PRICE EST NO:

Data Analysis

electrical

1 Specification Code: 1.14.2

SUBHEAD : 1.0

WIRING

1.14 Wiring for circuit/ submain wiring alongwith earth wire with the following sizes of FRLS PVC
insulated copper conductor, single core cable in surface / recessed medium class PVC conduit as
required

1.14.2 2X 2.5 sq. mm + 1 X 2.5 sq. mm earth wire

Code Description Unit Quantity Rate Amount

2.5 sq. mm ISI marked, FRLS PVC


159.0800
1102 insulated, single core copper conductor metre 14.00 2227.12
0
cable

=50.5x3 = 151.5 + 7.58 (wastage @ 5%) =


159.08m
Other Engineering Organisations
1224 20 mm dia, ISI marked, PVC conduit metre 52.50000 10.44 548.10

1229 20 mm PVC bends


PRICE
= 50 + 2.5 (wastage @ 5%) = 52.5m

each 4.00000 4.71 18.84

1234 20 mm PVC couplers each 15.00000 3.00 45.00

1218 20 mm iron staples/saddles/ screws each 85.00000 1.50 127.50

2857 PVC fastener 40mm long each 85.00000 0.30 25.50

2935 Cement, paint, sand etc. L.S 1.00000 5.00 5.00

Total Cost of Materials 2997.06

printed on 12-11-2023 14:34:46 page 1


PRICE EST NO:

Cartage @1.0% of Cost of Materials 29.97

LABOUR

1001 Wireman Day 2.00000 673.00 1346.00

1010 Mason, Grade 2 Day 0.75000 612.00 459.00

1007 Khallasi Day 2.75000 553.00 1520.75

TOTAL 6352.78

AddOverheads & Profit @ 15.0% 952.92

TOTAL 7305.70

Costof 50.000 metre 7305.70

Rate per metre 146.11

Say 146.0

Other Engineering Organisations

PRICE Cost index 33.05% 48.25

Total with Cost index 194.25

Say 194.25

2 Specification Code: 1.14.3

SUBHEAD : 1.0

WIRING

1.14 Wiring for circuit/ submain wiring alongwith earth wire with the following sizes of FRLS PVC
insulated copper conductor, single core cable in surface / recessed medium class PVC conduit as
required

1.14.3 2 X 4 sq. mm + 1 X 4 sq. mm earth wire

printed on 12-11-2023 14:34:46 page 2


PRICE EST NO:

Code Description Unit Quantity Rate Amount

4.0 sq. mm ISI marked, FRLS PVC


159.0800
1103 insulated, single core copper conductor metre 22.00 3499.76
0
cable

=50.5x3 = 151.5 + 7.58 (wastage @ 5%) =


159.08m

1224 20 mm dia, ISI marked, PVC conduit metre 52.50000 10.44 548.10

= 50 + 2.5 (wastage @ 5%) = 52.5m

1229 20 mm PVC bends each 4.00000 4.71 18.84

1234 20 mm PVC couplers each 15.00000 3.00 45.00

1218 20 mm iron staples/saddles/ screws each 85.00000 1.50 127.50

2857 PVC fastener 40mm long each 85.00000 0.30 25.50


Other Engineering Organisations

2935
PRICE
Cement, paint, sand etc. L.S 1.00000 5.00 5.00

Total Cost of Materials 4269.70

Cartage @1.0% of Cost of Materials 42.70

LABOUR

1001 Wireman Day 2.00000 673.00 1346.00

1010 Mason, Grade 2 Day 0.75000 612.00 459.00

1007 Khallasi Day 2.75000 553.00 1520.75

TOTAL 7638.15

printed on 12-11-2023 14:34:46 page 3


PRICE EST NO:

AddOverheads & Profit @ 15.0% 1145.72

TOTAL 8783.87

Costof 50.000 metre 8783.87

Rate per metre 175.68

Say 176.0

Cost index 33.05% 58.17

Total with Cost index 234.17

Say 234.17

3 Specification Code: 1.14.8

SUBHEAD : 1.0

WIRING
Other Engineering Organisations
1.14 Wiring for circuit/ submain wiring alongwith earth wire with the following sizes of FRLS PVC

required
PRICE
insulated copper conductor, single core cable in surface / recessed medium class PVC conduit as

1.14.8 4 X 4 sq. mm + 2 X 4 sq. mm earth wire

Code Description Unit Quantity Rate Amount

4.0 sq. mm ISI marked, FRLS PVC


318.1500
1103 insulated, single core copper conductor metre 22.00 6999.30
0
cable

=50.5x6 = 303.0 + 15.15 (wastage @ 5%)


= 318.15m

1225 25 mm dia, ISI marked, PVC conduit metre 52.50000 14.00 735.00

= 50 + 2.5 (wastage @ 5%) = 52.5m

1230 25 mm PVC bends each 4.00000 6.40 25.60

printed on 12-11-2023 14:34:46 page 4


PRICE EST NO:

1235 25 mm PVC couplers each 15.00000 4.00 60.00

1219 25 mm iron staples/saddles/screws each 85.00000 2.10 178.50

2857 PVC fastener 40mm long each 85.00000 0.30 25.50

2935 Cement, paint, sand etc. L.S 1.00000 5.00 5.00

Total Cost of Materials 8028.90

Cartage @1.0% of Cost of Materials 80.29

LABOUR

1001 Wireman Day 2.25000 673.00 1514.25

1010 Mason, Grade 2 Day 0.75000 612.00 459.00


Other Engineering Organisations
1007 Khallasi
PRICE Day 3.00000 553.00 1659.00

TOTAL 11741.44

AddOverheads & Profit @ 15.0% 1761.22

TOTAL 13502.65

Costof 50.000 metre 13502.65

Rate per metre 270.05

Say 270.0

Cost index 33.05% 89.23

Total with Cost index 359.24

printed on 12-11-2023 14:34:46 page 5


PRICE EST NO:

Say 359.24

4 Specification Code: 1.21.1

SUBHEAD : 1.0

WIRING

1.21 Supplying and fixing of following sizes of medium class PVC conduit along with accessories
in surface/ recess including cutting the wall and making good the same in case of recessed
conduit as required.

1.21.1 20 mm

Code Description Unit Quantity Rate Amount

1224 20 mm dia, ISI marked, PVC conduit metre 52.50000 10.44 548.10

= 50.0 + 2.5 (wastage@ 5%)


= 52.50 m Other Engineering Organisations

PRICE
1229 20 mm PVC bends each 4.00000 4.71 18.84

1234 20 mm PVC couplers each 15.00000 3.00 45.00

1218 20 mm iron staples/saddles/ screws each 85.00000 1.50 127.50

2857 PVC fastener 40mm long each 85.00000 0.30 25.50

2935 Cement, paint, sand etc. L.S 1.00000 5.00 5.00

Total Cost of Materials 769.94

Cartage @1.0% of Cost of Materials 7.70

LABOUR

printed on 12-11-2023 14:34:46 page 6


PRICE EST NO:

1001 Wireman Day 1.25000 673.00 841.25

1010 Mason, Grade 2 Day 0.75000 612.00 459.00

1007 Khallasi Day 2.00000 553.00 1106.00

TOTAL 3183.89

AddOverheads & Profit @ 15.0% 477.58

TOTAL 3661.47

Costof 50.000 metre 3661.47

Rate per metre 73.23

Say 73.0

Cost index 33.05% 24.13


Other Engineering Organisations
Total with Cost index 97.13

PRICE Say 97.13

5 Specification Code: 1.24.1

SUBHEAD : 1.0

WIRING

1.24 Supplying and fixing following modular switch/ socket on the existing modular plate &
switch box including connections but excluding modular plate etc. as required.

1.24.1 5/6 amps switch

Code Description Unit Quantity Rate Amount

Details of cost for one each


MATERIAL

printed on 12-11-2023 14:34:46 page 7


PRICE EST NO:

S.P. 5/6 amps, one way modular switch,


1402 each 1.00000 28.00 28.00
ISI marked

Total Cost of Materials 28.00

Cartage @1.0% of Cost of Materials .28

LABOUR

1001 Wireman Day 0.03000 673.00 20.19

1007 Khallasi Day 0.03000 553.00 16.59

TOTAL 65.06

AddOverheads & Profit @ 15.0% 9.76

TOTAL 74.82

Costof 1.000 each 74.82

Rate per each 74.82


Other Engineering
SayOrganisations 75.0

PRICE Cost index 33.05% 24.79

Total with Cost index 99.79

Say 99.79

6 Specification Code: 1.24.3

SUBHEAD : 1.0

WIRING

1.24 Supplying and fixing following modular switch/ socket on the existing modular plate &
switch box including connections but excluding modular plate etc. as required.

1.24.3 15/16 amp switch

printed on 12-11-2023 14:34:46 page 8


PRICE EST NO:

Code Description Unit Quantity Rate Amount

Details of cost for one each


MATERIAL

S.P.15/16 amps, one way modular switch,


1404 each 1.00000 63.00 63.00
ISI marked

Total Cost of Materials 63.00

Cartage @1.0% of Cost of Materials .63

LABOUR

1001 Wireman Day 0.03000 673.00 20.19

1007 Khallasi Day 0.03000 553.00 16.59

TOTAL 100.41

AddOverheads & Profit @ 15.0% 15.06


Other Engineering Organisations
TOTAL 115.47

PRICE Costof 1.000 each

Rate per each


115.47

115.47

Say 115.0

Cost index 33.05% 38.01

Total with Cost index 153.01

Say 153.01

7 Specification Code: 1.24.4

SUBHEAD : 1.0

WIRING

printed on 12-11-2023 14:34:46 page 9


PRICE EST NO:

1.24 Supplying and fixing following modular switch/ socket on the existing modular plate &
switch box including connections but excluding modular plate etc. as required.

1.24.4 3 pin 5/6 amp socket outlet

Code Description Unit Quantity Rate Amount

Details of cost for one each


MATERIAL

3 pin 5/6 amps modular socket outlet, ISI


1405 each 1.00000 59.50 59.50
marked

Total Cost of Materials 59.50

Cartage @1.0% of Cost of Materials .59

LABOUR

1001 Wireman Day 0.02000 673.00 13.46

1007 Khallasi Other Engineering Organisations


Day 0.02000 553.00 11.06

PRICE TOTAL

AddOverheads & Profit @ 15.0%


84.62

12.69

TOTAL 97.31

Costof 1.000 each 97.31

Rate per each 97.31

Say 97.0

Cost index 33.05% 32.06

Total with Cost index 129.06

Say 129.06

printed on 12-11-2023 14:34:46 page 10


PRICE EST NO:

8 Specification Code: 1.24.5

SUBHEAD : 1.0

WIRING

1.24 Supplying and fixing following modular switch/ socket on the existing modular plate &
switch box including connections but excluding modular plate etc. as required.

1.24.5 6 pin 15/16 amp socket outlet

Code Description Unit Quantity Rate Amount

Details of cost for one each


MATERIAL

6 pin 15/16 amps modular socket outlet,


1406 each 1.00000 95.50 95.50
ISI marked

Total Cost of Materials 95.50

Cartage @1.0% of Cost of Materials .95


Other Engineering Organisations
LABOUR

1001 Wireman
PRICE Day 0.03000 673.00 20.19

1007 Khallasi Day 0.03000 553.00 16.59

TOTAL 133.24

AddOverheads & Profit @ 15.0% 19.99

TOTAL 153.22

Costof 1.000 each 153.22

Rate per each 153.22

Say 153.0

Cost index 33.05% 50.57

printed on 12-11-2023 14:34:46 page 11


PRICE EST NO:

Total with Cost index 203.57

Say 203.57

9 Specification Code: 1.28.4

SUBHEAD : 1.0

WIRING

1.28 Supplying and fixing following Modular base & cover plate on existing modular metal boxes
etc. as required.

1.28.4 6 Module

Code Description Unit Quantity Rate Amount

Details of cost for one each


MATERIAL

1424 Modular base & cover plate for 6 module each 1.00000 77.50 77.50
Other Engineering Organisations

LABOUR
PRICE
Total Cost of Materials

Cartage @1.0% of Cost of Materials


77.50

.78

1001 Wireman Day 0.04000 673.00 26.92

1007 Khallasi Day 0.04000 553.00 22.12

TOTAL 127.32

AddOverheads & Profit @ 15.0% 19.10

TOTAL 146.41

Costof 1.000 each 146.41

Rate per each 146.41

printed on 12-11-2023 14:34:46 page 12


PRICE EST NO:

Say 146.0

Cost index 33.05% 48.25

Total with Cost index 194.25

Say 194.25

10 Specification Code: 1.28.5

SUBHEAD : 1.0

WIRING

1.28 Supplying and fixing following Modular base & cover plate on existing modular metal boxes
etc. as required.

1.28.5 8 Module

Code Description Unit Quantity Rate Amount


Other Engineering Organisations
Details of cost for one each

1425
MATERIAL
PRICE
Modular base & cover plate for 8 module each 1.00000 99.50 99.50

Total Cost of Materials 99.50

Cartage @1.0% of Cost of Materials .99

LABOUR

1001 Wireman Day 0.04000 673.00 26.92

1007 Khallasi Day 0.04000 553.00 22.12

TOTAL 149.53

AddOverheads & Profit @ 15.0% 22.43

printed on 12-11-2023 14:34:46 page 13


PRICE EST NO:

TOTAL 171.97

Costof 1.000 each 171.97

Rate per each 171.97

Say 172.0

Cost index 33.05% 56.85

Total with Cost index 228.85

Say 228.85

11 Specification Code: 2.4.3

SUBHEAD : 2.0

MCCB, MCB & DBS

2.4 Supplying and fixing following way, horizontal type three pole and neutral, sheet steel, MCB
Other
distribution board, 415 volts, Engineering
on surface Organisations
/ recess, complete with tinned copper bus bar, neutral

PRICE
bus bar, earth bar, din bar, interconnections, powder painted including earthing etc. as required.
(But without MCB/RCCB/Isolator)

2.4.3 8 way (4 + 24), Double door

Code Description Unit Quantity Rate Amount

Details of cost for one each


MATERIAL

8 way (4+24), TPN, MCB DB, double door,


1756 each 1.00000 3162.00 3162.00
horizontal type

2855 Steel fastener 6 mm X 75 mm each 4.00000 5.50 22.00

2935 Cement, paint, sand etc. L.S 1.00000 5.00 5.00

printed on 12-11-2023 14:34:46 page 14


PRICE EST NO:

Total Cost of Materials 3189.00

Cartage @1.0% of Cost of Materials 31.89

LABOUR

1001 Wireman Day 0.12000 673.00 80.76

1010 Mason, Grade 2 Day 0.12000 612.00 73.44

1007 Khallasi Day 0.24000 553.00 132.72

TOTAL 3507.81

AddOverheads & Profit @ 15.0% 526.17

TOTAL 4033.98

Costof 1.000 each 4033.98

Say 4034.0

Other Engineering Organisations

PRICE Cost index 33.05% 1333.24

Total with Cost index 5367.24

Say 5367.24

12 Specification Code: 2.10.1

SUBHEAD : 2.0

MCCB, MCB & DBS

2.10 Supplying and fixing 5 amps to 32 amps rating, 240/415 volts, "C" curve, miniature circuit
breaker suitable for inductive load of following poles in the existing MCB DB complete with
connections, testing and commissioning etc. as required.

2.10.1 Single pole

printed on 12-11-2023 14:34:46 page 15


PRICE EST NO:

Code Description Unit Quantity Rate Amount

Details of cost for one each


MATERIAL

1706 6 amps. to 32 amps. ratings, SP MCB, each 1.00000 102.00 102.00

"C" Curve, 10 KA breaking capacity

Total Cost of Materials 102.00

Cartage @1.0% of Cost of Materials 1.02

LABOUR

1001 Wireman Day 0.04000 673.00 26.92

1007 Khallasi Day 0.04000 553.00 22.12

TOTAL 152.06

AddOverheads & Profit @ 15.0% 22.81

TOTAL 174.87
Other Engineering
Costof 1.000 eachOrganisations 174.87

PRICE Rate per each

Say
174.87

175.0

Cost index 33.05% 57.84

Total with Cost index 232.84

Say 232.84

13 Specification Code: 2.12.2

SUBHEAD : 2.0

MCCB, MCB & DBS

2.12 Supplying and fixing following rating, double pole, 240 volts, isolator in the existing MCB
printed on 12-11-2023 14:34:46 page 16
PRICE EST NO:

DB complete with connections, testing and commissioning etc. as required.

2.12.2 63 amps

Code Description Unit Quantity Rate Amount

Details of cost for one each


MATERIAL

1713 63 amps.,2 pole isolator each 1.00000 242.00 242.00

Total Cost of Materials 242.00

Cartage @1.0% of Cost of Materials 2.42

LABOUR

1001 Wireman Day 0.04000 673.00 26.92

1007 Khallasi Day 0.04000 553.00 22.12

Other Engineering Organisations

PRICE
TOTAL 293.46

AddOverheads & Profit @ 15.0% 44.02

TOTAL 337.48

Costof 1.000 each 337.48

Rate per each 337.48

Say 337.0

Cost index 33.05% 111.38

Total with Cost index 448.38

Say 448.38

14 Specification Code: od232059/2023_2024

printed on 12-11-2023 14:34:46 page 17


PRICE EST NO:

Supplying and fixing following size/ modules, PVC box without modular base &
od232059/202
cover plate for modular switches in surface etc. as required.<br>Modular PVC box
3_2024 :
for 8 Module

Code Description Unit Quantity Rate Amount

2857 PVC fastener 40mm long each 6.00000 0.30 1.80

Add Cartage@1.00 0.02

total 1.82

2853 Iron screws, 40 mm X 6 mm each 6.00000 1.00 6.00

Add Cartage@1.00 0.06

total 6.06

2920 Washers each 6.00000 0.00 0.00

Add Cartage@1.00 0.00

total 0.00

MR1100 8 module Moulded Plastic boxes each 1.00000 123.73 123.73


Other Engineering Organisations
Total Cost of Materials 131.61

1001

1007
Wireman

Khallasi PRICE Day

Day
0.02000

0.06000
673.00

553.00

TOTAL 178.25
13.46

33.18

Add CPOH @ 15% 26.74

cost for one point 205.0

Say 205.0

Cost index 33.05 % 20.82

Total with Cost index 225.82

Say 225.82

15 Specification Code: od232060/2023_2024

od232060/202 Supplying and fixing following size/ modules, PVC box without modular base &
printed on 12-11-2023 14:34:46 page 18
PRICE EST NO:

3_2024 : cover plate for modular switches in surface etc. as required.

Code Description Unit Quantity Rate Amount

MR1099 6 module Moulded Plastic boxes each 1.00000 81.36 81.36

2857 PVC fastener 40mm long each 6.00000 0.30 1.80

Add Cartage@1.00 0.02

total 1.82

2853 Iron screws, 40 mm X 6 mm each 6.00000 1.00 6.00

Add Cartage@1.00 0.06

total 6.06

2920 Washers each 6.00000 0.00 0.00

Add Cartage@1.00 0.00

total 0.00

Total Cost of Materials 89.24

1001 Wireman Day 0.02000


Other Engineering Organisations 673.00 13.46

PRICE
1007 Khallasi Day 0.06000 553.00 33.18

TOTAL 135.88

Add CPOH @ 15% 20.38

cost for one point 156.0

Say 156.0

Cost index 33.05 % 20.49

Total with Cost index 176.49

Say 176.49

printed on 12-11-2023 14:34:46 page 19