Module 3 CPM
Module 3 CPM
Once the project is selected, the focus of project manager shifts to its implementation. This involves
completion of numerous activities by deployment of various resources. The activities of a project have
inter-relationship arising from physical, technical, and other considerations. Some of these activities
are performed in series and some of them in parallel.
Network techniques are quite useful for proper planning scheduling and controlling project activities.
They provide a rational approach to planning and controlling of construction works.
Since bar charts except for their simplicity, have several limitations, they are not effective for
controlling project works. Network techniques are in essence a modification of bar charts for
controlling various activities of a project. Both network and bar charts are graphical techniques. Their
basic requirements is to analyse various work components of the project.
For this it is necessary to list out various activities from beginning to end of the project. There are two
basic planning and controlling techniques that utilise the network to complete the planned project.
They are Programme(project) Evaluation Review Technique (PERT) and Critical Path Method (CPM).
Limitations
• Not useful if time estimates cannot be made for programmes
• Not practicable for mass production
• Lays emphasis on time and not on cost
© Acharya's NRV School of Architecture
• Linear mode and not in series operations only.
Critical Path Method
What is a Network?
Network is a graphic plan of all activities that must be completed to reach the end objective of
the project showing their interdependency and inter-relationship. The components that make up
the network are activities and events.
Event:
An event is also called as mode, is a specific definable accomplishment in a project plan. It is a
point in time at which an activity begins or ends. It is recognisable at particular instant of time. It
consumes neither time nor resources. It is point in time and not passage of time. It is a stage
between the completion of preceding activity and beginning of succeeding one. It is represented
by circle or any geometric shape.
Activity:
Is the smallest unit of productive effort in a project. It is the performance of task between any
two events. It is task performed over a period of time. It is a homogeneous element of
continuous work consuming time and resources in a network plan. It is represented by an arrow.
Description of the activity is written above the arrow and the time taken for its completion is
shown in the middle underneath.
The tail of the arrow indicates the
commencement of the task. The
head of arrow indicates its
completion.
Dummy Activity:
It is a zero time activity shown in
dotted arrows. As shown in
example(4-2) is a dummy activity. It
indicates the activity(2-5) can not
start unless activity(1-2) and (3-4) are
completed.
It does not consume any resource. It
maintains logic of network by keeping
inter dependencies in perfect order. It
also helps to maintain numbering
systems unique in the network
diagram. It indicates dependency of
one activity on the other
G
Project crashing
This is when the triple constraint usually comes into play; scope, time and cost. If one falls
behind, the others have to make up the slack. There are many ways to adjust things on
your project to make up for the time you’ve lost. That includes adding extra resources
along the way, which is a method called project crashing.
Normal time NT
Crash time CT
If there is only one critical path in the network, crash that critical activity which has the least cost
slope. Crashing should be done within crushable limit of that critical activity and within free float
limit of the project.
If there is more than one critical path, crash one critical activity on each critical path which has
least cost slope within the crashable limit of the critical activity and within free float limit.
if there is one critical activity common to two or more critical paths, crash that common critical
activity within its crashable limit and within free float limit.
When critical activity/activities is/ are crashed its corresponding crash time must be adopted for
those crashed activities and normal time for all other activities. Analyse the network, mark critical
path ( there may be shift in critical path in some cases), and compute project completion time.
Compute extra direct cost incurred and indirect cost corresponding to compressed project
completion time.
Repeat this process until there is at least one critical path on which none of the activities can be
crashed , i.e. the critical activities have reached their respective crashable limits. Then stop
further crashing.
Total project cost = sum of normal direct costs of all activities corresponding to normal activity
durations + extra direct cost due to crashing + indirect cost corresponding to compressed project
completion time.
As the project completion time is crashed , there will be increase in direct cost and decrease in
indirect cost. Sum of these representing total cost will be minimum for a particular project
completion time. There are Cmin and Tmin (optimum project cost and project completion time)
Ex: A project consists of five activities as detailed below. Determine optimum project completion
time assuming indirect costs @ 450/- per week.
2
2
1 5 4 5 5
4 1 5 4
0 4
8 0 0
8 9 9
3 3
4 3
3 4
5
3 5
Critical path (1-2) – (2-4), project completion time 5+4 = 9 weeks
Direct cost = 3000
Indirect cost = 9X450
= 4050
STEP 2: Calculate cost slope for each activity and compute sum of normal direct cost of all activities.
Activity Times in weeks Direct cost in RS Cost slope =∆T/∆C/week
= CC-NC/NT-CT
(1-2) 5 4 600 800 800-600/5-4 =200
Analyze the network by adopting crash time for critical activity (1-2) and normal time for other
activities as given below.
2
4 4
1 4 4
4
0 0
8 8 8
3 3
4
3 4
Further crashing is not feasible since critical path 1-2, 2-4, both critical activities have
reached their crashable limits of 4 weeks and 2 weeks respectively.
Project Direct costs Inditrect costs Total costs
completion time
9 weeks 3000 4050 7050
Hence optimum time and cost are 7 weeks and rs 6750/- respectively.