Offshore Operations Notes
Offshore Operations Notes
• Submersible rigs, also suitable for shallow water, are like jackup rigs
as they come in contact with the ocean or lake floor.
• These rigs consist of platforms with two hulls positioned on top of
one another. The upper hull contains the living quarters for the crew,
as well as the actual drilling platform. The lower hull works much like
the outer hull in a submarine—when the platform is being moved
from one place to another, the lower hull is filled with air—making
the entire rig buoyant.
• When the rig is positioned over the drill site, the air is let out of the
lower hull, and the rig submerses to the sea or lake floor. This type of
rig has the advantage of mobility in the water but the use is usually
limited to shallow water areas.
TYPES OF OFFSHORE STRUCTURES
• Fixed Platform (FP)- Jacket, Jack up etc.,
• Complaint Tower (CT)
• Tension Leg Platform (TLP)
• Spar Platform
• Semi-submersible
• Articulated Tower
• Floating Production System (FPS)
• Floating Production, Storage and Offloading
System (FPSO)
• Gravity Platform (Concrete Structure)
• Source: MMS, USA
Jacket Platform
• The term ‘jacket’ here means a
steel structure in the shape of a
truncated pyramid that rises from
the seabed to above the water line.
• This is built from tubular steel
members and not structural irons.
• The cylindrical shapes of the
tubular members create less
resistance to waves and currents,
reducing the amount of steel and
thus its weight and cost.
• These skirt piles are used to
increase the capacity of the
structure in resisting the
overturning moment.
Jacket Platform
• The jacketed platform consists of
the ‘decks’ or the ‘superstructure’
on which the drilling, production
and all other equipment rest, and
‘piles,’ which are driven through
the leg of the jacket for securing
the platform to the seabed.
• The superstructure generally
comprises three decks, namely,
(1) drilling deck or main deck, (2)
wellhead/production or
mezzanine deck, and (3) cellar
deck.
Jacket Platform
• The jacket consists commonly
of eight large-diameter tubular
legs framed together by many
relatively smaller sized tubular
members known as ‘braces.’
These braces can be of three
types, that is,
(1) horizontal bracing,
(2) diagonal bracing both in the
vertical and horizontal plane
and
(3) X- or K-type bracing
Jacket Platform
• The leg spacing at sea deck level (i.e. at an elevation of 10–14 ft above
mean water level [MWL]) in the longitudinal direction is
approximately 36–45 ft, and the spacing between the two central legs
is approximately 45–60 ft.
• Other than three main components of an 8-leg platform, that is, jacket,
superstructure and piles, there are some auxiliary elements in it. Those
are skirt-pile sleeves, drilling area deck substructure, deck modules,
drilling area, conductor/riser area, boat landing facility, barge
bumpers, launch runner, bracing stub and jacket leg can.
Jacket Platform
• The deck substructure in between two decks or between the cellar deck
and the top of the jacket is usually made up of a group of parallel
Warren trusses with Warren type bracing to form the planar trusses
into a space frame. The web members and the upper and lower
portions may be tubular.
• There are two deck levels – the lower level is high above the splash
zone and the upper deck is placed at a sufficient elevation to place and
operate the equipment at the lower level.
Installation of Platform
Installation of a platform consists of transporting the various
components of the platform to the installation site, positioning the
platform on the site, and assembling the various components into a
stable structure in accordance with the design.
The installation procedure is classified as below:
a. Transportation
b. Removal of jacket from transport barge
c. Erection
d. Pile installation
e. Super structure installation
f. Grounding of installation welding equipment
Transportation
• The jacket is normally taken to the site on a launch barge itself which
is properly balanced before sailing and sea fastenings are done at
several places.
• By sea fastening, the jacket almost becomes an integral part of the
barge. The jacket is provided with a launch truss on the side of it
laying on the barge.
• The jacket is supported on these two launch trusses on the barge with a
thick layer of grease in between to provide a smooth launching of the
jacket into the sea. The other platform parts should be loaded on the
barge in such a manner to ensure a balanced and stable condition.
• Ballasting of the barge as required is done to provide a good balance.
• From the fabrication yard to the installation site, a safe route is fixed
based on ocean survey maps, to ensure a safe journey in the sea.
b. Removal of jacket from transport barge
c. Erection
d. Pile installation
e. Super structure installation
f. Grounding of installation welding equipment
b. Removal of jacket from transport barge:
• Jacket is launched into the sea around 1½ miles away from the exact
location of installation.
• The launch barge consists of launch ways, rocker arms, controlled
ballast and dewatering unit and a power unit (hydraulic ram, etc.)
to assist the jacket to slide down the ways.
• So, for launching the jacket, the barge is first anchored in the opposite
direction of launching.
• The hydraulic rams are placed on the launch ways, sea fastenings are
cut, and a winch is connected to the jacket via a pulley so that pulling
the sling on the winch helps in launching the jacket.
• After that the ballast tanks of the launching barge are flooded.
• Then by giving hydraulic pressure in rams, the winch sling is
simultaneously pulled to assist the launching.
• Rocker arms take care of the easy dropping of the jacket into the sea.
A jacket that is to be launched has to be water-tight and buoyant.
b. Erection:
• Erection is accomplished with the help of a ‘derrick barge,’ which has
a high capacity derrick (crane) that can rotate in any direction, living
facilities for about 100–200 people, a helipad, all necessary diving
facilities, NDT facilities and all sorts of facilities for anchoring, power,
steam and so on.
• Anchors should hold the barge tight enough so that at the time of
erection, the barge should not move from its position.
• When the jacket floats in the sea, with the help of two boats, it is
brought to the site of erection where the derrick barge is already
anchored.
• Anchors should hold the barge tight enough so that at the time of
erection, the barge should not move from its position.
b. Erection:
• At the site of installation, four slings are attached to the top portion
of the jacket for which lifting eyes are provided and the jacket is
slowly upended.
• In this process, the jacket comes to the position of installation. It is
kept in this position (orientation) with the help of slings and tugs.
• Then flooding valves are opened slowly by which water starts
entering into the legs and buoyancy tanks and the jacket starts sitting
down.
• But before upending, divers survey the sea bottom for any possible
collection of debris and other things that may create problems in the
installation.
• When the jacket is put on the sea bottom, the level of the top portion
is measured and levelled so that after piling proper correction could
be avoided
Pile Installation
• Platform and pile identification
• Penetration of pile under its own weight
• Blow counts throughout driving with hammer identification
• Penetration of pile under its own weight and weight of hammer
• Unusual behaviour of hammer or pile during driving
• Interruptions in driving, including ‘setup’ time
• Lapsed time for driving each section
• Elevations of soil plug and internal water surface after driving
• Actual length of each pile and cut offs
• Pertinent data of a similar nature covering driving, drilling, grouting,
or concreting of grouted or belled piles
Grouting
• Grouting is the next step that is performed after piling. For this there
is a grout line for each leg and sleeve which is connected to the
bottom of the leg.
• Cement slurry is pumped into this and from the top return water
present in the annular space comes out through an outlet connection.
After some time when the cement is fully filled in the annular space,
cement starts coming out.
• The samples of cement slurry going in and coming out of each leg
and sleeve are taken and cubes are made out of them by placing in
wooden frames which are later sent for hardness tests to get an idea
of cementation in the annular space.
• Diver survey the cementation of sleeves.
Superstructure installation
• Normally four decks are installed on an unmanned platform. These are
1. Cellar deck 2. Main deck 3. Mezzanine deck 4. Helideck
• The main deck and the cellar deck are fabricated in one piece and the
mezzanine deck and helideck are in another piece. They are transported on a
cargo barge and are directly lifted and stabbed over the piles.
• But before stabbing a transition piece is added which makes slanted piles
vertical.
• The main deck with the cellar deck is lifted with the help of a derrick and set
with proper care being exercised to ensure proper alignment and elevation.
The deck elevation shall not vary more than ±3 in. (76 mm) from the design
elevation shown in the drawing. The finished elevation of the deck shall be
within ½ in. (13 mm) of level.
• Once the super structures are installed, all stairways, hand rails, boat
landings, rub strips and barge bumpers and other similar systems are
installed.
• After this all piping hook up work takes place. Simultaneously, all electrical
connections are made, various pumps and generators are tested and
commissioned.
• After hook-up of all piping systems, they are hydraulically tested according
to the codes and contract specifications
Template Type Tower Type
Concrete gravity structures
• Generally, surge and sway are the motions that are considered for
station keeping.
• In a drilling vessel to carry out drilling operations, its horizontal
movement should be limited because the vessel is normally connected
to the wellhead at the sea bottom by a drilling riser and any
displacement from its origin, known as offset, will cause damage to
the riser, even snapping.
Station Keeping
Components:
• Anchors:
Station Keeping
Components:
• Anchors:
Station Keeping
Components:
• Anchors:
Station Keeping
Components:
• Mooring lines are freely
hanging lines connecting the
floating platform to anchors
or piles on the seabed
positioned at some distance
from the platform.
• Mooring lines can be either
steel-linked chain or wire
rope or a combination of
rope and chain depending on
the strength-to-weight ratio.
Station Keeping
Components:
Winches:
• Winches are used to handle and store wire rope.
• The size of a winch depends on the amount of wire rope to be stored
on the drum and the maximum line pull to be exerted.
Windlasses
• Used to pull in and run out chain. The chain is not stored on the
windlass itself, but in chain lockers below.
Station Keeping
Station Keeping
• Turret mooring systems are the mooring systems that permit the
vessel to freely ‘weathervane’ 360° thereby allowing normal
operations in moderate to extreme sea conditions.
• The turret mooring system got its name because of the use of a turret
structure (turret means a small tower or tower-shaped projection
having great height in proportion to its diameter and having an ability
to revolve or rotate).
• Types: moonpool turret mooring, external turret mooring and
‘internal turret mooring.
• Moonpool turret mooring is used with drillships. From a roller-
mounted turret in the ship’s well beneath the derrick, eight anchor
lines extend outward to the anchors (Figure 3.89). The marine
conductor is the vertical axis around which the entire ship rotates
Station Keeping
Station Keeping
Dynamic Positioning System
Reference Systems:
(3) sensors.
Dynamic Positioning System
• Hoisting
• Rotation
• Circulation
Difference in Spudding from Land Drilling
• The word ‘spudding’ in the context of drilling means the very start of
drilling operations in a new well or that moment when the drilling bit
penetrates the surface.
• In offshore drilling, all the drilling equipment and its ancillaries have to
be transported over the sea/ocean surface.
• The next step before spudding is to make the drilling bit touch the ground
surface, in this case the sea bed or mud line, for which a conduit between
the topside and the sea bottom is essential which is commonly known as
conductor or drilling riser.
• To connect this conductor or riser at the sea bottom, some provision has
to be made and that is known as subsea facility or subsea unit. Among the
subsea units, common ones are subsea template, subsea wellhead and
subsea BOP.
Topsides
• Topsides come in many sizes and shapes but can be loosely categorised
into three main types:
1. Skid-mounted equipment
2. Integrated decks
3. Modularised decks
Skid-mounted equipment
• Advantage of this design was that the structural deck could first be used
to accommodate the drilling and completion rigs and then later receive
the production skids.
• A disadvantage was the reality that doing offshore hook-ups cost 5 to 15
times as much as those done onshore.
Topsides
• Integrated deck:
• An integrated deck may be divided into many levels and areas depending
on the functions they support. Typical levels are as follows.
• Main (upper) deck, which supports the drilling/production systems and
several modules (drilling, process, utilities, living quarters, compression,
etc.)
• Cellar deck, which supports systems that need to be placed at a lower
elevation and installed with the deck structures, such as pumps, some
utilities, pig launchers/receivers, Christmas trees, wellhead manifolds,
piping and so on.
• Additional deck levels, if needed. For example, if simultaneous drilling
and production operations are planned, some process equipment may be
located in a mezzanine deck.
Topsides
Modular deck
• As the deepwater decks became larger and larger, it was a necessity to
split the deck into smaller, liftable pieces and to allow them to be built
more cost-effectively.
Typical modular deck components are as follows:
• Module Support Frame (MSF) – It provides a space frame for supporting
the modules and transferring their load to the jacket/tower structure. The
MSF may also be designed to include many platform facilities, such as
the storage tanks, pig launching and receiving systems, metering/proving
devices and the associated piping systems.
• Modules – These provide a number of drilling/production and life support
systems.
Topsides
Modular deck
• Modules – These provide a number of drilling/production and life support
systems.
• Living quarters module: supports a heliport, communication systems, canteen,
office and recreational facilities.
• Utilities module generally supports power generation and electrical and
production control systems including a control room.
• Wellhead module generally supports the wellheads, well test and control
equipment.
• Drill rig module contains the derrick, draw-works, drillers and control rooms, drill
pipe and casing storage racks and pipe handling systems.
• Production module contains the oil/gas/water separation and treatment systems,
other piping, control systems and valves.
• Power module contains either gas turbines or diesel engines for generation of
electricity to drive rotating equipment such as compressors and pumps.
• Pumps and compressors module contains various pumps for different purposes in
drilling and production as well as compressors for pneumatic lines.
Topsides
Topsides
Linkage between Topside and
Subsea
• Conductors or risers are such devices which act as conduits from the
topside to the ocean floor and primarily act as guides for the drill string.
• The conductors are used in the case of fixed platforms whereas risers are
used with the compliant platforms and mobile units.
• Conductor
• In a conventional fixed platform, individual conductor pipes must be
provided for each well to be drilled through them for protecting the
surface casing from the natural forces of the sea as well as geomechanical
conditions such as mudslides.
• These conductors are large diameter steel pipes usually 26–36 in. in size
which are driven into the soil at the sea bed through guides connected to a
jacket or within the legs of gravity platforms and the deck structure of the
platforms.
• Conductor guides for positioning and guiding the conductors are framed
at various elevations within the jacket and decks to provide support for
the conductors such that the usual effects of environment such as waves,
etc. can be safely withstood.
Linkage between Topside and
Subsea
• Conductor
• The first system consists of guides that are rigidly connected to the
jacket and deck framework. The conductors are placed through these
guides.
• The conductor guides and structural framework provide support for the
conductors at various levels throughout the jacket and deck or decks.
• This type of system generally includes three kinds of conductor guide
assemblies.
• The first kind are those within the horizontal framework levels of the
jacket and typically consist of vertical guides made from steel tubes
welded to the horizontal jacket tubular members.
• The other types are located in the upper and lower deck levels.
• Second System: Jacket conductor guides positioned inside a large
diameter pile which has previously been driven through a jacket sleeve.
The pile protects the conductors from environmental loading.
Linkage between Topside and
Subsea
• While the conductor is lowered through the guides located at different levels
in the jacket and the decks, different types of centralisers are used to hold
them centrally inside those guides.
Risers
• Drilling risers are categorized into two types –
(1) marine drilling riser and
(2) tie-back drilling riser
• Marine drilling risers are used by a floating vessel when the
blowout preventer (BOP) is placed at the sea bottom.
• Tie-back drilling risers are used with bottom supported units
like jack-up platforms or compliant types like TLPs when the
BOP is placed at the platform deck.
Risers
Risers
Tie-back drilling risers:
Risers
Marine risers:
The components of a marine riser
system from bottom to top are
• hydraulic connector
• lower flexible joint (ball joint)
• flexible piping for choke and kill
lines
• riser pipe and connectors
• choke and kill lines and
connections
• telescopic (slip) joint
• diverter system or bell nipple
• riser tensioning equipment
Risers
Marine risers:
• The hydraulic connector joins the bottom section of the marine riser
to the top of the BOP stack. Clamps and release mechanisms are
activated by hydraulic pressure from the BOP system.
• Flexible or ball joints at the base of the marine riser package
accommodate up to 10° of deviation from the vertical to allow for
any horizontal movement to which the drilling vessel might be
subjected.
• Riser pipe is a seamless pipe with mechanical connectors welded on
the ends. Its size is determined by the bore of the BOP stack and
wellhead with allowance for clearance in running drilling assemblies,
casing and casing hangers.
Risers
Integral marine riser pipe
with choke and kill lines
Risers
• The telescopic, or slip joint, is used at the top of a marine riser
and performs these functions:
1. Compensates for vertical movement of the vessel while
drilling and for added dimension required for any horizontal
displacement of the platform.
2. Provides fitting for choke and kill line hoses.
3. Provides for connecting bell nipple or diverter assembly.
4. Provides for attachment of riser tensioner system.
Risers
• A diverter system controls flow of gas or other fluids which
may enter the wellbore under pressure before the BOP stack
and the casing which supports it have been run.
• The diverter is an integral part of the bell nipple. It may be a
bag-type unit or a modified rotating BOP.
• The diverter redirects the flow of mud and cuttings during a
kick when the BOPs are not used and the diverted fluids flow
overboard.
• Control is from a hydraulic system. It is valuable at the time of
drilling through shallow gas zones or for diverting gas kicks in
deep high-pressure zones.
Risers
• Riser tensioners support a major portion of the weight of
the marine riser system plus the drilling mud it contains.
• These tensioners also provide a means of compensating
for heave motions of the platform.
• Without the riser tensioning system, only a very short
riser could be supported by the BOP stack.
Guide Base and Drilling Template
• The TGB or mud mat is a circular, octagonal, or square flat steel frame of about 400
sq. ft. in area that has compartments in which ballast materials can be placed.
• It is designed to be installed through the moonpool of a drilling vessel.
• With the wings folded, the mud mat has dimensions of 20 ft × 20 ft.
• The unit alone weighs about 4–8 tons, but is heavily weighted with bags of cement,
barite, or other heavy materials before being lowered to the seabed on the end of a
string of drill pipe.
• In the centre of the TGB frame is a wide circular aperture with a funnel shape
projecting above it into which the bottom of another frame – the permanent guide
base – will fit.
Permanent Guide Base (TGB)/Mud Mat
A. Tubing Hanger
B. Subsea Christmas Tree
1. Tree guide frame 2. Wellhead connector 3. Valve
block(s) 4. Wye spools swab valve block 5. Flow-line
loops and crossovers 6. Tree manifold 7. Tree cap
assembly
C. Control System
D. Flow-Line Connection System
Floating Production Units
Fabrication Yard
Loading the Jacket
Loading of Jacket at Site and ready for
towing
Decks
Jacket on the barge
Launching the Jacket in to the sea
Sequences of launching
Gravity structure Installation
Gravity structure Construction
Towing and installation
Gravity steel base structure