requires that cost be allocated on the basis
of benefits accruing to the several cost objectives. All
cost objectives benefiting from a cost must be allocated a
proportionate share of the cost. A cost of sales base is
objectionable because it does not consider the total
activity of the business unit during the period--only sales
activity. Thus, all cost objectives that benefit from
incurrence of a cost may not receive a proportionate
allocation. See e.g., Westinghouse Elec., ASBCA 25787, 85-1
BCA 17,910 at 89,676-81 (stating that CAS 410 "ruled out" use
of the cost of sales method of G&A allocation for CAS-covered
contracts); AC Elecs. Div., General Motors Corp., ASBCA
14388, 72-2 BCA 9558 at 44,521; Daystrom Instrument, Div of
Daystrom, ASBCA 3438, 58-1 BCA 1588 at 5,760, aff'd on motion
for reconsid. 58-2 BCA 2050, "The cost-of-sales basis of
allocation of G&A expense is proper only if . . . there is no
great disparity in the amount of inventory between the
beginning and the end of the allocation period." See
Curtiss-Wright Corp., Wright Aeronautical Div., ASBCA 9032,
65-2 BCA 4960 at 23,146. The Government questioned use of a
cost of sales method of allocation because it did not
allocate any G&A costs to a company-sponsored research and
development program. The Board did not reach this issue
because the amount involved was de minimis. See R. W.
Borrowdale Co., ASBCA 11362, 69-1 BCA 7564 at 35,036-37;
Litton Sys., ASBCA 10395, 66-1 BCA 5599. But see American
Int'l Mfg., ASBCA 25816, 84-3 BCA 17698 at 88,288, where the
Government made no objection to the contractor's use of a
cost of sales base for allocation of G&A.
9 8 FAR 31.204(e).
188
-w
p.. - ww p ..p w p. .p..- - g.~jP ~ ~ p I
1 0 0 FAR 31.204(e). Under FAR 30.302(a), "full CAS coverage"
applies to contractor business units that:
189
4* - * -).
'. a~N WV
contractor was disallowed because it did not accurately
allocate G&A expenses to the operations which generated such 6
expenses. But see National Manufacturing, ASBCA 18806, 74-1
BCA 10580 at 50,160, where the Board found it more reasonable
to use a four year, composite, G&A rate in pricing a
defective specification claim than the annualized rate argued
for by the Government because direct costs were low and
overhead high during the initial years of the contract.
1 0 6 See Penberthy Electromelt Int'l v. United States, 11 Cl.
1 0 8 See
Bulloch, Keller, & Vlasho, supra note 23, at 17.12-13.
See also Fischer & Frank, supra note 47, at 27-31.
1 0 9 Bulloch, Keller, & Vlasho, supra note 23, at 17.12.
l1d, at 17.13.
iii Id.
190
II
1 2 0 Horngren,
supra note 25, at 45. The formula used to
calculate the breakeven point is: fixed expense divided by
unit contribution margin.
1 2 1 "Period
costs" are listed in the income statement in their
entirety as expenses of the period . . . and are not charged
to the work-in-process inventory and not traced through the
finished-goods inventory into cost of sales." Bulloch,
Keller, & Vlasho, supra note 23, at 5.40.
12 2
See e.g., Bedingfield & Rosen supra note 27, at 5-15;
Horngren, supra note 25, at 52; S. MOSCOvE, G. CROWNINGSHIELD,
K. GORMAN, COST ACCOUNTING WITH MANAGERIAL APPLICATIONS, Chapter 12
(5th ed. 1985).
127 Id.
128
Rishe, supra note 27, at 11-3.
12 9
Anderson, supra note 27, at 9-6.
191
al.
including a portion of G&A expense; no costs are
charged to the period in which they were incurred.
1 3 0 More
properly stated, all costs are allocated to
"contracts." For Government contract purposes, the focal
point of cost accumulation is the contract rather than a
"product." See Anderson, supra note 27, at 9-6.
1 31
Rishe, supra note 27, at 11-3.
13 2
Bedingfield & Rosen, supra note 27, at 5-15.
13 3
d. at 5-16.
1 3 4 FAR 31.201-6(a).
1 3 5 FAR 31.201-1.
1 3 6 FAR 31.201-2.
192 J
~~~~~~~~~~~~~ d. P ~ Ps
01X ~ %\ ** ~%SV ~ ~ p ~ -
lN
1 4 0 FAC
84-26 (July 30, 1987) amends FAR 31.201-3 as follows:
(1) "no presumption of reasonableness shall be attached to
the incurrence of costs by a contractor," and (2) upon
challenge "the burden of proof shall be upon the contractor
to establish that such cost is reasonable."
14 1
Bruce Constr. v. United States, 324 F.2d 516 (1963).
Inroads on the rule set forth by Bruce Construction were made
by Section 933 of the Defense Procurement Improvement Act of %
1985 (P.L. 99-145) which placed the burden of proof on the
contractor to establish that disputed costs were reasonable.
The statute did not, however, expressly state that actual
costs were not to be "presumed reasonable" and applied only
to proving the reasonableness of indirect costs and to DOD.
See Gov't Contr., Vol. 28, No. 6 (March 17, 1986).
Id.
1 4 5 "Although
the GAAP's do not appear in a single, definitive,
codified form, most public auditors agree on the majority of
the items they 'generally accept' as accounting principles."
Bedingfield & Rosen, supra note 27, at 4-11.
1 4 6 FAR 31.201-2(a)(3).
1 4 7 Bedingfield
& Rosen, supra note 27, at 4-4. See Celesco
Indus., ASBCA 22402, 80-1 BCA 14271 at 70,297. "Such r%
principles have been developed for asset valuation and income I%
measurement, and 'are not cost accounting principles' as
such, although cost accounting principles (may] evolve out of
I
193
W, IlkA V 1. dm lll I
them." Id. (citations omitted). See also Wolf Research and
Dev., ASBCA 10913, 68-2 BCA 7222 at 33,546.
14 8 See
F. ALSTON, F. JOHNSON, M. WORTHINGTON, L. GOLDSTEIN, & F.
DEVITO,CONTRACTING WITH THE FEDERAL GOVERNMENT, 161 (1984)
[hereinafter Alston)i.
1 4 9 Trueger,
supra note 27, at 430-31. See also Gould Defense
Sys., ASBCA 24881, 83-2 BCA 16676 at 82,390.
1 5 0 Trueger,
supra note 27, at 431. See Boeing Co., ASBCA
11866, 69-2 BCA 7898 at 36,753. See also Daystrom
Instrument, Div. of Daystrom, ASBCA 3438, 58-1 BCA 1588 at
5756, aff'd on motion for reconsid., 58-2 BCA 2050. " [Ijt
should be recognized that many public accountants and many
well-managed business firms follow accounting principles and
practices that do not conform to the A.I.A. bulletins, and
such accounting principles and practices must also be
recognized as being "generally accepted."
1 51
FAR 31.109.
1 5 2 FAR 31.109(h) .
1 5 3 FAR 31.109(b) .
1 54
FAR 31.109(c).
1 5 5 Limiting
clauses are often included in construction
contracts. Agencies that commonly use such clauses include
the General Services Administration, the Postal Service, the
Veterans Administration, and the Navy. See Cibinic & Nash,
supra note 1, at 519-23.
1 5 6 See
Samuel S. Barnett Co., GSBCA 4855, 80-1 BCA 14355 at
70,768-69; Jack Picoult, GSBCA 2351, 69-1 BCA 7678, aff'd on
motion for reconsid., 69-2 BCA 7820.
1 57
See Central Mechanical, Inc., DOT CAB 1234, 83-2 BCA 16642
at 82,753; ACS Constr., ASBCA 23471, 79-2 BCA 23471 at
69,388 and 69,390.
1 58 See infra Chapter 2, Part I.F.
1 5 9 FAR 31.205.
194
S
1 6 0 FAR
31.201-6.
161FAR 31.201-6(c).
16 2
FAR 31.201-6(a). "A directly associated cost is any cost
which is generated solely as a result of incurring another
cost and which would not have been incurred had the other
cost not been incurred." Id.
1 6 3 See e.g., J.W.
Bateson Co., ASBCA 22337, 78-2 BCA 13523 at
66,265.
1 6 4 FAR 31.201-6(d) provides the following exception:
1 6 5 1d.
If a fragmented distribution base were used for
allocation purposes, the excluded portion of the base would
not absorb the overhead costs it purportedly generated or
benefited from. For example, assume that certain direct
material costs, having been unreasonably incurred, were
deemed unallowable and assume that the distribution base for
material overhead is direct material cost. The purchase of
the unallowable material gen'erated the same material
acquisition and handling effort as did any other purchase.
Its removal from the distribution base establishes a
distribution base in the amount it would have been had the
unallowable costs not been incurred, but leaves in the
overhead pool for distribution the increased material
overhead costs generated by the unreasonable purchase. .
1 6 6 Because
the unallowable cost portion of the distribution
base is not linked to a cost objective, the indirect cost
grouping will not be totally distributed to the several cost
groupings. The remaining portion of the indirect cost
grouping is in effect allocck.ea to the unallowable costs. In
sum, although not a cost objective, unallowable costs in the
distribution base are treated like one.
1 67
FAR 31.203(c) provides:
195
ft.. %. t . .% '.=....t* *f
4 - -; - - -. - . .- , , , .. -. . . ,. - ' - - . " -.. .-
$3
1 7 0 The
distribution base normally used in pricing changes is
direct labor dollars or another direct cost of the change.
As noted in chapter 1, distribution bases other than direct
costs are occasionally used. See supra note 95 and
accompanying text.
1 7 1 See
Cal-Tom Constr., VABCA 85-3 BCA18211 at 91,407 (the
equitable adjustment was a lump sum figure including all
markups); E. Arthur Higgins, AGBCA 76-128, 79-2 BCA 14050 at
69,067; Datametrics, Inc., ASBCA 16086 BCA 74-2 10742 at
51,103 (jury verdict did not separately show the amount
allocated to individual cost elements such as G&A); Webber
Constructors, IBCA 72-6-8, 69-2 BCA 7895; Geris, Inc., DOT
CAB 67-6, 69-1 BCA 7450 at 34,577-78.
17 2
Estimates "if they are supported by detailed
substantiating data or are reasonably based on verifiable
experience" form an acceptable starting point for computing
an equitable adjustment. Celesco Indus., ASBCA 21928, 81-2
BCA 15260 at 75,547-48.
17 3Aprojected overhead rate is developed through a five step
process: (1) select a base period, (2) estimate production
volume for the period, (3) estimate indirect expenses for the
period, (4) estimate the distribution base for the period,
and (5) divide estimated indirect expenses by the estimated
distribution base. See Fultz, supra note 71, at 32.
196
Ii'
17 4
See Alston, supra note 148, at 367. U
1 8 0 FAR 15.809(b).
181FAR 15.809 (c).
1 8 2 Assuming
that the contractor uses direct cost as its
distribution base. If a distribution base other than direct
cost is used, the indirect cost portion of the adjustment is
determined by multiplying the contractor's indirect cost rate
by the increase in that distribution base.
18 3
See e.g., Stewart Avionics, ASBCA 23161, 78-1 BCA 13130
(because the contractor was unable to prove in which fiscal
year the retrofit took place the Board applied the lower of
the overhead rates for the two years--270% as compared to
661%).
18 4Achange deleting work, particularly if major, may be
treated as a partial termination for convenience rather than
a change. If so, settlement would be handled under the
Terminations for Convenience clause rather than under the
Changes clause. See Cibinic and Nash, supra note 1, at 784.
See generally Ideker, Inc., ENG BCA 4389, 87-3 BCA 20145 at
101,974.
197
V
1 8 5 Assuming
that the contractor's distribution base is direct
cost. If a distribution base other than direct cost is used,
the indirect cost portion of the downward equitable
adjustment is determined by multiplying the contractor's
indirect cost rate by the estimated decrease in that
distribution base.
1 8 6 See
e.g., Fordel Films West, ASBCA 23071, 79-2 BCA 13913
at 68,298.
1 87
See Algernon Blair, Inc., ASBCA 10738, 65-2 BCA 5127 at
24,141, where the contractor claimed that deductive changes
caused additional expenses--preparing estimates, securing
prices and subcontractor proposals, preparing and submitting
proposals for the changes and additional contract
administration. It argued therefore, that its overhead was
not reduced by the deductive change. The Board rejected this
reasoning but stated in dicta that if a contractor could show
"special circumstances" the credit due the Government might
be reduced. See also Sun Elec. Corp., ASBCA 13031, 70-2 BCA
8371. Here, the contractor unsuccessfully argued that the
Government was not due a credit for material handling charges
because the costs of ordering the material and cancelling the
order had already been incurred. The Board reasoned:
Id. at 38,395.
1 8 8 See Pacific Contractors, ENG BCA PCC-29, 79-2 BCA 13998 at
68,720.
1 8 9 See
Dawson Construction, GSBCA 5364, 82-1 BCA 15701 at
77,661 where the Board stated "deductive and additive changes
must be priced in the manner dictated by the Equitable
Adjustments provision of the contract's general conditions,
that is, by applying the markups to the net increases in
198
direct costs." See also J. F. Shea Co. v. United States, 10
Cl. Ct. 620, 628 (1986); Glover Constr., ASBCA 29194, 85-2
BCA 18093 at 90,809-10; J. Harvy Crow, GSBCA 41423, 75-2 BCA
11423 at 54,390-91.
1 9 0 1d.
But See CRF-A Joint Venture of Cemco and R. F.
Communications, ASBCA 17340, 76-1 BCA 11857 at 56,803-04,
where different indirect costs rates were used to determine
indirect costs of the deleted and the added work. The board
held that when the "plus-and-minus changes net out on the
plus side" current overhead rates are used to price both--but
when the change is a net deductive change it is proper to
price the additive portion of the change using the
contractor's higher actual overhead rates and the deductive
portion of the change using the contractor's lower projected
rates. The Board reasoned that the deletion reduced the
quantity of the contractor's work, thereby increasing the
contractor's overhead rates and that the Government, who had
the burden of proof with respect to the deductive portion of
the change, had failed to prove that the contractor's
projected rates were not reasonable. The reasoning f this
decision has not been applied in any subsequent cases. See
also Massman Construction, ENG BCA 3660, 81-1 BCA 15049 at
74,454-55, where indirect costs of the substituted work were
determined using the contractor's bid rather than actual
indirect cost rate. The event necessitating the equitable
adjustment was the Government's substitution of a more
expensive cement. The Board reasoned that since the
contractor's original bid did not adequately provide for
recovery of indirect cost it was necessary to use the
original bid's indirect cost rate to preserve the loss
position of the contractor. The Board was incorrect in
holding that application of the originally bid indirect cost
rate to the net increase in direct cost was necessary to
preserve the contractor's profit/loss position on the
unchanged work. The profit/loss position on the unchanged
work is unaffected by the indirect cost rate applied to the
net increase or decrease in direct costs caused by a
substitution. The Board simply forced the contractor to
perform the net change at a loss.
1 9 1 See
e.g., Flores Drilling and Pump Co., AGBCA 82-204-3,
83-1 BCA 16200. The contractor claimed overhead at a rate of
114%. Because the contractor did not submit evidence
substantiating that rate the Board used a standard overhead
rate (15%). See also Forest Rd. Constr., AGBCA 84-221-3, 85-
2 BCA 18160 at 91,188; ACS Constr., ASBCA 23471, 79-2 BCA
23471 at 69,390. The contractor "not know[ing) what its
199
I
actual overhead was doing" claimed overhead at 10%; its most
recent year's corporate overhead rate was 16%.
19 2
See C. N. Flagg & Co., ASBCA 26444, 84-1 BCA 17120
(holding that the contractor's actual indirect cost rate of
10.3% should be used rather than 15% standard markup used to
price change orders prior to the actual rate being
available); Brezina Constr., IBCA 757-1-69, 73-1 BCA 10195
at 48,062 (holding that the contractor's actual indirect cost
rate of 6.5% should be used rather than the 10% standard
markup used to price change orders prior to the audited rate
being available). See also Arnold M. Diamond, Inc., ASBCA
20667, 77-2 BCA 12769. The contractor originally proposed a
10% overhead rate for a change. The proposal was not
accepted. After a DCAA audit found the contractor's overhead
rate to be 30.5% the contractor revised its claim
accordingly. The Board awarded overhead at the 30.5% rate.
See also supra note 177.
1 9 3 See
American Federal Contractors, PSBCA 1359, 87-1 BCA
19595 at 99,119, where the board stated, "A contractor, upon
a proper showing with specific evidence can recover overhead
costs beyond the standard allowance."
1941Id.
1 9 5 See
Flores Drilling and Pump Co., AGBCA 82-204-3, 83-1 BCA
16200 at 80,487; Urban Plumbing and Heating Co., ASBCA 9831,
71-2 BCA 8980 at 41,744.
1 9 6 Cases
in which a 10% rate was adopted include: Salem
Eng'g and Constr. v. United States, 2 Cl. Ct. 803, 809
(1983); American Fed. Contractors, PSBCA 1359, 87-1 BCA
19595 at 99,119; Arctic Corner, ASBCA 29545, 86-3 BCA 19304
at 97,605-06; KenCom, Inc., GSBCA 7717, 86-2 BCA 18900 at
95,341; Steven E. Jawitz, ASBCA 31164, 86-1 BCA 18620 at
93,555 (allowed both field office overhead of 10% and a
separate charge for G&A of 3%); 3A/Magnolia-Ju, IBCA 1885,
85-3 BCA 18202 at 91,370; R & E Elecs., VABCA 2227, 85-3 BCA
18316 at 91,897; Glover Constr., ASBCA 29194, 85-2 BCA 18093
at 90,810; Forest Rd. Constr., AGBCA 84-221-3, 85-2 BCA
18160 at 91,188; Fred A. Arnold, Inc., ASBCA 20150, 84-3 BCA
17624; ACS Constr., ASBCA 23471, 79-2 BCA 23471 at 69,390;
Alps Corp., ASBCA 19632, 75-1 BCA 11260 at 53,672; Detweiler
Bros. ASBCA 17897, 74-2 BCA 10858 at 51,644; Cecil Pruitt,
Inc., ASBCA 18344, 73-2 BCA 10213 at 48,150-51; Varo, Inc.,
ASBCA 15000, 72-2 BCA 9717 at 45,360; Bregman Constr., ASBCA
15020, 72-1 BCA 9411 at 43,718; Framlau Corp., ASBCA 15516,
200
71-2 BCA 9145 at 43298; Ray D. Bolander Co., IBCA 331, 70-1
BCA 8200 at 38,133-34; Algernon Blair, Inc., ASBCA 10738,
65-2 BCA 5127 at 24,141.
19 7 See Urban Plumbing and Heating Co., ASBCA 9831, 71-2 BCA
8980 at 41,745 (the Board lowered the contractor's recovery
of overhead to 13% after stating that 15% was standard);
Trans-Eastern Constructors, Inc., ASBCA 13612, 70-2 BCA 8453
at 39,325.
1 9 8 Trans-Eastern
Constructors, Inc., ASBCA 13612, 70-2 BCA
8453 at 39,325.
1 9 9 1n
American Federal Contractors, PSBCA 1359, 87-1 BCA
19595 at 99,119, the board held that:
See also Hoyer Constr., ASBCA 31241, 86-1 BCA 18619 at 93,553
(construction manager, project manager, and secretary's
salaries were not allowable as direct costs but included in
15% markup for overhead); ACS Constr., ASBCA 23471, 79-2 BCA
23471 at 69,390 (supervisor's salary was not allowable as a
direct cost but was included in the 10% markup); Fred A.
Arnold, Inc., ASBCA 20150, 84-3 BCA 17624 at 87,838 ("impact
labor costs" to review change, orient crew to change, prepare
estimate, negotiate change, and perform clerical work were
not allowed as direct costs--"including such costs in the
201
direct cost base while using the standard . . . markup rates,
would result in a duplicative recovery of such costs"); A.
Geris, Inc., DOT CAB 67-6, 69-1 BCA 7450 at 34,577, (clerical
expenses were held to be a minor general expense includable
in the 15% markup for overhead and profit).
2 0 0 For
over 20 years the General Services Administration
(GSA) has used a clause limiting overhead recovery. Most of
the cases testing the validity of clauses limiting overhead
recovery, even today, involve GSA contracts. The Veterans
Administration and the Postal Service also use a limiting
clause.
2 0 1 Such
terms have been interpreted as permicting a
contractor to compound overhead and profit and thus recover a
combined 21% for overhead and profit. See Tutor-Saliba-
Parini, PSBCA 1201, 87-1 BCA 19775 at 100,079.
2 0 2 The
current GSA and Veterans Administration clauses are
set out in Appendix 1.
2 0 3 See
Santa Fe Eng'rs v. United States, 801 F.2d 379 (Fed
Cir. 1986) (10% limitation included delay overhead on the
change so contractor was precluded from making a separate
claim for this item); Pipe Installation Co., VABCA 2157, 86-
3 BCA 19055 at 96248 (the Changes clause defined overhead to
include insurance, field and office supervisors and
assistants, incidental job burden, and general home office
expense and effectively limited contractor's recovery to 10%
of direct costs); Jack Cooper Constr., VABCA 1663, 84-3 BCA
17703 at 88,341-42; Gulf-Tex Constr., VACAB 1341, 83-1 BCA
16355 at 81,279-80; Colton Constr., VABCA 1574, 83-1 BCA
16220 at 80,601; West Land Builders, VABCA 1664, 83-1 BCA
16235 (successfully limiting recovery of extended overhead);
Biscayne Constr., GSBCA 3827, 74-1 BCA 10637 at 50,514; J.
Harvy Crow, GSBCA 41423, 75-2 BCA 11423 at 54,389-91; Elec.
& Missile Facilities, GSBCA 2306, 69-2 BCA 7787 (contractor
was denied increased field office overhead and home office
overhead on unchanged work--10% commission fully compensated
contractor); Jack Picoult, GSBCA 2351, 69-1 BCA 7678, aff'd
on motion for reconsid., 69-2 BCA 7820 (successfully limiting
the number of markups on subcontracted work). But see Jervis
B. Webb, PSBCA 420, 78-2 BCA 13544 where the Board allowed
the contractor to recover engineering overhead at 105%, shop
overhead at 303%, and installation overhead at 25% rather
than at the 10% rate specified in the contract. A long
history of prior contracts disclosed the parties' intent that S
202
.° .
i !. -
203
2 0 6 Calculation
of indirect cost rate at 12 million units
Variable indirect costs (12 million units X $1 per unit) $12 million
Fixed indirect costs $20 million
Total indirect costs $32 million
Direct costs (12 million units X $2 per unit) $24 million
Overhead rate ($32 million/$24 million) 133%
2 0 7 Calculation
of the amount of over absorbed indirect cost
1. Amount of indirect cost assigned to the change at the originally projected overhead rate:
2 0 8 Generally,
a contractor is expected to prove its costs
through the best evidence available. Thus, "[tihe preferred
method for establishing the amount of an adjustment is
through the introduction of the actual cost data for the
additional work" (as opposed to estimates). Cibinic & Nash,
supra note 1, at 462. See also ACS Constr., ASBCA 33550,
87-1 BCA 19660 at 99,550; American Elec., ASBCA 15152, 73-1
BCA 9787 at 45,733.
209
Cibinic & Nash, supra note 1, at 514.
2 1 0 Assuming
such costs are not unallowable.
2 1 1 Bruce
Constr. v United States, 163 Ct.Cl. 97, 100, 324
F.2d 516 (1963); J. F. Shea Co. v. United ftatcz, C1I.Ct.
204
2 1 3 Bulloch,
Keller, & Vlasho, supra note 23, at 19.8, point
out that "[iln estimating the impact of a change in activity
on departmental overhead, only the variable component is
considered. The fixed overhead does not change within the
relevant range."
2 1 4 M.
Rishe, supra note 27, at 6-15 (1st ed. 1984), citing
Coley Properties v. United States, 593 F.2d 380 (Ct.Cl.1979).
See supra notes 15 and 16, the cases cited therein, and
accompanying text.
2 15
Underdirect costing only variable manufacturing costs
are allocated to products. To properly keep a contractor
whole, all variable costs, not just manufacturing costs, have
to be recovered. Therefore, "direct costing" as used in this
section is a method of costing that allocates all variable
costs to cost objectives. The concepts of full and direct
costing are discussed at supra Chapter 1, Parts VI.B. and
VI.C.
2 1 6A
profit rate of 10% is often treated as a standard. See
Cibinic & Nash, supra note 1, at 518.
2 17
Assuming
of course that the change did not prevent the
contractor from obtaining work priced at a level permitting
recovery of fixed indirect costs.
205
lop*
* ~~
W ~ %p ~q Saa~V ~ . .~%,
* I !r. a Kr XF V
2 2 2 FAR 31.203(b).
223 FAR 31.203(c).
224
Trueger, supra note 27, at 95-96.
221.at 96.
.
'.."
'I
206S
206
'I.
207 ):
-=.-. i i i ss i i l i iT - " . .. . ..
the additional costs generated during that period.
Extended overhead focuses on the extended period of
contract performance at the end of a project, which
results from delays during performance--and the
additional costs created by extension of the contract
period.
208
other work in the plant to sustain an increased
allocation of the burdens over what would have been
experienced if there had been no delay and disruption.
Id. at 53,089.
2 3 6 See
R. W. Contracting, ASBCA 24627, 84-2 BCA 17302 at
86,219; Switlik Parachute Co., ASBCA 18024, 75-1 BCA 11434
at 54,445:
2 39
See e.g., Excavation-Constr., ENG BCA 3858, 83-1 BCA 16338
at 81,209. See also Fred R. Comb Co. v. United States, 103
Cl. Ct. 174, 184 (1945):
209
2 4 2 Net
under absorption of overhead occurs when delay shifts
work into a later, more active accounting period. Because
production is greater in the later accounting period, the
delayed work will absorb less fixed indirect cost per unit of
production than it would have in the earlier period. In
contrast, net over absorption of overhead occurs when delay
shifts work into a later, less active accounting period.
Because the volume of work is less in the later accounting
period, the delayed work will absorb more fixed indirect cost
per unit of production than it would have in the earlier
period. For a criticism of the concept of over absorbed
overhead see Walters, Capital Electric--Eichleay's Swan Song,
19 Pub. Cont. Newsl. 3, at 12 (Winter 1984).
243
See Capital Elec., GSBCA 5316, 83-2 BCA 16548 at 82,311,
rev'd on other grounds, 729 F. 2d 743 (C.A.F.C. 1984).
2 4 4A
claim for unabsorbed overhead, could be framed as a
claim for extended overhead as well. However because
entitlement to extended overhead has not yet been
authoritatively decided, an assumption is made that a
contractor would attempt to recover unabsorbed overhead
rather than extended overhead if entitlement to unabsorbed
overhead could be proven.
2 4 5 The
Claims Court in Savoy Construction v. United States, 2
Cl. Ct. 338,341-42, rev'd, unpublished decision, Appeal No.
83-1029 (C. A. F. C. 1984), explained it this way:
210
that a contractor should recover extended overhead because
the Government benefits from the extended home office
efforts and that the Government should not get a "free ride"
in the period of contract extension.
211
V - . .' 5 .
248
See e.g., Capital Elec., GSBCA 5316, 83-2 BCA 16548 at
82,311, rev'd on other grounds, 729 F. 2d 743 (C.A.F.C.
1984). Here, in a very thorough and scholarly opinion, the
GSBCA attempted to distinguish unabsorbed and extended
overhead and show why extended overhead was not recoverable.
While the Board easily defined unabsorbed overhead, it was
unable to define the basis of extended overhead. Its
comments were limited to the statement that extended overhead
has as its premise that extending the performance period will
increase overhead costs.
2 4 9 See
Bruce Constr. v. United States, 163 Ct.Cl. 97,100
(1963).
Id. See also supra notes 15-16 and the cases cited therein.
250
"[C]ourts have yet to develop a rationale to support a
recovery, absent an increase in overhead expenditures or
postponement of future work." Note, Home Office Overhead for
Construction Delays, 17 Ga. L. Rev. 761, 774 n.28 (1983).
See also A.C.E.S., INC., ASBCA 21417, 79-1 BCA 13809 at
67,721; Fischbach & Moore Int'l, ASBCA 18146, 77-1 BCA 12300
at 59,224, "It is axiomatic that a contractor asserting a
claim against the Government must prove not only that it
incurred the additional costs making up its claim but also
that such costs would not have been incurred but for the
Government action."
2 5 1 See
e.g., B. J. Lucarelli & Co., ASBCA 8768, 65-1 BCA
4655, at 22,257, where the Board stated:
212
(delay] caused any increase in home office expense, we
do not even reach the question of how to compute the
amount of the increase.
213
:-.-,-
-.
u - , ..-.-.-.
...
.,. .. ,- -.. -... , ....
•..-k' " , -,.-...
,. -',,k ' - k del
home office during such extended period. Eichleay
represents such a method. Id. at 89,354.
214
accounting concept." Accord Braude and Kovars, Extended Home
Office Overhead, Constr. Briefings, No. 84-6, at 2 (June
1984). "Extended overhead is unique to construction
contracting, while unabsorbed overhead is only appropriate to
manufacturing." Accord Capital Elec., GSBCA 5316, 83-2 BCA
16548 at 82,311, rev'd on other grounds, 729 F. 2d 743
(C.A.F.C. 1984). "Extended overhead is a concept unique to
construction contracting. It has as its premise . . . that
extending the performance period will increase overhead
costs." Accord Recovery of Extended Home Office Overhead--
The Latest Chapter, Constr. L. Advisor (June 1984).
2 6 1 See
R.G. Beer Corp., ENG BCA 4885, 86-3 BCA 19012.
Id. at 96,027. -S
2 62
See Kent and Walters, supra note 260, at 12. "A delay, or
suspension of work, generally does not influence [a
construction contractor's] decision to take on additional
projects because--unlike a manufacturing company--a
construction company's ability to take on new work is limited
only by its bonding capacity and the availability of its
managerial personnel." Accord Braude and Kovars, supra note
260, at 2. "[Tlhe construction contractor simply opens up a
new 'plant' at each jobsite on which he works ... .
2 6 3 See
e.g., Stephenson Assocs., GSBCA 6573, 86-3 BCA 19071.
2 6 4 As
distinguished from extended overhead.
2 6 5 Performance of the substituted work maintains the
integrity of the distribution base so there is no unabsorbed
overhead. In contrast, the construction contractor's
distribution base is reduced by the delay resulting in
unabsorbed overhead in that period. However, this unabsorbed
9'
215
LI
overhead will be offset by overabsorbed overhead in the
following period. See supra Chapter 3, Part II.B.2.
2 66
Entitlement
to recovery of any "net" unabsorbed overhead
is discussed at supra note 242 and accompanying text.
2 67
FAR 52.212-12. The Suspension of Work clause is a
mandatory clause for fixed-price construction contracts. It
permits the contracting officer to suspend work for a
reasonable period of time. Under the Suspension of Work
clause, a contractor is entitled to recover only its
increased costs of performance (no profit) for the
unreasonable portion of any delay. See FAR 12.502.
2 6 8 FAR
52.212-13. The Stop-Work-Order clause is an optional
clause for supply, services, and research and development
contracts. It permits the contracting officer to order the
contractor to stop contract performance. Under the Stop-
Work-Order clause, a contractor is entitled to an equitable
adjustment for its increased costs caused by the stop work
order. See FAR 12.503.
2 6 9 FAR
52.212-15. The Government Delay of Work clause is a
mandatory clause for most fixed price supply contracts and
optional for fixed price service contracts. It allows
compensation for delays and interruptions in the contract
work caused by the acts, or failures to act, of the
contracting officer. Under the Government Delay of Work
clause, a contractor is entitled to recover only its
increased costs of performance caused by the delay or
interruption (no profit). See FAR 12.504.
2 7 0 FAR
52.243-4. The Changes clause is a mandatory clause for
fixed-price contracts. It permits the contracting officer to
make changes in the work within the scope of the contract at
any time. Under the Changes clause, a contractor is entitled
to an equitable adjustment for its increased costs of
performance caused by the change. See FAR 43.201(a).
4
2 7 1 FAR
52.236-2. The Differing Site Conditions clause is a
mandatory clause for fixed-price construction contracts when
the contract amount is expected to exceed the small purchase
limitation. It provides an equitable adjustment whenever
subsurface or latent conditions at a site differ materially
from those indicated in the contract or when the contractor
encounters unknown physical conditions at the site, of an
216
eter- er 4
EM
unusual nature, that differ materially from those ordinarily
encountered in work of the type specified in the contract.
Under the Differing Site Conditions clause, a contractor is
entitled to an equitable adjustment for its increased costs
of performance caused by the differing site condition. See
FAR 36.502.
2 7 2 FAR
52.249-2. The Termination for Convenience clause is a
mandatory clause for all fixed-price contracts. See supra
note 17. Under the Termination for Convenience clause,
contractors can recover pre-termination unabsorbed overhead
plus reasonable profit. See infra notes 421-428 and
accompanying text. They also can recover an equitable
adjustment for the increased costs of performing the
unterminated portion of the contract caused by the
termination. Recovery of unabsorbed overhead under partially
terminated contracts is discussed infra notes 547-554 and
accompanying text.
2 7 3 See
e.g., Federal Contracting, ASBCA 28957, 84-2 BCA
17481. Here the contractor was entitled to recover a portion
of its unabsorbed overhead claim under the Differing Site
Conditions clause and a portion under the Suspension of Work
clause--recovery was computed using the Eichleay formula.
Under the Suspension of Work clause, the contractor was
entitled to an adjustment for the unreasonable period of
delay only (7 days of delay were considered reasonable) and
was not entitled to any profit on the amount recovered. In
contrast, the contractor was entitled to an adjustment for
the entire period of delay attributable to the differing site
condition and profit as well.
2 7 4 Cases
permitting recovery of unabsorbed overhead under the
Changes or Differing Site Conditions clause include Savoy
Construction v. United States, unpublished opinion, Appeal
No. 83-1029 (C.A.F.C., Feb 7, 1984); Fortec Constructors v.
United States, 8 Cl. Ct. 490 (1985); Cieszko Construction,
ASBCA 34199, 88-1 BCA 20223 at 102,419; Roberts
Construction, ASBCA 34062, 87-3 BCA 20117; Excavation-
Construction, ENG BCA 3837, 86-1 BCA 18638; E. Patti & Sons,
Inc., PSBCA 1024, 85-2 BCA 18144; Savoy Construction ASBCA
21218, 85-2 BCA 18073; George E. Jenson Contractor, ASBCA
29772, 85-1 BCA 17833; Excavation-Construction, ENG BCA
3851, 84-3 BCA 17646; Federal ContractingASBCA 28957, 84-2
BCA 17482; Therm-Air Manufacturing, ASBCA 16543, 73-1 BCA
9983. For cases permitting recovery of unabsorbed overhead
217 0
pI
I
7 ~ ~~~~~~~~~~~~~~~
a*~~* .{ I, J LU * ~ ~ ~ 'V ~ %lm~'%
-- ~ I, . I n p -
218
H I.,U
2 8 2 Cateret
Work Uniforms, ASBCA 1647, 6 CCF 61561 (1954), at
52,254.
2 83
Allied Materials and Equip. Co., ASBCA 17318, 75-1 BCA
11150 at 53,089-90. This is considered a variation of the
Allegheny method. See Capital Electric, GSBCA 5316, 83-2 BCA
16548 at 82,313, rev'd on other grounds, 729 F.2d 743
(C.A.F.C. 1984).
2 84
See Bedingfield and Wright, supra note 27, at 14-30 to 14-
36.
2 8 5 See
Capital Elec. v. United States, 729 F.2d 743, 744
(C.A.F.C. 1984).
286
See e.g., Berley Indus. v. City of New York, 412 NYS2d
589, 592 (1978). "(T]he mathematical computations under the
'Eichleay formula' produce a figure with at best a chance
relationship to actual damages, and at worst no relationship
at all." (characterizing the daily overhead rate calculated
under Eichleay as a "harsh daily penalty"). Accord Kansas
City Bridge Co. v. Kansas City Structural Steel Co., 317
S.W.2d 370, (1958); General Ins. Co. v. Hercules Constr., 385
F.2d 13 (8th Cir. 1967); W. G. Cornell Co. v. Ceramic Coating
Co., 626 F.2d 990 (5th Cir. 1980); Guy James Constr. v.
Trinity Indus., 644 F.2d 525 (5th Cir. 1981).
2 8 7 Capital
Elec., GSBCA 5316, 83-2 BCA 16548 at 82,315, rev'd
on other grounds, 729 F.2d 743 (C.A.F.C. 1984).
2 8 8 1d. at 82,313-14.
2 8 9 Capital
Elec. v. United States, 729 F.2d 743 (C.A.F.C.
1984).
29 0 1d. at 745-46.
2 9 1 Fred
R. Comb Co. v. United States, 103 Ct.CI. 174 (1945).
29 2
Capital Elec. v. United States, 729 F.2d 743, 746
(C.A.F.C. 1984).
29 3 1d. at 746-47.
219
-.. Me - -. •. - - -:- , - 7 .
2 9 4 Savoy
Constr., ASBCA 21218, 80-1 BCA 14392, motion for
reconsid. denied, 80-2 BCA 14724, aff'd, 2 CI.Ct. 338 (1983),
rev'd, unpublished opinion, Appeal No. 83-1029 (C.A.F.C.
1984).
29 5 1d. at 70,970.
29 6 1d. at 341-42.
297 Excavation-Constr., ENG BCA 3851, 84-3 BCA 17646.
2981d. at 8730.
29 9
See e.g., Irwin, The Return of Eichleay: Is It Here to
Stay? Constr. Claims Monthly, Vol. 6, No. 6 (June 1984)
(stating that the Court failed to address the very real
criticisms of the Eichleay formula and suggesting that the
Eichleay formula will not be around long); McGovern,
Compensating Contractors for Delay-Related Costs, "Hichleay"
After Capital Electric, Cont. Mgmt. J., 14 (Oct. 1984);
Melton, Common Sense About Home Office Overhead--Part I & II,
Constr. Claims Monthly, Vol. 7, Nos. 5 and 6 (May & June
1985).
3 0 0 Bromley
Contractors v. United States, 14 CI.Ct 69, 81
(1987); Fortec Constructors v. United States, 8 Cl.Ct. 490
(1985); Cieszko Constr., ASBCA 34199, 88-1 BCA 20223 at
102,419; Stephenson Assocs., GSBCA 6573, 86-3 BCA 19071;
R.G. Beer Corp., ENG BCA 4885, 86-3 BCA 19012; Ricway, Inc.
ASBCA 30056, 86-3 BCA 19138; G.S. and L. Mechanical and
Constr., DOT CAB 1640, 86-3 BCA 19026; Ricway, Inc. ASBCA
29983, 86-2 BCA 18841; Wickham Contracting, IBCA 1301-8-79,
86-2 BCA 18887; Excavation-Constr., ENG BCA 3837, 86-1 BCA
18638; Don Cherry, Inc., ASBCA 27795, 85-2 BCA 18150; Able
Contracting, ASBCA 27411, 85-2 BCA 27411; E. Patti & Sons,
Inc., PSBCA 1024, 85-2 BCA 18144; Savoy Constr., ASBCA
21218, 85-2 BCA 18073; Worsham Constr., ASBCA 25907, 85-2
BCA 18016; Shirley Contracting, ASBCA 29848, 85-1 BCA 17858,
aff'd on reconsid., ASBCA 29848, 85-2 BCA 18019; George
Hyman Constr., ENG BCA 4541, 85-1 BCA 17847, aff'd, 621 F.
Supp. 898 (D.C.D. 1985); George E. Jenson Contractor, ASBCA
29772, 85-1 BCA 17833; Excavation-Constr., ENG BCA 3851, 84-
3 BCA 17646; Federal Contracting, ASBCA 28957, 84-2 BCA
17482; Vepco, Inc., ASBCA 26993, 84-2 BCA 17255; R. W.
Contracting, ASBCA 24627, 84-2 BCA 17302.
220
221
CHANGES, 394 (1st ed. 1975), 648 (1981 Supplement); R.G. Beer
Corp., ENG BCA 4885, 86-3 BCA 19012 at 96,029-30; Kemmons-
Wilson, Inc., ASBCA 16167, 72-2 BCA 9689 at 45,254-55.
3 08 "In
the construction contract environment there is a
presumption, rebuttable by the Government, that home office
costs are fixed and no reduction to eliminate variable costs
is necessary." R.G. Beer Corp., ENG BCA 4885, 86-3 BCA 19012
at 96,030. See also Salt City Contractors, VACAB 1366, 80-2
BCA 14713 at 72,559; Braude and Kovars, supra note 260, at
7; Nash, supra note 307, at 648.
3 09 1n
addition to other contract work, idle crew members may
perform routine cleaning of tools and other housekeeping
functions, obtain needed training, or take accrued vacation
time- -all necessary for the contractor's continued existence
as a business entity.
3 1 0 5ee
R.G. Beer Corp., ENG BCA 4885, 86-3 BCA 19012 at
96,027.
3 1 1 Several
recent board cases have incorrectly stated that
the Eichleay formula has a built in corrective mechanism to
reflect the extent of other work performed. See George
Hyman Constr., ENG BCA 4541. 85-1 BCA 17847 at 89,354; R.G.
ENG BCA 4885, 86-3 BCA 19012 at 96,028:
Beer Corp., hd.%~
~ hihi~ *'@f*K ~ f%**.',~ * ~ *~~*
(Tihe Eichleay formula has a built-in corrective
mechanism to reflect the extent of other projects
performed during the delay period. To the degree
other work is performed and billed, the billings ratio
denominator is decreased, automatically shifting
overhead costs from the delayed contract to such other
work proportionate to the amount billed.
222
-..
of Technology Library, Wright-Patterson AFB, Ohio, at 120
(Sept. 1985). See also McDonald, Recovery of Home Office
Overhead--A Different Point of View, Constr. Claims Monthly,
Vol. 5, No. 12 (Dec. 1983).
31 3
See Edem, supra note 312, at 120.
3 1 4 See
Able Contracting, ASBCA 27411, 85-2 BCA 18017 at
90,385, where the contractor recovered only half its
unabsorbed overhead as calculated under the Eichleay formula
because the Board found it was capable of doing two jobs at
the same time. "The Government-responsible delay was not
responsible for [the contractor's) failure to obtain other
work." Id.
3 1 5 With
respect to unabsorbed overhead, the presumption is
that the contractor's distribution base is decreased by the
same amount regardless of when during contract performance
the delay occurs or at what time during the year that the
delay occurs. With respect to extended overhead, the
presumption is that a contract receives benefits from home
office costs at a constant rate throughout the contract .
3 1 6 This
criticism of the Eichleay formula was acknowledged 21
years ago in Fullerton Construction, ASBCA 11500, 67-2 BCA
6394 at 29619. The ASBCA held that the Eichleay formula "is
not always an appropriate formula" and refused to apply it to
a delay occurring after substantial completion of the
contract. See also Seckinger & Co., ASBCA 26233, 82-1 BCA
15793.
.4
3 17
See e.g., Worsham Constr., ASBCA 25907, 85-2 BCA 18016.
Here the contractor claimed its "overhead largely was
'incurred' at the beginning of the project rather than evenly
throughout the project because most of the overhead is
expended in setting the job in motion including negotiating
with subcontractors, determining delivery dates, submittals,
scheduling the project, reviewing the plans and
specifications, meetings with the superintendent, site
visits, preconstruction conferences, etc." Id. at 90,365.
Likewise, the end of a construction project often requires
considerable home office attention; final inspection must be
scheduled, punch list items must be monitored, and clean up
efforts must .e made. See Capital Electric--Eichleay's Swan
223
'00 P 0 _F vi N w r r rsp r f
Song? R. Walters, 19 Pub. Cont. Newsl. 3, at 4 (Winter
1984).
3 18
See G.S. and L. Mechanical and Constr., DOT CAB 1640, 86-
3 BCA 19026.
Id. at 96,097-98.
3 1 9 See
supra notes 100-05 and accompanying text.
32 0
See supra note 99 and accompanying text.
3211d".-
3 2 2 For
a discussion of how costs respond to change see supra
notes 108-118.
3 2 3 See
e.g., Allied Materials and Equip., ASBCA 17318, 75-1
BCA 11150 at 53,089, where recovery of unabsorbed overhead
using the Eichleay formula would have allowed a recovery of
$145,915 more than the contractor's actual unallocated
residual manufacturing overhead and G&A expense.
32 4
Note, Home Office Overhead as Damage for Construction
Delays, Ga. L. Rev., 799-809 (1983).
325Id., at 800. See also Therm-Air Mfg., ASBCA 16453, 73-1
BCA 9983 at 46,865.
326 Note, Home Office Overhead as Damage for Construction
Delays, Ga. L. Rev., 804 (1983).
224
i 224
!/
3 3 3 The
reasonable cost of providing the additional home
office services can be determined in the following manner.
Multiply the number of hours worked by each home office
employee to provide the additional services by the employee's
hourly wage rate. Then determine a proportionate share of
other fixed home office costs based on the ratio of home
office labor dollars of the increased administrative effort "5-
to total home office labor dollars of the period. The sum of
the two computations equals reasonable cost.
225
services provided the contract during the period of extension
have been removed therefrom.
(3) Subtract the allocable portion of the indirect cost
grouping as determined in step 1 from that as determined in
step 2 to obtain the adjustment necessary to prevent double
recovery.
3 3 5 Capital
Elec. v. United States, 729 F. 2d 743 (C.A.F.C.
1984).
3 3 6 Savoy
Constr. v. United States, unpublished opinion,
Appeal No. 83-1029 (C.A.F.C. 1984).
3 37The Government Contractor, No. 84-2, 13 (Feb. 1984), after
noting that the Court of Appeals for the Federal Circuit had
reversed Capital Electric and Savoy Construction stated:
"This means that the Eichleay formula is not dead. However,
the circumstances under which it can be applied are not yet
perfectly clear."
3 3 8 Capital
Elec. v. United States, 729 F. 2d 743, 746
(C.A.F.C. 1984).
3 3 9Also
note that the Federal Circuit's decision in Savoy
Construction is an unpublished opinion. See Savoy Constr.
v. United States, unpublished opinion, Appeal No. 83-1029
(C.A.F.C. 1984). Unpublished opinions have no precedential
value.
3 4 0 Capital
Elec. v. United States, 729 F. 2d 743, 746
(C.A.F.C. 1984).
34 1
See supra Chapter 3, Part II.C.2.d.
3 42 See supra notes 304-22 and accompanying text.
3 4 3 G.S.
and L. Mechanical and Constr., DOT CAB 1640, 86-3 BCA a"
"
226
227
3 93
See Sante Fe Eng'rs v. United States, 801 F.2d 379
(C.A.F.C. 1986).
354
GSA has used a clause limiting recovery of overhead on
construction contracts for over 20 years. Only two Federal
agencies have followed GSA's lead--the Postal Service and the
VA. Notably, DOD has not adopted a similar clause.
355
A percentage markup for indirect costs can be at either
the contractor's normal indirect cost rate or at the standard
markup for indirect costs (normally 10% or 15%).
356
See Luria Bros. & Co. v. United States, 177 Ct. Cl. 676,
693 (1966); J. D. Hedin Constr. v. United States, 171 Ct.
Cl. 70, 108 (1965); R. G. Beer Corp., ENG BCA 4885, 86-3 BCA
19012 at 96,031-32; Excavation-Constr., ENG BCA 3837, 86-1
BCA 18638 at 93,669 (crediting the Government with $40,647 of
home office expense already recovered by the contractor as a
percentage markup on direct costs incurred during the delay);
Able Contracting, ASBCA 27411, 85-2 BCA 18017 at 90,386;
Savoy Constr., ASBCA 21218, 85-2 BCA 18073 at 90,723; George
Hyman Constr., ENG BCA 4541, 85-1 BCA 17847 at 89,355, aff'd,
621 F. Supp. 898 (D.D.C. 1985); Excavation-Constr., ENG BCA
3851, 84-3 BCA 17646 at 87,930; R.W. Contracting, ASBCA
24627, 84-2 BCA 17302 at 86,223; Sovereign Constr., ASBCA
17792, 75-1 BCA 11,251 at 53,611; Eichleay Corp., ASBCA
5183, 60-2 BCA 2688, aff'd on reconsid., 61-1 BCA 2894 at
13,576 (a percentage markup on increased direct costs
resulting from the delay was denied as duplicative of
unabsorbed overhead). See also Stephenson Assoc., 86-3 BCA
19071 at 96,354 (to compensate for duplication in overhead
between change orders already priced out by mutual agreement
of the parties and Eichleay unabsorbed overhead allowed by
the Board, profit on the unabsorbed overhead was disallowed).
But see Shirley Contracting, ASBCA 29848, 85-1 BCA 17858, P
228
.q V . p :-P
3 57
The formula used in Cateret Work Uniforms, ASBCA 1647, CCF
61,561 (1954) is one example. Here unabsorbed overhead is
computed by multiplying the excess rate of overhead by total
base costs during the period of delay. Any additional work
performed by the Contractor during the delay will reduce the
excess rate of overhead.
3 58
See supra notes 309-13 and accompanying text.
229
I'-P!. I I..**
'ew*~~~~~~~~~ ~ * .~ L6~a
36 3
FAR 49.201(a). Stated somewhat differently, "the purpose
of a settlement agreement is to make the contractor
'financially whole for all the direct consequences' of the
termination, anticipated profits aside." Tera Advanced
Servs., GSBCA 6713-NRC, 85-2 BCA 17940 at 89,882 (citations
omitted).
3 64 FAR 52.249-2(f) (3) .
365
FAR 49.201(b).
3 6 6 FAR 49.109-7(a).
3 67 FAR 49.109-7 (d).
3 6 8 FAR
49.201(a). "In a given case, various methods may be
equally appropriate for arriving at fair compensation. The
use of business judgment, as distinguished from strict
accounting principles, is the heart of a settlement." Id.
3 69 See Celesco Indus., ASBCA 22460, 84-2 BCA 17264 at 86,162.
37 0
See e.g., Agrinautics, ASBCA 21512, 79-2 BCA 14149 at
69,647-48; Allied Materials and Equip., ASBCA 17318, 75-1
BCA 11150 at 53,085; Bell and Howell Co., ASBCA 18464, 75-1
BCA 10993 at 52,348; Cresent Precision Prods., ASBCA 18705,
74-2 BCA 10898 at 51,870; Algonac Mfg., ASBCA 10534, 66-2
BCA 26,718 at 26,726.
37 1
See e.g., Worsham Constr., ASBCA 25907, 85-2 BCA 18016 at
90,378 (actual audited rate); Hewitt Contracting, ENG BCA
4596, 83-2 BCA 16816 at 83,640-41 (audited rate); Paul E.
McCollum, Sr., ASBCA 23269, 81-2 BCA 15311 at 15,311-12;
Globe Air, Inc., AGBCA 76-119, 78-1 BCA 13079 at 63,877;
Henry Spen & Co., ASBCA 20766, 77-2 BCA 12784 at 62,172
(audited rate); Varo, Inc., ASBCA 16606, 72-2 BCA 9720 at
v 45,395-96; Manuel M. Liodas, ASBCA 12829, 71-2 BCA 9015 at
41,879; Nolan Bros., ENG BCA 2680, 67-1 BCA 6095 at 28,219.
But see Rossen Builders, ASBCA 32305, 87-1 BCA 19538 at
98,727-28 (prior year's G&A rate was used by Government and
accepted by Board in lieu of unsupported rate claimed by
contractor).
3 7 2 Termination settlements because of their complexity and
* because not all costs are known at the time of contract
termination, take time to prepare and negotiate. The
contractor's accounting period normally ends well before a
230
settlement agreement is reached. The cost of safeguarding
and disposing of the terminated inventory is an example of a
cost not knrown at the time of termination.
37 3
See generally supra notes 98-106 and accompanying text.
37 4
Surprisingly, the choice of base period is infrequently
litigated or discussed in Board cases. Chapter 5 argues that
use of the period of contract performance as the base period
rather than the contractor's normal base period is an
inconsistent accounting practice. See infra notes 705-09 and
accompanying text.
37 5
See
Penberthy Electromelt Int'l v. United States, 11
Cl.Ct. 307, 319 (1986) . In Penberthy the Court denied
contractor's use of a four year average G&A base period
holding that the base period "must be a period during which
contract costs are incurred." Id. See also R-D Mounts,
Inc., ASBCA 17422, 75-1 BCA 11077 at 52,741-42 (allowing the
six month base period proposed.by the Government because it
was longer, more representative, and included a portion of
the performance period whereas the base period proposed by
the contractor did not). See also Francis Assoc., ASBCA
14100, 70-2 BCA 8493 at 39,474-76. The contractor
unsuccessfully argued that year ending prior to the period of
contract performance should be the base period used for the
termination because it constituted a fair representation of
normal operations as evidenced by previous acceptance on this
contract and others by the Government. The Government had
audited the indirect cost rates of the prior period and had
approved their use for progress payment purposes for the
terminated contract. Nonetheless, the Board adopted the 18
month period of contract performance as the base period. Use %
231
I
Id. at 90,375
38 2
See FAR 31.205-42(c) (2)
38 3 Id.
38 4
See e.g. Dunbar Kapple, Inc., ASBCA 3631, 57-2 BCA 1448 at
4890. Cf. infra notes 476-77.
232
233
234
V. - ~~ . ~ ~
. ~
*II. . .11I
0 A
direct or indirect but discusses consistency in other
contexts as well.
3 9 1 FAR 31.202(a); FAR 30.402-40.
392
See FAR 31.205-42(c).
3 9 3 The
ASBCA in Kollmorgen Corp., Electro-Optical Division,
ASBCA 18,919, 86-2 BCA 18919 at 95,409-10, declined to decide
the issue of whether CAS 402 precluded direct charging of
time spent on termination settlement activities by in-house
accounting, legal, clerical, and supervisory personnel (G&A
expense pool type costs). The reason for the Board's
refusal was the small dollar amount ($3,879) at stake.
Kollmorgen involved post-termination costs rather than pre-
termination costs, but the issue is similar.
39 4
See supra note 377.
235
,~ .~.
Up, .. r or. C %*%
t~,I 9. - -r . -r 9
%~%U r o rN,
4 0 0 FAR
31.205-42(c) does not specifically allow all initial
costs to be charged directly--only those starting load costs
"not fully absorbed because of termination." FAR 31.205-
42(c) (1) (emphasis added). The language "not fully absorbed
because of tcrmination" evidences an intent to limit direct
charging to instances where the contractor's normal method of
recovering such costs is inequitable.
401
See FAR 52.230-3 and 52.230-5. See infra notes 663-65.
for a discussion of the permissibity of retroactive change in
accounting practice for CAS-covered and modified CAS-covered
contracts.
4 0 2 As
explained in Chapter 4, Part I.A, supra, the overriding
objective of a termination settlement is to compensate a
contractor fairly for its costs of performing and preparing
to perform the terminated contract. Fair compensation rather
than strict accounting principles form the heart of a
termination settlement. See FAR 49.201(a). When necessary
to allow fair compensation boards and courts have allowed
costs that would not be allowable under the cost principles.
See infra notes 444-53 and accompanying text. This principle
should apply by analogy to each of these two clauses.
Further, it is difficult to argue that either of the two
clauses were intended to exclude direct charging of pre-
termination costs that FAR 31.205-42(c) specifically allows.
Finally, the clauses seldom have been used as a basis for
prohibiting retroactive change even when apparently
applicable. See infra note 663.
4 0 3 The
need to remove the direct charge from the indirect
cost pool is obvious to all commentators and to courts and
boards. See e.g., Joseph & O'Donnell, supra note 377, at X-
13. "Clearly the cost reallocated from indirect to direct
must be removed from the overhead pool." See also Robert M.
Tobin, HUD BCA 79-388-C20, 84-3 BCA 17651 at 87,971;
Agrinautics, ASBCA 21512, 79-2 BCA 14149 at 69648; Okaw-
Indus., ASBCA 17863, 77-2 BCA 12793 at 62,235; Allied
Materials & Equip., ASBCA 17318, 75-1 BCA 11150 at 53,087;
Dunbar Kapple Inc., ASBCA 3631, 57-2 BCA 1448 at 4,890. Cf.
Tera Advanced Servs., GSBCA 6713-NRC, 85-2 BCA 17940 at
89,890. "[If we were shown that some of the costs in
appellant's G&A pool were also claimed as settlement costs,
we would disallow them instantly."
4 0 4 FAR
31.203(a). CAS 402 uses slightly different language
but the meaning is identical. See FAR 30.402-40.
236
r r A
i
4 0 5 See
e.g., Alston, supra note 148, at 390; Joseph &
O'Donnell, supra note 377, at X-14; Petit and Victorino,
supra note 377, at 4. But see Bedingfield and Rosen, supra
note 27, at 15-21. As discussed at supra Chapter 4, Part
II.B.3.a, a termination for convenience changes neither the
purpose for which a cost was incurred nor the circumstances
of its incurrence--it changes only the circumstances of its
recovery.
4 06
Note that if this were to happen, the terminated contract
would not be "double" charged, although the term "double
counting" is commonly used to describe this effect. The
amount of cost allocated to the terminated contract, directly
and indirectly, would be less than twice its properly
allocable share. First, the amount charged directly is
subtracted from the indirect cost pool before its
distribution. Second, and more importantly, the amount of
direct cost generated by the terminated contract is probably
small enough that the terminated contract will not pick up a
significant amount of an indirect cost grouping containing
other costs incurred for the same purpose. The reason direct
charging is permitted is that the direct costs of the
terminated contract are such that the contractor's normal
indirect cost rates as applied thereto do not fairly
compensate the contractor. Therefore, although the
terminated contract will be overburdened if costs incurred
for the same purpose are not removed from the indirect cost
pool, the Government will not pay twice the amount properly
chargeable.
4 07
See e.g., Tera Advanced Servs., GSBCA 6713-NRC, 85-2 BCA
17940 at 89,890; General Elec., ASBCA 24111, 82-1 BCA 15725
at 77,802, motion for reconsid. denied, 82-2 BCA 16,207;
Bailfield Indus., Div. of A-T-O, ASBCA 20006, 76-2 BCA 12096
at 58,114-15.
4 0 8 Settlement
costs are not incurred in performance of the
contract but are costs directly .resulting from termination-- ,
costs specifically required by the Termination for
Convenience clause. The CASB has interpreted differing
circumstances to exist under CAS 402 when a cost is incurred
pursuant to a specific requirement of an exiting
* contract. The CASB Interpretation involved bid and proposal
costs required by specific contract provisions--an analogous
situation. See FAR 30.402-61:
237
requirement of an existing contract are considered to
have been incurred in different circumstances from the
circumstances under which costs are incurred in
preparing proposals which do not result from such
specific requirement. The circumstances are different
because the costs of preparing proposals specifically
required by the provision of an existing contract
relate only to that contract while other proposal
costs relate to all the all the work of the
contractor.
4 0 9 Removal
of attorney fees, unrelated to the termination
settlement and otherwise properly includable in the indirect
cost base, is not necessary to prevent double recovery and
would result in the terminated contract not bearing a fair
share of such costs. The pre-termination work benefited from
the incurrence of attorneys' fees in the same general way as
did other cost objectives and for this reason should bear a
proportionate share of such costs. See e.g., Hewitt
Contracting, ENG BCA 4596, 83-2 BCA 16816 at 83,645.
4 10
See supra notes 90-94 and accompanying text.
4 111d.
Instead, machine hours, square footage, number of
employees, or some other factor which more closely
approximates the relative benefits received by the several
cost objectives than direct cost is used.
4 12
See e.g., Sunstrand Turbo, ASBCA 9112, 65-1 BCA 4653 at
22,227; Dunbar Kapple Inc., ASBCA 3631, 57-2 BCA 1448 at
4,895. Compare Agrinautics, ASBCA 21512, 79-2 BCA 14149 at
69647-48 (allowing engineering overhead and G&A on
president's salary reclassified as a direct engineering labor
cost--the Board did not discuss why it allowed the markup for
engineering overhead or G&A--it may have believed that the
President was performing direct cost functions). While
manufacturing overhead on a cost normally classified as
manufacturing overhead or G&A on a cost normally classified
as G&A cannot be recovered, G&A can be recovered on a cost
normally classified as manufacturing overhead which for
purposes of the termination has been reclassified as a direct
cost. See e.g., Allied Materials & Equip., ASBCA 17318, 75-1
BCA 11150 at 53,087-88.
4 13
id. In Sunstrand Turbo, ASBCA 9112, 65-1 BCA 4653 at
22,227, the Board held that the contractor could not recover
additional G&A allowance on costs of a general and
238
..
. .. .. . . . . .. . ." ,,7a , , '" .. . .. . . . ... . ..
."N'.N
administrative nature for which it was reimbursed directly
reasoning as follows:
419 Id.
239
S
42 1
Pre-termination unabsorbed overhead should be
distinguished from post-termination unabsorbed overhead
which is no- allowable. Entitlement to post-termination
overhead is discussed infra Chapter 4, Part V.
42 2
See e.g., Worsham Constr., ASBCA 25907, 85-2 BCA 18016 at
90,362. The Board excluded subcontract costs of the
terminated contract from "billings" and "total billings" when
computing Eichleay damages. Subcontract costs were excluded
to prevent over recovery of home office costs. The cause of
the Board's concern was the contractor's failure to establish
the degree to which the subcontract had benefited from home
office costs. The Board had already allowed home office
costs to be applied to the subcontract but at 50% of the
contractor's normal rate. The Board was concerned that
inclusion of subcontract costs in the Eichleay formula
"billings" would result in the contractor's being
overcompensated for home office costs with respect to the
subcontract. See also Marlin Assoc., GSBCA 5663, 82-1 BCA
15,738 at 77,881(finding that Eichleay formula "total
billings" included the Board's award for completed work,
termination inventory, labor, subcontractor work, overhead,
and profit; and excluded settlement preparation costs).
42 3
See e.g., Worsham Constr., ASBCA 25907, 85-2 BCA 18016 at
90,362; Marlin Assoc., GSBCA 5663, 82-1 BCA 15,738 at
77,881; Racquette River Constr., ASBCA 26486, 82-1 BCA 15769
at 78,053; Agrinautics, ASBCA 21512, 79-2 BCA 14149 at
69,648-49; A.C.E.S., INC., ASBCA 21417, 79-1 BCA 21417 at
67,722; Allied Materials & Equip., ASBCA 17318, 75-1 BCA
11,150 at 53,089-90.
4 2 4 See
Worsham Constr., ASBCA 25907, 85-2 BCA 18016 at
90,369.
4251d"
426 Id"
240
Remedies, 11 Pub. Cont. L. J. 269, 278 (1980); Cibinic &
Nash, supra note 1, at 795; Joseph & O'Donnell, supra note
377, at X-5; W. KEYES, GOVERNMENT CONTRACTS UNDER THE FEDERAL
ACQUISITION REGULATION, 725 (1986); Halifax Eng'g, ASBCA 34779,
88-1 BCA 20,227 at 102,430; Fiesta Leasing and Sales, ASBCA
29311, 87-1 BCA 19622 at 99,292; Worsham Constr., ASBCA
25907, 85-2 BCA 18016 at 90,369; Robert M. Tobin, HUD BCA
79-388-C20, 84-3 BCA 17651 at 87,970; Racquette River
Constr., ASBCA 82-1 BCA 15769 at 78,051; Paul E. McCollum,
Sr., ASBCA 23,269, 81-2 BCA 15311 at 75,822; Southland Mfg.,
ASBCA 16830, 75-1 BCA 10994; International Space Corp.,
ASBCA 13883, 70-2 BCA 8519; Caskel Forge, Inc.; ASBCA 7638,
1962 BCA 3318.
4 3 0 Determining
costs incurred in performance of the
terminated contract is a major issue in most fixed priced
settlement negotiations. In contrast, when a cost-
reimbursement contract is terminated, establishing what
performance costs were incurred is seldom a problem. See
Andrews and Peacock, supra note 429, at 277. The reason is
that the Government will not issue a cost reimbursement
contract to a contractor whose accounting system is incapable
of tracking costs. See FAR 16.301-3(a). See also Rishe,
supra note 27.
Id. at 6-43. See also Algonac Mfg., ASBCA 10534, 66-2 BCA
5731 at 26,724. "This settlement would have been made much
more easily if appellant's books had been kept in conformity
with the regulations and forins of the Government concerning
termination settlements. They were not, however, and there
was not reason nor requirement that they should be." Id.
4 3 1 See
Trueger, supra note 27, at 738. "Terminations cause
unique accounting problems. All cost accounting systems rely
on assumptions of normality and continuity." See also
Alston, supra note 148, at 387; Bedingfield and Rosen, supra
note 27, at 15-11.
43 2
"Terminations are aberrations." Bedingfield and Rosen,
supra note 27, at 15-11.
241
~ "r~%
4
q~w ~ ~ ~ ~ '.4'\ ~ ..*..~ -~ ~ . - . ~ 4or
4 3 3 Bedingfield
and Rosen, supra note 27, at 15-13. See also
Trueger, supra note 27, at 729. Paul Trueger comments: "If
most [preparatory] expenses are generally charged to overhead
accounts, without segregation by contract, there may be
considerable difficulty in finding and supporting their
applicability to the satisfaction of the government auditors.
Somewhat similar problems obtain with respect to starting-
load costs. .. ." Id. at 761.
4 34
See Rishe, supra note 27, at 6-23; Joseph & O'Donnell,
supra note 377, at X-12. Maintenance of such a system on the
outside possibility that the Government will terminate a
contract for convenience is not economically sound. See
e.g., Racquette River Constr., ASBCA 82-1 BCA 15769 at 78,050
(books consisted of a cash receipts journal, cash
disbursements journal, and a general journal--common among
small contractors in Northwest Florida); Metered Laundry
Serv., ASBCA 21573, 78-2 BCA 13451 at 64,601 (ledger did not
even allocate costs to particular jobs because doing so could
not be cost justified); Starks Contracting, VACAB 1339, 79-2
1448 at 68,847-48 (contractor's books not oriented towards a
cost system).
435
FAR 49.206-1(c).
4 3 6 See
Arctic Corner, Inc. VABCA 2393, 86-3 BCA 19278 at
97,456-57 ("while comprehensive documentation" is not
required the contractor "still must meet the burden of
proving the costs were incurred and offer some explanation as
to just how those costs were treated (direct or indirect) in
its normal business operation"). See also Tagarelli Bros.
Constr., ASBCA 34793, 88-1 BCA 20363 at 102,989; Humphrey
Logging Co., AGBCA 84-359-3, 85-3 BCA 18433 at 92,572; H&H
Reforestation, AGBCA 84-311-3, 85-3 BCA 18255 at 91,637;
Tera Advanced Servs., GSBCA 6713-NRC, 85-2 BCA 17940 at
89,883-84; Celesco, Indus., ASBCA 22460, 84-2 BCA 17295 at
86,160; R.G. Robbins & Co., ASBCA 27516, 83-1 BCA 27516 at
81,692; Paul E. McCollum, Sr., ASBCA 23,269, 81-2 BCA 15311
at 75,822; Allied Materials and Equip., ASBCA 17318, 75-1
BCA 11150 at 53,085; Dairy Sales Corp., ASBCA 21193, 75-2
BCA 11613 at 55,455, aff'd, 219 Ct. Cl. 431 (1979); Clary
Corp., ASBCA 19274, 74-2 BCA 19247 at 52,103.
4 37
FAR 49.206-1(c).
4 3 8 See
e.g., R-D Mounts, Inc., ASBCA 17422, 75-1 BCA 11077 at
52,744, aff'd on motion for reconsid., (disallowing 10%
242
243
y- -
proprietor's settlement claim, the Board assumed that the
contractor had included overhead cost in the $27 cost per
labor hour apparently used in computing its fixed price bid.
Therefore, a termination settlement based upon this $27 per
hour figure adequately compensated contractor for its
indirect costs. See also Andrews and Peacock, supra note
429, at 278; Rishe, supra note 27, at 6-46; Petit and
Victorino, supra note 377, at 5. To protect the Federal
purse, the Government closely reviews termination settlements
to ensure that the costs claimed are adequately supported.
Cost proposals of $25,000 or more are submitted to the
appropriate audit agency for audit. See FAR 49.107(a).
244
-a- J% J J!P . 7r
4 4 9 For
example, costs incurred before contract award are not,
except in limited circumstances, allowable under the Cost
Principles. See Codex Corp., ASBCA 17983, 75-2 BCA 11554 at
55,154, rev'd on other grounds, 226 Ct. Cl. 693 (1981).
4 5 0FAR 49.113 (emphasis added).
4 5 1 "A
settlement should compensate the contractor fairly for
the work done and the preparations made for the terminated
portions of the contract. . . . Fair compensation is a matter
of judgment. . . The use of business judgment, as
distinguished from strict accounting principles is the heart
of a settlement." FAR 49.201(a).
4 5 2 See
Codex Corp. v. United States, 226 Ct. Cl. 693 (1981);
Fiesta Leasing and Sales, ASBCA 29311, 87-1 BCA 19622 at
99,292; Arctic Corner, Inc. VABCA 2393, 86-3 BCA 19278 at
97,456-57; Huskie Oil NPR Operations, IBCA 1792, 86-1 BCA
18568; H &H Reforestation, AGBCA 84-311-3, 85-3 BCA 18,255
at 91.637: Kalser Elec., DOTCAB 1425, 84-2 BCA 17343;
Celesco Indus., ASBCA 22460, 84-2 BCA 17295 at 86,162;
General Elec., ASBCA 24111, 82-1 BCA 15,725 at 77,803, motion
for reconsid. denied, 82-2 BCA 16,207; Marlin Assoc., GSBCA
5663, 82-1 BCA 15738 at 77,876; American Elec., ASBCA. 16635,
76-2 BCA 12151 at 58,512-13. But see Allied Materials and
Equip., ASBCA 17318, 75-1 BCA 11150 at 53,084 (Cost
Principles were not "guide" but mandatory for Board); Big
Three Indus., ASBCA 16949, 74-1 BCA 10,483 at 49,593-94 (Cost
Principles mandatory).
453
Bedingfield and Rosen, supra note 27, at 15-7, comment
that the Cost Principles will be applied except in very
limited circumstances. They credit changes in the Cost
Principles and the increasing influence of DCAA for this
result. See e.g., Penberthy Electromelt Int'l v. United
States, 11 Cl. Ct. 307, 319 (1986). Court did not use the
overhead rates which best reflected the average overhead
costs of contractor. "[P]laintiff's concept of 'equity'
flies squarely in the face of the principle of cost
allocability." Id.
4 54
FAR 49.207.
4551d".
4 5 6A
constructive change occurs when a contractor performs
work beyond the contract requirements without a formal change
245
order and such work was informally ordered by the Government
or caused by Government fault. See Cibinic & Nash, supra
note 1, at 304-5.
4 57 A
differing site condition exists when (1) subsurface or
latent physical conditions at the site differ materially from
those indicated in the contract or (2) unknown physical
conditions, of an unusual nature, differing materially from
those ordinarily encountered and generally recognized as
inhering in work of the character provided for in the
contract, are encountered. See FAR 52.236-2 and Cibinic &
Nash, supra note 1, at Chapter 5.
4 5 8 Normally,
it is the Government and not the contractor who
is concerned that costs properly characterized as settlement
costs are not claimed as performance costs. The reason is
twofold. First, profit is allowed on costs of performance
but not on settlement costs. Second, FAR 31.205-42(g) limits
the indirect cost markup applied to settlement costs.
246
4 67
See Rishe, supra note 27 at 6-52; Trueger, supra note 27
at 757-58. But see Detroit Diesel Allison Div., General
Motors Corp., ASBCA 20199, 77-1 BCA 20199 at 60,115,
(disallowing severence pay as a direct cost because the
contractor's established accounting practice was to recover
abnormal as well as normal separation costs through
overhead).
468But see Systems Dev., ASBCA 16947, 73-1 BCA 9788 (allowing
G&A on severance pay).
4 6 9 See
FAR 49.104 and FAR 52.249, Termination for Convenience
of the Government (Fixed-Price), paras. (b) through (d).
470 Id.
471
See FAR 49.207.
47 2
See FAR 52.249-4. See also Maibens, Inc., ASBCA 25915,
82-1 BCA 12668 at 77,478-79; Mrs. Landscaping and Nursery,
HUD BCA 76-29, 78-1 BCA 13077 at 63,860-61; American Maint.
and Mgt Servs., ASBCA 19556, 76-2 BCA 11,960 at 57,341;
Contract Maint., ASBCA 21186, 76-2 BCA 12,102 at 58,143. The
short-form termination for convenience clause allows recovery
for zervices rendered before the effective date of
termination only. It is included in service contracts when
it is anticipated that the only claim made would be for
services rendered prior to termination if the contract were
terminated for convenience. The boards have shown some
willingness not to enforce the provisions of the clause when
doing so would deny fair compensation to the contractor. See
*Tefft, Kelly and Motley, Inc., GSBCA 6562, 83-1 BCA 16177 at
80,388.
47 3 FAR 49.202(a).
247
costs in indirect cost groupings distributes a portion of
such costs to the terminated contract through allocations to
the pre-terminated work. However, such distribution is not
proportional to the relative benefits received from the
indirect cost grouping by the terminated contract. But see
Fiesta Leasing and Sales, ASBCA 29311, 87-1 BCA 19622 at
99,292. In Fiesta Leasing, the Board disallowed, as a direct
settlement cost, a salaried employee's time spent in
preparation and presentation of the settlement proposal
reasoning that no additional employees were hired to free him
from performance of his normal duties--therefore, his salary
was recoverable through G&A and not as a direct cost. The
Board limited direct recovery to incremental costs only. See
also infra note 489 and accompanying text where Bedingfield
and Rosen suggest a one time special indirect cost allocation
as an alternative to direct charging. d
47 6
See
e.g., Fiesta Leasing and Sales, ASBCA 29311, 87-1 BCA
19622 at 99,295 (disallowing direct recovery of utility,
computer and copy expense and of office rental and painting
in the absence of proof that an adjustment to overhead was
made to prevent double counting); Bob Tucker and Assoc., LBCA
83-BCA-16, 86-2 BCA 18990 at 95,902 (disallowing accounting,
supplies, and telephone services charged as direct costs
because they may have been included in contractor's indirect
cost rate; finding it reasonable for the contractor to
produce documents evidencing their specific authorization as
a direct cost and subsequent removal from the indirect cost
grouping); Celesco Indus., ASBCA 22460, 84-2 BCA 17295 at
86,167-68; Marlin Assoc., GSBCA 5663, 82-1 BCA 15738 at
77,880 (labor costs of manager and president were included in
overhead and therefore could not be charged directly as a
mobilization cost); Bermite Div. of Tasker Indus., ASBCA
18280, 77-1 BCA 12349, aff'd on motion for reconsid., 77-2
BCA 12731 at 61,883 (disallowing employee salary expense that
had been included in G&A). Boards have allowed direct
recovery of costs included in an indirect cost grouping on
occasions where such costs make up only a small and
insignificant amount of the indirect cost grouping or where
the factual pattern is such that duplicate recovery is not
present. See Celesco Indus., ASBCA 22460, 84-2 BCA 17295 at "A
86,167-68.
4 7 7 1n
Bermite Div. of Tasker Industries, ASBCA 18280, 77-1
BCA 12349, aff'd on motion for reconsid, 77-2 BCA 12731 at
61,883, the double recovery threat was stated as follows:
248 p
Expenses carried as an element of G&A are assumed to
be recovered in the year they are incurred and
recorded, absent persuasive evidence to the contrary,
and this recovery is derived from the totality of the
contractor's then on-going business. Expenses so
recorded and presumably recovered cannot
retrospectively be removed from the indirect expense
pool. Such 'relief' can be done only prospectively,
i.e. before the expenses are recorded or, more
importantly, before they are allocated to and
recovered from the on-going business. In a situation
such as is present here, we are faced with recovery
which has already taken place. Thus, we are not
concerned with 'relieving the G&A pool'
retrospectively but we are concerned with and faced
with the fact that recovery as a direct settlement
expense now would result in double recovery of these
expenses.
47 8
See infra notes 490-97 and accompanying text.
249
4 8 3 The
relationship of the settlement action to indirect cost
groupings differs from that of other cost objectives. For
example, a termination action usually benefits much more from
the incurrence of attorney and accounting costs than do other
cost objectives. Also it benefits less than other cost
objectives from the incurrence of certain indirect costs.
'[N]ormal factory burden cannot be applied to settlement
expense direct labor. To do so would allocate depreciation
on factory machinery to a nonproducing cost objective."
Bedingfield and Rosen, supra note 27, at 15-26. 4,
.4
4 84
"Settlement expenses including the following, are
generally allowable . . . (iii) Indirect costs related to
salary and wages incurred as settlement expenses . .
normally, such indirect costs shall be limited to payroll
taxes, fringe benefits, occupancy costs, and immediate
supervision costs." FAR 31.205-42(g) (iii) (emphasis added).
4 8 5 See
Celesco Indus., ASBCA 22460, 84-2 BCA 17295 at 86,166-
68 (direct manufacturing labor was allocated normal indirect
costs--labor of indirect employees was allocated only fringe
benefits); Essex Electro Eng'rs, DOT CAB 1025, 81-1 BCA
14838 at 73,247, aff'd on motion for reconsid., 81-1 BCA
73,251 (adding normal indirect burden to direct labor costs
of assembling the residual inventory for storage); Okaw
Indus., ASBCA 17863, 77-2 BCA 12793, at 62,229 (normal
overhead and G&A allowed on post-termination packaging);
Thiokol Chem., ASBCA 17544, 76-1 BCA 11731 at 55,933-39
(adding normal indirect burden to direct labor required to
shut down activities, to conduct final audit, and to
negotiate a settlement agreement); Condec Corp., ASBCA
14324, 73-1 BCA 9808 at 45,844; Varo, Inc., ASBCA 16606, 72-
2 BCA 9720 at 45,396 (although not convinced the contractor
was entitled to one-half its normal burden on settlement
costs, the Board was hesitant to question the contracting
officer's decision allowing it); Boeing Co., ASBCA 12685,
69-2 BCA 7795 (allowing direct settlement labor to be
burdened with an indirect cost rate developed specifically
for special service work orders--only indirect costs related
to special service work orders were included in the indirect
cost grouping). In a number of cases the board has, without
discussion, allowed recovery of indirect costs at the
contractor's normal indirect cost rates. See e.g., Penberthy
Electromelt Int'l v. United States, 11 Cl. Ct. 307, 327
(1986) (allowing G&A on time spent by settlement negotiator);
Agrinautics, ASBCA 21512, 79-2 BCA 14149 at 69,648 (allowing
manufacturing overhead and G&A); Allied Materials and
25
250
CVd. C. W
C.C. .., U.... W..
Equip., ASBCA 17318, 75-1 BCA 11150 at 53,084 (allowing
indirect expense and G&A).
4861d. See Okaw Indus., ASBCA 17863, 77-2 BCA 12793 at
62,229. "The nature of the work was such that we believed in
order to adequately to compensate the appellant for the work
performed it would be inappropriate not to allow the
appellant's overhead and G&A in effect during the post-
termination period."
4 87
See supra note 485-86.
4 8 8 See
Bedingfield and Rosen, supra note 27, at 15-28.
489 1d.
490 See supra note 436-43 and accompanying text.
491 See Petit and Victorino, supra note 377, at 2. Failure of
proof is a common cause of disallowance. See Acme Process
Equip. v. United States, 171 Ct. Cl. 251, 313-14 (1965), (no
breakdown or justification--allowing only 440 of the 1332
hours claimed); Arctic Corner, Inc., VABCA 2393, 86-3 BCA
19278 at 97,459-60 (in the absence of probative documentation
allowing $1,356 of $12,900 claimed); Worsham Constr., ASBCA
25907, 85-2 BCA 18016 at 90,367 and 90,378 (in the absence of
documentation allowing only 80 of 280 hours claimed in
connection with post-termination settlement action;
disallowing indirect costs related to salaries and wages
incurred as settlement expenses because the contractor failed
to put on evidence of such costs); Racquette River Constr.,
ASBCA 82-1 BCA 15769 at 78,054 (no records--limiting recovery
ato what the Government had allowed); Chesterfield Assoc.,
DOT CAB 1028, 80-2 BCA 14580 at 71,900 (no documentation,
jury verdict allowed $450--63 page settlement proposal);
Henry Spen & Co., ASBCA 20766, 77-2 BCA 12784 at 62,178-83
(lack of documentary foundation--allowing of hours claimed
for: president 272 of 848 hours, vice-president 184 of 750
hours, sales engineer 40 of 302 hours, production engineer 64
of 345 hours, purchasing agent 160 of 1,014 hours, original
contract administrator 150 of 656 hours, successor contract
administrator 368 of 1,863 hours); H & J Constr., ASBCA
18521, 76-1 BCA 11903 at 57,085 (unsupported claim--allowing
$1500 of $35,607.64 claimed); Bell and Howell Co., ASBCA
18464, 75-1 BCA 10993 at 52,348 (settlement costs
unsupported--allowing $250 of $3,909 claimed); Clary Corp.,
ASBCA 19274, 74-2 BCA 19247 (allowing $231.70 of $4,339 of
costs claimed--no accounting records--proof consisted of
251
- -
-31,
- 6%
- '.
% %j~%
" " " "'."" '. "J.." J ", " ." " % - " k" '- " " " -- - -"--- .
.4-
estimates); Francis Assoc., ASBCA 14100, 70-2 BCA 8493 at
39,477 (lack of records--allowing $5,411 of the $42,126.31
claimed); Dunbar Kapple Inc., ASBCA 3631, 57-2 BCA 1448 at
4,895. But see Codex Corp., ASBCA 17983, 74-2 BCA 10827,at
51,499 (allowing all of $2825 claimed--costs were supported
by affidavits of persons concerned); Dunbar Kapple Inc.,
ASBCA 3631, 57-2 BCA 1448 at 4,897-98 (allowing all time
claimed in preparation of termination claim based on
estimates).
49 2
See Alston, supra note 148, at 390. "Contractors must
abandon their usual accounting methods for the allocation of
indirect costs. They must directly identify all the cost
elements concerned . . . to ensure that they will recover all
the expenses incurred." See also Bedingfield and Rosen,
supra note 27, at 15-26; Trueger, supra note 27, at 765-66.
493
See Petit and Victorino, supra note 377, at 5.
4 9 4 Note
that FAR 31.205-42(g) (iii), in effect, mandates
direct recovery of settlement costs. See supra notes 474-89
and accompanying text.
4 9 5 Normally,
a contractor's accounting system is not -et up'
to segregate and specifically identify indirect costs to any
one cost objective. FAR 31.205-42(g) (2) requires
establishment of a cost account or work order to separately
identify and accumulate settlement costs when settlement
expenses are expected to be significant.
4 9 6 Contractors
should be prepared to negate the possibility
of double charging. "Salaries of personnel preparing the
termination claim may be unallowable as direct charges to the
terminated contract, where they are included in the
contractor's general and administrative expense pool and
charged on a prorated basis to ongoing business, if the
evidence is insufficient to negate possible double counting."
Andrews and Peacock, supra note 429, at 288 (citing Bermite
Div., Tasker Indus., ASBCA 18280, 77-1 BCA 12349).
4 9 7 Petit
and Victorino, supra note 377, at 5, comment:
252
,-
253
appears probable that the decisions are influenced, at least
in part, by disbelief that the contractor spent the number of
hours claimed preparing its settlement proposal. See e.g.,
Celesco Indus., ASBCA 22460, 84-2 BCA 17295, at 86,166
(finding a lack of supporting documentation or testimonial
evidence); Clary Corp., ASBCA 19274, 74-2 BCA 19247, at
52,102 (finding the claim unsupported); Bailfield Indus.,
ASBCA 20006, 76-2 BCA 12096 (finding the number of hours high
but not excessive--good records).
5 0 3 The
boards of contract appeals find it unreasonable to
have professional or executive personnel perform clerical
work and limit reimbursement accordingly.
5 04 See Celesco Indus., ASBCA 22640, 84-2 BCA 17295 at 86,165.
5 0 5 See
FAR 31.205-34(d): "Costs of legal, accounting, and
consultant services and directly associated costs incurred in
connection with . . . the prosecution of claims or appeals
against the Government . . . are unallowable" The
proscription is not limited to outside services but includes
any cost incurred in prosecuting a claim against the
Government including management and clerical costs. See
e.g., American Elec., ASBCA 16635, 76-2 BCA 12151, at 58,501-
02; Bailfield Indus., ASBCA 20006, 76-2 BCA 12096 at 58,103;
Lieb Bros., ASBCA 10007, 74-1 BCA 10509; Frigitemp Corp.,
VABCA 646, 68-1 BCA 6766; Q.V.S., Inc., ASBCA 7513, 1963 BCA
3699.
506
"When allowable and unallowable claimed costs are
commingled and there is not sufficient proof to segregate the
allowable from the unallowable, the entire claim must be
rejected." Paul E. McCollum, Sr., ASBCA 23,269, 81-2 BCA
15311 at 75, 824, aff'd, 6 Ct.Cl. 373, 380 (1985).
507" [It is the responsibility of an appellant seeking to
recover legal expenses allegedly incurred in the settlement
of a terminated contract to separate legal fees into proper
categories or show some reasonable basis for separating
settlement charges from charges for other work." Henry Spen
& Co., ASBCA 20766, 77-2 BCA 12784 at 62,187. See Nolan
Bros. v. United States, 194 Ct. Cl. 1, 36-37, 437 F.2d
1371(1971); H &H Reforestation, AGBCA 84-311-3, 85-3 BCA
18,255 at 91,640 (disallowing $750 consultant fee because it
was unclear whether or not the fee was incurred in litigation
of a claim against the Government); Robert M. Tobin, HUD BCA
79-388-C20, 84-3 BCA 17,651 at 87,971 (denying all settlement
preparation costs because contractor failed to explain the
254
nature and purpose of costs claimed); A-American, Inc.,
ASBCA 28823, 84-2 BCA 17479 at 87,088 (allowing only $500 of
$8000 in legal fees claimed because the Board was unable with
reasonable assurance to determine the amount of effort
expended by the legal firm in settlement of the termination
claim); R.G. Robbins & Co., ASBCA 27516, 83-1 BCA 27516 at
81,693; Contract Maint., ASBCA 20689, 77-1 BCA 12446 at
60,294; Cyro-Sonics, Inc., ASBCA 13219, 70-1 BCA 8313 at
38,658 (in the absence of an explanation as to why they were
incurred accounting fees were considered as incurred in the
prosecution of a claim against the Government); Western
States Painting, ASBCA 13843, 69-1 BCA 7616 at 35,375
(denying recovery of all legal fees for failure to properly
segregate the legal costs of preparing and presenting the
settlement proposal to the contracting officer from those of
making a claim against the Government); Algonac Mfg., ASBCA
10534, 66-2 BCA 5731 at 26,729 (allowing only $10,000 of
$275,000 claimed for legal, accounting, and clerical
expenses--not shown to relate to preparation or negotiation
of the settlement agreement).
5 08 See Bailfield Indus., ASBCA 20006, 76-2 BCA 12096.
Id. at 58,104. See e.g., Kalvar Corp. v. Unites States, 211 'V
L"
255
*** -: 1F WI X W I r -
256
p. -.. _ . . 4 '
. . -' ... - . . . * ' ? ..
" . . -.. . . . '- "
I p l
257
contractor fairly for the work done and the preparations
made for the terminated portions of the contract including a
reasonable allowance for profit. . . ." (emphasis added).
Unabsorbed overhead, like anticipatory profits, represents an
opportunity cost and is neither work done nor preparations
made for the terminated portion of the contract.
5 2 0 Joseph
and O'Donnell quote UCC Section 2-708(2) for this
proposition:
258 '"
N,..
5 2 5 The
regulatory objective of fair compensation may not be
as broad as Joseph and O'Donnell assert. FAR 49.201(a) reads
"A settlement should compensate the contractor fairly for
the work done and the preparations made for the
terminated portions of the contract. . . ." (emphasis added).
The regulations do not state as a goal nor define fair
compensation in terms of putting the contractor in the same
position it would have been in had the contract not been
terminated. Recovery of anticipatory profits would be
necessary to put the contractor back in the position it would
have been in but for the termination. Nonetheless, the
regulations expressly prohibit anticipatory profits. See FAR
49.202(a).
". ~. - V. N~r~~,;qw
N -. ' ~
* 5 N* N. ,
259
530Or as Paul Trueger would put it for a "reasonable" period
of time after contract termination. See supra note 27, at
756.
5 3 1 See
Note, Home Office Overhead for Construction Delays, 17
Ga. L. Rev. 761, 765 at note 15 (1983). Reasearch conducted
by the author of the Note discloses that when computing lost
profits most state courts characterize fixed overhead as a
deductible cost of performance and, therefore, have not
allowed its recovery.
53 21d. at 764-68. Unabsorbed overhead is convincingly
analogized to lost profits. At footnote 15, the author cites
Vitex Manufacturing Corp. v. Caribtex Corp., 377 F.2d 795,798
(3 Cir. 1967): "Although there is authority to the contrary,
we feel the better view, is that normally, in a claim for
lost profits, overhead should be treated as a part of gross
profits and recoverable as damages, and should not be
considered as part of the seller's costs." The Uniform
Commercial Code also defines lost profit to include
unabsorbed fixed overhead. See UCC 2-708(2), quoted at supra
note 520. Thus, arguably unabsorbed overhead after contract
termination is unallowable as anticipatory profit.
53 3
See Metadure Corp., ASBCA 21183, 83-1 BCA 16208 at 80,536.
534 See Trueger, supra note 27 at 757-58. See also Rishe,
supra note 27, at 6-52. "[A]lthough the costs of unabsorbed
overhead . . . normally are unallowable in a terminaticn
settlement, normal cost components of unabsorbed overhead may
be recoverable if separately identified and proven to be
continuing costs of the termination. Id. (citing Chamberlain
Mfg., ASBCA 16877, 73-2 BCA 10139 and Technology, Inc.,
ASBCA 14083, 71-2 BCA 8956).
53 5
Trueger, supra note 27, at 758.
5 3 6 See
Andrews and Peacock, supra note 429, at 288; Rishe,
supra note 27, at 6-64.
5 3 7 1t
is sometimes difficult to determine the amount of the
original contract price applicable to the terminated
contract. See Ideker, Inc., ENG BCA 4389, 87-3 BCA 20145 at
101,982-84. For purposes of illustration assume that one of
several separately priced line items is terminated. Reducing
;h%:.ntract price by the unit price of the terminated line
item may not be appropriate if the line items are not of
260
average profitability. For example, assume an item costing
$1000 direct labor and $250 in indirect costs were deleted
from the contract under a partial termination for
convenience. Reduction of the contract price by item's unit
price of $1000 is improper. The contract price should be
reduced by $1250 plus reasonable profit (assuming the
contract as a whole is profitable). Further, in some
instances, the work terminated will be part of a lump sum
bid. To determine the amount by which the contract price
should be reduced the parties may have to estimate the direct
costs of performing the terminated work, the indirect cost
markup and reasonable profit on the terminated work.
5 38
See Alston, supra note 148, at 389; Andrews and Peacock,
supra note 429, at 294; Bedingfield and Rosen, supra note
27, at 15-20.
5 39
See e.g., Marlin Assoc., GSBCA 5663, 82-1 BCA 15738 at
77,873.
54 0
FAR 49.104(d) and FAR 52.249-2(k).
5 4 1 SeeVaro,
Inc., ASBCA 16606, 72-2 BCA 9720 at 45,393;
Continental Elec, Mfg., ASBCA 14749, 71-1 BCA 9108 at 42,206.
5 42 See
Seirracin/Sylmar, ASBCA 27531, 85-1 BCA 17875 at
89,551-52; Capital Elec., GSBCA 5300, 81-2 BCA 15281 at
75,679-80; Celesco Indus., ASBCA 21928, 81-2 BCA 15260;
Varo, Inc., ASBCA 16606, 72-2 BCA 9720 at 45,396;
Continental Elec., Mfg., ASBCA 14749, 71-1 BCA 9108 at
42,208; International Aircraft Servs., 65-1 BCA 4793.
5 4 3 See
Varo, Inc., ASBCA 16606, 72-2 BCA 9720 at 45,394-95
(finding that nonrecurring tooling costs of $10,503 were
absorbed by 135 units rather than the 200 units called for in
the original contract).
5 4 4 See
e.g., Celesco Indus., ASBCA 22640, 84-2 BCA 17295 at
86,164; Askenazy Constr., HUD BCA 78-2, 78-2 BCA 13402 at
65,526; Henry Spen & Co., ASBCA 20766, 77-2 BCA 12784 at
62,178-83; American Maint. and Mgt Servs., ASBCA 18348, 74-2
BCA 18348; Dunbar Kapple Inc., ASBCA 3631, 57-2 BCA 1448 at
4,883-84.
5 4 5 Computation
and use of learning curves are discussed in
the Armed Services Pricing Manual, supra note 24, at 3-28 to
3-29.
261
I
54 6
See e.g., Seirracin/Sylmar, ASBCA 27531, 85-1 BCA 17875 at
89,552 (adding both manufacturing burden and G&A); Capital
Elec., GSBCA 5300, 81-2 BCA 15281 at 75,679-80; Bermite Div.
of Tasker Indus., ASBCA 18280, 77-1 BCA 12349 at 59,762,
afff'd on motion for reconsid., 77-2 BCA 12731; Varo, Inc.,
ASBCA 16606, 72-2 BCA 9720 at 45,396.
547
See supra note 544.
5 4 8 See
e.g., Robert M. Tobin, HUD BCA 79-388-C20, 84-3 BCA
17651 at 87,969-70 (holding that unabsorbed overhead was
unrecoverable despite a large reduction in volume of work
because the contractor failed to perform the unterminated
work within the contractually specified completion date--the
partial termination did not cause the decreased distribution
base); R.G. Robbins & Co., ASBCA 27516, 83-1 BCA 27516, at
81,692-93 (disallowing unabsorbed overhead because evidence
was lacking as to how the partial termination affected G&A);
Chamberlain Mfg., ASBCA 14759, 71-1 BCA 8837 at 41,094
(disallowing unabsorbed overhead because no evidence was
introduced as to the plant's activity or lack of activity on
new business after termination).
54 9 Id.
5 50
See Dunbar Kapple Inc., ASBCA 3631, 57-2 BCA 1448 at
4,883-84. Variations of the above computation sometimes
appear in board decisions. See e.g., Henry Spen & Co., ASBCA
20766, 77-2 BCA 12784 at 62,180-81. Also other approaches
are sometimes used. For example, in Marlin Associates, GSBCA
5663, 82-1 BCA 15,738 at 77,874, the parties agreed to a 15%
loss-of-volume surcharge applied to the direct costs of the
completed portion of the contract.
5 5 1 See
FAR 49.208 allowing the contractor an equitable
adjustment for its increased costs of performing the
unterminated portion of the contract. *
5 5 2 Celesco
Indus., ASBCA 22640, 84-2 BCA 17295 at 86,164
(citing Fairchild Stratos Corp., ASBCA 9169, 67-1 BCA 6225,
aff'd on motion for reconsid., 68-1 BCA 7053).
5 5 3 The
212% indirect cost rate used for contract pricing was
substantially higher than the actual indirect cost rate.
Thus, either more work was performed during the period than
anticipated despite the partial termination or fewer indirect
262
costs were incurred than anticipated, or both. The Board's
rationale for finding that the contractor suffered no loss is
that the contractor prepared its bid using a cost rate that
was higher than it actually experienced. Had the contractor
known in advance what its actual indirect cost rate would be
the contract price would have been lower, not higher.
5 5 4 The
amount of an equitable adjustment is based on "the
difference between what it reasonably would have cost to
perform the work as originally required and what it
reasonably cost to perform the work as changed" not on what
the parties would have agreed to at the time of contracting
had they known what actual costs would be. See supra note 13
and accompanying text.
5 5 5 Wheeler
Bros., ASBCA 20465, 79-1 BCA 20465.
5 5 6 1d. at 66,919.
557 A
40% increase in the sales volume of almost any business
is going to substantially increase indirect costs. More
administrative, clerical, and warehousing time are needed to
process additional sales. Similarly more paper, machine time
and clerical supplies are needed. The effect of increased
volume on cost is discussed at supra notes 108-16 and
accompanying text.
263
5 6 7 Denial
of recovery is in essence a forfeiture and boards
and courts seldom enforce forfeitures. The most likely
result is that recovery would be allowed but in the manner
least favorable to the contractor.
568
See supra Chapter 1, para. IV.B. If the contract is
subject to the CAS, then any modification to the contract or r
termination of the contract is likewise subject to the CAS.
Similarly if a contract is not subject to the CAS, any
modification or termination of the contract is not subject to
264
the CAS, unless of course the modification independently
meets the dollar thresholds of the CAS.
56 9ADisclosure Statement is not required of all contractors
performing CAS-covered contracts. Only contractors receiving
(1) a negotiated national defense contract or subcontract of
$10 million or more, or (2) net awards of negotiated national
defense contracts and subcontracts totaling more than $10
million in their most recent cost accounting period are
required to submit Disclosure Statements. See FAR 30.202-1.
57 0
FAR 30.401-40.
5 7 1 FAR 30.401-50(a).
57 2 Anderson,
supra note 27, at 10-4, describes "actual cost"
as follows:
265
",.4 . "-.
f :
57 8
Rishe, supra note 27, at 13-13.
57 9
FAR 30.402-20.
5 8 0 See
FAR 30.402-20. See also supra notes 594-97 and
accompanying text.
58 1
FAR 30.402-40.
5 8 2 FAR
30.402-50(b).
5 8 3 FAR 30.402-50(c).
58 4
FAR 30.402-50(d). Change is accomplished through the
process of formally proposing a change in accounting practice
and obtaining Government acceptance.
58 5
See DCAA Audit Manual, 8-402b (1983).
5 8 6 For
example, without a consistency requirement a
contractor could shift costs among cost pools or between
accounting periods in order to increase its recovery of cost
on Government contracts
587
See Boeing Co., ASBCA 19224, 79-1 BCA 13708 at 67,248-49
(citing proposed but withdrawn CAS 417, Distinguishing
between Direct and Indirect Costs).
5 8 8 See
e.g., Starks Contracting, VACAB 1339, 79-2 BCA 14018
at 68,848 (stating that costs not specifically identifiable
with a contract cannot be charged to that contract as a
direct cost).
5 8 9 See
Peter Kiewit Sons' Co., ENG BCA 4742, 85-1 BCA 17911
at 89,708; Foster Constr., DOT CAB 71-16, 73-1 BCA 9869.
"It is rarely an easy task to determine whether a particular
cost should be classified as direct cost or an indirect one.
. . . Clearly, the procurement regulations provide no more
than very broad, general definitions in differentiating
between the two categories." Id. at 46,150.
59 0
See Kleen-Rite Corp., GSBCA 5893, 83-2 BCA 16582.
"Ultimately, 'direct' and 'indirect' are arbitrary
categories, and the decision whether to call a given cost
direct or indirect is to a great extent a matter of
convenience." Id. at 82,467 (citation omitted).
266
,.
". .. .. .% . . .. . . . . . ... . . ,. ' -. - -. . . % . . -, % . < '.
| g .
5 9 1 See
e.g., Peter Kiewit Sons' Co., ENG BCA 4742, 85-1 BCA
17911 at 89,708 (holding that the procurement regulations
prefer "non-field labor be charged directly to a final cost
objective whenever possible, but permit such labor to be
treated as overhead, provided, in either case, that such
treatment is consistently observed").
5 9 2 Change
in accounting practice is discussed supra Chapter
5, Part III.
59 3
See FMC Corp., ASBCA 30130, 87-2 BCA 19791. Here a
contractor attempted to include the costs of prosecuting a
claim against another contractor in its G&A. The Board held
that legal fees and other costs incurred prosecuting contract
claims were direct costs of the contract from which they
arose. Despite the contractor's established practice of
including such costs in G&A the Board denied recovery
stating:
267
-~ ~ *
[A] contractor charges contract administration
directly to contracts if a contract requires a full-
time administrator. Contract administrators that
handle more than one contract are charged to the G&A
expense pool. Thus, the contract with a full-time
administrator gets charged with its own contract
administration plus a share of the contract
administration performed for contracts that do not
require a full-time administrator.
268
60 5
1d. If the direct labor base inequitably distributes
planning costs to the several cost objectives, the contractor
should propose a change in its method of allocating such
costs. The proposed change must be for all planning costs.
The illustration suggests using the number of planning
documents processed rather than direct labor as a allocation
base.
60 6
p.I See FAR 30.402-60(b).
607
FAR 30.402-61.
6 0 8 This
language has been the subject of a recent ASBCA
decision, Boeing Co., ASBCA 29793, 88-1 BCA*** (decided Dec.
3, 1987). Boeing had been awarded a Phase I design contract
specifically requiring it to submit a proposal for the Phase
2 production contract. Because it was Boeing's disclosed
accounting practice to classify bid and proposal costs as
direct costs if required by a specific contract task, bid and
proposal costs for the Phase 2 contract were properly charged
as direct costs. The question before the Board in Boeing was
classification of proposal costs not specifically required
by the Phase I contract but incurred by Boeing to enhance its
chances of obtaining the follow-on contract--proposal costs
incurred before the Government issued the detailed proposal
instruction package and costs incurred after submission of
the proposal in preparation of a best and final offer. The
Board held that the Interpretation's rationale for permitting
proposal preparation costs to be treated as direct costs
applied with equal force to these costs. They were incurred
for the same purpose and in like circumstances as the bid and
proposal costs the contractor was specifically required to
incur (both sets of proposal costs were incurred to obtain
the follow-on contract). Therefore, the Board required that
they be classified as a direct cost.
6 09
See e.g., Hurd-Darbee, Inc., ASBCA 12928, 68-2 BCA 7402 at
34,418.
6 10
In many cases the contractor is trying to recover the same
cost twice, directly and as part of an indirect charge. The
duplication and inconsistency are obvious requiring little
discussion. Even when it is not the same cost that is being
claimed twice, the consistency issue is obvious in most
circumstances. See e.g., Volk Constr., IBCA 1419-1-81, 87-3
BCA 19,968 at 101,107 (reclassifying supervisory salaries
from a direct cost to an indirect cost); Webster-Martin,
269
. . ~
.a . - . - - . .- -
- I - --. I - j
27
~270
services way out of proportion to contractor's normal
accounting patterns).
6 1 4 The
various forms of overcharging are discussed supra
notes 594-97 and accompanying text.
6 1 5 Note
that CAS 402 uses this same factual pattern to
illustrate a "cost incurred for the same purpose." See FAR
30.402-60(a) (2). See also supra notes 603-604 and
accompanying text. However, Rishe, supra note 27, at 11-7
and 11-10, comments that quantitative differences do
constitute a sufficient change in circumstances to justify
direct charging so long as similar costs are eliminated from
the distribution base.
6 1 6 For
a discussion of accounting changes see supra notes
638-77 and accompanying text.
6 1 7 CAS
410, Allocation of Business Unit General and
Administrative Expenses to Final Cost Objectives, permits a
"special allocation" from the G&A expense pool when a
particular final cost objective in relation to other final
cost objectives receives significantly more or less benefit
from G&A expense than would be reflected by the allocation of
such expenses using a cost input base. See FAR 30.410-50(4). p
A special allocation is allowable only in exceptional
circumstances. See Boeing Co., ASBCA 19224, 79-1 BCA 13708
at 67,241-42. Many of the earlier cases state in dicta that
deviation from a contractor's established accounting
practices is allowable in exceptional circumstances. Note
that in each of the cited cases exceptional circumstances
were found not to exist. See e.g., Telecomputing Servs.,
ASBCA 10644, 68-1 BCA 7023 at 32,472; American Scientific
Corp., IBCA 576-666, 67-2 BCA 6670 at 30,957 (permitting
deviation if the usual practice causes inequitable results);
Reynolds Metals Co., ASBCA 7686, 1964 BCA 4312, motion for
reconsid. denied, 1964 BCA 4477. "It might under some
circumstances be proper to make exceptions to appellant's
ordinary accounting methods in order to meet special
circumstances and more accurately reflect the costs of
performing a particular contract and we have frequently so
held." Id. at 20,856.
6 18
See Kleen-Rite Corp., GSBCA 5893, 83-2 BCA 16582 at 82,464
(finding no inconsistency in directly charging time spent as
project manager and indirectly charging time spent as an area '.
271
personnel were removed for periods of time from
administrative duties to direct labor functions; it was
consistent to charge a portion of these salaries as a direct
cost and the remainder indirectly).
6 19
Airtech Servs., DOT CAB 68-19, 68-2 BCA 7209.
6 2 0 Under
the current procurement regulations, FPR 1-15.202(a)
is now FAR 31.202(a).
62 1
Airtech Servs., DOT CAB 68-19, 68-2 BCA 7209 at 33,905.
62 2
See American Fed. Contractors, PSBCA 1354, 87-1 BCA 19595
at 99,119 (holding that to recover labor costs of supervisory
employees directly, contractor must show that they performed
other than normal supervisory duties and directed themselves
exclusively to the work directed by the modification). See
also Electronics Corp., ASBCA 4770, 61-2 BCA 3134. The Board
reasoned that no inconsistency existed: 5
In none of these instances is there attempted to be
charged direct any supervisory, administrative,
clerical or other activity of an indirect nature. In
every case it was as though the employee resigned his
position and accepted employment as a direct laborer.
The production supervisors picked up tools and joined
the army of direct production workers.
* 6 2 5 See
supra notes 74-88 and accompanying text.
62 6
See e.g., American Scientific Corp., IBCA 576-666, 67-2
BCA 6670 at 30,956 (not allowing contractor to segregate the
manufacturing overhead and labor costs of its two facilities
272
because it had established an accounting practice that
combined such costs) N
6 3 1 Change
in cost accounting practice is discussed infra
notes 638-677.
6 32
See FAR 31.202(c). "Once an appropriate base for
distributing indirect costs has been accepted it shall not be
fragmented by removing individual elements. All items
properly includable in an indirect cost base should bear a
pro rata share of indirect costs irrespective of their
acceptance as Government contract costs." Id. See also
Celesco Indus., ASBCA 22402, 80-1 BCA 14271 at 70,299.
273 .
6 33
See FAR 31.202(c). For a discussion explaining that
unallowable costs should not be excluded from the
distribution base see supra notes 165-67. Although the FAR
prohibits removal of unallowable costs from a distribution
base, not all authorities agree that removal of such costs is
necessarily an inconsistent accounting practice or results in
Government contracts being burdened with costs properly
attributable to the unallowable costs. See e.g., Martin
Marietta Corp., ASBCA 14159, 71-1 BCA 8793 at 40,794-95.
6 3 4 Base
periods are discussed supra notes 98-106 and
accompanying text.
6 35
See Nash-Hammond, Inc., ASBCA 15563, 71-1 BCA 9166 at
42,529 (finding that the contractor properly used its fiscal
year for its distribution base despite the fact that during
the last six months of its fiscal year (1) no work was done
on the Government contract and (2) production volume
substantially declined); EMR-Aerospace Sciences, NASA BCA
269-2, 70-2 BCA 8381 (finding that it was a departure from
established accounting practice for contractor to use a two
year base for start-up costs); Electronics Corp., ASBCA
4770, 61-2 BCA 3134 at 16,287-89 (not permitting contractor
to use the period of contract performance--1 Oct 1954 to 31
Aug 1956--as its base period because this period was
inconsistent with contractor's normal accounting practice);
Daystrom Instrument, ASBCA 3438 at 5772, modified on other
grounds, 58-2 BCA 2050 (not permitting contractor to use the
45-month period of contract performance as its base period
because, among other things, such use was inconsistent with
its established accounting practices). But see Itek Corp.,
NASA 27, 1963 BCA 3967 at 19,641. Only the last eight months
of contractor's fiscal year were used as the base period.
Use of the entire year was considered inequitable because it
was contractor's first year in business and the first four
months in existence were not representative of its normal
operations.
6 3 6 The
propriety of using a base period shorter than one year
is discussed supra note 103.
6 3 7 Base
period selection for terminations settlements is
discussed supra notes 373-75 and accompanying text.
Surprisingly, the contractor's choice of the period of
contract performance as a base period rather than its normal
base period has not been challenged as an inconsistent
accounting practice.
274
6 3 8 Change
in product mix, organization, volume of business,
among others factors may make a once equitable cost
accounting practice inequitable. FAR 31.203(d) describes
three sets of circumstances under which a contractor should
examine its accounting practices including (1) substantial
differences in the cost patterns of work under the contract
as compared to the contractor's other work, (2) changes in
the nature of the contractor's business, and (3) application
of cost groupings developed for the contractor's primary
location to off site locations. See also Rishe supra note
27, at 13-16 to 13-19.
6 3 9 Both
requirements must be demonstrated. See Celesco
Indus., ASBCA 23165, 80-1 BCA 14455 at 71,246; Celesco
Indus., ASBCA 22402, 80-1 BCA 14271 at 70,297-98; Optimal
Data Corp., NASA BCA 976-8, 79-1 BCA 13624 at 66,834; Unidex
Sys., PSBCA 24, 75-2 BCA 11,549 at 55,108; Frederick Burk
Found., ASBCA 15728, 73-1 BCA 9959 at 44,738; Plasmadyne
Corp., ASBCA 7731, 1962 BCA 7731 at 17684; Hardy Mfg., ASBCA
4201, 58-1 BCA 1789 at 6941. But see McDonnell Douglas
Corp., NASA BCA 873-10, 75-1 BCA 11337 at 53,995 and 54,000,
motion for reconsid. denied, 75-2 BCA 11568. The Board
refused to require a contractor to demonstrate that its
established cost accounting practices produced inequitable
results as a prerequisite to its making a change. The
contractcr had only to prove that the change produce
equitable results. In contrast the Board would require the
Government to demonstrate that the contractor's established
cost accounting practices were inequitable as a prerequisite
to imposing an accounting change upon the contractor.
6 4 0 1n
Celesco Industries, ASBCA 22402, 80-1 BCA 14271 at
70,298, the Board recognized that the contractor's
established method of distributing G&A disproportionately
allocated G&A to the discontinuing Marine Systems segment of
the contractor's business yet denied the change because other
segments of the contractor's business had borne a
disproportionately large share G&A during the start up period
for the Marine Systems segment.
6 41
See General Dynamics Corp., ASBCA 7963, 1964 BCA 4133 at
20,162, stating that "the sole fact that it would favor the
Government does not justify a change in the circumstances to
which these procedures are applied" (citations omitted).
See Boeing Co., ASBCA 11866, 69-2 BCA 7898 at 36,752, stating
that "ordinarily, a contractor cannot change accounting
practices merely for the purpose of obtaining the greatest
275
reimbursement on the basis of events that have previously
occurred" (citations omitted). See also General Dynamics
Corp., ASBCA 22461, 78-2 BCA 13270 at 64,886; Federal Elec.,
ASBCA 11324, 67-2 BCA 6416 at 29,733; Borg-Warner Corp.,
ASBCA 9144, 1964 BCA 4507 at 21,630 (stating that the
Government cannot require a change merely because it would
produce a more favorable dollar result for the Government).
6 42
See Unidex Sys., PSBCA 24, 75-2 BCA 11549 at 55,109;
Industrial Research Assocs., CAB WB-5, 71-1 BCA 8680 at
40,319; Telecomputing Servs., ASBCA 10644, 68-1 BCA 7023 at
32,472; Reynolds Metals Co., 1964 BCA 4312 (not permitting a
change in accounting practice that affected only 1 of 16
plants).
It is not permissible . . . to establish a company-
wide system of accounting, including a company-wide
item of cost, and then to revise this system with
respect to a single plant or program in order to
revise the allocation of cost so as to charge it to
that plant or program, contrary to its established
method.
276
- J *d-I
647Prospective versus retroactive application of changes to
cost accounting practices is discussed generally and with
respect to CAS-covered contracts infra notes 663-77 and
accompanying text.
64 8
See FAR 30.401-50(b) and PAR 30.402-50(d).
64 9
See FAR 30.602-3.
6 50
See FAR 30.602-3(a).
6 51
See FAR 30.602-3(b). The cost impact proposal must be
sufficiently detailed to allow evaluation and negotiation of
the cost impact on each CAS-covered contract and subcontract.
6 52
See FAR 30.602-3(c) .
6 53 See Anderson, supra note 27 at 4-17. 3
6 54
1d. If the contracting officer determines that the change
is desirable and not detrimental to the Government, an
equitable adjustment to contract price is negotiated under
the Changes clause of the contract. See FAR 52.230-
3(a) (4)(iii) and FAR 52.230-5(a) (3)(ii).
6 55
A downward equitable adjustment to a firm fixed-price
contract is warranted if as a result of the change the
contractor allocates less cost to a fixed-price contract than
would have been allocated by use of its disclosed cost
accounting practices on which the contract negotiation was
based. See Anderson, supra note 27, at 4-23 for a discussion
of downward equitable adjustments to firm fixed-price
contracts.
6 56 See FAR 52.230-3(a) (5) and FAR 52.230-5(a) (4).
27
277
regulations] recognize, by implication the possibility
of changes arising out of circumstances peculiar to
the business of the contractor. In addition, the
Board has also recognized the right of the contractor
to change its accounting methods when it can show a
valid basis therefor.
278
'
.VVt.- %T _ ,If 7. -
I.h- -
Id. at 101,814.
6 6 3 The
Cost Accounting Standards clause, FAR 52.230-3 is a
mandatory clause for CAS-covered contracts. The limitation
is set forth as follows: "If any change in cost accounting
. practice is made for the purposes of any contract or
subcontract subject to CAS requirements, the change must be
applied prospectively to this contract and the Disclosure
Statement must be amended accordingly" (emphasis added).
The Disclosure and Consistency of Cost Accounting Practices
clause, FAR 52.230-5 is a mandatory clause for contracts
subject to modified CAS coverage. Its limitation is set
forth as follows: "After the terms and conditions underwhich
such change is to be made have been agreed to, the change
must be applied prospectively to this contract and the
Disclosure Statement, if affected, must be amended
accordingly" (emphasis added). Although these clauses have
been mandatory since at least 1978 (See DAR 7-104.83(a)),
they have not been used by courts or boards as a basis for
denying retroactive application of changes in cost accounting
practices. See e.g., Data-Design Laboratories, ASBCA 27245,
86-2 BCA 18830 (refusing to allow the Government to
retroactively apply a change in cost accounting practice,
discussing retroactive application from the viewpoint of the
CAS, but not mentioning the prospective application language
included in the Cost Accounting Standards clause of the
contract).
6 6 4 Under
the Cost Principles, the terms of the contract are
one of five factors considered in determining whether a cost
is allowable. See FAR 31.201-2(a) (4). When a contractor's
cost accounting practices are inconsistent with the terms of
the contract, the costs resulting from such inconsistent
practices are not allowable in excess of the amount that
would have resulted from consistent practices. See FAR
31.201-2(c). Compare FMC Corp., ASBCA 30130, 87-2 BCA 19791
at 100,138 (denying costs in excess of the amount that would
have resulted from the use of accounting practices consistent
with the Cost Principles).
6 65
See e.g., FMC Corp., ASBCA 30130, 87-2 BCA 19791 at
100,139.
279
Po0
6 66
For CAS-covered contracts, the requirement for prospective
application is contained in the Cost Accounting Standards
clause, FAR 52.230-3 and the Disclosure and Consistency of
Cost Accounting Practices clause, FAR 52.230-5. There are no
similar clauses that apply to non-CAS-covered contracts.
6 6 7 Celesco
)J Indus., ASBCA 20569, 77-1 BCA 12445 at 60,287-88.
6 68Amid-year change in effect reduces the base period into
two shorter base periods. Use of base periods shorter than
one year may yield cost allocation rates which do not
accurately reflect the normal operations of a contractor's
business. See supra notes 98-104 and accompanying text.
6 69
See Celesco Indus., ASBCA 23165, 80-1 BCA 14455 at 71,2467
(applying a more stringent test applied to mid-year
accounting changes than to changes in accounting practices
proposed to begin at the beginning of a year).
67 0
See Blue Cross and Blue Shield Ass'n, ASBCA 26529, 86-2
BCA 18,571 at 94,427; Celesco Indus., ASBCA 20569, 77-1 BCA
12445 at 60,287; Stanwick Corp., ASBCA 18083, 76-2 BCA
12,114 at 58,179; Unidex Systems, Inc., PSBCA 24, 75-2 BCA
11,549 at 55,109; Peninsular Chemresearch, Inc., ASBCA
14384, 71-2 BCA 9066 at 42,054-55; Reynolds Metals Co.,
AqBCA 7686, 1964 BCA 4312 at 20,856; Daystrom Instrument
Div. of Daystrom, ASBCA 3438, 58-2 BCA 2050 at 8628-29.
6 7 1 Zero
Mfg., ASBCA 14558, 70-2 BCA 8489 at 39,460 (emphasis
added). See also Celesco Indus., ASBCA 20569, 77-1 BCA 12445
at 60,287.
67 2
See Blue Cross and Blue Shield Ass'n, ASBCA 26529, 86-2
BCA 18,571. The Board denied the contractor's claim that
certain indirect costs should be allocated on a retroactive
basis to the contractor's Government as well as commercial
business. "Neither appellant or the Government (in the
absence of some possible peculiar circumstance not present
here) may retrospectively change the accounting treatment of
an item of cost to the prejudice of the other. The
commercial havoc which could otherwise ensue is obvious."
Id. at 94,427 (citations omitted).
67 3 See
e.g., Litton Sys. v. United States, 449 F.2d 392, 398-
401 (Cl.Ct. 1971); Data Design Laboratories, 86-2 BCA 18830
at 94,889; Falcon Research & Dev., ASBCA 19784, 77-1 BCA
12312 at 59,484; AC Elecs. Div., General Motors Corp., ASBCA
280
14388, 72-2 BCA 9558 at 44,521-22; Martin Marietta Corp,
ASBCA 14159, 71-1 BCA 8783 at 40,794; Zero Mfg., ASBCA
14558, 70-2 BCA 8489 at 39,460 (allowing a change to be given
retroactive effect based in part on finding no evidence that
the contractor's fixed price contracts would have been lower
priced had the new practice been in effect at their
inception).
67 4
Obviously,
a contractor cannot reprice any of its
commercial fixed-price contracts. Repricing of fixed-price
Government contracts raises the question of whether the
contractor would have received the contract in the first
instance had its price been higher.
6 7 5 See
e.g., Litton Sys. v. United States, 449 F.2d 392, 398-
401 (1971); Data Design Laboratories, 86-2 BCA 18830, at
94,889; Falcon Research & Dev., ASBCA 19784, 77-1 BCA 12312
at 59,484; AC Elecs. Div., General Motors Corp., ASBCA
14388, 72-2 BCA 9558 at 44,521-22. Compare Chrysler Corp.,
NASA BCA 107501, 77-1 BCA 12482 at 60,511. The Board
retroactively changed the contractor's method of accumulating
and allocating costs from a single pool to a multiple pool
method. The contractor, in accordance with its established
accounting practices, had charged all of an off-site
facility's rental, occupaiiy, and other costs to the single
burden pool. When the character of work at this off-site
location changed from bid and proposal to commercial
production type work, the contractor continued to charge such
costs to the single pool for distribution to all the
contractor's work even though such work was only marginally
beneficial to Government contracts and specifically
identifiable with a commercial venture. Chrysler Corp. can
be distinguished from the other cases involving retroactive
application of change in that the costs sought to be
retroactively applied were specifically identifiable with
commercial work. The contractor's ability or inability tu
reprice fixed-price contracts was not discussed.
67 6
The role of cost in the pricing of commercial and
Government contracts is discussed at supra notes 23-24, and
accompanying text. In the absence of competition, cost
plays a dominant role in pricing Government contracts. Thus,
forfeiture is a possibility to the extent that the
contractor's business, during the period for which
retroactive application is sought, included sole source
Government contracts, modifications to fixed-price Government
contracts, or terminations for convenience of Government
contracts.
281
282
6 82
See supra note 597 and accompanying text.
6831d.
283
employees time is often permitted. See supra notes 614-18
and accompanying text.
68 8
See e.g., Metro Eng'g, AGBCA 77-121-4, 83-1 BCA 16143 at
80,187. Absent evidence by contractor as to its established
method of distributing indirect costs, the Board used the
distribution base recommended by the Government, "proportion
of job income" (12% markup) rather than the distribution base
recommended by the contractor, direct labor (25% markup).
68 9 See supra notes 191-98 and accompanying text.
69 0 See supra notes 192-93 and accompanying text.
69 1
See supra note 235 and accompanying text.
6 92
See supra notes 282-88 and accompanying text.
6 9 3 The
change in circumstance is that the delay has made
recovery of fixed indirect costs using the contractor's
normal accounting practices inequitable. See supra note 639
and accompanying text.
6 9 4 Doing
so results in over recovery of fixed indirect costs
for the delay period. See supra notes 356-59 and
accompanying text.
6 9 5 See
supra notes 598-99 and accompanying text.
6 9 6 FAR 30.402-61.
284
7 00
See Moloney & Rubien Contr., ASBCA 22280, 78-1 BCA 13000
at 63,401.
7 01Atermination for convenience in effect turns a fixed-
price contract into a cost reimbursement contract. See supra
note 429 and accompanying text.
7 02
Consistency
as it applies to assignment of costs to
indirect costs groupings was discussed supra notes 623-26,
and as it applies to distribution base supra notes 627-33.
7 0 3 Reclassification
of costs for purposes of terminations for
convenience is discussed at supra Chapter 4, Parts II.B and
IV.A. Part II.B discusses reclassification as it applies to
pre-termination costs; Part IV.A discusses reclassification
as it applies to settlement costs. Classification of costs
as direct or indirect, including overcharging caused by
inconsistent classification, is discussed generally supra
Chapter 5, Part II.A.
704See supra notes 374-75 and accompanying text.
7 0 5See
supra notes 560-63, 634-37, and accompanying text.
7 0 8 Few
events other than the contractor going out of business
will make accumulation of indirect costs over the
contractor's fiscal year inequitable.
7 09
See supra notes 99-105.
7 1 0 Likewise,
allowing the Government to selectively chose
either the contractor's fiscal year or the period of contract
performance as the base period depending upon which yields
the most favorable result to the Government is inequitable.
285
I
(a) ....
(d) Allowances not to exceed 10 percent each for overhead and profit for the
party performing the work will be based on the value of labor material, and use of
construction equipment required to accomplish the change. As the value of the
change increases, a declining scale will be used in negotiating the percentage of
overhead and profit. Allowable percentages on changes will not exceed the following.
10 percent overhead and 10 percent profit on first $20,000; 7 1/2 percent overhead
and 7 1/2 percent profit on next $30,000; 5 percent overhead and 5 percent profit on
balance over $50,000. Profit shall be computed by multiplying the profit percentage
by the sum of the direct costs and computed overhead costs.
(f) Not more than four percentages, none of which exceed the percentages
shown above, will be allowed regardless of the number of tiers of subcontractors.
(h) Cost of Federal Old Age Benefit (Social Security) tax and of Workmen's
Compensation and Public Liability insurance appertaining to changes are allowable.
While no percentage will be allowed thereon for overhead or profit. Prime
Contractor's fee will be allowed on such items in subcontractor's proposals.
I
(i) Overhead and Contractor's fee percentages shall be considered to include
insurance other than mentioned herein, field and office supervisors and assistants,
watchmen, use of small tools, incidental job burdens, and general home office .
expenses, and no separate allowance will be made therefor.
41 CFR Jul 80
286
GSA OVERHEAD LIMITATION CLAUSE
(a) The provisions of the "Changes" clause prescribed by FAR 52.243-4 are
supplemented as follows:
(1) .
(2) The allowable overhead shall be determined in accordance with the contract cost
principles and procedures in Part 31 of the Federal Acquisition Regulation (48 CFR Part
31) in effect on the date of this contract. The percentages for profit and commission shall
be negotiated and may vary according to the nature, extent and complexity of the work
involved, but in no case shall exceed the following unless the contractor demonstrates
entitlement to a higher percentage:
Profit Commission
Overhead (percent) (Dercent)
- 1
To be negotiated.
Not more than four percentages will be allowed regardless of the number of tier
subcontractors. The Contractor shall not be allowed a commission on the commission
received by a first tier subcontractor. Equitable adjustments for deleted work shall include
credits for overhead, profit and commission. On proposals covering both increases and
decreases in the amount of the contract, the application of overhead and profit shall be on
the net change in direct costs for the Contractor or subcontractor performing the work.
(3) ....
(b) The provisions of the "Differing Site Conditions" clause prescribed by FAR 52.236-
2, are supplemented as follows: The Contractor shall submit all claims for equitable
adjustment in accordance with, and subject to the requirements and limitations set out in,
paragraph (a) of this "Equitable Adjustments" clause.
(End of Clause)
3. Carteret
288 '
* - - -. - - .
6. Allied Materials and Equipment (Burdc, Fluctuation Method)
Total contractor direct labor - Direct labor attributable - Residual direct labor
during period of contract to the contract
performance
Residual direct labor X Fluctuation in overhead rate - Unabsorbed overhead
7. Simulation
Contract billings Average contract billings per day worked
Actual days worked
Average contract billings X Number of days = Simulated additional work
per day worked of delay
Simulated additional + Contract billings - Simulated contract billings
work
Simulated contract billings + Total billings = Simulated total billings
Simulated contract billings X Total home office = Overhead allocable
Simulated total billings overhead during to contract
contract period
2'_
I..
289