Bridge Slides All
Bridge Slides All
Bridge Slides All
Components of
Bridge
Superstructure
Bearing
Substructure
Appurtenances and
Site related Structures
Superstructure
The structural components above the level of bearing are classed as
superstructure. Superstructure provides base for moving vehicles,
trains and pedestrians. Wearing course, deck slab, secondary
members (cross beams, bracings etc.) and primary members (main
girders, truss, arch etc.) are superstructure of bridge.
Secondary
Member
Deck
Wearing Primary
Course Member
Bearing
The mechanical device placed between superstructure and substructure
to transmit vertical and horizontal load to substructure allowing some
translational and rotational movements of bridge deck.
Bearing
Substructure
The structural components below the bearing level are classed as substructure.
Substructure provides support for superstructure and transfers loads from
superstructure to the bearing soil. Abutments, piers and foundations are
substructure of bridge.
Abutment
Pier
4
Appurtenances and site related structures
Appurtenances and site related structures are the supplementary parts of
bridge structure, which are required for overall functioning of bridge.
Embankment and slope protection structure, river training structure,
expansion joint, approach slab, wing walls etc. are appurtenances.
Wing wall
Slope protection
structure River training
structures
Components of Bridge
Steel Truss
Approach Slab RC Girder Road Way
Bearing
River
Abutment with
Pile Foundation
Embankment
protection work River Bed Pier with Well Foundation
6
Different types of bridges
According to the type of
superstructure
According to the materials used in
the superstructure Slab Bridge
T-beam Bridge
Timber Bridge Box Girder Bridge
Masonry Bridge Frame Bridge
RCC Bridge Truss Bridge
Steel Bridge Arch Bridge
Composite Bridge Suspension Bridge
Prestressed Concrete Bridge Cable Stayed Bridge
Permanent Bridge
Temporary Bridge
According to the means of
transport
According to the
Highway Bridge profile of the bridge
Railway Bridge
Pedestrians Bridge • Straight bridge
Utility Bridge • Skewed bridge
• Curved bridge
According to the
floor arrangement Curved bridge
Deck Bridge
Through Bridge
Half Through Bridge
Skewed bridge 8
Slab Bridge
Solid slab bridge
Negative aspects
Has heavy self weight
Economically not effective for large span
of bridge
Can only cover small span
Positive aspects
Increases clearance above the afflux due to the
shallow depth of slab
Gives clean attractive appearance
Has good lateral load distribution characteristics
due to its good torsional stiffness
Requires low maintenance cost
T-Beam Bridge
Negative aspects
Kerb
Steel Beam
Elastomeric Bearing
Pier
Expansion Joint
Abutment
Approach Slab
Truss Bridge
Bracing
Top Chord Joint Vertical
Diagonal Member
Member
Bridge Deck
Bottom Chord
Negative aspects
Positive aspects Reduces vertical clearances above the
afflux due to its depth
Easy to construct Requires thorough maintenance regularly
Has rigid structure and can cover No longer economically competitive
relatively larger span (300m) Gives rough appearance
Components of Truss Bridge
Top Lateral Bracing
Portal Bracing
Sway Bracing
Stringer
Floor Beam
(Cross Beam)
Bearing
Box Girder Bridge
Negative aspects
Positive aspects
Negative aspects
16
Frame Bridge
Positive aspects
Negative aspects
18
Cable Stayed Bridge
Positive aspects
Negative aspects
Cable System
Truss System
Arch System
Frame System
Bridge as a Different Structure
Mostly length of bridge structures come about large. Large length promotes
huge translational and rotational movements. Consequently, arises need of
some mechanism at the joint of superstructure and substructure in bridges,
which could allow these movements to prevent large secondary stresses.
Primary loads on bridges are heavy moving loads. These moving loads have
governing role on the structural behaviour of bridge structure. Consequently,
arises need of minute examination of the responses of bridge to moving loads.
Mostly bridges are built over the obstructions or in difficult places i.e. over the
river, streams, marshy land, gorge or intersection of roadway or railway, which
always adds complications in the construction. Consequently bridges are not
designed, without considering their construction methods.
• Cost of labor
• Cost of material
• Construction details
• Transportation and erection cost
• Weight of elements if precast construction is used
• Span length and pier height
• No. of span
• Structural system and its cross section
• Time available for construction
• Design load
• Maintenance cost
An example of the breakdown of cost
for typical medium span PSC Bridge in remote location
2
RC T-Beam RC Box girder
Bridge
1 RC solid
slab bridge
Span, m
0 5 10 15 20 25 30 35
RC/Composite
Girder
RC Slab
6–8m 8 – 50 m 6–8m
9
Span Arrangement with
Girder/Slab and Truss Alternate 2
Steel Truss
RC/Composite
Girder/Slab
6 – 50 m 2 5 – 300 m 6 – 50 m
10
Span Arrangement with Steel Truss
Alternate 3
Steel Truss
25 m - 300 m
11
Span Arrangement with
RC Continuous Girder Alternate 4
RC continuous girder
12
Trend of Construction of Bridges
A case study of Japan
Based on the inventory report
Other
Bridges
4.2%
RC Bridges
19.4%
Steel
Bridges PC Bridges
40.7% 35.7%
Data to be acquired
Data required for
• Flood type • Length of bridge
Hydrological • Water current • Height of bridge
Study • Design discharge • River training works
• Flood level • Type and depth of
• Scouring depth foundation
• Linear water way
Data required for
Data to be acquired
• Location of bridge
Geological & • Engineering
• Location of pier
Geotechnical properties of soil
and abutment
Study • Geological feature
• Depth and type of
of subsoil
foundation
Data to be acquired
Data required for
• Topographic feature
of bridge site • Location of bridge
Topographic • Length of bridge
• Cross section of river
Study profile • Height of bridge
• Longitudinal section • Type of pier and
of river profile abutment
Bridge Hydrology and Hydraulic Design
Bridge hydrology is based on the principle of determining opening of bridge so that
peak flood of the river can pass without either overtopping the banks or endangering
the bridge itself. So in hydrological study following hydrological data should be carefully
found.
1. Design Discharge
Volume of water passing through a particular intersection of river/stream per
unit time considered in design
Design discharge is decided on the basis of maximum flood discharge record for a
period of not less than 50 years.
Design discharge is calculated by using rational formulas like area velocity formula or
by applying Unit hydrograph
2. Design Highest Flood Level (HFL)
Distance between the banks required to pass the full discharge at design velocity
- Distance between the bank at HFL in the river with rigid banks and bed
- Distance between the bank at HFL in the river with rigid banks and
erodible bed
- For river in alluvial beds and having undefined banks the linear waterway
shall be determined from the design discharge.
(Lacey’s formula)
Where,
W = effective linear waterway in m
Q = design discharge in m3/sec
C = 4.5 to 6.3
4. Scour Depth – Expected erodible depth of river bed
For natural channels with alluvial bed and bank , mean depth of scour ‘dsm’ is
Carriage Way
No of lane
(m)
<5.3 1
≥ 5.3 Min. width of carriage way = 4.25m
2
<9.6
Min. Width of footway = 1.5 m
≥ 9.6 Min. width of safety kerb = 750 mm
3
<13.1
≥ 13.1
4
<16.6
Vertical Clearances
Minimum distance between the HFL with afflux of the channel
to the lowest point of the bridge superstructure
Vertical
clearance Carriageway Carriageway
5m
• Height of railing above kerb surface should not be less than 1.1m – half
the width of rail
• Width and height of safety kerb should be greater than 225 mm.
Road Kerb
225 mm
175 mm
Road
Railing R = 25 mm Surface
225 mm
Bridge Loading
Refer IRC 6-2014
While designing the bridges the following loads and forces should be
considered where applicable.
1. Dead load
2. Live load
3. Dynamic load
4. Longitudinal forces
a. Longitudinal forces by the tractive effort of vehicles
b. Longitudinal forces by braking of vehicles
c. Longitudinal forces due to frictional resistance of expansion bearings
5. Wind load
6. Centrifugal forces of vehicle due to curvature of bridge
7. Horizontal forces due to water currents
8. Buoyancy
9. Force exerted by earth pressure
10. Load induced by temperature variation effect
11. Load induced by creep, shrinkage and other secondary effect
12. Erection load
13. Loads induced by earthquake
Pedestrian load
IRC Bridge
Live Load Vehicular load
Class A load
Class B load
Normal load • Wheeled load
Represents normal • Tracked load
vehicular traffic
Class AA load
Abnormal load • Single, Two and
Represents industrial or Seven Axel
military vehicular traffic wheeled load
Class 70R load
• Tracked load
Class A/B Loading
20 1.1 3.2 1.2 4.3 3 3 3 20 C/C distance of axle (m)
Total length of a train = 18.8m
16 16 68 68 41 41 41 41
CLASS B LOADING (KN)
1.8 m
f g
B
1.1m Cross section
3.2m
Carriageway
G F
Width
1.2m
Uniformly increasing
5.3 to 6.1m 150 mm
from 0.4 to 1.2.m
W
Above 6.1m 1.2 m 150 mm
Plan
Class 70R Loading
Class 70R tracked vehicle
1.22m
350KN 350KN
2.06m
Class 70R Loading Cross-section of Class 70R two
axel wheeled load 400KN
70R seven axel wheeled load 1000 KN
C
1.22m
2.79 m
2.79 m Plan
Plan
Wheel Arrangement of 70R Wheeled Load
2.79 m
0.86 m
0.61 m
0.41 m
‘L’ Type
2.79 m
0.23 m 0.25 m
0.51 m
0.51 m
‘N’ Type
Class AA Loading
[Refer Annex]
Cross-section of Class AA
wheeled load 400KN
C
Total Weight 700 KN
90m
3.6 m 37.5 62.5 62.5 37.5 KN
7.2m
≥20.1
<23.6 6
Combination of live loads
Class A
1.8 m
0.4m
5 KN / m2 For Single Lane Bridge
0.15m 0.5m
2.3 m
Class A Class A
1.2m
For Two Lanes Bridge
Pedestrian Load
Length of bridge ≤7.5 m ; Intensity of load = 4 or 5 KN/m2
>7.5m; Intensity of load ≤ 4 KN/m2
P = P’ – (40L – 300)/9 for up to 30 m span
P = (P’ – 260 + 4800/L) × (16.5 – W)/15 for greater than 30 m span
P’ = 4 or 5 KN/m2
P – Intensity of load
W – Width of foot way
L – Span of bridge
Live load information required for
analysis of bridge deck
• Type of load
• Number of axle of vehicle
• Magnitude of load on each axle
• Spacing of axle
• Contact area of wheel /track
• Spacing of vehicle in transverse and longitudinal direction
• Maximum lane load
• Reduction of live load in excess of two lanes
• Arrangement of wheel in case of 70R wheeled and train loading
• Combination of live loads
Impact Load Moving live load with its dynamic effect.
Dynamic effect of live load is calculated by the impact factor.
Impact load = static value of live load × Impact factor
For Class AA and Class 70R loading for span less than 9 m
• For tracked vehicles: 25% for span up to 5m linearly reducing to 10% for spans of 9 m
• For wheeled vehicles: 25%
50
A and B ( Steel bridge )
25
Class AA/70R tracked ( Concrete bridge )
Class AA/70R tracked ( steel bridge )
10
0
0 5 10 20 25 45 Span of bridge, m
LONGITUDINAL FORCES
1. Externally applied longitudinal forces
• Tractive effort caused through acceleration of driving wheels
• Braking effort due to application of brakes to the wheels
• Frictional resistance offered by free bearings due to change of
temperature, shrinkage and creep
• For single or two lane bridge, braking loads taken as 20%of the first
train load and 10% of the loads of succeeding trains.
• For multilane bridge, braking load is taken as in (a) for the first two
lanes and 5% of the loads on the other lanes.
• The force due to braking effort shall be assumed to act 1.2m above
the roadway.
Forces due to frictional resistance offered by bearing
Span with
elastomeric bearings
Fh /2+ sδ Fh /2+ sδ
II. Simply Supported/ Continuous
deck on flexible support
1 2 3
µW CL Sn + Fh X Sn /∑S CL Sn + Fh X Sn /∑S
3 0.68
4 0.73
Pier Pier
R Ground
Shaking
Enveloping
Enveloping cylinder
Ground
cylinder
Shaking
Load Combinations
in the Design of Bridge [WSDM]
Combination
of loads
I
II A
II B Increase in
permissible stress
III A 0 - 50 %
III B according to load
IV combination
V
VI
VII
VIII
IX
Load Combination [WSDM]
Load Combinations
in the Design of Bridge [LSDM]
IRC 6 define four cases separately i.e. foundation, stability, limit state of
strength and limit state of serviceability to be considered in Limit State
Design Method. In each cases, there are further three combinations of loads
to be considered.
Partial safety factors for loads for different combinations and for different
works are not similar. They are chosen as specified in code
Refer IRC 6 – 2014, Table 3.1, 3.2, 3.3 and 3.4 for combination of loads
BRIDGE RESPONSES
The term bridge responses refers to
LBM causes flexure in
1. Longitudinal Bending Moment longitudinal vertical plane
Shear in transverse
2. Longitudinal Shear vertical plane
Shear in longitudinal
5. Transverse Shear vertical plane
Torsion in transverse
6. Transverse Twisting Moment vertical plane
• The responses, which need to be determined for
nearly all bridges, are longitudinal bending
moment, longitudinal shear and transverse
bending moment
bef/bact udl
Effective width of beam for Point
bridge load is always lesser than load
the effective width of beam for
ordinary load.
L/B
Longitudinal Shear
Transverse distribution of
longitudinal shear force is markedly
different from transverse
distribution of longitudinal BM. It
is peakier in nature.
Pattern of longitudinal SF
distribution across the transverse
section of bridge deck is same not Transverse
depending upon the longitudinal dist n of LSF
position of live load.
Longitudinal SF is assumed to be
resisted by the web of girder.
Transverse Bending Moment
x1
L1
x1 L1 L1
L
Equal distance
R
Section of Absolute
Maximum BM W1 W2 W3 W4 W5
L1 L
l
Method of Bridge Deck Analysis
METHOD OF LATERAL LOAD DISTRIBUTION
Support
Type of Deck Plan Profile
Method Condition
of Analysis Box
Slab T-Beam Straight Skew Curve Simple Contin.
Girder
Effective Width
√ √ √ √
Method
Courbon’s Method √ √ √ √
Hendry Jaeger
Method
√ √ √ √ √
Method of Elastic √ √ √ √ √
Support
Distribution
Coefficient Method √ √ √ √ √
AASHTO Method
√ √ √ √ √
Grillage Analogy √ √ √ √ √ √ √ √
Finite Element
Method √ √ √ √ √ √ √ √
Effective Width Method of Lateral Load Distribution
• Load on the slab is borne by the strip parallel to the
supporting edges on the either side of the load. The
strip is called effective width of slab.
bef = 1.2a + b1
Where
bef - Effective width of slab on which the loads acts
a - Distance of center of gravity of load from the
face of the cantilever support
b1 - Breadth of concentration area of load (W+2h)
h - Thickness of wearing coat
W- Contact width of wheel/track parallel to support
of slab
Effective Width of
Cantilever Slab
• Effective width of cantilever
slab should less or equal to
one third length of cantilever
a slab
Find live load on slab bridge for its unit width at mid span for the following
data
• Effective span of bridge = 8 m
• Width of kerb = 0.6 m
• Carriage Way = 7.5 m Track of 0.85 m width
• Live load = Class AA(T)
• Thickness of wearing coat = 60 mm
• Depth of slab = 650 mm
a=4m
4.28 m
Since the effective widths of tracks overlap, 2.05 m
find the modified width for two tracks. 1.625 m
LL per unit width of slab = 700/7.37 = 88.61 KN/m Positioning of track load
Lateral distribution of load
COURBON'S METHOD OF
LATERAL LOAD DISTRIBUTION
1 2 3 4
I1 I2 I3 I4
In Courbon’s method, load shared by each girder in
central region of bridge deck is found by
R1 = P I1 / ∑I ± M I1 h1 / ∑Ih2
R2 = P I2 / ∑I ± M I2 h2 / ∑Ih2
R3 = P I3 / ∑I ± M I3 h3 / ∑Ih2
R4 = P I4 / ∑I ± M I4 h4 / ∑Ih2
In end region i.e., 5.5 m from the support, simple beam method is
employed for lateral load distribution.
Find load on girder 1, 2 and 3 from the following For Point Load
loading conditions. R1 = P I1 / ∑I + M I1 h1 / ∑Ih2
= 200/3 + 200/2 = 500/3 KN
1 2 3 R3 = P I3 / ∑I - M I3 h3 / ∑Ih2
I I I Cross Section of Bridge = 200/3 - 200/2 = - 100/3 KN
1m 1m
R3 = P I3 / ∑I + M I3 h3 / ∑Ih2
1 2 3
= 10/3 + 0 = 10/3 KN for central region
=0 for end region
1 2 3 1 2 3
1 2 3
3. Find load on each girder
0.75 m 3m 3m 0.75 m = ∑Distribution coefficient × Eq. Loads
R1 = p11H1 + p12H2 + p13H3 = 1.355 W
R2 = p21H1 + p22H2 + p23H3 = 1.347 W
R3 = p31H1 + p32H2 + p33H3 = 1.298 W
Where ,
p11 = 0.365, p12 = 0.325, p13 = 0.310
p21 = 0.325, p22 = 0.350, p23 = 0.325
P31 = 0.310, p32 = 0.325, p33 = 0.365
Distribution Coefficient Method
• Distribution coefficient method is a simplified method of
bridge deck analysis based on orthotropic plate theory
• In this method distribution coefficients are used to
distribute the load and determine responses of bridge deck.
• Distribution coefficient depends on flexural and torsional
characterizing parameters of bridge deck.
1-1
M1
M’1
2-2
M2
M’2
M’1/M1 = M’2/M2 = K
• For accuracy of distribution coefficient, bridge deck is
converted into a plate with eight segments/ nine
reference stations and distribution coefficient
coefficients are found for these reference stations.
Actual Bridge Deck Orthotropic Plate
B
P
2a
L
• To determine distribution coefficients graphs drawn
against flexural characterizing parameter (θ) and load
positions are used. Such graphs have been drawn for
torsionally weak ( =0) and torsionally strong ( =1)
bridge deck.
For intermediate value of ‘ ’ interpolation is made to
determine the distribution coefficients.
K = K0+(K1-K0)
2b = 9 m
2a =21 m
3. Find distribution coefficient for required value of ‘α’
K' = ∑KW/∑W
= 1.25 for girder 1
= 1.02 for girder 2
= 0.73 for girder 3
100%
80% 80%
Transverse Section
100%
75% 75%
Longitudinal Section
for ‘0’ ∑
ref. st. 0 b/4 b/2 0.471b
1
2.5 m
2 3 1 ✓ ✓ 0.2674
1.85 m 2.5 m 1.85m
3 ✓ ✓ 0.1006
5 ✓ ✓ 0.0500
Lateral Load Distribution in Through Truss Bridge ILD of reaction
For Track Loading
Lever Arm Method of a truss
p
1
• Construct ILD of reaction of a truss.
RC Slab
D
Tar Paper
Abutment
Approach
Slab
Design Steps of RCC Solid Slab Bridge
Railing B D Slab
emax
emin
x1
L1
x1 L1 L1
L
l
• Compute effective width of slab at each critical section and obtain live load
bending moment and shear force per unit width at these sections.
✓ Strip of slab, which bears the load on the slab is effective width of slab.
Where,
bef - Effective width of slab on which the loads acts
l - Effective span in case of simply supported slab and clear span in case of
continuous slab
a - Distance of center of gravity of load from nearer support
b1 - Width of concentration area of load (b1 = W + 2h )
- Constant depending upon the ratio l'/l (See table of IRC 21 for value of )
l' - Width of slab
h - Thickness of wearing course
W- Contact width of wheel/track parallel to the width of bridge (Ref. IRC 6)
Effective Width of Slab ✓ Effective width should not
exceed the actual width of
the slab.
bef = a (1-a/l) + b1
✓ When concentrated load is
close to the unsupported
edge of a slab, the
Abutment Load effective width shall not
a
exceed the above value or
half of the above value
River plus the distance of the
l
load from the unsupported
edge.
b1 = W+2h
✓ When effective widths for
two adjacent loads
overlap, in such cases the
resultant effective width
l΄ will be equal to the sum of
individual widths minus the
Plan of Slab Bridge overlap.
• Compute dead load and find dead load bending moment and shear force per unit
width at critical sections.
wu
Self wt of slab and wearing coat
per unit width of slab
l
• Find transverse bending moment (TBM) due to live load and dead load per unit width
of slab. Use codal formula to find TBM. [Refer cl.305.18.1, IRC 21]
Find area of steel of longitudinal bars Ast, diameter of bars and their spacing
Ast = Mu / 0.87fy(d - 0.416xu) for SRURS
Ast ≥ Ast,min = 0.12% of gross sectional area of slab
Find area of steel of longitudinal bars Ast, diameter of bars and their spacing
Ast = Max. TBM / 0.87fy(dtr - 0.416xu)
Ast ≥ Ast,min = 0.12% of gross sectional area of slab
• Check slab for shear
𝒍
≤ 𝜶𝜷𝜸𝜹𝝀
𝒅
Or
Δ max ≤ Δ max
• Design kerb/foot path as a beam for edge stiffening
Edge stiffening beam is designed for its self weight, dead and live load on it and
horizontal load of 7.5 KN/m at top of kerb/footpath.
Provide 250 mm2 area of steel bars per unit meter in both direction of
slab or minimum area of steel bars as temperature bars
Reinforcement of Slab Bridge
Vertical stirrups
of edge stiffening beam Temperature reinforcement
Side face
reinforcement Transverse reinforcement
Bars of edge Longitudinal reinforcement
stiffening beam
Design Problem
Design a Slab Bridge to meet the following requirements
➢ Bridge clear span – 6m
➢ Bearing width of slab – 400 mm
➢ Carriage way – Two lane
➢ Safety kerb on either side of bridge
➢ Wearing coat – Asphalt concrete
Design of bridge deck has been carried out in the following steps.
B. Material Selection
Take
Take
0.1 m
0.4 m
1.1 m
Fig: Railing
0.4 m
0.4 m
0.225 m
Take Standard type of drainage spout with 100 mm dia. drainage pipe
Take Asphalt Concrete for wearing coat of bridge. Thickness of wearing coat is taken 50 mm
at edge and 110 mm at mid of carriage way to give about 2.5% camber.
Length of Bridge
1.1 m
7.5 m RC post of 225 mm × 225 mm
with three heavy steel pipes
0.55m
9.5 m
Longitudinal Section
of Bridge at B-B
6.4 m
L = 6.8 m
A
Take self-weight of RC slab and wearing coat as dead loads for middle strip of slab.
Design load due to self-weight of slab and wearing course for one meter strip (𝑤𝑢 )
= 𝐷𝑠 𝛾𝑅𝐶 𝑟𝑓 𝐷𝐿 + 𝐷𝑤𝑐 𝛾𝑤𝑐 𝑟𝑓 𝑤𝑐 = 0.55 × 25 × 1.35 + 0.08 × 22 × 1.75 = 21.65 𝐾𝑁/𝑚
wu = 21.65KN / m
6.4 m
Where,
Unit weight of reinforced concrete 𝛾𝑅𝐶 =25 KN/m3
Unit weight of Asphalt concrete (wearing coat) 𝛾𝑤𝑐 =22 KN/m3
Partial safety factor for DL (slab) 𝑟𝑓 𝐷𝐿 = 1.35
Partial safety factor for wearing coat 𝑟𝑓 𝑤𝑐 = 1.75
Average depth for wearing course 𝐷𝑤𝑐 = (0.11 + 0.05)/2 = 0.08 m
[For partial safety factor for load refer IRC 6 -2010]
According to IRC 6 -2010 Table 2, following live load shall be considered for two Lane Bridge.
Calculation of maximum longitudinal bending moment (LBM) at critical section of bridge deck
Longitudinal bending moment is maximum at mid span of slab. So in this example, LBM due to
dead load and live load have been calculated for mid span of slab.
Find LBM due to Class A load, Class AA tracked load and Class AA wheeled load at mid
span. Maximum value of LBM is taken for design.
Position two trains of Class A load transversely at maximum eccentricity from the
center of deck maintaining minimum clearance from footpath.
Take minimum clearance from footpath for class A load = 0.15 m and clear distance
between two trains of Class A load = 1.2 m
Position Class A train longitudinally to give maximum LBM at mid span. In 6.4 m span
maximum loaded axles of Class A load is placed symmetrically with respect to mid
span of bridge to get maximum LBM at mid span.
Longitudinal dispersion of the Class A load has not been considered in the example
0.5 m
B = 9.5 m
Find effective width (bef) of a wheel of Class A load [Refer IRC 21-2000 Cl. 305.16.2]
𝑎 2.6
bef = 𝛼 × 𝑎 1 − + 𝑏1 = 2.83 × 2.6 1 − + 0.66 = 5.03 m
𝑙 6.4
𝐵 9.5
𝑊ℎ𝑒𝑟𝑒, 𝑎 = 2.6 m, l = 6.4 m, b1 = 0.08 × 2 + 0.5 = 0.66 m, 𝛼 = 2.83 𝑓𝑜𝑟 = = 1.484
𝑙 6.4
Since the bef of individual wheel overlaps, find modified effective width for all wheels of axle I
and axle II.
𝑏 𝑒𝑓
bef 𝑚𝑜𝑑 = bef 𝑚𝑜𝑑 𝐼 = bef 𝑚𝑜𝑑 𝐼𝐼
= 1 + 0.4 + 1.8 + 1.7 + 1.8 + = 9.125 < 𝐵 = 9.5 𝑚
2
Hence, Adopt bef 𝑚𝑜𝑑 = 9.215 𝑚
2 × 114 × 𝐼𝐹 × 𝛾𝐿𝐿
𝑓 2 × 114 × 1.363 × 1.5
Load per unit width of slab = 𝑚𝑜𝑑 = = 50.6 KN/m
b ef 9.215
Maximum LBM at mid span = 50.6 × 3.2 - 50.6 × 0.6 = 131.6 KN-m
Position a set of Class AA (T) load transversely at maximum eccentricity from the
center of deck maintaining minimum clearance from footpath.
Take minimum clearance from footpath for class AA load in two lane bridge 1.2 m
Position Class AA (T) longitudinally to give maximum LBM at mid span. Symmetrical
placement of track at mid span gives maximum LBM.
Consider Longitudinal dispersion of track load (along span)
Ldis = 3.6 +2 × (D + h) = 3.6 + 2 × (0.55 + 0.08) = 4.86 m
4.86 m
a = 3.2 m
I = 6.4 m
1.625m
1m 1.2m 1.2m
0.85 m 0.85 m
B = 9.5m
Find effective width (bef) of individual track [Refer IRC 21-2000 Cl. 305.16.2]
𝑎 3.2
bef = 𝛼 × 𝑎 1 − + 𝑏1 = 2.83 × 3.2 1 − 6.4 + 1.01 = 5.538 m
𝑙
Where a = 3.2 m, l = 6.4 m, b1 = 0.08 × 2 + 0.85 = 1.01 m, 𝛼 = 2.83 for B/L = 1.484
Since the bef of individual track overlaps, find modified effective width for two tracks.
𝑚𝑜𝑑
𝑏𝑒𝑓 = 1 + 1.625 + 2.05 + bef /2 = 7.44 m < B = 9.5 m
𝑚𝑜𝑑
Adopt 𝑏𝑒𝑓 = 7.44 𝑚
700 × 𝐼𝐹 × 𝑟 𝑓 𝐿𝐿 700 × 1.1975 × 1.5
Load per unit width = 𝑚𝑜𝑑 = = 34.77 KN/m
b 𝑒𝑓 × 𝐿𝑑𝑖𝑠 7.44 × 4.86
Position a set of Class AA (W) load transversely at maximum eccentricity from the
center of deck maintaining minimum clearance from footpath.
Take minimum clearance from footpath for class AA load in two lane bridge 1.2 m
Position Class AA (W) longitudinally to give maximum LBM at mid span. Symmetrical
placement of two axle at mid span gives maximum LBM.
Longitudinal dispersion of load has not been considered in the example
0.3 m
B = 9.5 m
Find effective width (bef) of individual track [Refer IRC 21-2000 Cl. 305.16.2]
𝑎 2.6
bef = 𝛼 × 𝑎 1 − + 𝑏1 = 2.83 × 2.6 1 − 6.4 + 0.46 = 4.829 m
𝑙
Where a = 2.6m, l = 6.4 m, b1 = 0.08 × 2 + 0.3 = 0.46 m, 𝛼 = 2.83 for B/l = 1.484
Since the bef of individual wheel overlaps, find modified effective width for all wheels of
individual axle of Class AA (W)
0.3 𝑏𝑒𝑓
bef 𝑚𝑜𝑑 𝐼 = bef 𝑚𝑜𝑑 𝐼𝐼 = 1 + 1.2 + + 0.6 + 1 + 0.6 + = 6.96 𝑚 < 𝐵 = 9.5 𝑚
2 2
Adopt bef 𝑚𝑜𝑑 = 6.96 𝑚
Maximum LBM at mid span = 53.88 × 3.2 - 53.88 × 0.6 = 140.1 KN-m
LSF is maximum at support of slab. So in this example, LSF due to dead load and live load have
been calculated for support of slab.
wu = 21.65KN /
m
6.4 m
Find LSF due to Class A load, Class AA tracked load and Class AA wheeled load at support.
Maximum value of LSF is taken for design.
Position two trains of Class A load transversely at maximum eccentricity from the
center of deck maintaining minimum clearance from footpath. [Ref. LBM due to Class A]
Take minimum clearance from footpath for class A load = 0.15 m and clear distance
between two trains of Class A load = 1.2 m
Position Class A train longitudinally in such a way so that dispersion of wheels of axle I
will not go beyond the face of support.
Longitudinal dispersion of the Class A load has not been considered in the example
2×114×𝐼𝐹×𝑟 𝑓 𝐿𝐿 2×114×1.363×1.5
Load per unit width = = = 57.06 KN/m
𝑏𝑚𝑜𝑑
𝑒𝑓
𝐼
8.17
Similarly,
𝑚𝑜𝑑 𝐼𝐼
𝑏𝑒𝑓 =1 + 0.4 + 1.8 + 1.7 + 1.8 + 𝑏𝑒𝑓 𝐼𝐼 / 2
= 9.05 m < B = 9.5 m
𝑚𝑜𝑑 𝐼𝐼
Hence, 𝑏𝑒𝑓 = 8.17 𝑚
2×114×𝐼𝐹×𝑟 𝑓 𝐿𝐿 2×114×1.363×1.5
Load per unit width = 𝑚𝑜𝑑 𝐼𝐼 = = 51.51 KN/m
𝑏𝑒𝑓 9.05
S.F. at support VA
VA × 6.4 = 57.06 × (6.4 - 0.955) + 51.51 × (6.4 - 2.155)
∴ VA = 82.71 KN
Similarly,
𝑚𝑜𝑑
𝑏𝑒𝑓 𝐼𝐼
=1 + 1.35 + 0.6 + 1 + 0.6 + 𝑏𝑒𝑓 𝐼𝐼 /2 = 6.77 m < B = 9.5 m
𝑚𝑜𝑑 𝐼𝐼
Hence, 𝑏𝑒𝑓 = 6.77 𝑚
200×𝐼𝐹×𝑟 𝑓 𝐿𝐿 200×1.25×1.5
Load per unit width = = = 55.39 KN/m
𝑏𝑚𝑜𝑑
𝑒𝑓
𝐼𝐼 6.77
S.F. at support VA
VA × 6.4 = 63.83 × (6.4 - 0.905) + 51.51 × (6.4 - 2.105)
∴ VA = 89.37 KN
a = 2.63 m
m I = 6.4 m
S.F. at A
Calculation of maximum transverse bending moment (TBM) at mid of mid span of Slab Deck
Transverse bending moment of slab deck per unit width has been calculated according to IRC
21-2000 Cl. 305.18.1
Maximum TBM at mid of mid span = 0.3 × Max. LBM due to LL + 0.2 × Max. LBM due to DL
= 0.3 × 167.8 + 0.2 × 110.85
= 72.51 KN-m
III. Design
1000 mm
Take
Design Section
d (Log. Bar) = 550 – 40 – 20/2 = 500 mm
d (Tr. Bar)
Check depth of =slab
550 – 40 – 20 -12/2 = 484 mm
𝑀𝑢 278.65 × 10 6
𝑑𝑏𝑎𝑙 = = = 284.2 mm
𝑄×𝑏 3.45×1000
a. Longitudinal Reinforcement
𝑀𝑢
Find
𝑏𝑑 2
𝑀𝑢 278.65 × 10 6
= = 1.115 ≅ 1.15
𝑏×𝑑 2 1000×500 2
From table, pt= 0.338 % for fck= 25N/mm2 and fy= 415 N/mm2,
0.338
𝐴𝑟𝑒𝑞
𝑠𝑡 = × 1000 × 500 = 1690 mm2
100
Adopt 6 - 20 mm ∅ bar; 𝐴𝑝𝑟𝑜𝑣
𝑠𝑡 = 1885 mm2
Provide 20 mm ∅ @ 167 mm c/c
b. Transverse Reinforcement
𝑀𝑢 72.51 × 10 6
= =0.3095 ≅ 0.35
𝑏×𝑑 2 1000 × 484 2
c. Temperature Reinforcement
Provide 250 mm2 steel bars per m width as temperature reinforcements in both
direction of slab. [Refer IRC 21- 2000 Cl. 305.10]
Provide 12 mm ∅ bar @ 300mm c/c
𝒍
Check ≤ 𝜶𝜷𝜸𝜹𝝀
𝒅
Where,
𝑙 6.4
Actual span effective depth ratio of slab = = 12.8
𝑑 0.5
Limiting value of span effective depth ratio 𝛼𝛽𝛾𝛿𝜆= 20 × 1× 1.35 × 1 × 1 = 27
[Refer IS 456 Cl. 23.2.1]
𝑙
Since < 𝛼𝛽𝛾𝛿𝜆, deflection of slab deck is under control.
𝑑
Where,
2
Design Anchorage length = × 𝑙𝑑 = 385 mm [Refer IRC 21- 2000 Cl. 304.6.2]
3
𝑙𝑑 = 𝛼1 𝛼2 𝑙0
𝛼1 = 0.7 for bar with hooks
1690
𝛼2 = Bars required / Bar provided = = 0.896
1885
𝑙0 = 46 ∅ = 46 × 20 = 920 𝑚𝑚
2 1690
Provided anchorage length = 3 × 0.7 × 1885 × 46 × 20 = 385 mm
Design Section
Design Loads on Edge Stiffening Beam
Total design load (𝑊𝑢 ) = 36.35 KN/m [Without vehicular live load]
a. Longitudinal Reinforcement
𝑀𝑢
Find
𝑏𝑑 2
𝑀𝑢 354 × 10 6
= = 0.553 ≅ 0.6
𝑏×𝑑 2 1000 ×800 2
b. Shear Reinforcement
𝑉𝑢 216.84×1000
Find 𝜏𝑢𝑣 = = = 0.271 N/mm2
𝑏𝑑 1000 ×800
𝜏𝑢𝑐 = 0.29 N/mm2 for M25 and pt > 0.15 %,
Since 𝜏𝑢𝑣 < 𝜏𝑢𝑐 , shear reinforcement is not necessary to design. Provide
minimum shear reinforcement. Consider 8mm ∅ 4 legged stirrups
0.87×𝑓𝑦 ×𝐴𝑠𝑣
𝑆𝑣 = = 181.5 mm; Adopt 𝑆𝑣 = 180 mm
0.4×𝑏
Provide 8mm ∅ @ 180 mm c/c four legged vertical stirrups
Check provided shear reinforcement for horizontal load of 7.5 KN/m acting at the
top of footpath.
Negative aspects
In this Bridge, Main Load Bearing Members
Gives less clean appearance
in super structure of bridge are T-beams Can be economically effective up
to 30 m span of bridge
Economically Effective Span of T-Beam Bridge
Positive aspects
RC T-Beam Bridge - 10 m to 25m
Easy to construct due to its simple geometry
PSC T-Beam Bridge – up to 35m Gives economy due to monolithic construction
of beam and slab 2
General Arrangements of Deck of T-Beam Bridge
CW Wearing
Railing Course
Kerb
Drainage
Cross girder Spout
Main girder
at support Main girder
Elastomeric Bearing
Pier
Expansion Joint
Abutment
Approach
Slab
A Part of Longitudinal Section of Bridge at B-B
Mid line
A
Design Steps of RCC T-Beam Bridge
1. Determine approximate thickness of slab and depth, width and other
dimensions of girder and assign size of carriageway, footpath/kerb, wearing
course and railing.
2. Design cantilever slab. Calculate dead load, position live load, analyze the slab
by effective width method, verify the thickness of slab, find reinforcing bars
check for shear and carryout detailing of reinforcing bars.
3. Design restrained slab. Calculate dead load, position live load, analyze the
slab by Pigeaud’s Method, verify the thickness of slab, find reinforcing bars,
check for shear and carryout detailing of reinforcing bars.
4. Design main beam. Calculate dead load, position live load longitudinally and
transversely, analyze the beam, verify the thickness of beam, design beam for
longitudinal and transverse reinforcement and carryout detailing of
reinforcing bars.
5. Design Cross beam. Calculate dead load, position live load longitudinally and
transversely, analyze the cross beam, verify the thickness of beam, design
beam for longitudinal and transverse reinforcement and carryout detailing of
reinforcing bars.
Planning and Preliminary Design of T- Beam Bridge [Ref. IRC 5 & IRC 21]
• Assign sizes of slab, main girder, cross beam, carriageway, footpath/kerb, wearing
course and railing and determine number and spacing of beams
bact
• C.W. = 4.25 m for single lane
Df = 7 m or 7.5m for double lane
α • Ht. of railing (h) ≥ 1.1m – half width of railing
bw D • Width of kerb (b) ≥ 0.225m from face of railing
• Width of footpath (b)≥ 0.6m
α • Df min = 200mm (150mm at tip)
≥bw/2 • D = span/10 to span/15 for simple span
B = span/25 to span/20 for cont. span
• bw ≥ 250mm
C.W. • B ≤ 4bw
bact • α ≥ 1100
• S = 2-3m
• Spacing of cross beam = 3 to 5m
3/4D D • No of cross beam ≥ 5
• Depth of cross beam ≥ 3/4D
S S ½ to ¾ S
Analysis and Design of Cantilever Slab [Ref. IRC 21]
• Calculate dead load and analyze slab for dead load, position live load, analyze
the slab by effective width method for live load, verify the thickness of slab,
find reinforcing bars, check for shear and carryout detailing of reinforcing bars.
Pigeaud's method is applicable to rectangular slabs supported freely on all four sides
subjected to a symmetrically placed load at center.
P
L and B - Span lengths in the long and short span
b directions
L a a and b - Dimensions of the tire contact area in long
h and short span directions
b u =b+2h u and v - Dispersed load through the deck slab
K- Ratio of short to long span
M1 and M2 - Moments along the short and long spans
m1 and m2 - Coefficients for moments along short and
B
long spans
- Poisson's ratio
M1 = (m1+ m2)P P- Load from the wheel under consideration
M2 = (m2+ m1)P
Load Eccentric w.r.t . One Centroidal Axis
u
u
L P P v F
v = - 2P+F
b b
2u+b
Ma = (Mb - Mc)/2
l+v l -v
b-u b-u
Condition a
COURBON'S METHOD
A very simple, popular and powerful method to analyze girder
for live load in simply supported T-beam bridges.
In Courbon’s method, it is assumed that the transverse profile
of the bridge deck under loading remains straight.
P
Central load case ∆
I1 I2 I3 I4
Transverse profile of bridge 1 2 3
h2 h
4
deck after the application of h1 3
h4
central load and central
moment M
In end region i.e., 5.5m from the support, simple beam method is employed for
lateral load distribution.
The following conditions must be satisfied for the effective use of Courbon’s
method.
x1
L1
x1 L1 L1
L
l
Transverse Bending Moment by Distribution
Coefficient Method (Massonet Formula)
• Distribution coefficient method is a simplified method of
bridge deck analysis based on orthotropic plate theory
• In this method distribution coefficients are used to
distribute the load and determine responses of bridge deck.
• Distribution coefficient depends on flexural and torsional
characterizing parameters of bridge deck.
P
2a
L
• Maximum transverse bending moment occurs at the mid span
at the center of transverse section when the eccentricity of
load in transverse section of bridge is least and the load acts at
the mid span of bridge.
• Transverse bending moment is found by Massonnet formula
using distribution coefficient.
• Massonnet showed that TBM per unit width ‘My’
My = ∑n rn b sin(u/2a) sin(nx/2a)
Where
n - Distribution coefficient similar to K
rn – load factor
rn = P/a sin nπu/2a for wheeled load
rn = 4p0/nπ sin nπu/2a sin nπc/2a for tracked load
x - Distance from support to the section, where 'My' is required
P - Wheeled load acting at distance 'u' from abutment
p0 - Intensity of tracked load
2c - Length of tracked load
n - number of term of series
u - distance of load from the support
• Transverse bending moment per unit width, when x = a
Shear reinforcement
a9
Side face reinforcement
a5
Designed
a
longitudinal 8
Shear reinforcement a9 reinforcement
Side face
a5 reinforcement
a4 a4 a4 a4 a4
a2 a3 a3 a3 a2
a1 a1 a1 a1 a1
Designed
longitudinal
Longitudinal Section of Main Girder reinforcement
Shear reinforcement
Design of bridge deck has been carried out in the following three steps.
B. Material Selection
Take
Width of Carriageway
Take, Width of Kerb = offset + width of railing post + min. clearance from post
= 50 + 225 + 225 = 500 mm
Height of Kerb ≥ minimum height from road surface
= 300 mm
Minimum width of kerb = 0.225 m from the face of railing
Minimum raised height of safety kerb from wearing course = 0.225 m
[Refer IRC 5-1998 Cl. 111]
Take Asphalt Concrete for wearing coat of bridge. Thickness of wearing coat is taken
50 mm at edge and 92.5 mm at crown of carriage way to give about 2% camber.
Provide heavy steel pipe with RC post as railing. [Refer IRC 5-1998 Cl. 115]
Take
RC post of 225 mm × 225 mm × 1100 mm
No of Post = 9 on either side of bridge @ 1.5 m spacing
3 - 48.3 mm ∅ heavy steel pipe @ 4.37 kg per running meter [Refer steel section book]
0.4m
1.1m
Fig: Railing
0.4m
0.4m
0.225m
Size of RC Slab
Provide
200 mm thick restrained slab with 150 mm× 300mm fillet at their ends
Cantilever slab of tapering shape with 170 mm thickness at tip up to 0.5 m and
350 mm depth at the root of cantilever.
Minimum thickness of slab =200mm at mid and 150 mm at cantilever tip [Refer IRC 21 Cl.305.2]
Deck of T-Beam bridge consists of two types of slab i.e. cantilever and restrained slabs. Both
types of slabs are analyzed and designed for one meter strip. So in this example load and
responses have been calculated for one meter strip of slab
ANALYSIS OF SLAB
0.15m
0.325m Wheel of 114 KN
axle of Class A load
0.3m
0.17m
0.35m
0.5m 0.475m
m
Live load per unit width of slab is calculated placing a wheel of 114 KN Axle at 0.15 m
from the face of the kerb. Live load per unit width of slab is found by dividing live load
by effective width of slab ‘bef’
𝑙
bef = 1.2a + b1 ≤ ; Where, a = 0.1625, b1 = 0.25 + 2 × 0.072 = 0.394 m
3
𝑙 0.975
bef = 0.589 and = = 0.325 m ; Adopt, bef = 0.325 m
3 3
57×0.325×1.5×1.5
Live load per unit width with impact =
0.5×0.325
= 256.5 KN (acts at 0.1625 m from support)
DESIGN OF SLAB
Since, dbal < dprov , section of slab is designed as Singly Reinforced Under-Reinforced
Section (SRURS). In the example, section design has been done by using SP16.
a. Primary Reinforcement
𝑀𝑢 𝑀𝑢 49.92× 10 6
Find 2
; = = 0.4875 ≅ 0.5
𝑏×𝑑 𝑏×𝑑 2 1000 ×320 2
𝑝𝑡 = 0.142% [For fck= 25N/mm2 and fy= 415 N/mm2] ≥ 𝑝𝑡𝑚𝑖𝑛 = 0.12%
0.142
𝐴𝑟𝑒𝑞
𝑠𝑡 = × 1000 × 320 = 454.4 mm 2
100
Adopt 10 mm ∅ bar @ 150 mm c/c 𝐴𝑝𝑟𝑜𝑣
𝑠𝑡 = 523.6 mm2
b. Transverse Reinforcement
𝑀𝑢 14.15 × 10 6
= 10 10 = 0.147≅ 0.15
𝑏×𝑑 2 1000 ×(320− − )2
2 2
𝑝𝑡 = 0.084 % [For fck= 25N/mm2 and fy= 415 N/mm2] < 𝑝𝑡𝑚𝑖𝑛 = 0.12%
Provide 𝑝𝑡𝑚𝑖𝑛 = 0.12 % of bD
0.12
𝐴𝑟𝑒𝑞
𝑠𝑡 = × 1000 × 350 = 420 mm2
100
Adopt 10 mm ∅ bar @ 150 mm c/c 𝐴𝑝𝑟𝑜𝑣
𝑠𝑡 = 523.6 mm2
c. Temperature Reinforcement
Provide 𝐴𝑚𝑖𝑛
𝑠𝑡 = 402.2 mm2 per m width steel bars as temperature reinforcements
in both direction of slab at bottom. [Refer IRC 21- 2000 Cl. 305.17.4]
Adopt 10 mm ∅ bar @ 180 mm c/c.
Cantilever slab designed by effective width method is not necessary to check for
Shear. [Refer IRC 21- 2000 Cl. 305.16.2 note]
Assess dead load from its self-weight and wearing coat per its unit width.
Assess live load per unit width of slab, positioning wheels of 114KN axle of class A load at
the center of slab panel.
Find maximum BM at mid of shorter and longer span of Slab by Pigeaud’s Method.
Find maximum SF at support in shorter span of slab.
Design section of slab for bending moment and shear force and carryout detailing of
reinforcing bars.
ANALYSIS OF SLAB
Slab Panel
Direction
of traffic
500 mm st
Wheel of 1 114 KN
2.75 m I Axle of Class A load
250 mm
1.2 m
nd
Wheel of 2 114 KN
II Axle of Class A load
2.70 m
BM due to Wheel I
BM in shorter span = (m1 + µm2) × W × 0.8 = 18.88 KN-m
BM in longer span = (m2 + µm1) × W × 0.8 = 18.88 KN-m
Where,
𝑢 0.500 + 2 × 0.072
m1 = 0.16, m2 = 0.16 for K ≈ 1, = = 0.238,
𝐵 2.7
𝑣 0.250 + 2 × 0.072
= = 0.143, 𝜇 = 0.15, W = 57× IF × 𝑟𝑓 = 128.25 KN
𝐿 2.75
BM due to Wheel II
BM in shorter span = (BM of patch I – BM of patch II) × 1/2 = 2.63 KN-m
BM in longer span = (BM of patch I – BM of patch II) × 1/2 = 2.63 KN-m
Hypothetical Wheel
Identical to wheel II
II Direction
of traffic
2.75 m Patch I Patch II
= -
II
2.7m
Wheel of 114 KN
Axle of Class A
load
BM due to wheel I and wheel II in shorter span = 18.88 + 2.63= 21.51 KN-m
BM due to wheel I and wheel II in longer span = 18.88 + 2.63= 21.51 KN-m
Design moment due to DL and LL in shorter span = 21.51 + 2.98 = 24.49 KN-m
Design moment due to DL and LL in longer span = 21.51 + 2.98 = 24.49 KN-m
Max. SF due to dead load in shorter span of slab = SF due to Self Wt. of WC, & slab with fillet
𝑤𝑢 𝑙 0.2×25×1.35+0.072×22×1.75 × 2.70
= + Vufillet = + 0.25 × 0.15 × 0.3 × ½ × 2.75 × 25
3 3
= 9 KN [Only 25% of wt. of fillet is taken for shear calculation]
st
Wheel of 1 114 KN
1.8m Axle of Class A load
2.75m I II
1.2m I
I II
I
0.522m nd
Wheel of 2 114 KN
2.7m Axle of Class A load
Position of Class A
load for maximum SF
For wheel I
𝑎
𝑏𝑒𝑓 𝐼 = α × a 1 – + b1 = 2.24 × 0.522 × (1 - 0.522/2.70) + 0.394 = 1.34 m
𝑙
Where,
a = 0.25 + 0.2 + 0.072 = 0.522 m
𝐵
α = 2.24 for 𝐿 = 1 (For continuous slab)
b1 = W + 2h = 250 + 2 × 72 = 394 mm
Since the bef of individual wheel overlaps, find modified effective width.
𝑏𝑒𝑓 𝐼 𝑀𝑜𝑑 = 0.25+ 0.25/2 + 1.2 + 𝑏𝑒𝑓 𝐼 /2 = 2.245 m
Width of cross beam is taken into account for effective width calculation.
2 × 57 × 𝐼𝐹 × 𝑟 𝑓 𝐿𝐿
Load due to wheel I (FI) = = 114.2 KN/m
𝑏𝑒𝑓 𝐼 𝑀𝑜𝑑
L = 2.7 m
Reaction at A and B
RA × 2.7 = 114.20 × (2.7 – 0.522) + 120.14 × 0.378
∴ RA = 108.94 KN
RB = 125.4 KN
Design shear force due to DL and LL in shorter span = 125.4 × 0.8 + 9 = 109.32 KN
DESIGN OF SLAB
Since, dbal < dprov , section of slab is designed as Singly Reinforced Under-Reinforced
Section (SRURS). In the example, section design has been done by using SP16.
In long span
𝑀𝑢 24.49 × 10 6
= = 0.96
𝑏×𝑑 2 1000 × 160 2
𝑝𝑡 = 0.28% > 𝑝𝑡𝑚𝑖𝑛 = 0.12 %
0.28
𝐴𝑟𝑒𝑞
𝑠𝑡 = 100 × 1000 × 160 = 448 mm
2
b. Temperature Reinforcement
Provide 10 mm ∅ bar @ 300mm c/c in both directions at top of slab.
Bridge deck consists of two main girders and five cross girders with rigidly connected
deck slab. In the example, one main girder and two cross girders i.e. one end cross
girder and one intermediate cross girder have been analyzed and designed.
Assess loads dead load from slab, wearing coat, kerb and railing.
Assess live load on main girder. Combination of Class A load and uniformly
distributed load of 5 KN/m2 is taken as live load [Refer Cl. 204.3, IRC 6]
Find maximum BM at mid and quarter span of main girder due to DL and LL.
Find maximum SF at support and quarter span of main girder due to DL and LL.
Design Critical sections of main girder for bending moment and shear force.
Carry out curtailment, anchorage design and detailing of main steel bars.
A B
3m
RA l = 12 m RB
W W 5 KN / m
2
0.4m 1.8 m
0.5m
2.3 m 1.95 m
1 2
1.125 m 3m
2WI 2W ×0.825×I×1.5
R1 = + = 1.55 W
2I I×1.52 + I×1.52
In single lane bridge, Class A occupies 2.3 m strip of carriage way. Remaining strip
[4.25 - 2.3 = 1.95 m] should be loaded with UDL of 5 KN/m2 [Refer Table 2, IRC 6].
Reaction from UDL of girder 1 is found by Courbon’s Method.
2.29 KN/ m
Mu = 39.24 × 0.25 + 39.24 × 0.8 +165.66 × 2.4 + 165.66 × 3 + 98.82 × 0.85 + 0.5 × 3 × 12 ×
× 2.29 = 1060.99 KN-m
2.29 KN/ m
ILD of BM at
quarter span
2.25 1.95 0.875 0.125
1.2 m 4.3 m 3m with Class A
12 m and UDL
Mu = 165.66 × 2.25 + 165.66 × 1.95 + 98.82 × 0.875 + 98.82 × 0.125 + 0.5 × 12 × 2.25 ×
× 2.29 = 825.51 KN-m
ILD of SF at
support with
1 0.9 0.54 0.292 0.042
1.2 m 4.3 m 3m 3m Class A and UDL
2
12 m
ILD of SF at
0.75
quarter span
0.25 0.6 0.292 0.042
with Class A
1.2 m5 4.3 m 3m
12 m and UDL
bact = 2.625 m
bef = 2. 25 m
0.215 m
x x
1m
0.3 m 𝑦 = 0.729𝑚
1.125 m
Design Section
C.G. of section
0.785 0.215
0.785 × 0.3 × + 2.25 × 0.215 ×(0.785 + )
2 2
𝑦 = = 0.729 m
0.785 × 0.3 + 0.215 × 2.25
prov 2 max
Provide 10 – 28 mm ∅ bar Ast = 6157.52 mm Pt = 2.31 % < Pt =2.5%
4926.02×100
Provide 8 – 28 mm ∅ bar prov
Ast = 4926.02 mm
2
Pt = 918×300
=1.79% < Ptmax = 2.5%
Support Section
𝑉𝑢 665.37×1000
Find 𝜏𝑢𝑣 = = = 2.416N/mm2
𝑏𝑤 𝑑 300×918
Where, d = 1000 – 40 – 28 – 28/2 = 918 mm
Find 𝜏𝑢𝑐 = 0.785N/mm2 for M25 and pt = 1.79 %,
Quarter Section
𝑉𝑢 401.66×1000
Find 𝜏𝑢𝑣 = = = 1.504 N/mm2
𝑏𝑤 𝑑 300×890
Find 𝜏𝑢𝑐 = 0.885 N/mm2 For M25 and pt = 2.31 %
2
Find 𝜏𝑢𝑐 ,𝑚𝑎𝑥 = 3.1 N/mm
Since 𝜏𝑢𝑣 > 𝜏𝑢𝑐 , design shear reinforcement
Provide 10 mm ∅ 2-legged vertical stirrups 300 mm c/c from quarter span to quarter
span of other side.
3 Detailing of Reinforcement
Find the length of extension of bar beyond the theoretical cutoff point (𝑙𝑑 ).
𝐴𝑠𝑡 𝑟𝑒𝑞
𝑙𝑑 = 𝛼1 𝛼2 𝑙0 = 𝛼1 𝛼2 𝑛∅ = 1 × 𝐴𝑠𝑡 𝑝𝑟𝑜𝑣 × 46 × 28 = 1152.76 𝑚𝑚
1152.76 𝑚𝑚
Where, 𝛼1 = 1 for straight end
𝐴𝑠𝑡 𝑟𝑒𝑞 4409.52
𝛼2 = 𝐴𝑠𝑡 𝑝𝑟𝑜𝑣 = 4926.02 = 0.895 2∅ = 56 𝑚𝑚
Theoretical cutoff point
∅ = 28 𝑚𝑚
2/3ld = 569mm
𝑙
𝑆𝑖𝑛𝑐𝑒 < 𝛼𝛽𝛾𝛿𝜆 , 𝑑𝑒𝑓𝑙𝑒𝑐𝑡𝑖𝑜𝑛 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑔𝑖𝑟𝑑𝑒𝑟 𝑖𝑠 𝑢𝑛𝑑𝑒𝑟 𝑐𝑜𝑛𝑡𝑟𝑜𝑙.
𝑑
Load due to self-weight of slab and wearing coat acts on contributory area of
triangular shape.
- Self-weight of Wearing Coat = 0.072 × 22 × 1.5 × 2 × 1.75 = 8.316 KN/m
- Self-weight of Slab = 0.2 × 25 × 1.5 × 2 × 1.35 = 20.25 KN/m
Total = 28.57 KN/m
Load due to self-weight of cross beam and fillet acts as a uniformly distributed load.
28.57 KN/m
6.16 KN / m
l=3
m
1.8 m
1.5 m
l=3m
3m
3m
Longitudinal position of Class A
load for maximum BM Contributory
Area of load for
Cross Girder
114 KN axle
of Class A
load
1.8 m
1.5 m
l=3m
3m
Longitudinal position of Class A 3m
load for maximum SF
Contributory
Area of load for
Cross Girder
6.16 × 3
Mu = × 1.5 – 6.16 × 1.5 × 1.5/2 + ½ × 28.57 × 3 × ½ ×1.5 - 1/2 × 28.57 × 1.5 ×
2
1.5/3 + 128.25 × 1.5 -128.25 × 0.9 = 105.31 KN-m
Load due to self-weight of slab and wearing coat acts on contributory area of
triangular shape.
- Self-weight of Wearing Coat = 0.072 × 22 × 1.5 × 1.75 = 4.158 KN/m
- Self-weight of Slab = 0.2 × 25 × 1.5 × 1.35 = 10.125 KN/m
Total = 14.29 KN/m
Load due to self-weight of cross beam and fillet acts as a uniformly distributed load.
14.29 KN/m
3.3 KN / m
l=3
m
Dead Load on End Cross Girder
3m
57 × 1.5 × 1.5 57 × 1.5 × 1.5
= 128.25KN = 128.25KN
1.8 m
3m
1.8 m
1.5 m 1.2 m
l=3m
3.3 × 3
Mu = × 1.5 – 3.3 × 1.5 × 1.5/2 + ½ × 14.29 × 3 × ½ ×1.5 - 1/2 × 14.29 × 1.5 × 1.5/3
2
+ 128.25 × 1.5 -128.25 × 0.9 = 91.43 KN-m
Find Mu,l
Xu,l = 0.48 d = 334.08 mm
Since Xu,l > Df and Df > 0.43Xu,l, find Mu,l for when NA lies in web and Df > 0.43Xu,l
𝑉𝑢 261.52 × 1000
Find 𝜏𝑢𝑣 = = = 1.49 N/mm2
𝑏𝑤 𝑑 250 × 702
Where d= 750 – 40– 16/2 = 702 mm
Find 𝜏𝑢𝑐 = 0.41N/mm2 for M25 and pt= 0.347 %,
Find 𝜏𝑢𝑐 ,𝑚𝑎𝑥 = 3.1 N/mm2 for M25
Since 𝜏𝑢𝑣 > 𝜏𝑢𝑐 , design shear reinforcement.
Take, 10mm ∅ 2-legged vertical stirrups for shear reinforcement.
10 2
0.87 𝑓𝑦 × 𝐴𝑠𝑣 × 𝑑 0.87× 415× 2× 𝜋 × × 702
4
Sv = = = 210.05 mm
𝑉𝑢 𝑛𝑒𝑡 1.49−0.41 × 250 × 702
Sv < 0.75d =688.5 mm and < 300 mm adopt Sv=200 mm
Design Section
Find Mu,l
Xu,l = 0.48 d = 216.96 mm
Since Xu,l > Df and Df > 0.43Xu,l, find Mu,l for when NA lies in web and Df > 0.43Xu,l
𝑉𝑢 246.52 × 1000
Find 𝜏𝑢𝑣 = = = 2.18 N/mm2
𝑏𝑤 𝑑 250 × 452
Find 𝜏𝑢𝑐 = 0.5 N/mm2 for M25 and pt= 0.534 %,
Find 𝜏𝑢𝑐 ,𝑚𝑎𝑥 = 3.1 N/mm2 for M25
4- 20mm dia.
4- 20 mm dia.
8 – 28 mm dia. 10 – 28 mm dia.
Longitudinal Section of Main Girder
3 – 16 mm dia.
4 –8 mm dia.
Bracing
Top Chord Joint Vertical
Diagonal Member
Member
Bridge Deck
Bottom Chord
Negative aspects
Positive aspects Reduces vertical clearances above the afflux
due to its depth
Easy to construct Requires thorough maintenance regularly
Has rigid structure and can cover No longer economically competitive
relatively larger span (300m) Gives rough appearance
Components of Truss Bridge
Portal Bracing
Sway Bracing
Stringer
Floor Beam
(Cross Beam)
Bearing
Types of Truss Bridge
Deck Truss Bridge
Truss Bridge
Through Truss Bridge
Half Through Truss Bridge
Deck Truss
Bridge
Half Through
Truss Bridge
Through
Truss Bridge
Through Truss Bridge
General Arrangements of Through Truss Bridge
Elevation
Sectional Plan
Elevation
Top Bracing
Plan
Cross Section of
Braces
Design Steps of Truss Bridge
1. Select appropriate type/form of truss and decide panel no and depth of truss
and arrange components of bridge deck on truss and give their approximate sizes.
K Type Truss
Span coverage 75 to 150m
When panel length is large, subdivided panel in lower chord of truss may be introduced in
Warren, Pratt, K and other type trusses
H’ H
α
L
(Height of Truss)
H’’
H’ H
B
BIS recommends 9 grades of steel as structural steels. They are designated as E165,
E250 (A), E250 (B), E250 (C), E300, E350, E410, E450 (D) and E450 (E)
IS 1367:2002 classifies
bolts in to property classes 3.6, 4.6, 4.8, 5.6,
5.8, 8.8, 9.8, 10.9, 12.9 depending upon the strength of bolts
In steel truss bridge, generally bolts of 8.8 and 10.9 property class,
unfinished high strength bolts and M16 - M24 size of bolts are used.
3. Design components of bridge floor deck
Approximate self wt. of cross beam = 0.2L + 1 KN/m L – span of cr. beam
4. Analyze and design truss member
• Find self weight of truss and other dead load and distribute the loads on each joint of
truss. We can use Fuller’s formula to determine self wt. of truss and bracings
Approximate total self weight of truss and bracing per unit length = 0.15 × L + 5.5 KN/m
L – Span of truss Fuller’s formula is valid for 100 m span of bridge
• Draw IL diagram of truss members for axial loads and position live load
longitudinally to get maximum responses.
L0 L1
• Position the live load transversely in such a way so that the reaction on one truss is
maximum. Distribute live loads on trusses by simple beam theory or lever arm
method. Find responses (Axial Force) of truss member using ILD.
AF in truss mem. = ∑Point load × ordinate of ILD + UDL × occupied area of ILD by load
• Design truss member as tension / compression member
Check
σt ≤σat for tension member (WSDM)
T ≤Td (LSDM) Refer IRC 24 – 2010
Composite Bridge
Main Plate Girder
Steel Cross
Beam
N.A
N.A
Bending stress
diagram
Slippage
1. Propped Method
2. Unpropped Method
• In Propped Method, main steel beam is erected on prop and then RC slab and
other members are constructed.
In this method of construction, dead load from self wt. of main beam, cross beam and slab is
borne by girder - propped system and main girder remains unstressed at this stage. RC slab
attains its strength in propped condition. After attaining the desired strength of RC slab, the
total loads, i.e. DL, SIDL and LL are borne directly by composite section of beam.
So in this type of bridge, design is carried out for all loads directly considering composite
action.
• In Unpropped Method, main steel beam is erected without prop and then RC slab
and other members are constructed directly on the main beam.
In this method of construction, prior to attainment of strength of RC slab, dead load from self
wt. of main beam, cross beam and slab is borne by steel girder alone. Then after attaining the
desired strength of concrete of slab, the total loads, i.e. DL, SIDL and LL are borne by
composite section of girder.
So in this type of bridge, design is carried out for DL considering non composite action and
for all loads considering composite action .
Design Steps of Composite Bridge
1. Plan and configure the approximate transverse section of composite
bridge. Assign sizes of composite bridge deck elements.
2. Design cantilever slab. Calculate dead load, position live load, analyze the
slab, verify the thickness of slab, find reinforcing bars and carryout
detailing of reinforcing bars.
3. Design restrained slab. Calculate dead load, position live load, analyze the
slab by Pigeaud’s Method, verify the thickness of slab, find reinforcing
bars and carryout detailing of reinforcing bars.
4. Design main beam. Calculate dead load, position live load longitudinally
and transversely, analyze the beam, design beam for shear and bending,
check beam for deflection, design beam for lateral stability and design
shear connector .
5. Design Cross beam. Calculate dead load, position live load longitudinally
and transversely, analyze the cross beam, design cross beam for shear and
bending and check for lateral stability.
Preliminary Design of Composite Bridge
tf
• Af = M/D’σbt – Aw/8 ; Af –Sect. area of a flange
D’
• Aw = D’ × tw ; Aw – Sect. area of web
σbt = 0.66fy
tw
• α ≥ 1100 (150 mm × 300 mm)
• S=2–3m
• Spacing of cross beam = 3 to 5 m
• No of cross beam ≥ 5
Steel for beam is selected according to the standard of BIS.
BIS recommends 9 grades of steel as structural steels. They are designated as E165,
E250 (A), E250 (B), E250 (C), E300, E350, E410, E450 (D) and E450 (E)
Properties
Yield Stress
Grade /
(MPa) U. Tensile Stress Elongation
Classification
(MPa) (%)
<20mm 20-40mm >40mm
In composite bridge, the deck slab is supported on all the four sides of slab. In the case,
slab is analyzed for DL and LL by Pigeaud’s Method. Slab is designed as SRUR rectangular
section.
Pigeaud's Method
Pigeaud's Method is applicable to rectangular slabs supported freely
on all four sides subjected to a symmetrically placed load at center.
P
L and B - Span lengths in the long and short span
b directions
L a a and b - Dimensions of the tire contact area in long
h and short span directions
b u =b+2h u and v - Dispersed load through the deck slab
K- Ratio of short to long span
M1 and M2 - Moments along the short and long spans
B m1 and m2 - Coefficients for moments along short and
long spans
- Poisson's ratio
M1 = (m1+ m2)P P- Load from the wheel under consideration
M2 = (m2+ m1)P
To consider the degree of fixity of restrained slab at its edges, BM calculated
by Pigeaud’s Method is corrected by multiplying 0.8 factor
Pigeaud’s Method when load is eccentric w.r.t . one centroidal axis
B
u
u
L P P v F
v = - 2P+F
b b
2u+b
Ma = (Mb - Mc) / 2
l+ v l-v
L
b+u b+u
v
u P Condition b Condition c
B l b =
l+ v l-v
b-u b-u
Condition a
x1
L1
x1 L1 L1
L
l
Transverse Positioning of Live Load to Get Maximum Responses
emax
Main Girder
Cross Beam
emax
Main Girder
Cross Beam
Minimum eccentric vehicle gives maximum transverse BM
COURBON'S METHOD OF LATERAL LOAD DISTRIBUTION
Courbon is one of the methods of lateral load distribution in bridge deck,
which can be used in the analysis of main girder of composite bridge.
1 2 3 4
I1 I2 I3 I4
In Courbon’s method, load shared by each girder in central region of bridge deck
is found by
R1 = P I1 / ∑I + M I1 h1 / ∑Ih2
R2 = P I2 / ∑I + M I2 h2 / ∑Ih2
R3 = P I3 / ∑I + M I3 h3 / ∑Ih2
R4 = P I4 / ∑I + M I4 h4 / ∑Ih2
In end region i.e., 5.5 m from the support, simple beam method is employed for
lateral load distribution.
The following conditions must be satisfied for the effective use of Courbon’s
method.
• Compute dead load due to steel beam and slab and superimposed dead load due to
wearing surface, parapet etc. Find bending moment and shear force at critical sections
of beam for different load combinations i.e. DL, DL+SIDL and DL+SIDL+LL.
• Compute the transformed width of slab 'btr’ and find design sections for different load
combinations.
btr = bef /m for dead and live loads acting on the beam
b tr = bef /km for superimposed dead loads
Where,
bef = effective flange width of composite section
k - creep factor; k=2
m - modular ratio; m = Es /Ec
Design section of girder for
different loading conditions
Df Df Df
Actual composite beam section Actual steel beam Transformed section of Transformed section of
with effective width of flange section for DL beam for DL + SIDL beam for DL + SIDL + LL
• Design the section of composite beam
Design of composite beam depends on the method of construction of bridge . In Unpropped method of
construction beam is designed in two stages. In the first stage, main beam is designed as a steel beam for
DL and in the second stage, main beam is designed as composite beam for DL, SIDL and LL . In propped
method, main beam is designed directly as composite beam for DL, SIDL and LL .
I. Design of main beam for self weight of main and cross beam and self
weight of slab as a steel plate girder
Design in Shear
𝑽 ≤ 𝑽𝒅
V – Design SF
Vd – Design shear strength of girder
Shear strength of girder depends on
the shear buckling behavior of girder
Design in Bending
Main girder is designed as laterally unrestrained beam
𝑴 ≤ 𝑴𝒅
M – Design BM
Md – Design bending strength of girder
II. Design of main beam for self weight of main and cross beams, self
weight of slab superimposed load and live load as a composite beam
𝑴 ≤ 𝑴𝒅
Check bending stress at top fibre of concrete
σb = σDL + σSIDL+ σLL ≤ limiting flexural compressive stress in concrete × m
Where, σb - bending stress, σDL , σSIDL, σLL - bending stress due to dead load,
superimposed dead load and live load respectively, m – modular ratio
3. Check Deflection
Check maximum deflection of main girder
Δmax ≤ Δ limiting
If d1 / tw ≤ 85 no stiffeners require
If d2 / tw > 85 and ≤ 200 vertical stiffeners are designed
If d2 / tw > 200 and ≤ 250 vertical and one horizontal stiffeners are designed
If d2 / tw > 250 and ≤ 400 vertical and two horizontal stiffeners are designed
If d2 / tw > 400 thickness of the web of beam is increased
RC Slab
Web Plate Flange Plate Intermediate V. Stiffener X
X
Horizontal Stiffener
Horizontal Stiffener at 0.2 d at Neutral Axis
Bearing V. Stiffener from Compression Flange
Horizontal Stiffener
at 0.2 d from Compression Flange
Intermediate V.
Stiffener
Horizontal Stiffener
at Neutral Axis
Section at X-X
6. Design Shear Connector Shear Stud
Spacing of Mild Steel Shear Connector (stud type) is found by
hs d
P = ΣQu / Vl • Diameter of stud ≤ 4 × thickness
of flange of beam
For any case spacing of shear connectors P ≤ 600 mm • Head of stud ≥ 1.5 × dia. of stud
Min. spacing of connectors for stud = 75 mm • hs ≥ 4 × dia. of stud or 100 mm
Where,
𝑄𝑢 − 𝐷𝑒𝑠𝑖𝑔𝑛 𝑢𝑙𝑡𝑖𝑚𝑎𝑡𝑒 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑠𝑡𝑢𝑑 𝑖𝑛 𝑁
2
0.8𝑓𝑢 𝜋 𝑑 ൗ4 0.29𝛼𝑑2 0.8𝑓𝑐𝑘 𝐸𝑐𝑚
𝑄𝑢 = ≤
𝛾𝑣 𝛾𝑣
ℎ𝑠 ℎ𝑠 ℎ𝑠
𝛼 = 0.2 + 1 𝑓𝑜𝑟 3 < < 4 𝑎𝑛𝑑 𝛼 = 1 𝑓𝑜𝑟 ≥4
𝑑 𝑑 𝑑
𝛾𝑣 − 𝑃𝑎𝑟𝑡𝑖𝑎𝑙 𝑠𝑎𝑓𝑒𝑡𝑦 𝑓𝑎𝑐𝑡𝑜𝑟 𝑓𝑜𝑟 𝑠ℎ𝑒𝑎𝑟 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑜𝑟 = 1.25
d – Diameter of stud in mm
𝑓𝑢 − Ultimate tensile strength of stud ≤ 500 N/mm2
hs – Nominal height of stud in mm
Ecm – Modulus of elasticity of concrete
c1 • c1 ≥ 40 mm
• abc ≥ anchorage length
b c
c1
a
7. Design Transverse Reinforcement
Longitudinal shear force per unit length (Vl) transferred from the steel beam
to in situ slab through any shear plane shall not exceed either of the following
and the reinforcement shall be calculated accordingly
Vl ≤ 0.632 Ls (fck)1/2 Or
Vl ≤ 0.1 As fy + 0.0232 Ls (fck)1/2
Where,
Ls – length of shear plane under consideration in mm
As – sum of the cross sectional areas per unit length of beam of all
reinforcing bars intersected by the shear plane mm2/mm
Probable
shear plane
Bridge Bearing
Bearing is a mechanical device placed between
superstructure and substructure to transmit vertical and
horizontal load allowing some translational and rotational
movement of bridge superstructure.
Metalic Bearing
Bearing made up of Metal i.e. steel or cast iron
Elastomeric Bearing
Bearing made up of artificial rubber (Neoprene)
Metalic Bearing
▪ Roller Bearing
Single Roller Single Roller Bearing
Multiple Roller
▪ Rocker Bearing
Multiple Roller Bearing
Linear Rocker
Point Rocker
Rocker Cum Roller
▪ Knuckle Bearing Linear Rocker Bearing
Cylindrical Knuckle Bearing
Cylindrical Knuckle
Spherical Knuckle
Pin Knuckle Point Rocker
Bearing Spherical Knuckle Bearing
Leaf Knuckle
▪ Sliding Plate Bearing
▪ Spherical Bearing
Slide Plate Bearing
Elastomeric Bearing
Elastomeric Pad Bearing
▪ Pad Bearing
▪ Pot Bearing
▪ Disc Bearing
Elastomeric Pot Bearing
Leaf Knuckle Bearing
Sliding Plate Bearing
Sliding plate bearings comprise upper and
lower steel plates to slide on the contact
surface.
Plate of the bearing are made frictionless
using PTEF. These bearings can be used
for spans of less than 15 m
Rocker Bearing
Rocker bearings comprise a curved
surface in contact with a flat or
another curved surface and
constrained to prevent relative
horizontal movement. The curve
surface may be cylindrical or
spherical. The rotation is allowed
by rolling of one part on another.
Knuckle Bearing
Knuckle bearings are another type of fixed bearing.
They include two or more members with mating
curved surfaces, which may be spherical or
cylindrical. Another form is the pin type, where the
upper and the lower plates have a concave cylindrical
surface mating with a core pin. Knuckle bearings
permit rotation by rolling on the contact surface.
Leaf Bearing
Leaf bearings consist of a pin passing
through a number of interleaved plates
fixed alternatively to the upper and lower
outer bearing plates. Pin bearings permit
only rotational movement, but can be used
in combination with roller bearings to
provide rotation and translation. Uplift can
be accommodated by this type of bearing.
Roller Bearing
Similarly to disc bearings, this type of bearing is also a high load, multi-
rotational compact bearing that can be used to accommodate thermal,
seismic and mechanical expansion and contraction.
Pot Bearing
Pot bearings are used to sustain vertical forces in
the range of 1200 kN to 10000 kN and can
accommodate rotations of up to 0.02 rad, thus they
can be used for a wide range of modern bridges.
Low load eccentricity under rotation is one of their
strong features. However, they have limited ability
to accept rotation at low vertical load.
Laminated elastomeric
5000 100 0.04
bearings
Laminated Elastomeric Bearing
Laminated Elastomeric Bearing with Pin
Loads on Bearing
Vertical load
• DL from superstructure
• LL from superstructure
• Vertical load due to braking effort
• Vertical Seismic load
• Vertical wind load
Horizontal load
• Wind load from superstructure
• Load induced by creep, shrinkage and temperature effect
• Braking load
• Horizontal load due to earthquake
Geometrical Design
Find overall length (lo), breadth (bo) and thickness (ho) of elastomeric pad. Find number
of internal layers of elastomer(n), thickness of internal layers of elastomer (hi), number
of steel plates (ns), thickness of steel plates (hs), effective cover to steel plate (he) and
side cover (c). Approximate sizing of bearing is done on the basis guidelines provided by
IRC 83-1987 ( Part II) (Refer Table Appendix. I)
bo hs
b
Table Appendix I, IRC 83 - 1987 (Part II)
• The side cover (c) of elastomer for the steel laminates is 6 mm.
Where,
σm = Normal compressive stress
σm,max = 10 N/mm2
Total shear stress due to normal and horizontal loads and rotation ≤ 5 N/mm2
τc + τr + τα ≤ 5 N/mm2
Where,
Shear stress due to normal load (τc ) = (1.5 σm )/S
Shear stress due to horizontal load ( τr ) = Total shear strain
Shear stress due to rotation( τα ) = 0.5(b/hi)2 αbi max
Design Example
DESIGN OF METALLIC BEARING
Metallic bearing usually made of mild steel, cast steel and
stainless steel. It may be free or fixed.
d ≥ 16 mm 2.5mm
R t
0.5d
Rocker Pin
t
0.5d
≥ 1.1d or
D Saddle Plate
d + 2.5mm
Roller P Lug for Roller
S Bottom
Rocker Pin
Plate
Rocker cum Roller Bearing
• The width of plates shall not be less than 100 mm or the distance between outermost
rollers plus twice the thickness of the plate plus 10 mm.
• The top plates of sliding bearings shall project on all sides over the bottom plate by at
least 10 mm.
Design
• Minimum gap should not be less than 20 mm in order to prevent the transfer
of forces through the debris trapped in the joint.
Compression seal
Slab Seal Joint
Deck slab
Problem Statement
Design bearing for the simply supported T-Beam Bridge as shown in figure.
(Refer to the design example of T-Beam Bridge)
l = 12 m
L = 12.5 m
Cross girder Center line
@ 3 m c/c
A
❖ Loads have been organized for different combination and found maximum vertical
and horizontal forces acting on bearing for worst combination. In the example,
combinations I, II(A), III(A) and VI become critical.
❖ Geometrical and structural design of Elastomeric Bearings have been carried out for
worst combination of loads.
1. DL from Superstructure
Total DL from super structure (Wu) = 84.15 + 28.21 + 93.75 + 359.2 + 150 + 38 = 753.31 KN
𝟕𝟓𝟑.𝟑𝟏
DL from superstructure on a bearing (DLsup) = = 188.33 KN
𝟒
FbrH
2.272 m
Fbrv Fbrv
l = 12 m
𝟖𝟔.𝟒 × 𝟐.𝟐𝟕𝟐
Vertical reaction on a bearing due to Braking load (FbrV) = = 8.18 KN
𝟏𝟐 × 𝟐
4. Wind load
▪ Wind load in transverse direction of bridge (FWT) = PZ × A × G × CD = 30.1 KN
Take, Ht. of bridge = 10 m, Basic wind speed = 47 m/s and Terrain with obstruction
𝑍 𝐼 𝑆𝑎
▪ Seismic load (FSh) =2×𝑅× 𝑔
×𝑊 [Refer Cl. 219, IRC 6]
Take, Seismic Zone - V, Soil Strata - Medium, Damping - 5 %, Bridge Class - Normal
Where,
𝑍 𝐼 𝑆𝑎 𝑆𝑎
Ah = 𝛼ℎ = × × = 0.225; Z = 0.36, I = 1, R = 2, = 2.5
2 𝑅 𝑔 𝑔
W = 753.31 KN in longitudinal direction
W = 753.31 + 0.2 × (2 × 114 + 3 × 68) = 839.71 KN in transverse direction
𝟏𝟖𝟖.𝟗𝟑 × 𝟎.𝟗 𝟏
V. reaction on a bearing when s. load acts in tr. dir. (FSvT) = × = 28.34 KN
𝟑 𝟐
FShT
0.9 m
FSVT FSVT
l=3m
𝟏𝟔𝟗.𝟒𝟗×𝟎.𝟗 𝟏
Vert. react. on a bearing when seis. load acts in long. dir. (F SVL) = × 𝟐 = 6.36 KN
𝟏𝟐
FShL
0.9 m
FSVL FSVL
l = 12 m
Combination I [N]
Total Vertical load = DLSup + LL + FbrV = 188.33 + 267.55 + 8.18 = 459.06 KN
Total Horizontal load = FbrH = 21.6 KN
Combination VI [N+T+S]
Total Vertical load = D L+ 0.2 × LL + 0.5 × FbrV + FsvL
= 188.33 + 0.2 × 267.55 + 0.5 × 8.18 + 6.34= 252.27 KN
Total Horizontal load = 0.5 × FbrH + Fcst + FshL = 0.5 × 21.6 + 3.7 + 42.37 = 56.87KN
1. Geometrical design
In geometrical design, approximate length, breadth and thickness of elastomeric pad
and number, thickness and cover of steel laminates are found. Geometrical design is
carried out using the guidelines of IRC.
[Refer standard plan dimensions of IRC 83, Part II, Cl. 916.2, Appendix I]
Nmin = DL = 188.33 KN; Nmax = Tot. Vertical load on bearing = 459.06 KN; H = 21.6 KN
b
Take, Steel laminates
of 3 mm hi
h0
• b0 = 260 mm, b = 248mm
• l0 = 300 mm, l = 288 mm he
• hi = 10 mm b0
Cross Section
• he = hi/2 = 5 mm
• hs = 3 mm
c c
• n=3
• c = 6 mm c
• h0 = (n +1)hs +nhi + 2he = 52 mm
• h= nhi + 2he = 40 mm l l0
Plan
2. Structural design
Bearing is further checked for translation, rotation, friction and shear
Where,
760.35
MDL = = 563.22 KN-m
1.35
1060.99
MLL = = 707.33 KN-m
1.5
Ec = 5000√𝑓𝑐𝑘 = 25000 N/mm2
𝐼𝑔𝑟 = 0.05911154 m4
β = 0.1σm= 0.1× 6.427 = 0.64
n=3
0.5 𝜎𝑚 𝑚𝑎𝑥 × ℎ𝑖 0.5×10×10
αbimax = = = 0.0046
𝑏×𝑠2 248×6.662
Where,
𝜎𝑚 6.43
Shear stress due to axial compression (τc) = 1.5 × = 1.5 × = 1.45 N/mm2
𝑆 6.66
Shear stress due to horizontal deformation (τr) = γd = 0.377 N/mm2
𝑏 2 248 2
Shear st. due to rotation (τα) = 0.5 × (ℎ ) αbimax= 0.5 × ( 10 ) × 0.0046 = 1.41 N/mm2
𝑖
Loads are not varied significantly in first three combinations of loads. But in seismic
combination i.e. in N + T + S case, horizontal load is about two times greater than other
combinations. So designed bearing has been checked for seismic combination (along the
traffic) of loads only.
Size of bearing provided for loads of combination I (N) is not sufficient for loads of
combination VI (N+T+S). Check for translation shows that provided size of bearing could not
accommodate the horizontal force of combination VI. In the situation it is suggested to
provide elastomeric pad bearing with pin on one side of support to resist horizontal load
Diameter of Pin
Shear stress in pin due to horizontal loads ≤ Allowable shear stress in pin (𝜏 ≤ 𝜏𝑎 )
Take pin of Fe 250 grade
Provide 28mm dia. stainless steel pin. Pin should be extended up to the depth of cap of
support.
260
mm
248 mm
Steel laminates 6 mm c
of 3 mm c 6 mm
c
52 mm
10 mm 288 mm
300 mm
5 mm
28 mm
Provide bearing of 250 mm × 400 mm size and check all geometrical and structural
requirements of bearing.
• b0 = 250 mm, b = 238mm
• l0 = 400 mm, l = 388 mm
• hi = 12 mm
• he = hi/2 = 6 mm
• hs = 4 mm
• n=3
• c = 6 mm
• h0 = (n + 1)hs + nhi + 2he = 64 mm
• h= nhi + 2he = 48 mm
Problem Statement
Design rocker cum roller bearing for the following data.
Abutment Cap
Footing
1
Types of Abutment
Gravity Type
Balancing Type
Buried Type
2
Abutment with wing wall
Considerations in the preliminary planning of abutment
The following measures often help in achieving economy in the design of abutments
1 to 1.5 m
0.3h
1 to 1.5 m
HFL
H H H/12 to H/10
1/6 to 1/3 slope
> Max. Scouring
depth
> Max. scouring depth
H/8 to H/10
0.35 H to 0.45 H ≥ H/10 to H/8
2/5 H to 3/4 H
b
N = 305 +2.5L + 10H mm
L – span in m
H- Ht of support in m
0.4 to 0.6 m clear distance from
bearing to the edge of abutment
Plan of abutment
Materials for Abutments
[Minimum grade of material]
• Brick Masonry
(With Cement mortar of proportions 1:4)
2. Horizontal loads
• Force due to Braking Effort
• Force due to Frictional Resistance of Bearing
• Wind Load
• Force due to Earthquake
• Force due to Earth Pressure
• Force induced by creep, shrinkage and temperature variation
• Force due to surcharge
For working stress design method, there are nine
combinations of loads to be considered in design
Load Combination
(Refer to IRC 6)
In Limit State Design Method, there are three combinations
of loads to be considered in design. These three
combinations are
• Basic combination
• Seismic combination
• Accidental combination
✓ Refer to IRC 6 – 2017, Table B.1, B.2, B.3 and B.4 for
combination of loads
Design of RC Abutment
A
Loads on abutment from deck
• Find Self wt of railing, kerb/footpath, wearing course, slab , cross
Dead load from deck beam and main beam per unit length of abutment
(vertical) Weight / length of abutment
Live load from deck • Find maximum live load per unit length of abutment
(vertical) Live Load on Abutment / Length of Abutment
Load due to • Find force due to earthquake Feq from superstructure and substructure per unit
earthquake in length of abutment in longitudinal direction of bridge and find force due to
longitudinal and earthquake Feq from superstructure and substructure in transverse direction of
transverse direction of bridge
bridge (horizontal
Feq = Z/2× I/R× Sa/g
Load due to wind in • Find force due to wind Fw from superstructure and substructure per unit length
longitudinal and of abutment in longitudinal and transverse direction of bridge
transverse direction of
FT w = pACD G
bridge (horizontal)
FL w = fraction of FT w
Loads at rear of abutment
• Find force due to earth pressure Fb per unit length of abutment H
Fb = ½× ka×γ×H× H
Fs = ka×w×H
Stability Check
Refer IRC 78
1. Find overturning and restoring moment about toe of abutment for different
load combination
Design of Abutment Cap, Main Stem, Back Wall and Slab Base
• Design main stem of abutment as a RC slab and check the stem as a RC column
When design axial load on abutment ≤ 0.1fck A, abutment is designed as RC cantilever slab
When design axial load on abutment > 0.1fck A, abutment is designed as RC column
Vertical Reinforcement
✓ Dia. of bar ≥ 12 mm, ≤ 40 mm
✓ Total area steel of vertical bar 0.0024 to 0.04 of area of concrete
✓ area of bar in one face ≥ 0.0012 of area of concrete
✓ Spacing of vertical bars ≤ 200 mm
Horizontal Reinforcement
✓ Area of horizontal reinforcement ≥ 25% of total area of vertical bars
≥ 0.001 of concrete area
✓ Spacing of horizontal bars ≤ 300 mm
✓ Dia of bar ≥ 8 mm or one fourth of vertical bars
Transverse Reinforcement
✓ If the area of load carrying vertical bar in two faces > 0.02 × area of
concrete theses bars should be enclosed by stirrups
Reinforcement of Abutment
..
… …
… …
… …
…
A A
Section at A-A
Pier
Intermediate supports of bridge are referred as piers
Types of Pier
Framed Type
Cellular Type
Pier
Pier
Preliminary Sizing of Pier Take a = 1 m for span up to 10 m
2 m for span up to 60 m
3 m for span up to 100 m
1 to 1.5 m
HFL
≥1m 1 to 1.5 m
H H
HFL
300 mm
1/50 to 1/12 slope
Trestle Pier
Solid Pier
R = b/2
b N N
2. Horizontal loads
• Force due to Braking Effort
• Force due to Frictional Resistance of Bearing
• Wind Load
• Force due to Earthquake
• Force due to Hydrodynamic Pressure
• Force induced by creep, shrinkage and temperature variation
• Force due to Water Current
Design of RC Pier
Loads on Pier
Dead load from deck • Find Self wt of railing, kerb/footpath, wearing course, slab ,
(vertical) cross beam and main beam per unit length of pier
Weight / Length of Pier
Live load from deck • Find maximum live load per unit length of pier
(vertical) Live Load on Pier / Length of Pier
Load due to • Find force due to earthquake Feq from superstructure and
earthquake in substructure in longitudinal direction of bridge and find force due to
longitudinal and earthquake Feq from superstructure and substructure in transverse
transverse direction of direction of bridge
earthquake
(horizontal) Feq = Z/2× I/R × Sa/g × W
• Find pressure P due to water current of river in transverse direction
Load due to water in of bridge
transverse direction of
bridge (horizontal) P = 52K v2
• Find the force exerted by water pressure along and across the river.
Horizontal Reinforcement
✓ Area of horizontal reinforcement ≥ 25% of total area of vertical bars
≥ 0.001 of concrete area
✓ Spacing of horizontal bars ≤ 300 mm
✓ Dia of bar ≥ 8mm or one fourth dia of vertical bars
Transverse Reinforcement
✓ If the area of load carrying vertical bar in two faces > 0.02 × area of concrete theses bars
should be enclosed by stirrups
Reinforcement of Pier
Problem Statement
Design RC Abutment for a 12 m span T-Beam Bridge to meet the following requirements.
❖ Type of Bridge – T-Beam bridge of 12 m span
❖ Depth of T –Beam - 1 m
❖ Carriage way – Single lane without footpath
❖ Height of Abutment – 7 m
❖ Back fill characteristics – Angle of internal friction of soil (∅) = 350
Unit weight of soil ( 𝜸𝒔𝒐𝒊𝒍 ) = 18 KN/m3 , Backfill slope (i) = 00
❖ Allowable bearing capacity of bearing strata – 300 KN/m2
❖ Bearing size – 250 mm × 400 mm × 64 mm
Design
In the example, RC Abutment has been designed in the following steps.
I. Planning and Preliminary Design
Design of abutment is started with the planning of shape, sizes and selection materials
of abutment. In this stage, approximate sizes of abutment stem, bridge seating,
abutment cap and footing are found.
B. Material Selection
Take
❖ M20 grade of concrete for abutment stem
❖ M25 grade of concrete for abutment cap
❖ Fe 415 HYSD bars for all RC work
C. Geometry of Abutment
❖ Height of dirt wall = Depth of girder + height of bearing – thickness of approach slab
= 1 + 0.064 – 0.3 m = 0.764 m
❖ Thickness of footing = 1 m
𝐻
𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑜𝑓 𝑓𝑜𝑜𝑡𝑖𝑛𝑔 ≈ = 0.875 𝑚
8
Expansion Joint of 40 mm
3.5 m
0.3 m
0.764 m 1m
0.25 m
0.3 m 0.875 m
250 mm × 400 mm × 64 mm
Elastomeric Bearing
y
4.636 m 0.25 m
0.4 m 0.875 m
x
0.25 m mx
3m 0.6 m
4.2 m
3m 0.8 m 1.7 m
y
1m
5.5 m
Take area of steel AS = 1 % of area of cap and distribute these bars equally at top and
bottom of cap. [Refer IRC 78 CL. 716.2]
❖ As in longitudinal direction of abutment
= 1% of 300 × 875 = 2625 mm2, As on one side = 2625/2 = 1312.5 mm2
Take 12 mm ∅ bar, n = 11.6, Adopt n =12
❖ As in transverse direction of abutment
= 1% of 300 × 4200 = 12600 mm2 As on one side = 12600/2 = 6300 mm2
Take 12 mm ∅ bar n = 55.7 Adopt n = 56
In transverse direction bars are provided in the forms of stirrups.
12 – 12 mm dia.
Bearing
56 – 12 mm dia.
300 mm
Mesh of 6 mm dia. @ 75 mm c/c
875 mm in both directions
Abutment Cap
14.625 KN/ m
LL = 114 × 1.25 × (1 + 0.9) + 68 × 1.25 × (0.542 + 0.292 + 0.042) + 14.625 × 12.5 × 0.5 = 436.61 KN
𝟒𝟑𝟔.𝟔𝟏
Load on an abutment per unit length (LL) = = 103.95 KN/m
𝟒.𝟐
𝟑𝟖.𝟎𝟒
Vertical Wind load per unit length FWV = 𝟒.𝟐×𝟐 = 4.53 KN/m
Take, Seismic Zone - V, Soil Strata - Medium, Damping - 5 %, Bridge Class - Normal
Where,
𝑍 𝐼 𝑆 𝑆
Ah = 𝛼ℎ = × × 𝑎 = 0.15; Z = 0.36, I = 1, R = 3, 𝑎 = 2.5
2 𝑅 𝑔 𝑔
W = 753.31 KN in longitudinal direction
W = 753.31 + 0.2 × (2 × 114 + 3 × 68) = 839.71 KN in transverse direction
𝟏𝟐𝟔
Seismic load in transverse direction per unit length FShT = 𝟒.𝟐×𝟐= 15 KN/m
𝟏𝟏𝟑
Seismic load in longitudinal direction per unit length FShL = 𝟒.𝟐×𝟐 = 13.45 KN/m
Vertical reaction on abutment per unit length when seismic load acts in trans. dir.
𝟏𝟐𝟔 × 𝟎.𝟗
FSvT = = 4.5 KN
𝟑×𝟐×𝟒.𝟐
Vertical reaction on abutment per unit length when seismic load acts in long. dir.
𝟏𝟏𝟑×𝟎.𝟗
FSvL = = 2.02 KN
𝟏𝟐×𝟒.𝟐
9. Self-weight of Abutment
Self weight = (0.764 × 0.25 + 0.3 × 0.875 + 0.8 × 4.636) × 4.2 × 25 = 437.04 KN
𝟒𝟎𝟕.𝟑𝟑
Load per unit length DLAb = = 104.06 KN/m
𝟒.𝟐
Horizontal component of load per unit length PEPH(s) = PA cos (24°) = 98.3 KN/m
Vertical component of load per unit length PEPV(s) = PA sin (24°) = 43.77 KN/m
2
𝜑 = 350 , i = 00, 𝛿 = 3 × 350 ≈ 240 , 𝛼 = 00
PA
𝑍 𝐼 𝑆𝑎 2
αh= × × = 0.15, αv = 0.15 × 3= 0.1 H
2 𝑅 𝑔 δ
𝛼ℎ
ψ= tan-1 ( ) = 7.77° and 9.47° 0.6H
1 ± 𝛼𝑣
Horizontal component of load per unit length PEPH(d) = PA cos(24°) = 161.15 KN/m
Vertical component of load per unit length PEPV(d ) = PA sin(24°) = 71.75 KN/m
In the example, responses of abutment at bottom and at 2 m from the bottom for basic combination
and seismic combination of loads have been calculated. Loads taken are vertical and longitudinal
loads. Although seismic and wind load in transverse direction are greater than seismic and wind load
in longitudinal direction, reduction in earth pressure and other loads in transverse directions make the
longitudinal direction’s load critical.
[Refer annex B, Table 3.2, IRC 6-2010]
0.25 m
0.4 m 0.875 mm
x x
0.25 m
3m 0.6 m
4.2 m
Eccentricity
Load Dist. from Pu Mux Muy Hx Hy
γf
(KN) bottom (m) (KN) (KN-m) (KN-m) (KN) (KN)
x (m) y (m)
Eccentricity
Load Dist. from Pu Mux Muy Hx Hy
γf
(KN) bottom (m) (KN) (KN-m) (KN-m) (KN) (KN)
x (m) y (m)
Results of analysis shows that maximum design axial load (Pu = 527.57 KN) is less than 0.1 fck Ac
(0.1 × 20 × 1000 × 800 × 10-3 = 1600 KN ). For the case, where Pu ≤ 0.1 fck Ac , compression member is
treated as a flexure member. So in the example abutment stem has been designed as a cantilever slab.
Since design bending moment is higher in seismic combination of loads, design of abutment stem has
been carried out for seismic combination of loads only.
𝑀𝑢 628.77 × 106
𝑑𝑏𝑎𝑙 = √ =√ = 477.3 mm Where, Q = 0.36 fck× 0.48 × (1 – 0.416 × 0.48) = 2.76
𝑄×𝑏 2.76×1000
dprov > dbal
Since dprov > dbal , section is designed as Singly Reinforced Under-Reinforced Section (SRURS).
In the example, section design has been carried out by using SP 16.
c. Horizontal Reinforcement
Take, As = 0.1% of stem area of abutment or 25% of main vertical bars
= 0.001 × 800 × 4636 = 3708.8 mm2 Provide 17 - 12 mm ∅ on each face of abutment
𝑀𝑢 225.09 × 106
𝑑𝑏𝑎𝑙 = √ =√ = 285.6 mm Where, Q = 0.36 fck × 0.48 × (1 – 0.416 × 0.48) = 2.76
𝑄×𝑏 2.76×1000
dprov > dbal
Since dprov > dbal , section is designed as Singly Reinforced Under-Reinforced Section (SRURS). In
the example, section design has been carried out by using SP 16.
Curtail half of main vertical bars (bars designed for bottom section of abutment) at 2.74 m
(2 m + d) from the bottom of abutment.
b. Horizontal Reinforcement
Take, As = 0.1% of stem area of abutment or 25% of main vertical bars
= 0.001 × 800 × 4636 = 3708.8 mm2 Provide 17 - 12 mm ∅ on each face of abutment
Design the dirt wall as a cantilever slab of span 1.064 m. Consider basic combination and
seismic combination of loads to determine the responses of dirt wall.
Here seismic combination is considered for design. Dirt wall have been designed as a
cantilever slab of unit width. Detailing of wall is carried out as specified by
IRC 112 - 2011 Cl. 16.3.
764 mm
875 mm
Check
𝑻𝒐𝒕𝒂𝒍 𝑹𝒆𝒔𝒕𝒐𝒓𝒊𝒏𝒈 𝑴𝒐𝒎𝒆𝒏𝒕
a. = 𝟐. 𝟖𝟖 > 2 (Safe in overturning)
𝑻𝒐𝒕𝒂𝒍 𝒐𝒗𝒆𝒓𝒕𝒖𝒓𝒏𝒊𝒏𝒈 𝒎𝒐𝒎𝒆𝒏𝒕
𝑻𝒐𝒕𝒂𝒍 𝑹𝒆𝒔𝒊𝒔𝒕𝒊𝒏𝒈 𝒔𝒉𝒆𝒂𝒓 𝑽×𝒕𝒂𝒏∅
b. = = 𝟐. 𝟏𝟐 > 1.5 (Safe in sliding)
𝑻𝒐𝒕𝒂𝒍 𝒔𝒉𝒆𝒂𝒓 𝒂𝒕 𝒃𝒂𝒔𝒆 𝑯
Check
𝑻𝒐𝒕𝒂𝒍 𝑹𝒆𝒔𝒕𝒐𝒓𝒊𝒏𝒈 𝑴𝒐𝒎𝒆𝒏𝒕
a. = 2.47 > 1.5 (Safe in overturning)
𝑻𝒐𝒕𝒂𝒍 𝒐𝒗𝒆𝒓𝒕𝒖𝒓𝒏𝒊𝒏𝒈 𝒎𝒐𝒎𝒆𝒏𝒕
𝑻𝒐𝒕𝒂𝒍 𝑹𝒆𝒔𝒊𝒔𝒕𝒊𝒏𝒈 𝒔𝒉𝒆𝒂𝒓 𝑽×𝒕𝒂𝒏∅
b. = = 2.36 > 1.25 (Safe in sliding)
𝑻𝒐𝒕𝒂𝒍 𝒔𝒉𝒆𝒂𝒓 𝒂𝒕 𝒃𝒂𝒔𝒆 𝑯
X’ X
5.5 m
3m 0.8 m 1.7 m
Y’ 1m Y’
0.65 m
X’ X
Seismic Combination
𝑃𝑢 𝑀𝑢𝑥 ′ 𝑦 750.66 641.27 × 2.75
pu = ± = ± = 263.72 KN/m2 and 9.25 KN/m2
𝑨 𝐼𝑥′𝑥′ 5.5 13.86
1×5.53
Ix′x′ = = 13.86 m4, y = 2.75 m A = 1 × 5.5 = 5.5 m2
12
IIV IIM IM IV
271.08 KN/m2
182.94 KN/m2
297.39 KN/m2
113.06 KN/m2
Analysis of footing
Find Maximum BM at face of abutment and one-way shear at the section lying at d distance
from the face of abutment.
297.39+240.41 1.7
Maximum BM at ‘IM’ = × 1.7 × 1 × = 388.56 KN-m
2 2
113.06+213.6 3
Maximum BM at ‘IIM’ = × 3 × 1× = 734.99 KN-m
2 2
271.08+297.39
Maximum SF at ‘IV’ = × 0.785 × 1 = 223.13 KN
2
113.06+182.94
Maximum SF at ‘IIV’ = × 2.085 × 1= 308.58 KN
2
Design of footing
Check depth of footing
𝑀𝑢 734.99 × 106
𝑑𝑏𝑎𝑙 = √ =√ = 515.93 mm
𝑄×𝑏 2.76×1000
Since provided length > 𝒍𝒅 , additional anchorage for bars are not required
5.5 m
3m 0.8 m 1.7 m
20 mm dia. @ 250 mm
901.6 mm
20 mm dia. @ 125 mm
16 mm dia. @ 160 mm
4.2 m
Bottom arrangement of
reinforcing bars
0.464 m 1m
0.25 m
0.3 m 0.875 m
Cross Section of
Abutment
4.636 m
3m 0.8 m 1.7 m
1m
5.5 m
Longitudinal Section of
Abutment
Problem Statement
Design RC Pier for two spans T-Beam Bridge to meet the following requirements.
Type of Bridge –Two spans T-Beam Bridge
Effective span of T Beam on each side of pier – 12 m
Depth of T –Beam - 1 m
Carriage way – Single lane without footpath
Height of Pier – 8 m
Allowable bearing capacity of bearing strata – 300 KN/m2
Velocity of water current – 3 m/sec
HFL is 1.5m below the bearing level
Bearing size – 250 mm × 400 mm × 64 mm
Design
In the example, RC Pier has been designed in the following steps.
I. Planning and Preliminary Design
Design of pier is started with the planning of shape, sizes and selection materials of pier.
In this step, type of pier, grade of concrete, grade of steel bar, approximate sizes of pier
stem and pier cap have been found.
B. Material Selection
Take
M20 grade of concrete for pier stem
M25 grade of concrete for pier cap
Fe 415 HYSD bars for all RC work
C. Geometry of Pier
𝜏𝑢𝑣 ≤ 𝑘𝑠 𝜏𝑢𝑐
𝑉𝑢 459.06 × 1.5 × 1000 2
Where, 𝜏𝑢𝑣 =𝑏 =2× = 0.35 N/mm
0 ×𝑑 250 + 400+560 + 560 × 560
= 1237 KN [Refer bearing design] Design Axial load (Pu) = 1.5 × 1237 = 1855.5 KN
𝑝 𝐴𝑔 𝑝 𝐴𝑔
Pu= 0.4fck ( Ag − ) + 0.67 × fy Take p = 0.8 % [Minimum longitudinal reinforcement]
100 100
2
Ag ≈ 182621 mm Diameter of stem = 483 mm > Dmin = 1000 mm
Adopt D = 1200 mm to consider debris impact, horizontal load, eccentricity of vertical load and biaxial
moments
8m
1.2 m 1.2 m
0.7 m 3m 0.7 m
𝐿𝐿𝐼 = 114 × 1.25 × (1+ 0.9) + 68 × 1.25 × (0.542 + 0.292 + 0.042) = 345.21 KN
1.2 m 200
𝑳 0 2
𝑭𝑾𝑪 = 52 × K × (V × sin20 ) × A 6.5 m
= 52 × 0.66 × (3 × sin200)2 × 6.5 × 1.2 × 10-2 L
F WC
1.2 m
= 2.82 KN
Response Calculation
0.7 m 3m 0.7 m
0.4 m 0.4 m 0. 5 m
0. 75 m
Face of pier stem
(Critical section of cap for BM and SF)
SF at face due to DL from superstructure, LL from superstructure, VL and Self wt. of Cap
(669.16 × 1.35 + 84.15 × 1.75) + 483.8 × 1.5 + (10.5 × 1.15 + 30.8 × 1.5) + (0.5 × 1.6 × 1.3 ×
0.25
25 × 1.35 + × 1.6 × 1.3 × 25 × 1.35) = 1878.48 KN
2
BM at face due to DL from superstructure, LL from superstructure, VL and Self wt. of Cap
= [(669.16 × 1.35 + 84.15 × 1.75) + 483.8 × 1.5 + (10.5 × 1.15 + 30.8 × 1.5)] × 0.9 + 0.5 × 1.6
1.6 0.25 1.6
× 1.3 × 25 × × 1.35 + × 1.6 × 1.3 × 25 × × 1.35 = 1834.6 + 32.71 = 1867.32 KN-m
2 2 3
𝑑 > 𝑑𝑏𝑎𝑙
a. Primary Reinforcement
𝑀𝑢 1867 .32 × 10 6
Find = = 2.965
𝑏×𝑑 2 1300 ×696 2
𝑀𝑢 0.98
For = 2.965, pt= 0.98 % 𝐴𝑟𝑒𝑞
𝑠𝑡 = 100 × 1300 × 696 = 8867.04 mm
2
𝑏×𝑑 2
b. Distribution Reinforcement
16 2
𝐴𝑟𝑒𝑞
𝑠𝑡 = 0.25 × 𝜋 × × 15 = 2309.1 mm2
4
c. Temperature Reinforcement
Provide 𝐴𝑚𝑖𝑛
𝑠𝑡 per m width steel bars as temperature reinforcements in both
direction of slab at bottom. Adopt 10 mm ∅ bar @ 150 mm c/c.
𝑉𝑢 1878.48 × 1000
𝜏𝑢𝑣 = = = 2.08 N/mm2
𝑏𝑑 1300 × 696
𝜏𝑢𝑐 = 0.64 N/mm2 for M25 and pt = 1.02%
𝜏𝑢𝑐 ,𝑚𝑎𝑥 = 3.1 N/mm2
𝜏𝑢𝑣 > 𝜏𝑢𝑐 𝑎𝑛𝑑 < 𝜏𝑢𝑐 ,𝑚𝑎𝑥 . Hence, shear reinforcement requires.
In the example, responses of pier at bottom for basic combination and seismic combination of
loads have been calculated. Loads taken are vertical and longitudinal loads in first case and
vertical and transverse loads in second case. [Refer annex B, Table 3.2, IRC 6-2010]
Case I
Basic combination of loads
Dist. Eccentricity
Load from Pu Mux Muy Hx Hy
γf
(KN) bottom x (m) y (m) (KN) (KN-m) (KN-m) (KN) (KN)
(m)
DLss 669.16 1.35 903.37 0 0
DLwc 84.15 1.75 147.27 0 0
H
Fbr 55.40 1.15 8 0 509.68 63.71
V
Fbr 10.50 1.15 12.08 0 0
L
FW 7.53 1.5 8 0 90.36 11.30
Wpier 299.24 1.35 403.98 0 0
FWC T 2.82 1 4.33 0 0 12.21 2.82 0
L
FWC 21.27 1 4.33 0 92.1 21.27
Fbuoy -73.51 0.15 -11.03 0 0
Total (without LL) 1455.67 692.14 12.21 2.82 96.28
0.27
LLI 374.50 1.5 561.75 154.48 0
5
Total (with LLI) 2017.42 846.62 12.21 2.82 96.28
LLII 483.80 1.5 0 725.70 0 0
Total (with LLII) 2181.37 692.14 12.21 2.82 96.28
Y
0.7 m 3m 0.7 m
X 0.55 m 1.3 m
X
0.275 m
1.5 m
𝐷𝑒𝑠𝑖𝑔𝑛 𝐵𝑀 (𝑀𝑢 ) = 𝑀𝑢𝑥 2 + 𝑀𝑢𝑦 2 = 846.71 𝐾𝑁 𝐷𝑒𝑠𝑖𝑔𝑛 𝐵𝑀 (𝑀𝑢 ) = 𝑀𝑢𝑥 2 + 𝑀𝑢𝑦 2 = 692.25 𝐾𝑁𝑚
Note: When Column Section is axisymmetric as in circular column, the resultant axis of bending is also a
principal axis. In such a situation, the case of biaxial bending simplifies into uniaxial bending with
Case I
Seismic combination of loads Y
Dist. Eccentricity
Load from Pu Mux Muy Hx Hy
γf
(KN) bottom x (m) y (m) (KN) (KN-m) (KN-m) (KN) (KN)
(m)
DLss 669.16 1 669.16 0 0
DLwc 84.15 1 84.15 0 0
H
Fbr 55.40 0.2 8 0 88.64 11.08
V
Fbr 10.50 0.2 2.1 0 0
L
Fs 84.75 1 8 0 678 84.75
VL
Fs 6.36 1 6.36 0 0
L
Fs (sub) 33.66 1 4 0 134.64 33.66
L
Fhyd 6.20 1 3.25 0 20.15 6.20
Wpier 299.24 1 299.24 0 0
FWC T 2.82 1 4.33 0 0 12.21 2.82 0
L
FWC 21.27 1 4.33 0 92.1 21.27
Fbuoy -73.51 0.15 -11.03 0 0
Total (without LL) 1049.98 1013.53 12.21 2.82 156.96
LLI 374.50 0.2 0.275 74.90 20.6 0
Total (with LLI) 1124.88 1034.13 12.21 2.82 156.96
LL 483.80 0.2 0 96.76 0 0
Total (with LLII) 1146.74 1013.53 12.21 2.82 156.96
i. When loaded on only one span ii. When loaded on both span
Total Axial Load (Pu) = 1124.88 KN Total Axial Load (Pu) = 1146.74 KN
Total Mux = 1034.13 KN-m Total Mux = 1013.53KN-m
Total Muy = 12.21 KN-m Total Muy = 12.21 KN-m
Total Hx = 2.82 KN Total Hx = 2.82 KN
Total Hy = 156.96 KN Total Hy = 156.96 KN
𝐷𝑒𝑠𝑖𝑔𝑛 𝐵𝑀 (𝑀𝑢 ) = 𝑀𝑢𝑥 2 + 𝑀𝑢𝑦 2 = 1034.2 𝐾𝑁m 𝐷𝑒𝑠𝑖𝑔𝑛 𝐵𝑀 (𝑀𝑢 ) = 𝑀𝑢𝑥 2 + 𝑀𝑢𝑦 2 = 1013.6 𝐾𝑁𝑚
Case II
Basic combination of loads
Dist. Eccentricity
Load from Pu Mux Muy Hx Hy
γf
(KN) bottom x (m) y (m) (KN) (KN-m) (KN-m) (KN) (KN)
(m)
DLss 669.16 1.35 903.37 0 0
DLwc 84.15 1.75 147.27 0 0
H
Fbr 55.40 1.15 8 0 509.68 63.71
V
Fbr 10.50 1.15 12.08 0 0
T
FW 30.10 1.5 8 0 0 361.2 45.15 0
Wpier 299.24 1.35 403.98 0 0
FWC T 2.82 1 4.33 0 0 12.21 2.82 0
L
FWC 21.27 1 4.33 0 92.1 21.27
Fbuoy -73.51 0.15 -11.03 0 0
Total (without LL) 1455.67 601.78 373.41 47.97 84.98
LLI 374.50 1.5 0.275 561.75 154.48 0
I
Total (with LL ) 2017.42 756.26 373.41 47.97 84.98
LLII 483.80 1.5 0 725.70 0 0
Total (with LLII) 2181.37 601.78 373.41 47.97 84.98
𝐷𝑒𝑠𝑖𝑔𝑛 𝐵𝑀 (𝑀𝑢 ) = 𝑀𝑢𝑥 2 + 𝑀𝑢𝑦 2 = 843.42 𝐾𝑁𝑚 𝐷𝑒𝑠𝑖𝑔𝑛 𝐵𝑀 (𝑀𝑢 ) = 𝑀𝑢𝑥 2 + 𝑀𝑢𝑦 2 = 708.22 𝐾𝑁𝑚
Case II
Seismic combination of loads
Dist. Eccentricity
Load from Pu Mux Muy Hx Hy
γf
(KN) bottom x (m) y (m) (KN) (KN-m) (KN-m) (KN) (KN)
(m)
DLss 669.16 1 669.16 0 0
DLwc 84.15 1 84.15 0 0
H
Fbr 55.40 0.2 8 0 88.64 11.08
V
Fbr 10.50 0.2 2.1 0 0
T
Fs 95.64 1 8 0 0 765.12 95.64 0
VT
Fs 28.7 1 28.7 0 0
Fs
T 33.66 1 4 0 134.64 33.66
(sub)
T
Fhyd 6.20 1 3.25 0 20.15 6.20
Wpier 299.24 1 299.24 0 0
FWC T 2.82 1 4.33 0 0 12.21 2.82 0
L
FWC 21.27 1 4.33 0 92.1 21.27
Fbuoy -73.51 0.15 -11.03 0 0
Total (without LL) 1072.32 335.53 777.33 98.46 72.64
LLI 374.50 0.2 0.275 74.90 20.6 0
Total (with LLI) 1147.22 356.13 777.33 98.46 72.64
LLII 483.80 0.2 0 96.76 0 0
Total (with LLII) 1169.08 335.53 777.33 98.46 72.64
𝐷𝑒𝑠𝑖𝑔𝑛 𝐵𝑀 (𝑀𝑢 ) = 𝑀𝑢𝑥 2 + 𝑀𝑢𝑦 2 = 855.03 𝐾𝑁𝑚 𝐷𝑒𝑠𝑖𝑔𝑛 𝐵𝑀 (𝑀𝑢 ) = 𝑀𝑢𝑥 2 + 𝑀𝑢𝑦 2 = 846.65 𝐾𝑁𝑚
a. Longitudinal Reinforcement
Consider25 mm dia. bars with 50 mm cover.
25
𝑑ʹ 50+ 𝑑ʹ
2
= = 0.052. Use interaction diagram for = 0.05
𝐷 1200 𝐷
Design column for critical cases 1(i) and 2 (ii)
Case 1 (i)
𝑀𝑢 846.62 × 10 6
3
= = 0.025
𝑓 𝑐𝑘 ×𝐷 20×1200 3
𝑃𝑢 2017 .42 × 10 3
= =0.070
𝑓 𝑐𝑘 ×𝐷 2 20×1200 2
𝑝
= 0.013 [From chart 55, SP 16]
𝑓 𝑐𝑘
Case 2 (ii)
𝑀𝑢 846.65 × 10 6
3
= = 0.0245
𝑓 𝑐𝑘 ×𝐷 20×1200 3
𝑃𝑢 1169.08 × 10 3
= = 0.041
𝑓 𝑐𝑘 ×𝑑 2 20×1200 2
𝑝
= 0.015 [From chart 55, SP 16]
𝑓 𝑐𝑘
0.80
Hence, 𝐴𝑠𝑡 = 100 × 𝜋 × 6002 = 9047.8 mm2
9047.8 × 4
𝑛= = 18.43
𝜋×25 2
For making axisymmetric in reinforcement, adopt 20 - 25 mm ∅ bar
𝜋 × (1200 − 62.5 × 2)
Spacing of bar = = 177.75 mm < 200 mm
20−1
b. Transverse Reinforcement
In the example, transverse reinforcement of pier stem has not been governed by shear
force. So, transverse reinforcement is provided by detailing rules. [Refer IRC 112, Cl. 16.2]
∅
Take circular lateral tie of ∅ = 10 mm ∅ ≥ 𝑙𝑜𝑛𝑔 4
For potential plastic hinge region i.e. 1200 mm from the bottom of pier,
Spacing of tie (Sv) ≤ 5 × 25 = 125 mm
1200 – 2 × 62.5
≤ = 215 mm
5
Adopt spacing of tie (Sv) = 125 mm for potential plastic hinge region.
20 – 25 mm di
A
a.
A A
10 mm @ 200 mm c/c
10 mm @ 125 mm c/c
Up to 1.2 m height
10 mm @ 200 mm c/c
Foundation Type
Shallow
Foundation
Bridge
Foundation
Deep
Foundation
2
Shallow Foundation Normally shallow foundation is provided when soil
strata is good in upper layer and depth of
foundation does not exceed 6m (average).
Spread
Footing
Shallow Isolated
Foundation Footing
Combined
Footing
Shallow/Open
Foundation Mat
Foundation
Deep Foundation
Normally deep foundation is Deep
provided when soil strata is not Foundation Pile Foundation
good in upper layer and depth of
foundation exceeds 6 m (average) .
Well/Caisson Foundation
Pile Foundation
Well Foundation Foundation with piles
Foundation with well
Bridge Foundation
Isolated Footing Behaviour of isolated
footing under loads
Column
Isolated Footing
Elevation
Shear reinforcement
Spread Foundation Behaviour of spread
foundation under loads
P
M
Wall
Tends to bend like a
cantilever slab
Spread Footing
Elevation
Bottom arrangement of
reinforcing bars
Reinforcement of
Spread Footing
Foundation with
shear reinforcement
Top arrangement of
reinforcing bars
Shear reinforcement
Pile Foundation
(Refer to IS 2911)
Pile foundation
Foundation, which transmits loads to deep soil strata ,
to stronger soil base and to a larger area of soil
through skin friction and bearing area is pile
foundation
• Friction pile
• Bearing pile
• Bearing cum friction pile
• Vertical pile
• Rake pile
Pile Cap
Stem
Pile
Shoe
Shoe
Driven Pile
Bored Pile
Types of Pile Shoe
Arrangement of Driven Pile
Geometrical Requirements of Pile
Types of Piles
Short pile Free head pile
Pile
Long pile Fixed head pile
H
e
H
➢ Long pile fails when moment capacity of pile at the yield point
exceeded.
Reinforcement requirements of pile
Pre cast
L/D < 30 1.25
= 30-40 0.8 1.5
> 40 2 100
Reinforcement of Driven Pile
D
Spiral tie
3D 0.6 D
%
A A
0.2
% Section B-B
0.2
%
0.3
%
3D
B B
0.4 x Shoe Details
%
1
Shoe
Reinforcement of Bored Pile
A A
Well Foundation
Refer IS 3955/IRC 45
Well Foundation
Merit
▪ It has a larger bearing area and section modulus as compared with
the cross sectional area of the main body of pier and abutment.
This provides better load distribution and good lateral resistance.
▪ Concrete is cast over ground and has better quality control, as well
as good depth control.
▪ Skilled man power and technology easily available
Demerit
▪ Obsolete technology in many parts of the world
▪ Uneconomic for smaller bridges
▪ Problems of tilt and shift
▪ Time consuming in construction
▪ Quality control problem in bottom plugging of well
Types of Well
Well Cap
Top Plug
Well
Steining
Dredge Hole
with Granular Filling
Well Curb
Cutting Edge
Bottom Plug
Components of Well Foundations and their Functions
Well Steining
Well steining is the main body of a well. It should be heavy enough to sink the whole well
without excessive kentledge. It should be strong enough so that it is not to get damaged
during sinking and from the earth pressure from outside of well.
Well Curb
Lowest part of well steining to transfer load through the cutting edge to the ground. It is
made of richer concrete and is heavily reinforced. It withstands the force from bottom plug
due to arch action. It is made with tapering side inside the well and the taper angle is
around 60 degrees with the horizontal plane. Sometimes the curb is lined with steel plate
through out its height inside and outside to protect from damages due to boulders if any.
Its top diameter(outer) is kept 5 to 15 cm higher than the outer dia. of the well steining to
facilitate sinking.
Cutting Edge
Sharp cutting edge is provided at the end of well curb, where boulders are not expected.
Where as stud nose cutting edge is provided, where boulders are mixed with soil.
Cutting edge should be strong enough to resist cutting pressure and rigidly fixed with well
curb.
Bottom Plug
Concrete layer at end of curb to stop the sinking of well, transfer load of well in wider
area and to control the movement of underground water. It should be strong enough to
withstand large pressure and preferably in the shape of a bulb to produce arch action
and increase the bearing area. The concrete should be richer and with about 15% more
cement content. It should be more workable with slump about 150 to 200 mm.
Top Plug
Sand filling in the well is covered with top plug. It is usually made from lean concrete of
300 mm to 500 mm thickness. Its function is to make a smoother base for well cap.
Well Cap
Well cap is a RC slab cast monolithically with the well steining and transfers load from
superstructure / substructure to the well steining. Its diameter can be made larger by up
to 1.0 m from the steining to accommodate the long abutment or pier. It should be
strong enough to withstand the pressure from above by slab action. The top level of well
cap is usually flushed with the lowest water level or at the river bed level.
Shape and Size of Well Foundations
▪ Shape and size of well depends on the size of substructure ,load and type of
soil. Elongated shapes are used for long piers and abutments.
▪ The size of the dredge hole shall not be less than 2 m to facilitate dredging .
▪ Top diameter(outer) of curb should be higher than the outer diameter of the
well steining to facilitate sinking. Usually curb offset is taken in the range of
50 to 150 mm
▪ Thickness of steining should be sufficient so that well can be sunk by its self
weight . Minimum thickness of steining shall be 500 mm.
▪ Circular wells are most preferred because they are relatively strong, simple in
construction , easy in sinking. Circular wells are not suitable for wide roads
with wide substructures.
▪ Double D and rectangular types are commonly used wells after circular wells.
Tilt and shift of well
Soil stratum through which the wells are sunk are very rarely uniform and
therefore, the resistance offered by these layers to the sinking is different in
different parts of the wells due to which tilt and shift of well my occur. The
effect of tilt and shift is to cause extra foundation pressure and this pressure
shall be considered in design.
Well
Steining
Sectional Elevation
Well Curb
Sectional Plan
Reinforcement of Well Cap
Pier
Well Cap
Bottom Top
Reinforcement Reinforcement
Working Drawing 1 of Well