Throughtput Accounting Notes
Throughtput Accounting Notes
Learning Objectives
• After studying this chapter, readers will be able to understand
• Optimized production technology
• Theory of constraints
• Throughput Accounting
• Calculate and interpret a throughput accounting ratio (TPAR)
• Suggest how a throughput accounting ratio (TPAR) could be improved
• Apply throughput accounting to a multi-product decision-making problem
1
1.1 Optimized production technology (OPT)
1.1.1 During the 1980s Goldratt and Cox (1984) advocated a new approach to production
management called OPT. OPT is based on the principle that profits are expanded by
increasing the throughput of the plant. The OPT approach determines what prevents
throughput from being higher by distinguishing bottleneck and non-bottleneck resources.
1.1.2 A bottleneck might be a machine whose capacity limits the throughput of the whole
production process. The aim is to identify bottlenecks and remove them or, if this is
not possible, ensure that they are fully utilized at all times.
1.1.3 Non-bottleneck resources should be scheduled and operated based on constraints within
the system, and should not be used to produce more than the bottlenecks can absorb.
The OPT philosophy, therefore, advocates that non-bottleneck resources should not be
utilized to 100% of their capacity, since this would merely result in an increase in
inventory.
2
The traditional view is that machines should be working, not sitting idle. So if the
desired output from the above process were 8,100 kgs, machine X would be kept in
continual use and all 8,100 kgs would be processed through the machine in nine
hours. There would be a backlog of 900 kgs [8,100 – (9 hrs × 800)] of processed
material in front of machine Y, however. All this material would require handling
and storage space and create the additional costs related to these non-value added
activities. Its processing would not increase throughput contribution.
The goal is achieved by determining what factors prevent the throughput from being higher. This
constraint is called a bottleneck, for example there may be a limited number of machine hours or
labour hours. In the short term the best use should be made of this bottleneck. This may result in
some idle time in non- bottleneck resources, and may result in a small amount of inventory being
held so as not to delay production through the bottleneck.
In the long term, the bottleneck should be eliminated. For example a new, more efficient
machine may be purchased. However, this will generally result in another bottleneck, which
must then be addressed.
Note: The total factory cost is the fixed production cost, including labour. The total factory cost
may be referred to as 'operating expenses
4
Illustration
Number of units Sold per Day 500
Sales Price Shs. 25,000
Direct Materials Cost per unit Shs 10,000
Other Factory Costs per Day Shs 6,000,000
No. Hours of bottleneck used per day 8
Required
(a) Calculate the Throughput (Return) Per Factory Hour.
(b) Calculate the Throughput Accounting Ratio.
(c) Suggest how the ratio could be improved
Solution
(a) Throughput(Return) Per Factory Hour