Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Annex I BOQ For Construction of Sand Dam and Mini Water Supply System

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 7

CONSTRUCTION OF SAND DAM IN JIDHI VILLAGE

Annex I: BILL OF QUANTITY FOR CONSTRUCTION OF SAND DAM IN JIDHI VILLAGE- GEBILEY DISTRICT
RFT 335075 - SOM1038/2023/31

Notes: A site assessment visit shall be conductued by the contractor before filling the bill of quantitiy to check the site conditions.
The contractor shall contact WHH Office incase of any clarifications regarding the construction work and all rates of units shall be
included in the in the BOQ like transportaiton, cost of materials , installation cost, etc.

1. Sand Dam (23m Length)


No. Description Unit Quantity Unit cost ($) Total cost($)
A Earth work
A.1 site clearing & removal of depress and stones m2 100.00 -
A.2 Excavation of ordinary soil consolidated with boulders, loose soil to a
depth of m. This includes if there is sludge, loose rock,medium to
strong rock. Cost includes any necessary water pumping; Use a m3 144.90 -
hydraulic jack hammer and cart away excavated soil to a distance of
max. 1km
A.3 Back filling works refill of excavated soils; compacting in layers not
m3 90.28 -
eceeding 40cm thickness; profiling as requested by the Engineer.
A.4 Spread and compact 20cm thick clay layer below the structure;
profile as requested by the Supervising Engineer. Include necessary
m3 7.20 -
soil testing (Compaction test, plasticity test, particle size analysis of
existing soil)
A.5 Supply and install plastic sheet under the foundation of the concrete
m2 46.00 -
structure.
Sub-total A 0.00
B Masonary Work (Spillway and wings)

B.1 Construction of rubble stone masonry wall joined with cement sand
plaster of 1:3 mix ration. Use dressed stone pointed with a strong m3 46.78 -
cement/sand plaster

Sub-total B 0.00
C Concrete Work (core-spillway and Core- Wings)
C.1 Construction of Reinforced core concrete spillway and core wings as
shown in the design details. Use a longitudanal and trasverse iron
bars (Y16@30cm with strips of 10mm bars @15cm c/c). Use a
vibrator for 1:2:3 mix ratio and provide formworks. The rates of
concrete shall include testing (at least 2x times) concrete cubes on m3 31.66 -
Test laboratory approved by WHH Engineer. The report will include
compressive strength (specimen size 20x20x20 cm), workability, etc.
Also concrete hammer test shall be carried out by the contractor.

D Protection works
D.2
Construction of Rip-rap stone at the downstream apron of the sand
dam. Use a mortar cement sand ratio of 1:2 for the joints and dress m3 27.60 -
up the stone.

Sub-total (C+D) 0.00

Sub Total 1: Sand Dam 0.00


2.Elevated water tank (30M3)
Total
No. Description Unit Quantity Unit cost ($)
cost($)
A.1 Site clearing & grubbing up to an average depth of 20 cm to remove top
vegetated soil M 2 100 -

A.2 Excavation of footing trenches: 4No (1.0 m long x 1.0 wide x 1.0 m
deep) M 3 4.000 -

A.3 Footing blinding : lay 5 cm thick lean 4No (1.2 m long x 0.40 wide x
0.05) m concrete 1:4:8
/3bags of cem/0.4 cum of river sand /0.8 of graded stone 40mm
nominal size as per M 3 0.200 -
specification above the excavated footing and foundation
trenches ,cure the blinding

A.4 Footing concrete: provide and cast 4No (1 x1 x 1) R.C.C footing over the
blinding mix 1:2:3 reinforced concrete with double layer 6y14bar
spacing 150mmc/c deformed steel in both direction and using vibrator. M 3 4.000 -

A.5 Excavation of foundation trenches 4No (3.8 m long x 0.4 m wide x 0.1
m deep) M 3 0.608 -

A.6 Foundation blinding: lay 50 mm thick lean (15.2 m perimeter x 0.4 m


wide x 0.05 m deep) concrete 1:4:8 nominal size as per the M 3 0.304 -
specification.

A.7 Supply and cast four RCC beams, two middle tie beams and with
cement concrete of 1:1.5:3 proportions (M20), The beams should be
kept moist at least 4 days. Beam section dimensions. Middle tie beam,
4No (5.4 m long x 0.25 m deep x 0.40 m wide) + 2No (15.2 m
perimeter x 0.25 m deep x 0.40 m wide) R.C.C beam mix concrete M 3 5.2 -
reinforced with 4Y 14 linked and tied with Y8mm stirrups @150 mm c/c.

A.8 Floor concrete slab: lay 250 mm thick plain concrete over the
crashed stones mix 1:2:3 of concrete (Area: 14.44 m2 x 0.25 m high). M 3 3.61 -

A.9 RCC Columns: cast in place 4No (3.4 m high x 0.30m wide x 0.30m
thick) R.C.C columns mix 1:2:3 reinforced with 9Y 12 mm with 8mm M 3 1.22 -
@150 mmc/c double layer.

A.10 Bottom and Top R.C.C circular slabs: cast in place 150mm thick
R.C.C slab of the water storage with lid mix 1:2:3 reinforced with Y12
mm for main bar and 12 to distribution + 8mm stirrups 2No (Area: M 3 4.332 -
14.44 m2 x 0.15 m high/thick).

A.11 R.C.C circular shear walls: provide and cast 150 mm R.C.C wall
with mixt ratio of 1:2:3 concrete reinforced with Y12 with Y12 mm
distribution @150mm c/c at 2m level of roof beam for R.C.C wall
reinforced with Y12 linked with Y8 mm stirrups (Area: 1.720 m2 x2.6 m M 3 4.470 -
high). Include the cost of finishing using bondex water proofing for
internal walls.

A.12 Prepare and lay 5 mm thick cement flooring and walls screed finished
smooth cement slurry. M 3 1.901 -

A.13 Wall plastering: Apply 2 coats of 15 mm thick plastering mix 1:4 to


internal and external walls including sieving sand and even finish as M 2 28.589 -
per line in levels ,well curing twice per day.

A.14 Plastering of 4 columns: Apply 2 coats of 15mm thick plastering


with mixing ratio of 1:4 thoroughly 4No (2.6 m long x 0.25 m wide). M 2 2.600 -

A.15 White washing and emulsion paint: apply 2 coats of emulsion and
external of the elevated tank. M 2 28.589 -

A.16 Supply and install 4cm*4cm box steel external access ladder to the tank
with 7 m long ; and internal ladder of 4m long with same dimensions. Pcs 2 -

A.17 Provide and fix 2-inch diameter Inlet and outlet GI pipe class C with
valves 2-inch , overflow pipe 2 inch as well as pressure pipe
complete with all the fitting necessary for the full fictional No. 4 -
plumbing work.

A.18 Supply and install galvanized steel manhole lid (0.6x0.6m) for the
tank upper access and painting with one prime coat, and two oil No. 1 -
coats.
A.19 Steel frame fence for elevated tank Supply and fix steel frame painted
with approved antirust paint, include the cost for nuts, bolts and fix it to
the water tank. The frame should 2.5 x 2.5- inch Ms pipe with 180
cm height weldeded and bolted with mesh wire that have gate door 1m M2 100 -
x 1m with its hinges and lockable with 40- meter perimeter.

A.20 Visibility with WHH logo and Project details Painted on two side of the
tank. Ls 1 -

Sub-Total 2- for Elevated water tank (USD) 0.00


3.Construction of shallow well (Water source)
A. Earth work and excavation
A.1 site clearing & removal of top soil up to 20cm
depth 3
m 9.62 -

A.2 excavating/digging of well with diameter of 3


m for a depth of 8 m from GL. 3
m 56.52 -

A.3 Cart away surplus excavated soil 3


m 56.52 -
Sub-Total A 0.00
B. Concrete work
B.1 Producing & installing pre-cast reinforced concrete rings & of c-20
& 1.8 m internal 3 4.77 -
m
diameter and 10cm thick as per drawing

B.2 construction of apron above the concrete rings


to the 3
M 4.42 -

B.3 supply and prepare 25cm thick wooden planks(timber) with


eucalyptus bracing price 2 5.31 -
M
includes all other necessary materials

B.5 Grauting- putting lean concrete above the gravel pack with a mixed ration
of 1:3:6. 3
M 0.50 -

B.6 Construct reinforced concrete well cover slab with ø12mm


reinforcement bars spaced at 200mm c/c. Make a provision of
shallow well access inspection provision 0.6m wide x 0.6m 3
M 1.06 -
long.

Sub-total B 0.00
C.Masonry work
C.1 Filling 2.0m widex 1.5m depthx 4m length dressed hardcore protection m3
under the apron platform. 12.00 -

C.2 Gravel pack- putting gravel at the back of RCC m3


rings with a height of 3 m 31.4 -

C.3 Apply 12.5mm thick plastering on the cover M2


and well head (1:3) mix cement sand mortar 12.5 -

C.4 3mm cement sand screed punning for the M2


platform. 17 -

C.5 Dewatering and Disinfection costs. No 1 -


C.6 Supply and install a metallic lockable painted No
steel manhole lid 0.6mx0.6m on top of the slab. 1 -

Sub-total C 0.00
Sub-total 3- for shallow well (USD) 0.00
4. Construction of water point
No Description of actvity Unit Quantity Unit price Total price
A.1 Site clearance and excavation of the top soft soil, 6 m width, 5.2 m
width and 40 cm deep M3 12.48 -

A.2 filling hardcore on the excavated area M3 12.48 -


A.3 laying 5 cm thick lean concrete on the hardcore M3 2 -
A.4 Construction of Masonry wall, 16.8 m perimeter and 30 cm thick,
use mortar mixing ratio of 1:3 M3 2 -

A.5 Laying 10 cm thick RCC concrete slab, use No: 10 mm @15 cm


C/c, use mixing ratio 1:2:4 M3 1.28 -

A.6 Construction of concrete shear wall at the center, 4 m long, 0.8 m


height and 10 cm thick, provide concrete base for jerry cans of
dimensions (0.4m widthx 0.5m heightx4m long) on each side of M3 1.92 -
the shear wall , use bar #10mm @15 cm C/c

A.7 Purchase and installation of all necessary GI fittings such as


elbows, unions, nipples, sockets, gatevalves and TEEs, Each of LS 1 -
the water point will have eight faucets.
A.8 Plastering the shear wall and masonry walls. ( include cost white
washing and emulsion painting - WHH visibility on both ends.) M2 -
11.44

Sub-Total 4- For Water point (USD) 0.00


5. Pipeline Extension
SN Description Unit Quantity Unit cost ($) Total cost($)
A.1 Excavation and back filling of pipe lines: excavate all pipe
lines with dimensions of (0.4 m wide and 0.6 deep),and 70 m from
the shallow well to the water tank and ( 30m from water tank to
M3 25.6 -
points and troughs). Note that minimum excavation depth should be
1m across the valley.

A.2 Supply and installation of 3 pieces of 2-inch GI non-return valves and


1 piece of air valve. Pc 3 -

A.3 Supply all material and install 2" GI pipe class B of total 70m with
necessary valves , the pipe is from the source to the water tank.
This system should include all fittings (Tees, sockets ,gate
m 70 -
valves, caps, unions, reduces, Pegler non-return valves at the
shallow well and inlet tank, GI-HDPE adopters, 2 water meters)

A.4 Construction of five concrete block anchors for supporting the


pipeline length at valley (0.30mx0.30mx1m) at an interval of 3m. M3 0.45 -

A.5 Supply all material and install 2" diameter of total 10m HDPE
distribution branch pipe line to water kiosks with necessary fittings.
This system should include all fittings (Tees, HDPE couplings, m 30 -
gate valves, caps, unions, reduces and adopters)

Sub-Total 5- Pipeline Extension (USD) 0.00


6. Solar System Installation
A.1 Supply and install 6 Solar Panel Monocrystalline 350W ISO standard Preferable
German product. Pcs 6 -

A.2 Supply a 10mm2 thick Solar Cable for interconnections, PV cable MC4 and
neccessary solar asseccories. Ls 1 -

A.3 Supply and install cable splicing joint kit. Set 1 -


A.4 Steel frame for mounting solar panels: Supply and fix steel frame painted with
approved antirust paint, include the cost for nuts, bolts and fix it. The frame
should measure 5mm thickness, 50mm square hollow section on the roof to Ls 1 -
receive 6 pcs of solar panels. (Refer to the drawings for height dimensions-3m
min -height).

A.5 Flow control: Supply and fix Original England Pegler 2" none return valve at
the shallow and at the inlet of the tank- well's 2" G.I. pipe outlet. Ls 2 -

A.6 Provision, Installation and testing of 1 Pc of Submersible solar Pump power


rating (1.4 Kwts )- preferabbly Grandfos with with a sensor, controller and pump Ls 1 -
assecories.

A.7 Supply and fix 6mm thick blue original submersible water pump cable and install
from the shallow well to the solar panels.( Expected distance- 50m to 100m).
Ls 1 -

A.8 Fence for solar panels: Supply 2" steel hollow section pipes of 2m long, 1.5m
spaced and fix with concrete, supply chain link heavy gauge and install fence for
the solar panels. The dimension of the fence are (10m by 8m) Fence should m 80 -
also have a gate of 2m by 0.8m with frame and lock pad.

A.9 Training one person and supervising Engineer to do the light maintenance of
the solar system and provide them basic tools. Ls 1 -

Total 6: Cost for the Solar system (USD) 0.00


No. Description Price (USD dollars)
1 Constructio of sand dam -
2 Construction of elevated water tank -
3 Construction of shallow well -
4 Construction of Water point -
5 Pipleline extension -
6 Solar system installation -
Grand total 0.00

You might also like