Line Loadability
Line Loadability
Abstract: The importance of line loadability limit is well regulation where, bus reactor and line reactors are
understood in grid management for its reliable and efficient considered in the context of line loadability.
operation. Loading limit of any line depends on various II. LITERATURE SURVEY
parameters like its line length, fault level of connected
substations, inductor/capacitor connected in series/shunt etc.
Line loadability is defined as degree of line
In the year 1953 St. Clair has suggested Line loadability with loading expressed in terms of percentage of SIL, limited
respect to surge impedance loading and mathematical model by thermal, voltage drop and stability limit. This
was developed by R.D.Dunlop in 1979 for calculation of line concept was introduced by H.P. St. Clair in 1953 [1].
loading limit. Central Electricity Authority of India (CEA) St. Clair curve in Fig.1 shows the universal loadability
also came up with a modified method to calculate loadability curve for overhead uncompensated transmission line as
limit in its “Transmission planning manual” published in a function of line length up to 400miles applicable to all
year 1994. In this paper authors have dissuaded the voltage level. In 60Hz system for 300miles line length
limitations of earlier methods and proposed a new method has a loadability of about 1.0 SIL. It could be concluded
for calculation of voltage regulation which intern can be
utilized for calculation of line loading and supported by a
from St. Clair curve is that KW-Mile product is
case study. constant.
In 1967, the Planning Department of the
American Electric Power Service Corporation faced [2]
I. INTRODUCTION with a growing need for similar curves applicable to
lines of voltage classes higher than 345-kV and longer
With the enactment of Electricity act 2003, than 400 miles modified the St. Clair's curve, as shown
and introduction of non-discriminatory open access for in Fig. 2. This Fig.2, just like the original curve, was
the use of transmission system, Indian power sector has arrived at through practical considerations.
experienced paradigm shift in its governance. Apart
from already existing long term exchange of power, the
concept of short term exchange of power has helped for
seamless transfer of power from surplus area to shortage
area. This concept has further gained momentum with
the introduction of power exchange(s). all such new
product like advance short term open access (STOA),
day ahead STOA, contingency STOA etc. made
available for exchanging electricity has put a lot of
pressure on existing transmission system to
accommodate those transaction(s).
To operate system securely as well as to
accommodate all such transaction to the extent possible,
a term “Total Transfer Capability” (TTC) is introduced
by system operators which determine the quantum of
power which can be safely transferred from source to
sink through the existing network(s). TTC is generally
restricted by line loading limit which is minimum of
thermal limit, voltage limit and stability limit. Where
thermal and voltage limits are well define, steady state
stability limit are subjective and depends upon various
factors which are varying in nature. In past there are
many authors/utilities who have come up with their
Figure 1 St.clair curve
suggestions to define modified SIL taking consideration
of compensation and line length, the most famous
Analytical development of loadability characteristics
authors are H.P. St. Clair and R.D. Dunlop. In year 1996
for EHV and UHV transmission lines developed in
CEA also came up with “Transmission Planning
1979, by R.D.Dunlop et.al [3] where author has
Criteria” where they suggested same approach for
developed the mathematical model for calculation of
modification of SIL. In this paper authors have
line loadability for voltage level up to 1500Kv and
introduced a new method for calculation of voltage
600mile line length. Author has also shown the effect of
series and shunt compensation on line loading and
considered the maximum allowable voltage regulation is III. POINTS FOR DISCUSSION
5% and steady state stability margin is 30% shown in (i) In order to control over voltage in high voltage
Fig.3. substation both line reactors or/and bus reactors are
used. However for calculation of line loadability only
line reactors are considered but bus reactors are not
considered in CEA planning criteria 2006.
Typical 400KV sub-station single line diagram shown
in Fig.4 where bus reactor and line reactor are used to
control the over voltage.
400KV Sub-station
Line2
Line3
Line1
Bus Reactor
9.00
5 30% Stability Margin
4 8.00
3 7.00
2
50% Stability Margin 6.00
Line loading in SIL
1
5.00
0
25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400 425 450 475 500 525 4.00
Line length in KM
No Voltage Regulation
3.00
Figure 3 St.Clair curve for 30% and 50% Stability Margin 2.00
1.00
developed the Transmission Planning Criteria [4] and
suggested that voltage regulation of 5% and phase 0.00
25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400 425 450 475 500 525
angular difference of 30° between two ends of the line Line length in KM
MW
-1000.00
32.5 797 960 1016 1247
35 788 952 1010 1210 -1200.00
-1800.00
VI. CASE STUDY -2000.00
The Eastern Regional Grid comprises the states 0 1 2 3
ZOO
4 5 6 7 8 9 10
TIME
11 12 13 14 15 16
SCROLL
17 18 19 20 21 22 23
-400.00
Characteristics for EHV and UHV Transmission Lines,”
-600.00
IEEE Transactions on Power Apparatus and System
-800.00 1979
MW
-1000.00
-1200.00
-1400.00
-1600.00
-1800.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
TIME SCROLL
ZOO
[4] Central Electricity Authority “Transmission
Planning Criteria” 1994
[5] CBIP Mannual on Wind energy 2009.
[6] Power System Stability and Control by Prabha
Kundur, 2011