Scheduling and Planning
Scheduling and Planning
Scheduling and Planning
Scheduling
PERT/ CPM
PLANNING
• A fundamental and challenging activity in the
management and execution of construction
projects.
• It involves the choice of technology, the
definition of work tasks, the estimation of the
required resources and durations for
individual tasks, and the identification of any
interactions among the different work tasks
PLANNING
• Planning is an art, and the art of planning
only exists among human beings.
PLANNING
• The logic of its ssequence must be reviewed
for correctness.
• A final review should be entertained to
ascertain that all phases of works should
appear.
• The scope of work is correctly interpreted.
PLANNING
OBJECTI VES:
• To express graphically the specific job and
the proper sequence of the job.
• To establish a medium for estimating the
time, manpower or other resources necessary
for each job.
• To have available sequential arrangement of
the job, accurate estimate of resources and
the alternative plans based on the scope of
work.
SCHEDULING
• Is when a plan is assigned specific dates and
a chronological order to the tasks, so that a
plan can be put into action.
• Include contingencies for variances in the
plan.
• Secondary to planning.
PERT/CPM
PERT ( Program Evaluation and Review Technique )
• Was developed as a result of looking for an
improved method of planning and evaluating
progress on a large scale and development
program.
• Used to measure uncertain activities in a
project and focuses on time planning and
control.
CPM ( Critical Path Method )
• Statistical project management technique that
manages the well-defined activities of a
project, such as time and cost management.
• Its emphasis was on the work or activities to
be managed.
PERT/CPM Project Requirements
Presidential Decree (PD) 1594 provides that:
“The program of works shall include, among other
things, estimates of the work items, quantities, cost and a
PERT/CPM network of the project activities... in the
preparation of the bidding, documents the government
shall make and estimate of the actual number of working
days required to complete the project through
PERT/CPM analysis of the project activities and
corrrected for holidays and weekends.”
PERT/CPM Project Requirements
Memorandum Circular No. 153 ( January 27, 1968) provides
that:
“In order that the performance discipline on the field could
be controlled and easy reporting system could be made to
facilitate the monitoring, evaluation, inspection completion
of infrastructure projects, all heads of departments and chief
of bureaus and offices concerned are hereby required to
change the old system of preparing the work programs of
said projects from the Gantt Chart (Bar Type) to the
PERT/CPM network. Strict compliance herewith is
enjoined.”
PERT/CPM Project Requirements
resources
EVENT-A node (an event),
denoted by a circle, marks the
a
start and completion of an 1 2
B7 G4 K6
1 3 7 8
C8 F10
4 H6 J5
6
SAMPLE PROBLEM:
SAMPLE PROBLEM:
CRITICAL PATH : 1-3-6-8 D3
CRITICAL ACTIVITIES: B-F- 2 5
J PROJECT DURATION:
7+10+5 = 22 DAYS A2 E6 I2
B7 G4 K6
1 3 7 8
C8 F10
4 H6 J5
6
ESTIMATING TIME OF COMPLETION
USING PERT CHART
TERMINOLOGIES:
• OPTIMISTIC TIME (O) : Best time if everything goes
perfectly •
• REALISTIC TIME (M): Most likely time
• PESSIMISTIC TIME (P) : A worst-case situation
0 + 4M + P
ESTIMATED TIME =
6
TERMINOLOGIES:
• OPTIMISTIC TIME (O) : Best time if everything goes
perfectly •
• REALISTIC TIME (M): Most likely time
• PESSIMISTIC TIME (P) : A worst-case situation
0 + 4M + P
ESTIMATED TIME =
6
ADVANTAGES OF PERT:
• Expected project completion time.
• Probability of completion before a specified date.
• The critical path activities that directly impact the
completion time.
• The activities that have slack time and that can lend
resources to critical path activities.
• Activity start and end dates.
LIMITATIONS:
• The PERT Formula Requires Too Much Work.
• The network charts tend to be large and unwieldy.
• Calculating the time estimates is very complex for all the
activities.
• Updating of the project is time consuming and requires high
costs.
• Emphasis is laid only on time factors and cost factors are
neglected
STEPS IN PERT:
• Identify the specific activities.
• Determine proper sequence of the activities.
• Construct the network diagram.
• Estimate the time required for each activity.
• Determine the critical path.
• Update the PERT chart
SAMPLE PROBLEM:
Determine the duration of the project:
SAMPLE PROBLEM:
Determine the duration of the project:
SAMPLE PROBLEM:
Determine the duration of the project:
SAMPLE PROBLEM:
SAMPLE PROBLEM:
CRITICAL PATH:
A-C-E-G
WORKING DAYS = 4 + 5.17 +5.17 +5.17 = 19.51 DAYS
T
thH
anA
k
YsoOm N
yoKu
U
MUC O uS
c h
H!