Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

BoQ For Boreholes and Shallow Wells Rehabilitation - Gedo

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 13

PIPELINES - Borehole - Water tank

ITEM DESCRIPTION UNIT QTY RATE (USD)

1 Trenching, laying and backfilling of pipeline 21/2'' (for 63mm OD uPVC pipe) m 200
for the Pumping mains with 450mm x 600mm trench

2 Trenching, laying and backfilling of pipeline (for 50 mm OD uPVC pipe) for the m 500
distribution system with 450mm x 600mm trench

3 Construction of Valve chambers 1000x1000x1000mm Nr 2


4 Labour cost for plumbing works for water tank and water points L/S 1
Assorted fittings L/S 1
TOTAL COST FOR PIPELINE EXCAVATION/LAYING & BACKFILING
A 60M3 ELEVATED STORAGE WATER TANK
Excavation
Excavation including maintaining and supporting sides and keeping free from
water, mud and fallen materials by bailing, pumping or otherwise
Prepare site by stripping top 150 mm of soil to remove all debris including sand (if m2 63.0
any) from site and carting away spoil
Excavate trench commencing at reduced levels depth not exceeding 1.50m deep m3 42.0

Filing
300 mm thick approved hardcore filling spread, well rammed and compacted in m3 17.0
150mm layers
Concrete work
Mass Concrete class 15 (1:3:6) with 20mm thick maximum aggregate size in

50mm Thick blinding m3 3.0


Vibrated Reinforced Concrete class 25 (1:1.5:3) with 20mm thick maximum
aggregate size in
Ground beam,Column base,Tie beam ,Columns m3 18.0
Vibrated Reinforced Concrete class 30 (1:1:2) with 20mm thick maximum
aggregate size in
250mm thick Walls,250mm thick Base slab 250mm thick Base slab ,200mm thick m2 120.0
Cover slab
Reinforcement
Reinforcement bars (all sizes) as shown on drawings kg 3890.0
Sawn formwork
Formwork to sides of column bases ,sides and sofittes of beams, to sofittes of m2 315.0
base slab,to sofittes of cover slab, sides of columns,sides of walls
Formwork to sides of base slab girth over 150mm but not exceeding 225mm,slab m 35.0
girth over 150mm but not exceeding 225mm
200mm wide PVC water bar m 32.0
Finishes
Cement and sand mortar (1:3) rendering in:
25 mm Thick screed to base slab with waterproof cement m2 19.0
15mm internal plaster to cover slab with waterproof cement,internal walls,sides m2 300.0
of walls,cover slab,soffits of base slab,beams,columns
25x25mm Bondex sealing compound m 16.0
Water Supply System
Inlet pipe
3" GI Bends Nr 1
3" GI Union Nr 1
3" GI Sockets Nr 1
3" GI Gate valve Nr 1
3" GI Nipple Nr 2
3" GI barrel nipple Nr 2
3" GI pipes Nr 1
3" GI Elbows Nr 2
Outlet pipes
2"GI Bends Nr 1
2" GI Union Nr 1
2" GI Sockets Nr 1
2" Gate valve Nr 1
2" GI Nipple Nr 2
2" GI barrel nipple Nr 2
2" GI Pipes Nr 1
2" GI Elbows Nr 2
2"x1" Reducing Bush GI Nr 1
Scour pipes
2"x4' reducing socket Nr 1
2" GI Bends Nr 1
2" GI Union Nr 1
2" GI Sockets Nr 1
2" Gate valve Nr 1
2"GI Nipple Nr 2
2" GI Barrel Nipple Nr 2
2" GI pipes Nr 1
2" GI Elbows Nr 2
600x600x6mm heavy gauge steel primed metal manhole cover on slab with and No 2
including metal framing all around

20mm Diameter bars, ‘U’ shaped to form steps with ends embedded into No 11
retaining wall, average length 450mm

A TOTAL COST OF 60M3 ELEVATED STORAGE TANK


SUPPLIES
1 Submersible pump, Grundfos, SP8A - 18, with matching cut-off electrodes, drop each 1
cables control panel, all accessories included ( Stand by Pump)

2 Procure and install, Pipe, Galvanized iron, 5.8 metres long, 3" (75 mm) nominal No 38.0
diameter, rated for 14 Bar pressure in borehole

3 Pipe, uPVC class D, 5.8 metres long, 90mm nominal diameter, rated for 10 Bar No 35.0
pressure

4 Pipe, Galvanized iron, 5.8 metres long, 1" (50mm)nominal diameter, rated for 14 No 20.0
Bar pressure
5 uPVC pipe class D, 50mm OD, 10 bar, 5.8m length No 90.0
TOTAL COST FOR SUPPLIES
WATER KIOSK
ITEM DESCRIPTION UNIT QTY RATE (USD)
SUBSTRUCTURE (Provisional)
Excavation
Excavation including maintaining and supporting sides and keeping free from
water, mud and fallen materials by bailing, pumping or otherwise
Prepare site by stripping top 200 mm of soil to remove all debris including sand (if m2 18.9
any) from site and carting away spoil
Excavate for foundation strip commencing at stripped levels depth not exceeding m3 9.7
1.50m deep
Filing
300 mm thick approved hardcore filling spread, well rammed and compacted in m3 3.6
150mm layers to receive concrete surface bed
Insitu concrete: class 15: mix 1:3:6
50mm blinding layer under foundations,hardcore surfaces m2 25.0
Treat hardcore surface with approved insecticide m2 25.0
Concrete work
Reinforced Concrete class 25
Strip foundation m3 2.3
100mm thick floor slab with surface steel trowelled smooth m2 7.5
100mm thick sloping ramp m2 4.2
200 mm thick plinth m2 1.2
Reinforcement
Reinforcement bars (all sizes) as shown on the drawings kg 50.0
Mesh fabric reinforcement ref. No. A142 laid in floor slab with minimum 150 mm m2 21.4
side allowance
Sawn formwork
Formwork to sides of foundation strip girth over 75mm but not exceeding m 38.0
150mm ,plinth over 150mm but not exceeding 225mm, edges of floor slab girth
over 75mm but not exceeding 150mm

Walling
150mm Thick masonry foundation walling in cement and sand mortar (1:3) m2 4.2
400mm Thick masonry foundation walling in cement and sand mortar (1:3) m2 7.3
One layer 1000gauge polythene sheet damp proof membrane under beds: m2 20.1
300mm laps
200mm wide Bituminous felt damp-proof course m 12.2
Supply and fix 600x600x50mm thick medium duty precast concrete paving slabs m2 1.6
in cement sand mortar
Plinths
15mm thick cement sand rendering (1:3) to plinths m2 2.0
Prepare and apply three coats black bituminous paint to rendered plinths m2 2.0
externally
SUPERSTRUCTURES
Walling
150 Thick load bearing solid concrete block walling m2 26.9
Concrete Work
Vibrated reinforced concrete class 25 (1:1.5:3) with 20mm maximum aggregate
as described in:
Lintel m3 0.40
Reinforcement
8mm Diameter high tensile reinforcement bar kg 30.0
Sawn Formwork
Formwork to sides and soffits of ring beam m2 1.8
Roofing
Roof Structure
Sawn celcured cypress timber as described in:
200mm x 25mm Fascia Board m 15.0
l00x50mmRafters m 11.7
100mm x 50mm wall plate m 7.8
50 x 50 Purlins m 15.6
Roof Covering
30 Gauge galvanized corrugated iron sheets fixed to timber Purlins m2 15.2
Painting and Decorating
Knot prime stop and apply two undercoats and one gloss finishing coat oil paint m 15.2
to fascia board 200- 300 mm wide
Doors and Windows
Purpose-made Timber single door made of 1well seasoned timber, door No 1.0
complete with all the necessary locks overall size 1000 x 2100mm high
Purpose-made Timber window made of well seasoned timber complete with all No 1.0
the necessary ironmongery overall size 950 x 1100mm high
Precast concrete window cill size 260 x 50mm Thick sunk - weathered and m 1.0
throated and bedded and jointed in cement sand mortar
Prepare and apply two undercoats and one finishing coat oil paint to steel door m2 4.0

Ditto windows m2 2.0

Finishes

Floor Finishes
Cement and sand mortar (1:3) in:
30mm thick steel trowelled screed m2 14.9
100 x 25mm Thick skirting to junction with floor and wall finish m 11.0

Wall Finishes

Cement and sand mortar (1:3) rendering in:

13 mm Thick mortar rendering with steel float finish to masonry wall,walls and m2 60.0
beams,

Prepare and apply three coats plastic emulsion paint to:

Rendered surfaces and plastered surfaces m2 60.0

TOTAL COST FOR WATER KIOSK


No Summary of Borehole rehabilitation

1 Pipeline laying and joining works


2 Elevated Concrete Storage tank(25m3)
3 Supplies
4 Construction of 2 water kiosks
Total of Bore hole rehabilitation
Add 5% contigency
GRAND TOTAL
AMOUNT (USD)

-
-
-
-
-
-
-
-
-
-

-
SHALLOW WELL REHABILITATION
RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USD) (USD)

WELL REHABILITATION

Diameter 1.5m ; Average depth of excavation 9m


Excavation

Excavation including maintaining and supporting sides and


keeping free from water, mud and fallen materials by bailing,
pumping or otherwise
Excavate for foundation strip commencing at stripped level
depth not exceeding 9.50m deep m3 16 -

Extra-over for excavation in soft rock m3 3 -

Remove surplus excavated material from site m3 13 -


Filing
400mm thick approved natural ground material,Well compacted
approved selected material m3 25 -

Rubble stone embedded in sand cement mortar (1:4) m3 5 -

400 x 200mm stone steps built into wall No. 6 -


Vibrated Reinforced Concrete class 30(1:1:2) with 20mm
thick maximum aggregate size in
200mm Thick floor slab,200mm thick wall,200mm thick base
slab m2 27 -
Reinforcement
100mm thick perforated reinforced concrete rings reinforced as
shown on the drawings No 9 -

Sawn formwork

Formwork to sides and soffits of beam,sides and soffits of


pad,soffits of cover slab,sides of wall,Formwork to edges of
base slab over 150mm girth but not exceeding 225mm,base
slab over 75mm girth but not exceeding 150mm,cover slab over
75mm girth but not exceeding 150mm, m2 120 -
Walling

200mm Thick masonry walling in cement and sand mortar


(1:3),20 mm Thick plaster mixed with Sika or equivalent water
proofing admixture,15mm thick rendering m2 70 -
Hire of dewatering pump / lifting equipment x 45 day
@$50/day LS 1 -

TOTAL COST OF WELL REHABILITATION -


sahollow wells Bore hole rehabilitation
District Location Water source Distance HHs District Location Water sour
Beletxaaw Shirko sahollow wells 15 150 Luuq Luuq town Wells
GarbahareDabley sahollow wells 35 200 GarbaharreGarbaharreWells
GarbahareBurgudud sahollow wells 12 150 BeletxaawoBeletxaawoWells
GarbahareAnamalay sahollow wells 12 150
GarbahareBura sahollow wells 18 200
GarbahareResqode sahollow wells 18 200
Luuq Boholgarassahollow wells 80 200
Luuq Qoney sahollow wells 50 200
Luuq Cusbo sahollow wells 35 100
Luuq Godey sahollow wells 35 100

Total 1650 Total

Gedo project locations


Nr. Settleme District Region
nt
1 Dabley Garbaharrey Gedo
2 Resqode Garbaharrey Gedo
3 Anamaley Garbaharrey Gedo
4 Bura Garbaharrey Gedo
5 Godey Garbaharrey Gedo
6 Burgudud Garbaharrey Gedo
7 Maracade Garbaharrey Gedo
8 Degsharif Garbaharrey Gedo
9 Sirko Beletxaawo Gedo
10 Carabo Beletxaawo Gedo
11 Haroo Beletxaawo Gedo
12 Ceeldheer Beletxaawo Gedo
13 Lolays Beletxaawo Gedo
14 BoholgarasLuuq Gedo
15 Qoney Luuq Gedo
16 Cusbo Luuq Gedo
17 Karaban Luuq Gedo
18 Madawaje Luuq Gedo
19 Biyacade Luuq Gedo
hole rehabilitation
Distance HHs
500m 3300
600m 3300
5km 4000

10600

You might also like