Performance Certificate
Performance Certificate
Performance Certificate
Performance Certificate is the certificate issued under sub-clause 11.9 of the FIDIC contract
to constitute acceptance of the Works by the Engineer. This will enable the Contractor to
submit to the Engineer within 56 days, a draft final statement with supporting documents.
When the Engineer verifies the statement, the Contractor will issue a final statement (sub-
clause 14.11) and a discharge for full and final settlement (sub-clause 14.8). In addition,
insurance coverage will no longer be required to be maintained by the Contractor (sub-clause
18.2).
The Engineer will issue the Performance Certificate within 28 days after the latest of the
expiry dates of the Defects Notification Period or as soon as the Contractor has completed
and tested all the Works, including remedying any defects. The Defects Notification Period is
the period for notifying defects and/or damage in the works or a section or a part (as the case
may be) under sub-clause 11.1 [Completion of Outstanding Work and Remedying Defects],
as stated in the contract data (if not stated, one year), and as may be extended under sub-
clause 11.3 [Extension of Defects Notification Period]. This period is calculated from the
Date of Completion of the works or section or part.
The Defects Notification Period starts when the Engineer issues the Taking Over Certificate
if works are completed according to the contract. The Contractor may submit a notice to the
Engineer no earlier than 14 days before expected completion or requesting take over (sub-
clause 10.1).1