Report
Report
The major duties and responsibilities of the Consultant include review and analysis work schedule,
analysis and review of the cost estimate and submission and Approval of contract document like
Drawing and technical specification, issue taking-over payment certificate or instruct the
contractor and subcontractors to complete outstanding work, Construction supervision, approval
contractor and subcontractor work requisition , comment on the Contract Document and assisting
the Client during negotiation.
Generally, project status is summarized as below:
To Date Physical Progress work status …………………….....................30%
To Date Financial Progress work status…………....……………………. 0.00%
This Month project performance…………………………………………. 2%
Problems and Critical Issues need attention
The contract agreement made between Oromia construction corporation and Oromia seed Enterprise for
Construction of Serofta Lift Irrigation Project with Contract amount of 92,270,620.03 (Eighty-Eight
million, Two Hundred Seventy Thousand, Six Hundred Twenty and 03/100 ETB) with 15% VAT.
Source of water for this irrigation project is Wabe River, which has season flow and the system of
conveyance canals discharge capacity of ….l/s and Duty for 12hrs of irrigation is …l/s/ha, it will be
propose to irrigate the existing net command area of about 383 ha during dry season in order to benefit
serofta state farm.
The major components of the works undertaken in this project were: general items, earthen
canal excavation and farm structures works, rising main and electromechanical works.
nowadays the construction of the project is on progress and active in this week besides the
physical and financial progress of this project based on original contract information was 30%
and 0.00% respectively.
Under this Contract agreement annual plan 2015 was prepared to perform following major
activities:
❖ General items
SITE PHOTOGRAPHS
Figure 1: Pond/Night storage Excavation
Figure2 : Generator house construction
Figure 3: Earthen canal excavation