1. Introduction:
This procedural document delineates the systematic procedure for conducting a load test on the concrete grade slab
in accordance with ACI 437.2-13 standards at the HADR Warehouse and Facility. The primary aim is to assess the
structural integrity and load-bearing capacity of the slab. The test entails applying a dynamic load that accurately
simulates anticipated loads over the slab's operational lifespan, as detailed in the contract document on page 4 of 16
(SBU CONTRACTING & ACQUISITION). Specifically, the concrete pad is engineered to endure the transit of tracked
vehicles, such as the MTVR Cargo and Dump Truck, with a maximum weight of 15,000 kilograms, representing the
largest wheeled asset. The involvement of a third-party witness, Nematec, is integral to ensure impartial oversight
and validation throughout the testing process. These assessments play a pivotal role in ensuring the robustness and
longevity of the infrastructure.
2. Materials and Equipment:
For the load testing process, a tracked vehicle with a combined weight of 15,000 kilograms will be utilized to traverse
across the entirety of the grade slab. This vehicle serves as a representative load, simulating real-world conditions to
evaluate the slab's load-bearing capacity effectively. Additionally, surveying equipment such as levels and measuring
tapes will be employed to assess the slab's integrity. In case the passage of the vehicle causes any shifts or
damages, these tools will help in accurately measuring any changes in the level of the slab. Alongside, safety
equipment including helmets, safety vests, barriers, and warning signs will be provided to ensure the safety of
personnel involved in the testing process and to prevent any accidents or hazards on the site.
3. Preparation:
Preparation for the load testing of the concrete grade slab begins by ensuring that the slab has undergone the
specified duration of curing according to the concrete mix design and industry standards. This critical step ensures
that the concrete has achieved its optimal strength before subjecting it to the test. Subsequently, the testing area is
meticulously cleared of any debris or obstructions that could impede the movement of the load or compromise the
accuracy of the results. Safety measures are then implemented by installing barriers and warning signs to prevent
unauthorized access and ensure the protection of personnel and equipment involved in the testing process.
Additionally, the accuracy of load measuring devices and surveying equipment is thoroughly verified to guarantee
precise measurements and reliable data collection throughout the testing procedure.
6. Safety Precautions:
Safety precautions are paramount throughout the load testing process to mitigate potential risks and ensure the
well-being of all personnel involved. This begins with thorough briefings on safety procedures for everyone engaged
in the testing operation. Additionally, maintaining a safe distance from the test area during vehicle movement is
imperative to prevent accidents or injuries. Furthermore, adherence to appropriate personal protective equipment
(PPE) is strictly enforced at all times to minimize the risk of harm. Moreover, robust emergency response procedures
are established and readily available to swiftly address any accidents or structural failures that may occur during the
testing process, prioritizing the safety and security of all individuals involved.
7. Completion:
Upon the completion of the load test and subsequent analysis of results, the final step involves the systematic
removal of all testing equipment and the restoration of the site to its original condition. This process ensures that the
testing area is left in a safe and orderly manner, ready for subsequent activities. Additionally, all documentation
pertaining to the test, including observations, measurements, and reports, is meticulously archived for future
reference. This archival process facilitates easy access to critical information and serves as a valuable resource for
informing future decision-making processes related to the infrastructure's maintenance and development.
Observational Insights During Load Testing
A1 A2 A3 A4
B1 B2 B3 B4
C1 C2 C3 C4
D1 D2 D3 D4
E1 E2 E3 E4
F1 F2 F3 F4
G1 G2 G3 G4
H1 H2 H3 H4
I1 I2 I3 I4
J1 J2 J3 J4
K1 K2 K3 K4
L1 L2 L3 L4
M1 M2 M3 M4
N1 N2 N3 N4
O1 O2 O3 O4