Mech Equipment
Mech Equipment
Mech Equipment
P: (877) 322-5800
info@cedengineering.com
An Introduction to
Electrical Safety:
Substations and
Switchgear
1. SUBSTATION WORK
2. SWITCHING
3. FUSES
4. ENERGY STORING PROTECTIVE DEVICES
5. INSTRUMENT TRANSFORMERS
6. POWER TRANSFORMERS AND REGULATORS
7. METALCLAD SWITCHGEAR
8. STATIONARY BATTERIES
9. INSULATING OIL HANDLING OPERATIONS
(This publication is adapted from the Unified Facilities Criteria of the United States government which are
in the public domain, have been authorized for unlimited distribution, and are not copyrighted.)
1.4 SYSTEM OPERATION. System single line diagrams must be permanently mounted
at each substation. When Safe Clearance switching operations are performed, mimic
buses on a switchgear can be helpful as a visual indication of the lines or equipment being
operated.
1.4.2 ALARMS. System alarms, if blocked during maintenance, must be returned to their
correct operating condition at the completion of the maintenance.
1.6.2 IDENTIFY DEFECTIVE EQUIPMENT by painting a large red “X” on the body (not
on the top) of the equipment. The red X must remain on such equipment until it has been
repaired or until it has been properly disposed of. Local policy may dictate use of their
preferred defective equipment identification marking.
Switching operations above 600 volts may require a Switching Order. Switching
operations include changing the position of circuit breakers, fused equipment, switches,
and other devices.
2.1 AIR SWITCHES. Many air switches cannot be opened if there is a load on the line,
a large magnetizing current from a transformer, or a heavy charging current from an
unloaded transmission line. Understand the interrupting capability of each switch being
operated.
2.1.1.1 DISCONNECT SWITCHES can be used to open an energized line when not
under load.
2.1.1.3 EVALUATE THE HAZARD before using disconnect switches to open a tie line or
to break two parallel high-voltage lines.
2.1.2.1 THE HINGES OF AIRBREAK SWITCHES must be sufficiently stiff (and kept in
this condition) so that after the blades have been turned into the open position, they will
not accidentally fall back on their line-side energized clips.
2.1.2.2 THE SWITCH MUST BE INSPECTED after it has been opened to see that all
blades have opened the proper distance. Single-throw airbreak switches must be opened
to the maximum amount. Double-throw airbreak switches must be opened so that the
blades clear both sides of the switch by the same amount.
2.2 OIL SWITCHES. The consequences of operating a faulty oil switch, or closing into a
faulted circuit with an oil switch are likely to be catastrophic and, often fatal. Switching
procedures will be used to make sure that no energized oil switch is operated while
workers are in the vicinity. Unless the switch has been equipped for remote operation (at
least 20 ft (6.1 m)) away, the switch must be completely deenergized by an upstream
device before switching. The switch must be locked out and tagged out before allowing
maintenance. In addition, do not operate any energized high-voltage oil switch unless
routine maintenance has been performed within the past year. The switch must be
deenergized at the nearest upstream device following the lockout/tagout procedures of
Chapter 6 herein. Once maintenance has been performed on the switch, the switch shall
be considered operational following the guidelines of this paragraph. Oil switches must
incorporate a mechanical stop to prevent inadvertent operation to ground. Any
abnormalities or defects discovered in any oil switch must be reported to an authorized
individual.
2.3 SF6 SWITCHES. Follow all precautions specified by the manufacturer. Inspect the
switch before operating it for any signs of degradation, such as low SF6 pressure or signs
of SF6 leakage (accumulation of powder around seals). Verify that the SF6 pressure
gauge is in the green zone before operating the switch; operating a switch with low SF6
pressure can result in internal flashovers that will damage the equipment and cause
personal injury. Before energizing the switchgear for first use, verify that the shipping
3.2 FUSE HANDLING. Fuses must normally not be handled, except when they need to
be replaced. Pull them briskly, and remove completely. Use safety glasses and face
shields when replacing fuses in primary fuse cutouts; do not use your free arm in an
attempt to shield your eyes from possible flashes. The worker changing the fuses must
stand firmly on a level surface. Where operating in an elevated position, the worker will
be secured with a safety lanyard/harness to prevent a slip and fall if there is a flash. Use
live-line tools to remove energized fuses. Whenever possible, deenergize the circuit
before removing a fuse.
3.3 OPERATION OF ENERGIZED FUSES. Open all lines protected with energized fuses
in the same manner as for air switches. Deenergize non-load-break type installations.
For load-break installations, wait for a short time after fuse replacement in order to allow
the fuse to interrupt any fault condition that might remain prior to the fuse replacement.
3.4 OPEN FUSE HOLDER. Do not leave outdoor fuse holders open for an extended
period of time. Water damage/moisture or warping could make closing them dangerous,
or degrade their protective ability.
4.2 SURGE ARRESTERS. A surge arrester limits overvoltages and bypasses the related
current surge to a ground system that absorbs most of the energy. An overvoltage
condition can be caused by a fault in the electrical system, a lightning strike, or a surge
voltage related to load switching. All surge arrester equipment must be considered as
loaded to full circuit potential, unless it is positively disconnected from the circuit. Be sure
the permanent ground conductor is intact before any work is performed.
4.2.2 SURGE ARRESTERS must never be touched or approached, unless they are
completely disconnected from all live lines and live equipment, and all parts have been
discharged to ground and effectively grounded.
4.2.3 HORN GAP SWITCHES must be fully opened and completely separated from all
live lines and equipment whenever it is necessary to work near a surge arrester.
4.3 CHOKE COILS. Choke coils are inductors that operate in a manner similar to surge
arresters, except that they operate on over-frequency rather than over-voltage.
4.4.1 DISCHARGE CIRCUITS are intended to discharge capacitors after the circuit is
deenergized. Since there could be no indication that the circuit is burned out or otherwise
not functioning, always assume capacitors are fully charged until tested.
4.4.2 LINE CAPACITORS removed from service for any purpose must be considered at
full or higher voltage, until the terminals have been shorted together and discharged by
an approved method. Do not short terminals until capacitors have been deenergized for
at least 5 minutes to allow time for the voltage level to reduce.
4.4.3 IT IS NOT SAFE to use fuses or disconnect switches to disconnect large capacitor
banks (above 60 kilovolt-reactive single-phase, or 180 kilovolt-reactive three-phase).
Circuit breakers or switches designed specifically for this purpose must be used.
4.4.4 AFTER DISCONNECTING all capacitor banks, wait 5 minutes. Short together and
ground all terminals; ensure the neutral is grounded. All operations must be performed
using rubber gloves and a hot stick.
4.4.6 BARRICADE THE WORK AREA as a safety measure for other workers, when
working on or testing capacitors in the shop.
4.4.7 CAPACITORS made before 1979 usually contain PCBs. Observe required
precautions for hazardous materials if the case is ruptured or any liquid is visible on the
outside of the case.
4.5 COUPLING CAPACITORS. These capacitors have a high impedance, which results
in a long discharge period. This characteristic of coupling capacitors is typically
overlooked, which makes them particularly hazardous to personnel if not properly
grounded. To minimize shock hazard follow the precautions below:
5.1.1 PTS PROVIDE a means of obtaining a low voltage from a higher voltage circuit.
They are designed and selected to operate within certain accuracy limits and burdens.
5.1.3 THE CASE and one of the windings of the low-voltage side of voltage transformers
must always be grounded before energizing the transformer.
5.1.4.1 IF THE SECONDARY WINDINGS are inadvertently shorted together when the
primary windings are energized, a very high current will flow causing the windings to
quickly overheat. This may also create an arc flash hazard to anyone in the vicinity of the
transformer.
5.1.4.3.3 WHEN DISCONNECTING the primary service to the transformer, verify the
absence of voltage using a suitably rated voltmeter (a handheld test meter with a high
voltage probe is not acceptable). Lamps can be used in addition; however, note that a
non-illuminated lamp, connected on the low-voltage side of a voltage transformer, is not
an adequate indication that the primary side of the transformer is deenergized.
5.1.4.3.4 THE SECONDARY FUSES must also be removed before replacing the primary
fuse, and then reinstalled before the transformer is reenergized.
6.1.1 CONSIDER ALL TRANSFORMERS ENERGIZED and at full voltage, unless they
are disconnected from primary and secondary wires or disconnected from the primary
wires and all phases shorted together and grounded. The secondary neutral is normally
sufficient as a ground, provided that there is a grounding conductor interconnected with
the common neutral, the transformer case, and the ground electrode. Always check
continuity of the ground connection.
6.1.2 WHEN TRANSFORMERS are installed or replaced, the secondary terminals will be
checked for correct voltage and for phase rotation (if applicable).
6.1.3 WHEN TRANSFORMERS ARE installed, and before they are energized, the
ground connection must first be made to the case and to the neutral, when applicable.
6.1.6 NEVER OPERATE no-load (or manual) tap changers when the transformer is
energized. Only load-tap-changing (LTC) type tap changers can be operated when the
transformer is energized. When reenergizing a transformer after changing the position of
manual tap changers, maintain the minimum approach distances specified with all
6.1.7 IF NECESSARY to relieve pressure on a transformer, the pipe plug, pressure relief
device, or inspection cover plate must be loosened slowly so the internal pressure of the
transformer can dissipate gradually.
6.1.8 PRESSURE RELIEF VALVES must never be opened when there is precipitation or
high humidity, except on failed transformers and when re-fusing.
6.1.9 NEVER DRAW AN OIL SAMPLE, open a pressure relief valve, or otherwise open
a transformer when there is an internal vacuum on an energized transformer. Doing so
can cause an explosion.
6.1.10 TRANSFORMERS or tanks must not be entered unless forced ventilation or an air
supply is used to maintain a minimum oxygen level of 19.5 percent by volume in the work
area.
6.2.1 VOLTAGE REGULATORS are normally installed with bypass and disconnect
switches. Never open or close a regulator bypass switch, unless the regulator is set on
its neutral position and the control switch is open, or the automatic control feature is
inactivated in accordance with the manufacturer’s recommendations.
7.2 PERFORM THE FOLLOWING prior to drawout (rack out) of a circuit breaker
operating mechanism. Always rack out the switchgear breaker whenever there is work
on the circuit originating from that switchgear breaker.
7.2.4 CHECK that protective interlocks are functioning to protect against closed position
circuit breaker rack out.
7.2.5 ENSURE that all workers in the vicinity know the circuit breaker is being racked out.
• When both sets of terminals in a cell are deenergized (i.e., line and load, or bus
to bus).
7.4 A MANUFACTURER-APPROVED ground and test device can be used for access to
terminals for procedures such as the application of protective grounds, phase
identification on deenergized circuits, or phasing tests on live circuits. Use of this device
avoids the hazardous operation of opening and shutting the shutters of a high voltage
switchgear cell. It can be an extremely hazardous device if not used according to the
manufacturer’s instructions.
7.4.1 DO NOT install the device with ground cables already connected. Connect ground
cables after installing the device.
7.4.2 Shut All Access Doors on the device while installing and removing the device.
Use padlocks on any door where studs are intended to remain energized and access is
not needed for testing.
7.4.3 AFTER INSTALLING THE device, verify by using a voltage detector that exposed
studs are deenergized.
7.4.4 INSTALL THE GROUND cables, with the device end of the ground cables
connected last (and disconnected first upon removal of the ground cables). For a stud-
type device, the ground cables must be connected with the device in the “disconnect”
position. For a bale-type device, the ground cables can be connected with the device in
either the “disconnect” or the “engage” position.
7.5 FOR SOME OWNERS, a manufacturer-approved grounding breaker can be used for
access to the terminals, for procedures of connecting temporary protective grounds to
ground the main bus, ground the incoming lines or ground both the main bus and the
incoming lines.
8.1.1 BATTERIES AND DC SYSTEM components are different from AC electrical system
equipment. Batteries contain acid, which is harmful to skin and eyes, and the electrical
shock hazards associated with DC power can be more severe than those associated with
AC power for equivalent voltages and currents.
8.1.2 ONLY AUTHORIZED PERSONNEL who have been familiarized, trained, and
qualified on battery fundamentals and maintenance procedures are allowed to perform
maintenance-related activities on a battery.
8.1.3 THE FOLLOWING INDUSTRY STANDARDS provide the most complete safety
standards for stationary batteries and DC systems. Refer to the appropriate document
for the type of battery used in a particular application.
8.2 PROTECTIVE EQUIPMENT. The following equipment must be available for the safe
handling of the battery and protection of personnel:
• Acid-resistant gloves
• Portable or stationary water facilities for rinsing eyes and skin in case of contact
with acid electrolyte
• For lead acid batteries, bicarbonate of soda to neutralize any acid spillage (1
lb/gal or 0.1 kg/L of water)
8.3.1 WEAR PROPER SAFETY clothing to prevent contact with acid or live electrical
connections. Whenever working on or near batteries, wear a rubber apron and rubber
gloves. Ensure goggles and face shields are available for personnel.
8.3.2 USE ONLY INSULATED TOOLS in the battery area to prevent accidental shorting
across battery connections. Never lay tools or other metal objects on cells; shorting,
explosion, or personal injury could result. As a general rule, the length of the exposed
metal for any tool should be less than the distance between the positive and negative
posts of each cell.
8.3.3 WEAR ONLY NONCONDUCTIVE hard hats near batteries. Metal hard hats can
fall across the battery terminals or connections and create short circuits.
8.3.4 REMOVE ALL JEWELRY, wristwatches, or clothing with metal parts that could
come into contact with the battery terminals.
8.3.6 VENTED LEAD ACID, vented nickel cadmium batteries and valve-regulated lead
acid (VRLA) batteries can generate hydrogen gas that, in sufficient concentrations, can
be explosive if ignited. Never bring burning materials such as lighted matches, cigarettes,
or sparks of any kind near the battery. Avoid the use of spark-producing equipment near
batteries. Residual gases can remain within cells during storage and shipment. Smoking
is not permitted in battery rooms or near stationary batteries. Take these precautions at
all times while handling batteries.
8.3.7 ENSURE that the exit from the battery area is unobstructed.
8.3.8 MINIMIZE access to the battery by personnel unaware of battery safety precautions.
8.3.10 KEEP THE BATTERY and adjacent area clear of all tools and other foreign
objects.
8.3.11 AVOID STATIC BUILDUP by having personnel contact the ground periodically
while working on batteries.
9.1 ALWAYS PLACE potential and current transformers in an electrically safe work
condition before taking oil samples.
9.2 HAVE APPROPRIATE types and sizes of fire extinguishers readily available.
9.3 ONCE ALL EQUIPMENT has been placed in an electrically safe work condition and
insulating oil handling operations is to begin, employees shall don an approved
disposable coverall. Employees shall use extreme caution to ensure that oil does not
contaminate arc-rated PPE. Arc-rated PPE that has become contaminated shall be
immediately removed from service.