Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT FOR CHANGING FOR CHANGE IN ORIENTATION OF THE


PLACING BOOM OPENING
Dubai Creek Harbour Development - Dubai Creek Residences

Dubai Creek Residences: Main Contract Works

Table of contents

1. Scope/Objectives

2. Reference

3. Access/Egress and Location

4. Health & Safety hazards

5. Definitions

6. Responsibilities/Supervision

7. Sequence/Method to be employed

8. Man-power requirement

9.Equipment requirement

10.Materials requirement

11.Q.C. Approvals & Other documentation

12.Supporting documentation

13.Distribution

14.Other Information

15.Attachments

1
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT FOR CHANGING FOR CHANGE IN ORIENTATION OF THE


PLACING BOOM OPENING
1. Scope/Objectives
This method statement is to detail & to establish sequence of activities to carryout changing
the orientation of the placing boom opening in NW3 tower.
2. Reference
2.1 Contract Drawings
2.2 specifications
2.3 Project Quality Plan TS-ABM-CIV-PQP-0012 R.1
2.4 HSE Plan TS-ABM-CIV-HSE-0014 -R.1
2.5 Method statement of the placing boom TS-ABM-CIV-MS-0219
3. Access/Egress and Location
Access to the work place will be through designated and exit pathway.
4. Health & Safety
4.1.Contractor will comply with all safety measures as applicable to project safety
requirement.
4.2.Lack of supervision
4.3.Fall of material & persons
4.4.injuries while grinding
5. Definitions
ATK-ATK Engineering & Consultant
ABM-Al Basti & Muktha LLC
MS-Method Statements
QCP-Quality Control Procedures
6. Responsibilities/Supervision
6.1 Project Engineer:
 Shall be responsible to organize required machinery, material, man power to engineers
/ supervisor & foreman for effectively executing the work in a safe manner.
 To clarify any discrepancies in the work.
6.2. Site Engineer / Foreman:
 To execute the work as per Project Engineers instructions with the right methodology &
in a safe manner.

2
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT FOR CHANGING FOR CHANGE IN ORIENTATION OF THE


PLACING BOOM OPENING
 Make sure that all the works are completed prior to offering for inspections.
 To execute the works as per approved method statements.
 To attend all the comments made by Consultant at the time of inspection.
 Ensure the workers PPE, sufficient lighting.
6.3. QA / QC Engineer:
 To check the work is carried out as per the approved method statement.
 To ensure all approved materials are being used
 To raise the W.I.R. after co-ordination with Project Engineer.
6.4. Safety Personal:
 To advice Project Engineer/Site Engineer & foreman regarding the Safety precautions to be
taken and check for the safety implementations to execute the work.
 Ensure close monitoring of the activity
7 Sequence/Method to be Employed
 Marking will be made on the B1 lift lobby slab for changing the orientation of the placing
boom as per the attached hand sketch .
 The concrete in the marked area will be chipped with the chipping machine and the steel in
the chipped area will be cut by grinder .
 Back propping will be provided for this activity as per the approved method statement for
the placing boom TS-ABM-CIV-MS-0219.
 The drilled edges will be rectified with the approved concrete repair material Master Emaco
S423 as per the TS-ABM-CIV-MS-0269.
8. Man Power Requirement
 Site Engineer
 QA/QC Engineer
 Foreman
 Charge hand
 Mason
 Skilled labour
9 Equipment required
 Grinder/Cutting machine

3
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT FOR CHANGING FOR CHANGE IN ORIENTATION OF THE


PLACING BOOM OPENING
 Drilling machine
10 Materials required
 Approved concrete repair material
11. QC APPROVAL AND OTHER DOCUMENTRY REQUIREMENTS
Follow approved Method Statement, ITP, QCP, HSE Plan, and Material Approval.
12. SUPPORTING DOCUMENTATION
This MS to be read in conjunction with the below referenced documents
 Contract Drawings and specifications
 Project Quality Plan
 Project HSE Plan
13. DISTRIBUTION
Copies of this MS will be circulated to the following for Information & action
 Project Manager
 Construction Manager
 Site Engineer
 QA/QC Engineer
 HSE Engineer
14. OTHER INFORMATION
Ensure that all the activities have been carried out to suit the site conditions and involved with
Site in Charge.
15. ATTACHMENTS
 Risk Assessment