Methodology of PQC Laying
Methodology of PQC Laying
Methodology of PQC Laying
Km. 0+000) to Km. 73+000 (Design Ch. Km. 71+614) in the State of Uttarakhand
and Uttar Pradesh under NHDP Phase - IV on EPC Contract Basis
SCOPE
The work shall consist of construction of Dry Lean Concrete (DLC) Sub-base for
Cement Concrete Pavement in accordance with the requirement of technical
specifications and in conformity with approved lines, grades and cross-sections.
EQUIPMENT/MACHINERY REQUIREMENT:
1. Batching & Mixing plant
2. Slip form paver
3. Texturing & curing machine
4. Water tankers
5. Tippers
6. Concrete Saw
7. Cement pump
8. Front end loader
MATERIALS FOR PQC
Test certificates from manufacturer shall be presented for each lot of cement or
cement testing shall be carried out in our site laboratory and result will be submitted.
Joint test shall be carried out for the approval obtained from the engineer’s
representative for every 200 cum of material. Water shall be tested as per requirement
of IS: 456 and approval obtained in advance.
Cement shall be procured in polyethylene bags and loaded manually in to hopper of
cement pump. From hopper of pump it will be pumped to the Silo of the Batching
Plant.
Combined grading of aggregates (Coarse & Fine) will be carried out at laboratory
attached with the plant, at least daily and adjustments in Mix proportions will be
made for aggregates components, accordingly.
All approved aggregate shall be stacked separately at plant site in stack 5.00 Meter
clear distance apart and shall be identified by placards marked ‘APPROVED’ placed on
top of the heap.
Four Laning of Haridwar- Negina Section of NH-74 from Km. 0+000 (Design Ch.
Km. 0+000) to Km. 73+000 (Design Ch. Km. 71+614) in the State of Uttarakhand
and Uttar Pradesh under NHDP Phase - IV on EPC Contract Basis
MIX DESIGN
The Minimum Cement content in the PQC shall be not less than 360 kg/cum of
Concrete without Fly ash. And Minimum Cement Content is 310 Kg in case of Fly Ash
Material, which will be Not More than 20% and Max. W/C will be 0.50. If the Minimum
Cement content is sufficient to achieve the desired strength, it will be increased as
necessary. The average compressive & Flexure Strength of each consecutive group of
6 cubes & 6 Beams made in accordance with Clause 903.5.2.1. The compressive
strength of Cubes will not be less than and 40 MPA at 28 Days. The Flexure strength
of beams will not be less than and 4.5 MPA at 28 Days. Mix design as per the
stipulations of ‘MORT&H’ and as per IS: 10262 will be carried out at the Laboratory
and will be submitted to Engineer’s Representative for approval.
PLACING OF PQC
a. The work will be carried out with Suitable Paver or ‘Wirtgen made Paver or
equivalent Paver of laying capacity of 5-10. Meter. of main carriageway will be laid by
Censer Paver and with manually.
b. Prepared sub-base course shall be checked before laying of PQC and Cracks wider
than 5mm will be repaired with concrete prepared from aggregates lower than 10 mm
size.
c. Surveyor will fix the alignment for every day’s work, one day in advance, and get it
approved from Engineer’s Representative.
d. Prior to start of paving, string line will be set, approx. 200mm above PQC top levels
on each side, on longitudinal profile, on stakes placed 10 met apart.
e. Air and concrete temperature shall be measured and recorded in the concrete
docket, at the plant site as well as laying site. No concrete will be done when the
concrete temperature cannot be maintained below 30 deg cent & when ambient
temperature is more then. 35 deg. cent. Plant operation will be stopped based on
feedback from laying site.
f. Test Station at Laying Site will be maintained 80 to 100 meter. Ahead of the Paver
and will be shifted forward as the work progresses ahead.
g. Concrete production shall be stopped as per advice from paving site.
h. One copy of docket will be handed over to Engineer’s Representative at laying site
and the other copy will be retained by us.
i. Traceability of concrete received from the batching plant will be maintained by
recording data as shown on Traceability form.
Four Laning of Haridwar- Negina Section of NH-74 from Km. 0+000 (Design Ch.
Km. 0+000) to Km. 73+000 (Design Ch. Km. 71+614) in the State of Uttarakhand
and Uttar Pradesh under NHDP Phase - IV on EPC Contract Basis
Concrete will be vibrated and compacted by group of vibrators housed in the vibrator
box at the spacing of 40cms. Capable of providing variable output for achieving
required level of compaction.
m. Dowel bar location shall be identified by paint g on DLC. Tie bars shall be located
by taking reference from the dowel bar marking. n. Dowel bars at transverse joints
shall be inverted by vibration plastic
concrete and shall be placed at mid depth of the slab by dowel inserter. Similarly tie
bars at longitudinal joints shall be inserted by vibration into plastic concrete and shall
be placed at mid-depth of slab by Tie Bar inserter.
n. Concrete at all these locations shall be simultaneously vibrated & finished.
o. Finishing of concrete surface at the required level shall be carried out by Oscillating
Beam, which will be guided by the sensor.
p. Texturing shall be done by brush operated from texturing machine. Depth of the
surface texture shall be maintained at 1.0 mm, which shall be tested with the
Engineer’s Representative, and his approval shall be obtained.
q. Rate of evaporation from surface of concrete will be monitored at an interval of 01
hr. during laying. If rate of evaporation exceeds 01kg/M²/ Hr., evaporation retardant
will be used to minimize the effect of surface evaporation. If rate of evaporation
exceeds 2kg/M² / Hr., work will be stopped.
r. Barriers will be provided at each end of the paving site to prevent entry of vehicles.
Entry points will be guarded during day and night.
CURING OF PQC
Curing shall commence as soon as the completion of finishing operations of concrete
surface. Curing shall be carried out, by spaying approved curing compound at the
spray rate recommended by manufacturer. After 3 hours of spraying of curing
compound, moist Hessian shall cover concrete surface without causing damage to
curing compound film. Hessian shall be used and will be kept moist for 14 days by
regular sprinkling of water from flexible pipe attached with a water tanker. Water
tankers will be deployed round the clock for providing water for curing. Water will be
available from the bore wells along the length of the road. Hessian of 16-guage
thickness will used and stock to cover 40000 M² areas will be maintained.
a. Joint cutting will commence at the earliest possible after paving. (When the
pavement can withstand the weight of concrete saw and saw cutting does not
dislodge particles/aggregates from the side of the joint)
b. Initial cut shall be with 3 mm thick diamond saw blade. This cut will be washed out
immediately and a temporary seal shall be installed. 4mm thick Armour board shall be
used as a temporary seal.
c. Widening of the joint to a width of 12 mm will be taken after 2 to 3 weeks by
cutting with 10 mm thick saw blade operated by concrete saw. Widened joints shall
be washed immediately after the cut.
Joints shall be cleaned with compressed air and shall be dried completely before
filling with sealing compound. 15 mm thick Armour board shall be provided at the
bottom of the groove and masking tape shall be fixed on each side of the joint.
d. Sealant shall then be filled specified depth and finished by tooling specified shape.
TRIAL PAVE
a. Trail paving will be conducted at outside the road alignment and at our campsite.
b. Polyethylene film shall be spread over the prepared DLC surface. Paver shall be set
up accordingly, by providing stakes guided sensor string line at the required target
levels.
c. Mix shall be prepared as required by specification and as per approved Mix design.
d. Mix shall be carted to the laying site as per approved method in covered tippers.
e. Spreading, compacting & finishing shall be carried out in the manner
approved before.
f. Paving shall be carried out over two days and all transverse & longitudinal joints
will be constructed as required by specification.
g. Curing shall be carried out as specified & as per approved method. Insertion of
dowel bars 7 tie bars, surface texturing shall be done as specified and as per
approved method statement.
h. Length of laboratory pave shall be kept as 60-70 meter.
i. Target level for the trial shall be fixed prior to paving.
j. Suitability of moisture content of mix shall be examined during the trial length
construction to ensure that maximum density and compressive strength related to
corresponding water content are achieved.
k. Achieve levels will be compared with the target levels.
l. Sealing of joints shall be done as specified and as per approved method.
m. Tests on trial shall be carried out as specified vide clause 602.10.5 of MOST
specifications. Cores shall be taken to determine density of concrete & to check
segregation.
Four Laning of Haridwar- Negina Section of NH-74 from Km. 0+000 (Design Ch.
Km. 0+000) to Km. 73+000 (Design Ch. Km. 71+614) in the State of Uttarakhand
and Uttar Pradesh under NHDP Phase - IV on EPC Contract Basis
TESTING OF PQC
Testing will be carried out as per table enclosed (encl. -III). Level conformance of
finished DLC will be ensured by taking levels at specified grids and compared with the
target levels. Concrete testing records will be maintained as per format enclosed
(Encl- IV)
TOLERANCES
The tolerances for surface regularity, level, thickness, density and strength shall
conform to the requirements given in clause 903.5. Control of quality of material and
work shall conform to the specification as laid down in section 900 of MOST
Specifications.
TRAFFIC
No heavy or light commercial vehicles like trucks, buses etc. shall be permitted on the
PQC sub-base after its construction.
ENVIRONMENTAL SAFETY
I. Water will be obtained from the bore wells situated at our Camp Sites so that it will
not affect nearby localities.
II. The Batching Plants are situated at our Camp Sites and water sprinklers will be
installed to minimize Dust & Cement in the localities.
Fuel Storage and Refuelling Site are in the Camp Sites and Strict Supervision will be
maintained to stop Spillage or Leakage to any nearby water bodies.
IV. Our Mechanical Staff will maintain Batching Plant & other related Equipment’s
regularly to reduce Noise & Atmospheric Pollution.
V. The constructions Vehicles, Machineries and Equipment’s will move in our
designated area so it prevents compaction of any type of vegetation and plants.
Four Laning of Haridwar- Negina Section of NH-74 from Km. 0+000 (Design Ch.
Km. 0+000) to Km. 73+000 (Design Ch. Km. 71+614) in the State of Uttarakhand
and Uttar Pradesh under NHDP Phase - IV on EPC Contract Basis
VI. All workers will be suitably provided with safety guards &equipment’s at the site.
VII. Safety Signals & Sign boards will be provided at every 250 m at the Construction
Site.