TENDER DOCUMENT

Name of Work: Levelling and grading of area at 24 &


06 side in newly acquired land at S.V. Airport, Raipur.

AIRPORTS AUTHORITY OF INDIA


ENGINEERING WING,
S.V. AIRPORT, RAIPUR
INDEX
Name of Work: Levelling and grading of area at 24 & 06 side in newly acquired land
at S.V. Airport, Raipur

S. No. Description Page No.


1. General Guidelines GG 1-1
2. E-Notice inviting Tender ENIT 1-5
3. Instructions for on line bid submission ITB 1-4
4. General Guidelines for Bidders GGB 1-6
5. General Conditions of Contract GCC 1-138
6. Performa PR 1-23
7. Special Conditions of Contract SCC 1-14
8. Technical Specification TS 1-14
9. Bill Of Quantities / SCHEDULE -' A' BOQ 1-2
TOTAL 207

This Tender Document contains 207 pages as detailed above.


General Guidelines
AIRPORTS AUTHORITY OF INDIA
S.V. AIRPORT, RAIPUR

General Guidelines

Name of Work: Levelling and grading of area at 24 & 06 side in newly acquired land
at S.V. Airport, Raipur

First Important Step to Bidder for e-tender:


(CPP e-Procurement portal reference: https://etenders.gov.in/eprocure/app)

Bidders have to read the instructions to the bidders given in the e-tender portal of CPP and
take immediate steps to:
a) Register for bid to participate intendering.
b) Obtain digital signature well in advance which takes minimum 24 to 30hours.
c) Make sure availability of all required software in your PC as instructed under bidders
instruction head of e-procurement portal of CPP.

Correspondence on tender documents:


a) Tender Document:-The prospective bidder shall download the tender documents
on-line from CPP’s e-Procurement portal and upload digitally signed entire tender
document on CPP e-tender portal. Besides, whenever tenderer signatures are earmarked in
the tender documents shall put his signature and upload scan copies of the same.
b) Amendment to Tender Document: -At any time, prior to scheduled last date of
submission of bids, AAI if it deems appropriate to revise any part of this tender or to issue
additional date to clarify the interpretation of provisions of this tender, it may issue
addendum/corrigendum to this tender. Any such Addendum/ Corrigendum shall be
deemed to be incorporated by this reference into this tender and binding on the bidders.
Addendum/Corrigendum will be notified through CPP’s Website/Portal only.
c) Clarifications of Tender Document: -Bidder, requiring any clarifications of the
tender document, may submit their queries, if any, through provision of CPP’s
Website/Portal as per the critical dates given on Notice Inviting E-Tender. Replies to
queries by AAI will be uploaded through CPP’s e-Procurement portal. The bidders are
advised to visit CPP’s Website/Portal regularly.
d) No correspondence shall be entertained from the tenderer after opening of tenders,
other than asked by AAI for any clarifications if required.

GG-01
E- Notice Inviting Tender
भारतीय विमानपत्तन प्राविकरण
ISO 9001:2015 AIRPORTS AUTHORITY OF INDIA
ISO14001:2015 एस.व्ही. हिाई अड्डा, रायपरु - 492015
ISO45001:2018
S.V. AIRPORT, RAIPUR-492015

NOTICE INVITING E- TENDER (2 Bot - 2 Covers Open Tender)


TENDER I.D. NO.- 2022_AAI_101772_1

1. Item rate/EPC (Strike off whichever is not applicable) e-tenders are invited through
the e-tendering CPP portal by Asstt. Gen. Manager (Engg-C)-I, Airports Authority of
Iindia, Swami Vivekananda Airport, Raipur- 492015 (Bid Manager) Ph. No. 0771-
2418700 on behalf of Chairman, A.A.I. from the eligible contractors for the work of
“Levelling and grading of area at 24 & 06 side in newly acquired land at S.V.
Airport, Raipur.” at an estimated cost of Rs.3,05,35,323/- (Excluding G.S.T.) with
period of completion 08 (Eight) Months.
The tendering process is online at e-portal URL address
https://etenders.gov.in/eprocure/app or www.aai.aero. Prospective Tenderers may
download and go through the tender document.
Prospective tenderers are advised to get themselves register at CPP-portal, obtain
‘Login ID’ & Password and go through the instructions available in the home page
after login in to the CPP-portal https://etenders.gov.in/eprocure/app or www.aai.aero.
They should also obtain Digital Signature Certificate (DSC) in parallel which is
essentially required for submission of their application. The process normally takes
03 days time. The tenderer may also take guidance from AAI help desk support
through path aai.aero/tender/e-tender/help desk support.
(i) For any technical related queries please call the Helpdesk. The 24x7 Help
desk details are as below:-
Tel: 0120-4200462, 0120-4001002, Mobile : 91 8826246593,
E-mail:support-eproc@nic.in

Tenderers are requested to kindly mention the URL of the Portal and Tender ID in the
subject while emailing any issue along with the contract details.

For any further technical assistance with regards to functioning of CPP portal the tenderer
may contact to the following AAI help desk numbers on all working days only between.

(ii) 08:00 Hrs to 20:00 Hrs (Mon- Sat)


011-24632950, Ext-3512(sixlines), E-mail:- eprochelp@aai.aero

(iii) 09:30 Hrs to 18:00 Hrs (Mon- Fri)


011-24632950, Ext-3523, E-mail:- etendersupport@aai.aero,
sanjeevkumar@aai.aero and snita@aai.aero.

(iv) 09:30 Hrs to 18:00 Hrs (Mon- Fri)


011-24632950, Ext-3527, Email:- dkumar@aai.aero

(v) 09:30 Hrs to 18:00 Hrs (Mon- Fri)


011-24657900, Email:- gmitchq@aai.aero.

ENIT-1
Tender Processing fee of Rs. 1120 (i/c GST) Non-refundable will be required to be paid Online
through SBI MOPS Gateway using SBI/Other Banks/NEFT/RTGS mode.
2. Following 2 covers shall be submitted through online at CPP-Portal by the bidder as per the
following schedule:-
CRITICAL DATA SHEET
Publishing Date 07.06.2022 at 18:00 Hrs.
Bid Document Download/Sale start date 08.06.2022 at 09:30 Hrs.
Clarification start date 08.06.2022 at 09:30 Hrs.
Clarification end date 24.06.2022 at 18:00 Hrs.
Bid submission start date 08.06.2022 at 09:30 Hrs.
Bid submission end date 29.06.2022 at 18:00 Hrs.
Bid opening date (Envelope-I) 01.07.2022 at 11:00 Hrs.
Bid opening date (Envelope-II/Financial Bid) 11.07.2022 at 15:00 Hrs.
Tender Processing Fee (Non-Refundable), to be paid Rs. 1,120.00 (i/c GST) Non- Refundable
online through state bank of India payment gateway
in CPP portal.
Earnest Money Deposit (EMD) to be paid online Rs. 6,10,706/-
through State Bank of India payment gateway in
CPP portal.
Enevelope-I:- (Tender processing fee, EMD, Technical Bid and Pre-qualification):-
A. Tender processing fee:
i. Scanned copy of Tender fees online transaction receipt.
ii. Scanned copy of EMD online transaction receipt
B. Technical Bid containing the following:
i. Scanned copy of Unconditional Acceptance of AAI’s Tender Conditions on Company’s
Letter Head as per Annexure-1 at Page no. PR-1.
ii. Scanned copy of Permanent Account Number (PAN) and GST Registration Number
along with undertaking as per Annexure-6, at Page no. PR-9.
iii.Scanned copy of ‘Undertaking’ regarding Blacklisting/Debarment on Company’s Letter
Head as per Annexure-7, at page no. PR-10.
iv. Scanned copy of Affidavit for Minimum wages on Rs.100/- Stamp Paper as per
Annexure-5 at Page no. PR-8.
v. Tenderer should deploy sufficient plant and machinery as per the requirement of work in
consultation with the Engineer-in-charge (E-I-C) to achieve the milestones/targets and
overall completion within the time period. Tenderer shall submit scanned copy of
‘Undertaking’ on Company’s Letter Head as per Annexure-13 at page no. PR-23.
vi. Companies other than propriety firm shall submit, scanned copy of Authorization
Letter/Power of Attorney along with copy of certificate of incorporation of the Company
under Companies Act showing CIN/LLPIN/Name of Directors of the Company & Copy
of Board Resolution regarding Authority to assign Power of Attorney.
Proprietary firm shall submit scanned copy of Authorization Letter/ Power of Attorney
only if the tender is processed by a person other than proprietor.
vii. Digitally signed Tender Document should be submitted as per Annexure-11 at Page
no. PR-21.

ENIT-2
C. Qualifying requirements of contractors / tenderers containing the followings:-
(i) Should have satisfactorily completed (Phase/Part completion of the scope of work in a
contract shall not be considered, however pre-determined phasing of the work will be
accepted) three works for each of Rs. 1,22,14,129/- (excluding GST) or two works,
each of Rs. 1,52,67,662/- (excluding GST) or one work of Rs. 2,44,28,258/-
(excluding GST) in single contract of any Civil Works during last seven years ending
on last date of submission of e-Bid (including extended date, if any).
“The value of executed works shall be brought to current costing level by
enhancing the actual value of work at simple rate of 7% per annum, calculated
from the date of completion to the last date of submission of bid.
Client certificate for experience should show the nature of work, the value of work,
date of start, date of completion as per agreement, actual date of completion and
satisfactory completion of work. Tenderer showing work experience certificate from
non-government/non-PSU organizations should submit copy of tax deduction at
sources (TDS) certificate(s) along with a certificate issued by registered Chartered
Accountant and having UDIN, clearly specifying the name of work, total payment
received against the work and TDS amount for the work.
(ii) Should have UDIN generated annualized average financial turnover of 30% (Rs.
91,60,597/- excluding GST) against works executed during last three years ending 31st
March of the previous financial year. As a proof, UDIN generated copy of Abridged
Balance Sheet along with Profit and Loss Account Statement of the firm should be
submitted along with the application. Tenderers showing continuous losses for the last
three years in the balance sheet shall be summarily rejected.
(iii) The tenderer should have a minimum net worth of 15% (Rs. 45,80,298/- excluding GST)
issued by certified Chartered Accountants and having UDIN as per Annexure-12 at Page no.
PR-22.
Scan copy of all documents of Envelope-I mentioned above shall be submitted on the
CPP portal. Tender processing fee and EMD is required to be paid online only. The
tenderer, whose Tender processing fee and EMD are not received, then their tenders
will be liable to be rejected.
Refund of EMD
The refund of EMD to tenderers, who fail to qualify in the eligibility/technical criteria,
shall be initiated by CPP Portal after their rejection on the same day of opening of the
financial bid.
Envelope-II: - The Financial e-Bid through CPP portal.
All rates shall be quoted in the format provided and no other format is acceptable. If
the price bid has been given as a standard BOQ format with the tender document, then
the same is to be downloaded and to be filled by all the tenderers. Tenderers are
required to download the BOQ file, open it and complete the blue coloured
(unprotected) cells with their respective financial quotes and other details (such as
name of the tenderers). No other cells should be changed. Once the details have been
completed, the tenderer should save it and submit it online, without changing the file
name. If the BOQ file is found modified by the bidder, the bid will be rejected.

ENIT-3
3. Bid Submission: -
The tenderer shall submit their application only CPP Portal:
https://etenders.gov.in/eprocur/app. Tenderer/ Contractor are advised to follow the
instruction provided in the tender document for online submission of bids. Tenderers
are required to upload the digitally signed file of scanned documents as per Para 2. Bid
documents may be scanned with 100 dpi with black and white option which helps in
reducing size of the scanned document.
Uploading of application in location other than specified above shall not be considered.
Hard copy of application shall not be entertained.
4. Not more than one tender shall be submitted by one tenderer of tenderers having
business relationship. Under no circumstance will father and his son(s) or other closer
relations who have business relationship with one another (i.e. when one or more
partner(s)/director(s) are common) be allowed to tender for the same contract as
separate competitors. A breach of this condition will render the tenders of both parties
liable to rejection.
5. Tenderer who was downloaded the tender from Central Public Procurement Portal
(CPPP) website https://etenders.gov.in/eprocur/app, shall not tamper/modify the tender
form including downloaded proce bid template in any manner. In case if the same is
found to be tampered/modified in any manner., tender will be completely rejected and
EMD would be forfeited and tenderer is liable to be banned from doing business with
AAI.
6. Bids Opening Process is as below:-
Envelope–I: (Tender processing fee, EMD, Technical Bid and Pre-qualification):
Envelope-I containing documents as per Para 2 (A), (B) and (C) (uploaded by the
tenderers) shall be opened on date & time mentioned in Critical Data Sheet.
It the bidder has any query related to the Bid Document of the work, they should use
‘Seek Clarification’ on CPP portal to seek clarification. No other means of
communication in this regard shall be entertained.
If any clarification is needed from the tenderer about the deficiency in his uploaded
documents in Envelope-I, he will be asked to provide it through CPP portal or email if
required. The tenderer shall upload the requisite clarification/documents within time
specified by AAI, falling which, it shall be presumed that bidder does not have
anything to submit and bid shall be evaluated accordingly.
The intimation regarding acceptance/rejection of their bids will be intimated to the
tenderers through CPP portal.
Envelope-II (Financial Bid)
Envelope-II containing financial bid of the tenderers found to be meeting the technical
criteria and qualifying requirements shall be opened on date & time mentioned in
CRITICAL DATA SHEET. (In case the date and time for opening of Envelope-II
(Financial Bid) is required to be changed, the same shall be intimated through
CPP Portal).

ENIT-4
7. AAI reserves the right to accept or reject any or all applications without assigning any
reasons. AAI also reserves the right to call off tender at any stage without assigning
any reason.
8. AAI reserve the right to disallow issue of tender document to working agencies whose
performance at ongoing project (s) is below par and usually poor and has been issued
letter of restrain/Temporary or Permanent debarment/black listing by any department
of AAI or Central/State Govt. Depts./PSUs/World Bank/ADB etc. AAI reserve the
right to verify the credential submitted by the agency at any stage (before or after
the award of work). If at any stage, any information/documents submitted by the
applicant is found to be incorrect/false or have some discrepancy which
disqualifies the firm then AAI shall take the following action:

a) Forfeit the entire amount of EMD submitted by the tenderer.

b) The tenderer shall be liable for debarment from tendering in AAI, including
termination of the contract apart from any other appropriate contractual/ legal
action.

9. Consortium/JV companies shall not be permitted.


10. Purchase preference to Central Public Sector Undertaking shall be applicable as per the
directive of Govt. of India prevalent on the date of acceptance.
11. Concessions to Indian Micro & Small Enterprises (MSEs) units registered with
DIC/NSIC/KVIC/KVIB/Directorate of Handicraft and Handloom etc., to eb given as per
the provisions of Public Procurement Policy for MSEs order 2012 with up to date
amendments, shall be applicable for tenders of supply/services and shall not be extended
to construction work.
The Benefits of MSME firms shall not be extended to this work.
12. Tenderers have to submit UDIN generated documents like Balance Sheet/Turnover
certificate, Working Capital Certificate (works done during last 5 financial years &
works in hand), Net worth Certificate, Tax Deduction at Source (TDS) Certificates for
Non- Govt. works etc. as per NIT conditions duly certified by CA and having UDIN.
The documents submitted by bidders without UDIN shall not be entertained."

Asstt. Gen. Manager (Engg-C)-I


Bid Manager
AAI, S.V. Airport, Raipur

ENIT-5
Instruction for online bid
submission
Annexure-AA

Instructions for Online Bid Submission

The bidders are required to submit soft copies of their bids electronically on the CPP Portal, using
valid Digital Signature Certificates. The instructions given below are meant to assist the bidders in
registering on the CPP Portal, prepare their bids in accordance with the requirements and submitting
their bids online on the CPP Portal.

More information useful for submitting online bids on the CPP Portal may be obtained at:
http://etenders.gov.in/eprocure/app.

REGISTRATION

1) Bidders are required to enroll on the e-Procurement module of the Central Public Procurement
Portal (URL:http://etenders.gov.in/eprocure/app) by clicking on the link “Online bidder
Enrollment” on the CPP Portal which is free of charge.

2) As part of the enrolment process, the bidders will be required to choose a unique username and
assign a password for their accounts.

3) Bidders are advised to register their valid email address and mobile numbers as part of the
registration process. These would be used for any communication from the CPP Portal.

4) Upon enrolment, the bidders will be required to register their valid Digital Signature Certificate
(Class II or Class III Certificates with signing key usage) issued by any Certifying Authority
recognized by CCA India (e.g. Sify / nCode / eMudhra etc.), with their profile.

5) Only one valid DSC should be registered by a bidder. Please note that the bidders are responsible
to ensure that they do not lend their DSC’s to others which may lead to misuse.

6) Bidder then logs in to the site through the secured log-in by entering their user ID / password and
the password of the DSC /e-Token.

SEARCHING FOR TENDER DOCUMENTS

1) There are various search options built in the CPP Portal, to facilitate bidders to search active
tenders by several parameters. These parameters could include Tender ID, Organization Name,
Location, Date, Value, etc. There is also an option of advanced search for tenders, wherein the
bidders may combine a number of search parameters such as Organization Name, Form of
Contract, Location, Date, Other keywords etc. to search for a tender published on the CPP Portal.
2) Once the bidders have selected the tenders they are interested in, they may download the required
documents / tender schedules. These tenders can be moved to the respective ‘My Tenders’ folder.
This would enable the CPP Portal to intimate the bidders through SMS / e-mail in case there is any
corrigendum issued to the tender document.
3) Once the bidders have selected the tenders they are interested in, they may download the required
documents / tender schedules. These tenders can be moved to the respective ‘My Tenders’ folder.
This would enable the CPP Portal to intimate the bidders through SMS / e-mail in case there is any
corrigendum issued to the tender document.

(C-NIL I-NIL O- NIL)


ITB-1
4) The bidder should make a note of the unique Tender ID assigned to each tender, in case they want
to obtain any clarification / help from the Helpdesk.

PREPARATION OF BIDS
1) Bidder should take into account any corrigendum published on the tender document before
submitting their bids.
2) Please go through the tender advertisement and the tender document carefully to understand the
documents required to be submitted as part of the bid. Please note the number of covers in which
the bid documents have to be submitted, the number of documents - including the names and
content of each of the document that need to be submitted. Any deviations from these may lead to
rejection of the bid.
3) Bidder, in advance, should get ready the bid documents to be submitted as indicated in the tender
document / schedule and generally, they can be in PDF / XLS / RAR / DWF/JPG formats. Bid
documents may be scanned with 100 dpi with black and white option which helps in reducing size
of the scanned document.
4) To avoid the time and effort required in uploading the same set of standard documents which are
required to be submitted as a part of every bid, a provision of uploading such standard documents
(e.g. PAN card copy, annual reports, auditor certificates etc.) has been provided to the bidders.
Bidders can use “My Space” or ‘’Other Important Documents’’ area available to them to upload
such documents. These documents may be directly submitted from the “My Space” area while
submitting a bid, and need not be uploaded again and again. This will lead to a reduction in the time
required for bid submission process.
SUBMISSION OF BIDS
1) Bidder should log into the site well in advance for bid submission so that they can upload the bid
in time i.e. on or before the bid submission time. Bidder will be responsible for any delay due to
other issues.
2) The bidder has to digitally sign and upload the required bid documents one by one as indicated in
the tender document.
3) Bidder has to select the payment option as “Online” to pay the tender fee /EMD as applicable and
enter details of the instrument.
4) Bidder should prepare the EMD as per the instructions specified in the tender document.

5) Bidders are requested to note that they should necessarily submit their financial bids in the format
provided and no other format is acceptable. If the price bid has been given as a standard BOQ
format with the tender document, then the same is to be downloaded and to be filled by all the
bidders. Bidders are required to download the BOQ file, open it and complete the white coloured
(unprotected) cells with their respective financial quotes and other details (such as name of the
bidder). No other cells should be changed. Once the details have been completed, the bidder
should save it and submit it online, without changing the filename. If the BOQ file is found to be
modified by the bidder, the bid will be rejected.
6) The server time (which is displayed on the bidders’ dashboard) will be considered as the standard
time for referencing the deadlines for submission of the bids by the bidders, opening of bids etc.
The bidders should follow this time during bid submission.
7) All the documents being submitted by the bidders would be encrypted using PKI encryption
techniques to ensure the secrecy of the data. The data entered cannot be viewed by unauthorized
persons until the time of bid opening. The confidentiality of the bids is maintained using the
secured Socket Layer 128 bit encryption
(C-NILtechnology.
I-NIL DataO- storage
NIL) encryption of sensitive fields is
ITB-2
done. Any bid document that is uploaded to the server is subjected to symmetric encryption
using a system generated symmetric key. Further this key is subjected to asymmetric encryption
using buyers/bid opener’s public keys. Overall, the uploaded tender documents become readable
only after the tender opening by the authorized bid openers.
7) The uploaded tender documents become readable only after the tender opening by the authorized
bid openers.
8) Upon the successful and timely submission of bids (ie after Clicking “Freeze Bid Submission”
in the portal), the portal will give a successful bid submission message & a bid summary will be
displayed with the bid no. and the date & time of submission of the bid with all other relevant
details.
9) The bid summary has to be printed and kept as an acknowledgement of the submission of the
bid. This acknowledgement may be used as an entry pass for any bid opening meetings.

ASSISTANCE TO BIDDERS
1) Any queries relating to the tender document and the terms and conditions contained therein should
be addressed to the Tender Inviting Authority for a tender or the relevant contact person
indicated in the tender.
2) Any queries relating to the process of online bid submission or queries relating to CPP Portal in
general may be directed to the 24x7 CPP Portal Helpdesk.

(C-NIL I-NIL O- NIL)


ITB-3
CPP under GePNIC, Help Desk Services

1) For any technical related queries please call the Helpdesk. The 24 x 7 Help Desk Number 0120-
4200462,0120-4001002
Note- Bidders are requested to kindly mention the URL of the Portal and Tender Id in the subject
while emailing any issue along with the Contact details. For any issues/ clarifications relating to the
tender(s) published kindly contact the respective Tender Inviting Authority.

Tel: 0120-4200462,0120-4001002.

E-Mail:support-eproc@nic.in
For any Policy related matter / Clarifications Please contact Dept of Expenditure, Ministry of
Finance. E-Mail: CPP-doe@nic.in

2) For any Issues / Clarifications relating to the publishing and submission of AAI tender(s)

a. In order to facilitate the Vendors / Bidders as well as internal users from AAI, Help desk services
have been launched between 08.00-20.00 Hrs for the CPP under GePNIC https://eprocure.gov.in.
The help desk services shall be available on all working days (Except Sunday and Gazetted
Holiday) between 08.00-20.00 Hrs and shall assist users on issues related to the use of Central
Public Procurement Portal (CPP).
b. Before submitting queries, bidders are requested to follow the instructions given in “Guidelines to
Bidders” and get their computer system configured according to the recommended settings as
specified in the portal at “System Settings for CPP”.
3) In case of any issues faced, the escalation matrix is as mentionedbelow:

Sl. Support Escalation E-Mail Address Contact Timings


No. Person Matrix Number

1. Help Desk Instant


011- 24632950
-Ext-3512 09.30- 18.00 Hrs.
eprochelp@aai.aero (Six Lines)
2. Team Support Mon-Fri *

*The Helpdesk services shall remain closed on all Govt. Gazetted Holidays.

4) The above mentioned help desk numbers are intended only for queries related to the issues on
e-procurement portal and help needed on the operation of the portal. For queries related to the
tenders published on the portal, bidders are advised to contact concerned Bid Manager of AAI
through e-portal.

(C-NIL I-NIL O-NIL)


ITB-4
General Guidelines for Bidders

Bomb Coo lin Pit DNIT (17.12. 2 019)G


NOTICE INVITING TENDER
GENERAL GUIDELINES FOR THE
BIDDERS

1. Item rate e-tenders are invited on behalf of the Airports Authority of India for the
work as mentioned at Page No.131 of GCC. The estimated cost of the work is
mentioned at Page No. 131 of GCC. This estimate, however, is given merely as
rough guide.

2. The Tenders shall be in the prescribed Form.

3. The works are required to be completed within the period as mentioned at Page No.
133 of GCC.

4. Normally contractors whose names are borne on the approved list of contractors of
MES /CPWD/State PWD /Railways /P&T /PSU/Municipal Corporations &
Development Authorities of Delhi, Mumbai, Chennai & Kolkata only OR
Specialized Agencies and within whose financial category the estimated amount
falls will be permitted to Tender. Not more than one Tender shall be submitted by
a contractor or by a firm of contractors.

No two or more concerns in which an individual is interested, as Proprietor and/or


partner shall tender for the execution of the same works. If they do so, all such
Tenders shall be liable to be rejected.

5. The Accepting Authority as mentioned at Page No.132 of GCC shall be the


Accepting Officer hereinafter, referred to as such for the purpose of this contract.
6. Tender documents consisting of plans, specifications, Schedule(s) of quantities of
the various classes of work to be done, the conditions of contract and other
necessary documents will be open for inspection in the office of the Asstt. Gen.
Manager (Engg–C)-I, O/o Airport Director, S.V. Airport, Raipur-492015,
between hours of 11.00 am & 4.00 pm every day except Saturday, Sunday and
public holidays. Tender document can be downloaded from the NIC CPP e-
procurement portal without paying any tender fees. However, to participate in
the tender, the Bidders must pay tender fee Online through SBI MOPS Gateway
using SBI/Other Banks/NEFT/RTGS mode as mentioned in ENIT.
7. Bidders are advised to inspect and examine the site and its surroundings and
satisfy themselves before submitting their Tenders as to the nature of the ground
and sub soil (so far as is practicable), the form and nature of the site, the means of
access to the site, the accommodation they may require, working conditions
including space
Bomb Coo ling Pit DNIT (17.12. 2019)G

GGB - 1
for stacking of materials, installation of T&P, rates of various materials to be
incorporated in works, conditions affecting accommodation and movement of
labours etc. and in general shall themselves obtain all necessary information as to
risks, contingencies and other circumstances which may influence or affect their
Tender. A bidders shall be deemed to have full knowledge of the site whether he
inspects it or not and no extra charges consequent on any misunderstanding or
otherwise shall be allowed.

8. Submission of a Tender by a Tenderer implies that he has read this notice and all
other contract documents and has made himself aware of the scope and
specifications of the works to be done and of conditions and rates at which stores,
tools and plant, etc. will be issued to him by Airports Authority of India, local
conditions, local material rates and other factors bearing on the execution of the
works.

9. All rates shall be quoted in the NIC CPP e-tendering portal.

10. In the case of item rate Tenders only rates quoted shall be considered. Any Tender
containing percentage below/above the rates quoted is liable to be rejected.

11. Tenders shall be received through NIC CPP e-tender portal upto the date and time
as mentioned at Page no 2 of ENIT and shall be opened on the date and time as
mentioned at Page no 2 of ENIT

12. EARNEST MONEY


Earnest Money of amount as mentioned in ENIT and at Page No. 131 of GCC
shall be accepted Online through SBI MOPS Gateway using SBI/Other
Banks/NEFT/RTGS mode as mentioned in ENIT.

13. Notification of Award of contract will be made in writing to the successful Bidder
by the Accepting Authority or his representative. The contract will normally be
awarded to the qualified and responsive Bidder offering lowest evaluated bid in
conformity with the requirements of the specifications and contract documents and
the Accepting Authority shall be the sole judge in this regard. The Accepting
Authority does not bind himself to accept the lowest or, any tender or to give any
reason for his decision.

13.1 A responsive bidder is one who submits priced Tender and accepts all terms and
conditions of the specifications and contract documents.

GGB - 2
13.2 A major modification is one which affects in any way the quality, quantity and
period of completion of the work or which limits in any way the responsibilities or
liabilities of the Bidder or any right of AAI, as required in the specifications and
contract documents. Any modification in the terms and conditions of the Tender
which are not acceptable to AAI shall also be treated as a major modification.

13.3 A Tenderer shall submit a responsive bid, failing which his Tender will be liable
to be rejected.

13.4 The Accepting Authority reserves to himself the right of accepting the whole or
any part of the Tender and Tenderer shall be bound to perform the same at his
quoted rates.

14. On acceptance of Tender earnest money will be treated as part of the security
deposit.

15. Airports Authority of India will return the earnest money where applicable to
every unsuccessful bidder except as provided in the Tender documents.

16. Canvassing in connection with Tenders is strictly prohibited and the Tenders
submitted by the Tenderers who resort to canvassing will be liable to rejection.

17. The Tender for works shall remain open for acceptance for a period of Ninety
days from the date of opening of financial bid of tenders. If any Tenderer
withdraws his Tender before the said period or makes any modifications in
the terms and conditions of the Tender which are not acceptable to the AAI, then
Airports Authority of India shall without prejudice to any other right or remedy, be
at liberty to forfeit the full said earnest money absolutely.
18. On acceptance of the Tender, the name of the accredited representative(s) of the
contractor who would be responsible for taking instructions from the Engineer-in-
Charge shall be communicated to the Engineer-in-Charge.
19. A tenderer shall submit the tender which satisfies each and every condition laid
down in this notice failing which the Tender will be liable to be rejected. Also if
the credential submitted by the firm found to be incorrect or have some
discrepancy which disqualifies the firm then the AAI shall take the following
action:
a) Forfeit the entire amount of EMD submitted by the firm.
b) The agency shall be liable for debarment from tendering in AAI in any
name / style, apart from any other appropriate contractual / legal action.

GGB - 3
20. a) All tendered rates shall be inclusive of all taxes and levies payable under
respective statutes. However, pursuant to the Constitution (46th Amendment Act.
1982, if any further tax or levy is imposed by Statute, after the last stipulated date
for the receipt of tender including extensions if any and the contractor thereupon
necessarily and properly pays such taxes / levies, the contractor shall be
reimbursed the amount so paid, provided such payments, if any, is not, in the
opinion of the Engineer-In-Charge (whose decision shall be final and binding on
the contractor) attributable to delay in execution of work within the control of the
contractor.

b) In case of change in rate of Tax or any provision relating to levy of Tax after
the last stipulated date for the receipt of tender including extensions if any
resulting in increase in burden of Tax on the contractor, the contractor shall be
entitled to receive any compensation for such increase in quantum of Tax payable
by the contractor. Similarly, recovery shall be made from the contractor on
account of decrease of rate of Tax or any provision relating to levy of Tax.
c) The contractor shall keep necessary books of accounts and other documents for
the purpose of this condition as may be necessary and shall allow inspection of the
same by a duly authorized representative of Airports Authority of India and / or
Engineer-In-Charge and further shall furnish such other information/document as
the Engineer-In-Charge may require from time to time.
d) The contractor shall, within a period of 30 days of the imposition of any such
further tax or levy, pursuant to the Constitution (46th amendment) Act 1982, give
a written notice thereof to the Engineer-In-Charge that the same is given pursuant
to this condition, together with all necessary information relating thereto.
21. The Tender for composite works includes in addition to building work all other
works such as sanitary and water supply installations, electrical work, horticulture
work, roads and paths etc. The Tenderer apart from being a registered contractor
of appropriate class, must associates himself with agencies of appropriate class
which are eligible to tender for sanitary and water supply installations, electrical
work, horticulture work, roads and paths etc in a composite Tender.
22. The site for the work may be made available in parts as decided by Engineer- in-
charge.
23. MODE OF SUBMISSION OF TENDERS:
23.1 Following 2 covers shall be submitted through online at e-portal by the
bidder.
Last date and time of submission of bids (Cover I & II) is 29.06.2022 up to 18:00
hours.
Cover-I (a) Containing scanned copies of tender fee, EMD and Unconditional
Acceptance of AAI’s Tender Conditions shall be opened on 01.07.2022 at 11:00
hours. The intimation regarding eligible / non-eligible for participation in the
tendering will be intimated to the contractors / firms through e- tendering portal.

GGB - 4
(b) Containing qualifying requirements of Contractors/ firms:- Date of opening
of cover-I shall be opened on 01.07.2022 at 1100 hours.
If any clarification is needed from the bidder about the deficiency in his uploaded
documents in Cover-I, he will be asked to provide it through “Shortfall of
Documents” option in NIC CPP e-tendering portal. The bidder shall upload the
requisite clarification/documents within time specified by AAI, failing which
tender will be liable for rejection.
Cover-II Financial e- Bid through e-portal.
The financial bids of the contractors / firms found to be meeting the qualifying
requirements, fulfilling criteria of technical bid shall only be opened and date of
opening of cover-II shall be opened on 11.07.2022 at 1500 hours.
23.2 Rates to be quoted in the “Item” Section only.
23.3 Once the contractor has uploaded the digitally signed file of tender document along
with unconditional acceptance as an attachment, he is not permitted to upload any
additional file or put any remark(s)/ conditions(s) in / along with the Tender
Document (Except unconditional rebate on quoted rates. Unconditional rebate
i.e. header discount (%) if any is to be put in “Bid Invitation Information Price
component” Section only.
23.4 In case, the condition 23.1 to 23.3 above is found violated, the tender shall be
rejected.
24. Queries, Replies and Clarifications:
If the bidder has any query related to the Tender Document of the work they
should use ‘Query/ Reply’ tab in e-tendering portal to seek clarifications. No other
means of communication in this regards shall be entertained.
25. This notice of Tender shall form part of the contract documents. The successful
Tenderer/contractor, on acceptance of his Tender by the Accepting Authority,
shall within 15-days from the date of award of work sign the contract consisting of
Notice inviting Tenders, General conditions of contract, special/additional
condition, General and particular specifications, Tender conditions as issued at the
time of invitation of Tender and acceptance thereof with any correspondence
leading thereto.

26. PURCHASE PREFERENCE TO PUBLIC ENTERPRISES


The Accepting Authority reserves to him the right to allow to the public
enterprises purchase preference facilities as admissible under the existing policy
on the date of acceptance of tender.

GGB - 5
27. Implementation of Integrity Pact

27.1 Signing of Integrity Pact is mandatory for every bidder participating in this tender
and the contract who is awarded the work. The Pact signed on each page by the
person authorized by the bidder / sub – contractor / associate to sign the bid for
submission or the person authorized to sign the contract on behalf of successful
bidder. The scanned copy of the same shall be uploaded by the bidder (along with
unconditional acceptance as per Annexure-1 of tender document in “Technical Bid
/Attachments section of e- tendering portal) in Cover – I shall be enclosed with the
agreement by the contractor.

27.2 All sub – contractors / associates whose contribution in the project is Rs. 0.50
Crores (Rupees Fifty Lacs) or above shall sign Integrity Pact with the Authority
after the work is awarded to the successful bidder. All bidders shall inform their
sub – Contractors / associates accordingly.
27.3 The External Independent Monitor (EIM) for this work shall be Shri M.P. Juneja
& Dr. Anup K. Pujari. All correspondences to them regarding implementation of
Integrity Pact Shall be addressed to:

Sh.M.P.Juneja, Dr. Anup K.Pujari,


juneja@ ah
:09811733362.

GGB - 6
GENERAL CONDITIONS OF CONTRACT

2017

AIRPORTS AUTHORITY OF INDIA


AIRPORTS AUTHORITY OFINDIA

AIRPORTS AUTHORITY OF INDIA

INDEX

Sl. No. Details of Pages Page


No.
1. General Guidelines 2

2. Tender forms 3

i) General Rules and Directions. 5

ii) Conditions of contract 12

iii) Clauses of contract 15

iv) AAI Safety code 78

v) Model Rules 83

vi) AAI contractor's labour Regulations 88

vii) Various Formats to be maintained (Appendix I to XX) 93

viii) Sketch of Cement Godown 129

3. Proforma of Schedules A to F 130

A.A.I. C-NIL I-NIL O-NIL Page 1


General Guidelines AIRPORTS AUTHORITY OFINDIA

GENERAL GUIDELINES

1. This book of “General Conditions of Contract” is applicable to both


types of tenders i. e.” Percentage rate tenders and Item rate tenders”.
Accordingly, alternative provisions for conditions Nos. 4, 10 & 12 of
the General Rules and Directions are given in this book. The
appropriate alternatives will be applicable in specific cases
depending on whether this is used for percentage rate tenders or item
rate tenders

2. Notice Inviting Tender, Schedules A to F, special


conditions/specifications and drawings only will be issued to
intending bidders. The standard form will not be issued along with
the Tender Documents but the same shall form part of the agreement
to be drawn and signed by both parties after acceptance oftender.

3. All blanks are confined to Notice Inviting Tender and Schedules A


to F.

4. Authority approving the Notice Inviting Tenders (NIT) shall fill up


all the blanks in Notice Inviting Tender and in Schedules B to F
before issue of Tender documents.

5. The intending bidders will quote their rates in Schedule A.

6. The proforma for registers and Schedules A to F are only for


information and guidance. These are not to be filled in the Standard
Form. The Schedules with all blanks, duly filled, shall be separately
issued to all intending tenderers.

A.A.I. C-NIL I-NIL O-NIL Page 2


Tender forms AIRPORTS AUTHORITY OFINDIA

AIRPORTS AUTHORITY OF INDIA

Percentage Rate Tender/Item Rate Tender & Contract for Work


Airport : Raipur

Branch: Engineering Office of: AGM (Engg. (Civil)-I, S.V. Airport, Raipur

(A) Tender for the work of “Levelling and grading of area at 24 & 06 side in newly acquired land at S.V.
Airport, Raipur.

(i) To be submitted/uploaded up to (As per PNIT – 2) hours on in NIC CPP Portal.


(ii) To be opened in presence of tenders who may be present on at
hrs. in the office of

Issued to ------------------------------------------------------------------------------------------- *
Signature of officer issuing documents ----------------------------------------------------- *
Designation ---------------------------------------------------------------------------------- *
Date of issue --------------------------------------------------------------------------------- *

*(ii) Not applicable for e-tendering

TENDER

I/We have read and examined the notice inviting tender, schedule, A, B, C, D, E & F, Specifications
applicable, Drawings & Designs, General Rules and Directions, Conditions of Contract, Clauses of contract,
Special conditions, Schedule of Rates & other documents and Rules referred to in the conditions of contract
and all other contents in the tender document for the work.

I / We hereby tender for the execution of the work specified for the Chairman Airports Authority of India
within the time specified in Schedule 'F', viz., schedule of quantities and in accordance in all respects with the
referred to in Rule-1 of General Rules and Directions and in Clause 11 of the Conditions of contract and with
such material as are provided for, by and in respects in accordance with, such conditions so far as applicable.

We agree to keep the tender open for Ninety (90) days from the date of opening of financial bid in 3/2 bid
system and not to make any modifications in its terms and conditions.

I / We undertake and confirm that for eligibility of similar work(s) has / have not been got executed on back to
back basis through another contractor. Further that, if such a violation comes to the notice of AAI, then I/We
shall accept the decision of AAI if we are debarred for tendering in AAI in future works. Also, if such a
violation comes to the notice of AAI before date of start of work, the Engineer- in-Charge shall be free to
forfeit the entire amount of Earnest Money Deposit / Performance Guarantee.

I / We further undertake and confirm that information/ documents submitted by us are genuine, and if at any
stage such documents/ information found false, then we shall be liable for debarment from tendering in AAI,
and any other appropriate legal action.

A.A.I. C-NIL I-NIL O-NIL Page 3


Tender forms AIRPORTS AUTHORITY OFINDIA

A sum of Rs. 6,10,706/- Rupees Six Lakhs Ten Thousand Seven Hundred Six Only is to be paid Online
through SBI MOPS Gateway using SBI/Other Banks/NEFT/RTGS mode. If I/we, fail to furnish the prescribed
performance bank guarantee within prescribed period, I/we agree that the said Chairman, A.A.I. or his
successors in office shall without prejudice to any other right or remedy, be at liberty to take appropriate action
as per terms of contract. Further, if I/ we fail to commence work as specified, I/we agree that Chairman, A.A.I.
or his successors in office shall without prejudice to any other right or remedy available in law, be at liberty to
forfeit the said earnest money absolutely, otherwise the said earnest money shall be retained by AAI towards
security deposit to execute all the works referred to in the tender documents upon the terms and conditions
contained or referred to therein and to carry out such deviations as may be ordered, upto maximum of the
percentage mentioned in Schedule 'F' and those in excess of that limit at the rates to be determined in
accordance with the provision contained in Clause 12.2 and 12.3 of the tender form. Further, I/We agree that
in case of forfeiture of earnest money or Performance Guarantee or both Earnest Money & Performance
Guarantee as aforesaid, I/We shall be debarred for participation in the re-tendering process of the work.

I / We hereby declare that I/we shall treat the tender documents drawings and other records connected with the
work as secret/confidential documents and shall not communicate information/derived there from to any
person other than a person to whom I/we am/are authorized to communicate the same or use the information in
any manner prejudicial to the safety of the State.
(* To be deleted which are not applicable)

Date: Signatures of Contractor:

Witness: Postal Address

Occupation:
ACCEPTANCE

The above tender (as modified by you as provided in the letters mentioned hereunder) is accepted by
competent authority on behalf of the Chairman, Airports Authority of India for sum of Rs. _________(Rupees
_______________________________________________________________________________________).

The letters referred to below shall form part of this contract Agreement: -

(i)
(ii)
(iii)(iii)
For & on behalf of Chairman, Airports
Authority of India
Signature----------------------

Designation--------------------
Date-----------------------------

A.A.I. C-NIL I-NIL O-NIL Page 4


General Rules & Directions AIRPORTS AUTHORITY OFINDIA

AIRPORTS AUTHORITY OF INDIA

General Rules & Directions

1. General All work proposed for execution by contract are notified in a form of invitation to
Rules tender pasted in public places /NIC CPP Portal and signed by the officer inviting
& Directions tender or by publication in Newspapers and posted on AAI web-site and NIC
CPP Portal http://etenders.gov.in and www.aai.aero (for reference only).

This form will state the work to be carried out, as well as the date for submitting
and opening tenders and the time allowed for carrying out the work, also the
amount of earnest money to be deposited with the tender, and the amount of the
security deposit and Performance guarantee to be deposited by the successful
tenderer and the percentage, if any, to be deducted from bills. Copies of the
specifications, designs and drawings and any other documents required in
connection with the work signed for the purpose of identification by the officer
inviting tender shall also be open for inspection by the contractor at the office of
Officer inviting tender during office hours
2. In the event of the e-tender being submitted by a firm, it must be digitally signed.
Such tender will be treated as signed tender. For physical tender it must be signed
separately by each partner thereof or in the event of the absence of any partner, it
must be signed on his behalf by a person holding a power-of-attorney authorizing
him to do so, such power of attorney to be produced with the tender, and it must
disclose that the firm is duly registered under the Indian Partnership Act, 1952.
2. (A) In case of the tender submitted by a Joint Venture / Consortium, a copy of joint
venture / consortium agreement in the specified proforma defining the lead
partner should be submitted. The lead partner shall sign all the documents in
respect of the works. The documents signed by any other person or firm other
than the lead partner shall not be entertained.
3. Receipts for payment made on account of work, when executed by a firm, must
also be signed by all the partners, except where contractors are described in their
tender as a firm, in which case the receipts must be signed in the name of the firm
by one of the partners, or by some other person having due authority to give
effectual receipts for the firm. Bank details shall be furnished by the firm through
an application duly signed by all partners for payment to the firm through bank
transfer.
4. Applicable Any person who submits a tender shall fill up the usual printed form, stating at
for item what rate he is willing to undertake each item of the work. Tenderers, which
Rate Tender propose any alteration in the work specified in the said form of invitation to
only. tender, or in the time allowed for carrying out the work, or which contain any
other conditions of any sort, including conditional rebates, will be summarily
rejected. No single tender shall include more than one work, but contractors who
wish to tender for two or more works shall submit separate tender for each.
Tender shall have the name and number of the works to which they refer, written
on the envelopes.
The rate(s) must be quoted in decimal coinage. Amount must be quoted in full
Rupees by ignoring 50 paise and considering more than 50 paise as Rupee one.
In case the lowest tendered amount (worked out on the basis of quoted rate of
Individual items) of two or more contractors is same, then such lowest contractors
will be asked to submit revised offer quoting rate of each item of the schedule of
quantity for all sub sections/sub heads as the case may be, but the revised quoted
rate of each item of schedule of quantity for all sub sections/subheads should not
be higher than their respective original rate quoted already at the time of
submission of tender. The lowest tender shall be decided on the basis of revised
offer.

A.A.I. C-NIL I-NIL O-NIL Page 5


General Rules & Directions AIRPORTS AUTHORITY OFINDIA

revised offer.
If the revised tendered amount (worked out on the basis of quoted rate of
individual items) of two or more contractors received in revised offer is again
found to be equal, then the lowest tender, among such contractors, shall be
decided by draw of lots in the presence of Jt. GM (Engg) / DGM (Engg) / AGM
(Engg) / Sr. Manager (Engg) in-Charge of major and minor component(s) work
and the lowest contractors those have quoted equal amount of their tenders.
In case of any such lowest contractor in his revised offer quotes rate of any item
more than their respective original rate quoted earlier at the time of submission of
tender, then such revised offer shall be treated invalid. Such case of revised offer
of the lowest contractor or case of refusal to submit revised offer by the lowest
contractor shall be treated as withdrawal of his tender before acceptance and 50%
of his earnest money shall be forfeited.
In case all the lowest contractors those have same tendered amount (as a result of
their quoted rate of individual items), refuse to submit revised offers, then tenders
are to be recalled after forfeiting 50% of EMD of each lowest contractors.
Contractor, whose earnest money is forfeited because of non-submission of
revised offer, or quoting higher revised rate(s) of any item(s) than their respective
original rate quoted already at the time of submission of his bid shall not be
allowed to participate in the retendering process of the work.
Note: Till the time software supports the above provisions, revised offers from
tenderers forming the tie shall be obtained and procedure prescribed for
“Restricted call of tenders” shall be adopted (for e-tenders).
4. (A) Applicable In case of Percentage Rate Tenders, tenderer shall fill up the usual printed form,
for stating at what percentage below/above (in figures as well as in words) the total
Percentage estimated cost given in Schedule of Quantities at Schedule-A, he will be willing
Rate Tender to execute the work. The tender submitted shall be treated as invalid if;
only. 1. The contractor dose not quote percentage above/below on the total amount of
tender or any section/sub-head of the tender.
2. The percentage above / below is not quoted in figures & words both on the
total amount of tender or any section / sub-head of the tender.
3. The percentage quoted above/below is different in figures and words on the
total amount of tender or any section / sub-head of the tender.
Tenders, which propose any alteration in the work specified in the said form of
invitation to tender, or in the time allowed for carrying out the work, or which
contain any other conditions of any sort including conditional rebates, will be
summarily rejected.
No single tender shall include more than one work, but contractors who wish to
tender for two or more works shall submit separate tender for each. Tender shall
have the name and number of the works to which they refer, written on the
envelopes.
In case the lowest tendered amount (estimated cost + amount worked on the basis
of percentage above/below) of two or more bidders is same, such lowest bidders
will be asked to submit revised offer in the form of letter mentioning percentage
above/ below on estimated cost of tender including all sub sections/sub heads as
the case may be, but the revised percentage quoted above / below on tendered
cost or on each sub section/ sub head should not be higher than the percentage
quoted at the time of submission of tender. The lowest tender shall be decided on
the basis of revised offers. In case any of such contractor refuses to submit
revised offer, then it shall be treated as withdrawal of his tender before
acceptance and 50% of earnest money shall be forfeited.
If the revised tendered amount of two more bidders received in revised offer is
again found to be equal, the lowest tender, among such bidders, shall be decided
by draw of lots in the presence of Jt. GM (Engg) / DGM (Engg) / AGM (Engg) /

A.A.I. C-NIL I-NIL O-NIL Page 6


General Rules & Directions AIRPORTS AUTHORITY OFINDIA

Sr. Manager (Engg) in-Charge of work & the lowest bidders those who have
quoted equal amount of their tenders. In case all the lowest bidders those have
quoted same tendered amount, refuse to submit revised offers, then tenders are to
be recalled after forfeiting 50% of EMD of each bidder.
Bidders, whose earnest money is forfeited because of non-submission of revised
offer, shall not be allowed to participate in the re-tendering process of the work.
Note: Till the time software supports the above provisions, revised offers
from tenderers forming the tie shall be obtained and procedure
prescribed for “Restricted call of tenders” shall be adopted.
4. (B) In case the lowest tendered amount (estimated cost + amount worked on the basis
of percentage above/below) of two or more contractor is same, such lowest
contractor will be asked to submit sealed revised offer in the form of letter
mentioning percentage above/below on estimated cost of tender including all sub
section/sub heads as the case may be, but the revised percentage quoted
above/below on tendered cost or on each sub section /sub head should not be
higher than the percentage quoted at the time or submission of tender. The lowest
tender shall be decided on the basis of revised offers.
In case any of such contractor refuses to submit revised offer, then it shall be
treated as withdrawal of his tender before acceptance and 50% of earnest money
shall be forfeited.
If the revised tendered amount of two more contractors received in revised offers
is again found to be equal, the lowest tender, among such contractor, shall be
decided by draw of lots in the presence of Jt.GM (Engg) / DGM (Engg), AGM
(Engg) / Sr. Manager (Engg) in -Charge of major & minor component(s) of work
& the lowest bidders those who have quoted same tendered amount of their
tenders.
In case all the lowest contractors those have quoted same tendered amount, refuse
to submit revised offers, then tenders are to be recalled after forfeiting 50% of
EMD of each bidder.
Bidders, whose earnest money is forfeited because of non- submission of revised
offer, shall not be allowed to participate in the re-tendering process of the work.
5. The officer inviting tender or his duly authorized representative, will open tenders
in the presence of any intending bidders who may be present at the time, and will
enter the amounts of the several tenders in a comparative statement in a suitable
form. In the event of a tender being accepted, a receipt for the earnest money
shall thereupon be given to the contractor who shall thereupon for the purpose of
identification sign copies of the specifications and other documents mentioned in
Rule – I.
In the event of a tender being rejected, the earnest money shall thereupon be
returned to the contractor remitting the same, without any interest.
6. The officer inviting tenders shall have the right of rejecting all or any of the
tenders and will not be bound to accept the lowest or any other tender.
7. The receipt of an accountant or clerk for any money paid by the bidder towards
tender fee will not be considered as any acknowledgement or payment to the
officer inviting tender and the bidder shall be responsible for seeing that he
procures a receipt signed by the officer inviting tender or a duly authorised
cashier.
8. The memorandum of work tendered for and the schedule of materials to be
supplied by the department and their issue-rates, shall be filled and completed in
the office of the officer inviting tender before the tender form is issued. If a form
is issued to an intending bidder without having been so filled in and incomplete,
he shall request the officer to have this done before he completes and delivers his
tender.

A.A.I. C-NIL I-NIL O-NIL Page 7


General Rules & Directions AIRPORTS AUTHORITY OFINDIA

9. The bidders shall sign a declaration under the officials Secret Act 1923, for
maintaining secrecy of the tender documents drawings or other records connected
with the work given to them. The unsuccessful bidders shall return all the
drawings given to them.
9(A). Use of correcting fluid anywhere in tender document is not permitted. Such
tender is liable for rejection. If there is any correction it should be cut with a
straight line and should be initialed and cello tape to be provided on all the rates
quoted in case of physical tenders.
10. Applicable In the case of Item Rate Tenders, only rates quoted shall be considered. Any
for Item tender containing percentage below / above the rates quoted is liable to be
Rate Tender rejected. Rates quoted by the bidder in item rate tender in figures and words shall
Only. be accurately filled in so that there is no discrepancy in the rates written in figures
and words. However,
i. If a discrepancy is found between rates in figures and in words, then the
rates which correspond with the amount worked out by the bidder shall
unless otherwise proved be taken as correct.
ii. If the amount of an item is not worked out by the bidder or it does not
correspond with the rates written either in figures or in words, then the
rates quoted by the contractor in words shall be taken as correct.
iii. Where the rates quoted by the bidder in figures and in words tally, but the
amount is not worked out correctly, the rates quoted by the contractor will
unless otherwise proved be taken as correct and not the amount.
iv. In event no rate has been quoted for any item(s) leaving space blank both
in figure(s) and word(s) or cancelled the quoted rate in figure(s), and
word(s) but the amount corresponding to the item(s) is worked out by the
bidder and added to the grand total, then rate(s) of the items(s) shall be
derived from the amount(s) quoted by the contractor against such item(s).
v. In event no rate has been quoted for any item(s), leaving space both in
figure(s), word(s), and amount blank, it will be presumed that the bidder
has included the cost of this/these item(s) in other items and rate for such
item(s) will be considered as zero and work will be required to be executed
accordingly.
vi. Sub Para i to iv above shall not be applicable in case of e-tendering.
Applicable In case of percentage Rate Tenders only percentage quoted shall be considered.
for Any tender containing item rates is liable to be rejected Percentage quoted by the
percentage bidder in percentage rate tender shall be accurately filled in figures and words, so
rate tender that there is no discrepancy.
only. However, if the bidder has worked out the amount of the tender and if any
discrepancy is found in the percentage quoted in words and figures,
i. The percentage which corresponds with the amount worked out by the
bidder shall, unless otherwise proved, be taken as correct.
ii. If the amount of the tender is not worked out by the bidder or it does not
correspond with the percentage written either in figures or in words, then
the percentage quoted by the bidder in words shall be taken as correct.
iii. Where the percentage quoted by the bidder in figures and in words tally but
iv. the amount is not worked out correctly, the percentage quoted by the bidder
will, unless otherwise proved, be taken as correct and not the amount.
11. In the case of any tender where unit rate of any item / items appear unrealistic,
such tender will be considered as unbalanced and in case the tenderer is unable to
provide satisfactory explanation, such a tender is liable to be disqualified and
rejected.

A.A.I. C-NIL I-NIL O-NIL Page 8


General Rules & Directions AIRPORTS AUTHORITY OFINDIA

12. Applicable All rates shall be quoted on the tender form. The amount for each item should be
for Item worked out and requisite totals given. Special care should be taken to write the
Rate Tender rates in figures as well as in words and the amount in figures only, in such a way
only. that interpolation is not possible. The total amount should be written both in
figures and in words. In case of figures, the word ‘Rs’ should be written before
the figure of rupees and word ‘P’ after the decimal figures, e.g. ‘Rs. 2.15 P’ and
in case of words, the word ‘Rupees’ should precede and the word ‘Paise’ should
be written at the end. Unless the rate is in whole rupees and followed by the word
‘only’ it should invariably be upto two decimal places. While quoting the rate in
schedule of quantities, the word ‘only’ should be written closely following the
amount and it should not be written in the next line.
12(A). Applicable In Percentage Rate Tender, the tenderer shall quote percentage below / above (in
for figures as well as in words) at which he will be willing to execute the work. He
percentage shall also work out the total amount of his offer and the same should be written in
rate tender figures as well as in words in such a way that no interpolation is possible. In case
only. of figures, the word ‘Rs’ should be written before the figure of rupees and work
‘P’ after the decimal figures, e.g. ‘Rs. 2.15 P’ and in case of words, the word
‘Rupees’ should precede and the word ‘Paise’ should be written at the end.
(quoting of rates in Paise is not applicable in e-tenders)
13 Acceptance of Wherever the price of the lowest bidder is lower than the justified cost by more
abnormally than 25%, lowest bid can be termed as Abnormally Low Quoted Bid (ALQB).
low quoted bid Processing of such bid shall be as follows:
(Capital i) The bid processing Manager shall seek from lowest bidder, a Bank
& Revenue Guarantee amounting to 10% of the difference between 75% of the justified
Expenditure cost and the cost quoted by the bidder. This bank guarantee shall be termed
Contract) as Quality Protection Bank Guarantee (QPBG) and shall be over and above
the normal bank guarantee and shall be valid up to the completion of the
work.
ii) The lowest bidder has to submit the QPBG within 10 days of issue of letter
from Bid Manager.
iii) On receipt of QPBG from the lowest bidder, the bid processing Manager
shall submit the case to the officer competent to accept the tender as per
delegation of powers.
iv) In case of Percentage Rate Tenders, QPBG shall be asked for 10% of the
difference between 75% of the justified cost and the corresponding cost
worked out on the basis of percentage quoted by lowest bidder.
v) This QPBG for any tender shall be a fixed amount as one time measure and
will not vary at any stage during the currency of the work or contract.
vi) The justified cost worked out by AAI shall be final and binding on the
contractor.
vii) In case of labour intensive ALQB like MESS, Annual Maintenance Contract
for supply of labourers, Operation & Maintenance Contract and other similar
works, contractor shall transfer / deposit salary of the individual worker to
their bank account which should be linked with AADHAR and a statement
is to be submitted to AAI along with each running and final bill.
viii) In case the lowest bidder fails to submit QPBG within stipulated time, as decided by
Bid Manager or contractor does not transfer / deposit salary of the individual worker
to his / her bank account which should be linked with AADHAR and do not submit
statement to AAI as the case may be the tender shall be rejected / foreclosed and
EMD / SD collected till date shall be forfeited.
ix) In case of non-execution / completion of the work, QPBG and EMD /SD
collected till date shall be forfeited.

A.A.I. C-NIL I-NIL O-NIL Page 9


General Rules & Directions AIRPORTS AUTHORITY OFINDIA

13A In case the contractor does not carry out the work on ALQ items as per schedule
or as per NIT specifications, the Engineer-in-charge shall issue a letter to the
contractor to comply its obligations as per NIT, for ALQ items. Engineer-in-
charge shall also give one reminder after 10 days of 1st letter and if contractor
still do not start the work on ALQ items, then bank guarantee i.e. QPBG should
be encashed and work should be got executed through another agency at his risk
and cost.
14 i. The bidder, whose tender is accepted, will be required to furnish performance
guarantee of 5% (Five Percent) of the tendered amount within the period
specified in Schedule F. This guarantee shall be in the form of Fixed Deposit
Receipts or Guarantee Bonds of any Scheduled Bank but not co-operative or
Gramin Bank, in accordance with the prescribed form, provided confirmatory
advice is enclosed.

ii. The bidder, whose tender is accepted, will also be required to furnish by way
of Security Deposit for the fulfillment of his contract, an amount equal to 5%
of the contract amount of the work.

iii. In works where condition of submission of Performance Guarantee is not


applicable, the security deposit @ 10% of the tendered value shall be
deducted.

iv. The Security deposit (under ii & iii above) will be collected by deductions
from the running bills of the contractor at the rates mentioned above and the
earnest money deposited at the time of tenders, will be treated as a part of the
Security Deposit.

v. Security deposit will also be accepted in form of Fixed Deposit Receipts /


Guarantee Bonds of any Scheduled Bank but not co-operative or Gramin Bank
in accordance with the prescribed form, provided confirmatory advice is
enclosed.
15. On acceptance of the tender, the name of the accredited representative(s) of the
contractor who would be responsible for taking instructions from the Engineer-in-
Charge shall be communicated in writing to the Engineer-in-Charge.

16. 1. Rates to be quoted by the parties should be inclusive of all taxes, duties,
CESS, fee, royalty charges etc. levied under any statute but exclusive of
GST for all the items.

2. However GST, as applicable, shall be paid to the contractor, for any taxable
supply / services / construction rendered by the agency to AAI, against a
valid GST invoice as per terms and conditions of the contract.

3. In case supplies /services / works involve imports; the same should be


identified separately. Basic Custom Duty & IGST will be paid directly by
AAI by utilizing EPCG license / Duty Credit Scrip under service Export
from India Scheme (SEIS) of Govt. of India.
17. The contractor/ bidder shall give a list of AAI employees related to him.

A.A.I. C-NIL I-NIL O-NIL Page 10


General Rules & Directions AIRPORTS AUTHORITY OFINDIA

18. The tender for the work shall not be witnessed by a contractor or contractors /
bidders who himself / themselves has / have tendered or who may and has / have
tendered for the same work. Failure to observe this condition would render,
tenders of the contractors tendering, as well as witnessing the tender, liable to
summary rejection.
19. The tender for composite work includes, in addition to building work, all other
works such as sanitary and water supply installations drainage installation,
electrical work, horticulture work, roads and paths etc. The tenderer apart from
being a registered contractor (B&R) of appropriate class, must associate himself
with agencies of appropriate class which are eligible to tender for sanitary and
water supply drainage, electrical and horticulture works in the composite tender.
20. The contractor/ bidder shall submit list of works completed in last 5 years*as well
as which are in hand (in progress) in the following format for assessing bidding
capacity of the bidders:-

Name of Name and particulars Value of work Position of Remarks


work of Office where work is works in
being executed progress
1 2 3 4 5

21 The contractor/bidder shall comply with the provisions of the Apprentices Act
1961, and the rules and orders issued there under from time to time. If he fails to
do so, his failure will be a breach of the contract and the Executive Director
(Engg.)may in his discretion, without prejudice to any other right or remedy
available in law, cancel the contract. The contractor shall also be liable for any
pecuniary liability arising on account of any violation by him of the provisions of
the said Act.
22 If complete site is available for work, the work shall be completed in the manner
specified here in special condition of contract and NIT specifications.

Note: In such case para 23 below may be deleted by NIT approving authority
23 If complete site is not available for taking up the work, the same shall be made
available in phases. The scope of work covered in each phase, time for
completion of work in each phase and methodology of taking over completed
work in phased manner has been specified under special conditions of contract.
The completion time for each phase shall be applicable as indicated in tender
documents. The work shall also be taken over by Engineer-In-Charge in phases.
The warranty for the works executed in each phase shall be applied independently
w.e.f. date of completion /taking over of individual phase.

Note: In such case para 22 above may be deleted by NIT approving authority

A.A.I. C-NIL I-NIL O-NIL Page 11


Conditions of Contract AIRPORTS AUTHORITY OFINDIA

CONDITIONS OF CONTRACT
Definitions:
1 The contract means the documents forming the tender and acceptance thereof and
the formal agreement / agreements executed between the competent authority(s) on
behalf of the Chairman, Airports Authority of India and the Contractor, together
with the documents referred to therein including these conditions, the specifications,
designs, drawings and instructions issued from time to time by the Engineer-in-
Charge and all these documents taken together, shall be deemed to form one
contract / two contracts and shall be complimentary to one another. Contractor has
to sign two agreements, one consisting BOQ for Civil works and another one for
SITC and O&M /AMC / AICMC part. Engineer-in charge could be common for
both the agreements. Separate invoices for the civil /construction works and SITC /
O&M / AICMC / AMC works have to be raised by the agency referring to the
respective agreements to facilitate AAI to claim input tax credit on such SITC /
O&M / AICMC / AMC works as mentioned in Schedule 'F' para 2(v).
2. In the contract, the following expressions shall, unless the context otherwise
requires, have the meanings, hereby respectively assigned to them :-
i. The expression works or work shall, unless there be something either in the
subject or context repugnant to such construction, be construed and taken to mean
the works by or by virtue of the contract contracted to be executed whether
temporary or permanent, and whether original, altered, substituted or additional.
ii. The site shall mean the land / or other places on, into or through which work is to
be executed under the contract or any adjacent land, path or street through which
work is to be executed under the contract or any adjacent land, path or street
which may be allotted or used for the purpose of carrying out the contract.
iii. The Contractor / tenderer / bidder shall mean the individual, firm or company
whether incorporated or not, Joint Venture / Consortium undertaking the works
and shall include the legal personal representative of such individual or the
persons constituting such firm or company, or the successors of such firm or
company and the permitted assignees of such individual, firm or company.
iv. The Chairman means the Chairman Airports Authority of India and his
Successors.
v. The Engineer-in-Charge means the Engineering Officer who shall supervise and
be incharge of the work and who shall sign the contract on behalf of the
Chairman, Airports Authority of India as mentioned in Schedule ‘F’ hereunder.
vi. AAI or Airports Authority of India shall mean the Chairman Airports Authority
of India.
vii. The terms Member (Planning) means the head of Department of
Engineering, Airports Authority of India.
viii. Accepting Authority shall mean the authority mentioned in Schedule ‘F’.
ix. Excepted Risk are risks due to riots (other than those on account of contractor’s
employees), war (whether declared or not) invasion, act of foreign enemies,
hostilities, civil war, rebellion revolution, insurrection, terrorism, military or
usurped power, any acts of Airports Authority of India, damages from aircraft,
acts of God, such as earthquake, lightening and unprecedented floods, and other
causes over which the contractor has no control and accepted as such by the
Accepting Authority or causes solely due to use or occupation by Airports
Authority of India of the part of the works in respect of which a certificate of
completion has been issued or a cause solely due to Airports Authority of India’s
faulty design of works.
x. Market Rate shall be the rate as decided by the Engineer-in-Charge on the basis
of the prevailing cost of materials and labour at the site where the work is to be
executed plus the percentage mentioned in Schedule ‘F’ to cover, all overheads
and profits. Provided that no extra overheads and profits shall be payable on the
parts of works assigned to other agency(s) by the contractor as per terms of
contract.
A.A.I. C-NIL I-NIL O-NIL Page 12
Conditions of Contract AIRPORTS AUTHORITY OFINDIA

xi. Schedule(s) referred to in these conditions shall mean the relevant


schedule(s) annexed to the tender papers or the standard Schedule of Rates
of the government mentioned in Schedule ‘F’ hereunder, with the
amendments thereto issued upto the date of receipt of the tender.
xii. Department means Airports Authority of India, which invites tender on
behalf of Chairman, Airports Authority of India.
xiii. Tendered value means the value of the entire work as stipulated in the letter
of award.
3. Scope and Where the context so requires, words imparting the singular only also include the
Performance plural and vice versa. Any reference to masculine gender shall whenever required
include feminine gender and vice versa.
4. Headings and Marginal notes to these General Conditions of Contract shall not be
deemed to form part thereof or be taken into consideration in the interpretation or
construction thereof or of the contract.
5. The contractor shall be furnished, free of cost one certified copy of the contract
documents except standard specifications, Schedule of Rates and such other
printed and published documents, together with all drawings as may be forming
part of the tender papers. None of these documents shall be used for any purpose
other than that of this contract.
6. Works to be The work to be carried out under the Contract shall, except as otherwise provided
carried out in these conditions, include all labour, materials, tools, plants, equipment and
transport which may be required in preparation of and for and in the full and
entire execution and completion of the works. The descriptions given in the
Schedule of Quantities (Schedule – A) shall, unless otherwise stated, be held to
include wastage on materials, carriage and cartage, carrying and return of
empties, hoisting, setting, fitting and fixing in position and all other labours
necessary in and for the full and entire execution and completion of the work as
aforesaid in accordance with good practice and recognized principles.
7. Sufficiency of The Contractor shall be deemed to have satisfied himself before tendering as to
Tender the correctness and sufficiency of his tender for the works and of the rates and
prices quoted in the Schedule of Quantities, which rates and prices shall, except
as otherwise provided, cover all his obligations under the Contract and all matters
and things necessary for the proper completion and maintenance of the works.
8. Discrepancies The several documents forming the Contract are to be taken as mutually
and explanatory of one another, detailed drawings being followed in preference to
Adjustment small scale drawing and figured dimensions in preference to scale and special
of Errors conditions in preference to General Conditions.
8.1 In the case of discrepancy between the Schedule of Quantities, the Specifications
and / or the Drawings, the following order of preference shall be observed :-
i. Description of Schedule of Quantities.
ii. Particular/ technical Specification and Special Condition, if any.
iii. Drawings.
iv. C P W D Specifications.
v. Indian Standard Specifications of B I S / IRC Code of Practice / ASTM
standards.
vi. Sound Engineering practice as directed by the Engineer-in-charge, whose
decision in this regard shall final and binding on the contractor.
8.2 If there are varying or conflicting provisions made in any one document forming
part of the contract, the Accepting Authority shall be the deciding authority with
regard to the intention of the document and his decision shall be final and binding
on the contractor.
8.3 Any error in description, quantity or rate in Schedule of Quantities or any
omission therefrom shall not vitiate the Contract or release the Contractor from
the execution of the whole or any part of the works comprised therein according to
drawings and specifications or from any of his obligations under the contract.
A.A.I. C-NIL I-NIL O-NIL Page 13
Conditions of Contract AIRPORTS AUTHORITY OFINDIA

8.4 Payment for If the contractor has quoted different rates for the same item appearing in
similar items two or more subheads, then the lowest of the rates quoted shall only be
with different considered for payments during execution of work. In case of deviation of
quoted rates quantity of such item, payments shall be made at the lowest quoted rate for
in different
quantity executed upto the deviation limit specified in the contract.
subheads of
Beyond the deviation limit the rate shall be derived as per relevant contract
the contract
agreement provision.
9. Reverse AAI may opt for reverse auction in case of purchase tender if value of supplies
put to tender is more than Rs.2Cr.
Auction for
purchase
tenders
10. Signing of The successful tenderer / contractor, on acceptance of his tender by the Accepting
Contract Authority, shall, within 15 days from the stipulated date of start of the work, shall
sign either single or Two agreements , as the case may be, one consisting BOQ
for Civil works and another one for SITC and O&M / AMC / AICMC part.

i) i. The notice inviting tender, all the documents including drawings, if any,
forming the tender as issued at the time of invitation of tender and
acceptance thereof together with any correspondence leading thereto.

ii. Standard AAI Form as mentioned in Schedule ‘F’ consisting of :

a. Various standard clauses with corrections upto the date stipulated in


Schedule ‘F’ along with annexures thereto.

b. AAI Safety Code.

c. Model Rules for the protection of health, sanitary arrangements for


workers employed by AAI or its contractors.

d. AAI Contractor’s Labour Regulations.

e. List of Acts and omissions for which fines can be imposed.

iii. No payment for the work done will be made unless contract in form of
agreement is signed by the contractor.

A.A.I. C-NIL I-NIL O-NIL Page 14


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSES OF CONTRACT
CLAUSE 1

Performance This clause is applicable for the works for which the estimated cost put to tender
Guarantee is more than Rs.5 crores.
i. The contractor shall submit an irrevocable Performance Guarantee of 5% (Five
percent) of the Tendered amount in addition to other deposits mentioned
elsewhere in the contract for his proper performance of the contract
agreement, (not withstanding and/or without prejudice to any other provisions
in the contract) within period specified in Schedule ‘F’ from the date of issue
of award letter. This guarantee shall be in the form of Fixed Deposit Receipts
or Guarantee Bonds of any Scheduled bank but not Co- operative or Gramine
bank in accordance with the form annexed hereto.(Appendix-XI) In case a
fixed deposit receipts of any Bank is furnished by the contractor to the AAI as
part of the performance guarantee and the Bank is unable to make payment
against the said fixed deposit receipts or Guarantee Bonds, the loss caused
thereby shall fall on the contractor and the contractor shall forthwith on
demand furnish additional security to make good the deficit.
ii Performance guarantee should be furnished within 30 days of issue of award
letter. In case the contractor fails to deposit performance guarantee within
the stipulated period, no payment will be released to the contractor for the
work done in respect of 1st running account bill. Moreover, interest @10%
per annum on performance guarantee amount would be levied (non-
refundable) for delayed period of submission.
The Performance Guarantee shall be initially valid upto the stipulated date of
completion plus 180 days beyond that. In case the time for completion of
work gets enlarged, the contractor shall get the validity of Performance
Guarantee extended to cover such enlarged time for completion of work.
After recording of the completion certificate for the work by the competent
authority, the performance guarantee shall be returned to the contractor,
without any interest. However, in case of contracts involving maintenance of
buildings and services / any other work thereafter, 50% of Performance
Guarantee shall be retained as Security Deposit as per contract conditions.
The same shall be returned on successful completion of commitment year
wise proportionately.
iv. The Engineer-in-Charge shall not make a claim under the performance
guarantee except for amounts to which the AAI is entitled under the contract
(not withstanding and/or without prejudice to any other provisions in the
contract agreement) in the event of:
a. Failure by the contractor to extend the validity of the Performance
Guarantee as described herein above, in which event the Engineer-in-
Charge may claim the full amount of the Performance Guarantee.
b. Failure by the contractor to pay the Chairman, AAI any amount due,
either as agreed by the contractor or determined under any of the
Clauses / Conditions of the agreement, within 30 days of the service of
notice to this effect by Engineer-in-Charge.
v. In the event of the contract being determined or rescinded under provision of
any of the Clause/Condition of the agreement, the performance guarantee
shall stand forfeited in full and shall be absolutely at the disposal of the
Chairman, AAI.

A.A.I. C-NIL I-NIL O-NIL Page 15


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 1 A

Recovery of The person/persons whose tender(s) may be accepted (hereinafter called the
Security contractor) shall permit AAI at the time of making any payment to him for work
Deposit done under the contract to deduct a sum at the rate of 5% of the gross amount of
each running and final bill till the sum deducted alongwith the sum already
deposited as earnest money, will amount to security deposit of 5% of the tendered
value of the work. Earnest money shall be adjusted first in the security deposit
and further recovery of security deposit shall commence only when the update
amount of security deposit starts exceeding the earnest money. Such deductions
will be made and held by way of Security Deposit unless he/they has/have
deposited the amount of Security at the rate mentioned above in the form of fixed
deposit receipts or guarantee bonds of any Scheduled Bank but not Co-operative
or Gramin Bank. In case a fixed deposit receipts or Guarantee Bonds of any Bank
is furnished by the contractor to the AAI as part of the security deposit and the
Bank is unable to make payment against the said fixed deposit receipt or
Guarantee Bond, the loss caused thereby shall fall on the contractor and the
contractor shall forthwith on demand furnish additional security to the AAI to
make good the deficit. In works where condition of submission of performance
guarantee is not applicable, the security deposit at the rate of 10% (Ten Percent)
of gross amount of each running bill shall be deducted instead of 5%, till the sum
along with the sum already deposited as earnest money will amount to security
deposit of 10% of the contract value of work. Other conditions shall remain same
as stated above. All compensations or the other sums of money payable by the
contractor under the terms of this contract may be deducted from, or paid by the
sale of a sufficient part of his security deposit or from the interest arising
therefrom, or from any sums which may be due to or may become due to the
contractor by AAI on any account whatsoever and in the event of his Security
Deposit being reduced by reason of any such deductions or sale as aforesaid, the
contractor shall within 10 days make good in fixed deposit receipts or Guarantee
Bonds tendered by the Scheduled Banks (but not any Co-operative or Gramin
bank) (if deposited for more than 12 months) endorsed in favour of the Airports
Authority of India, any sum or sums which may have been deducted from, or
raised by sale of his security deposit or any part thereof. The security deposit
shall be collected from the running bills of the contractor at the rates mentioned
above and the Earnest money deposited at the time of tenders will be treated as
part of the Security Deposit. The security deposit as deducted above can be
released against bank guarantee issued by any Scheduled Bank (but not from Co-
operative / Gramin Bank), on its accumulations to a minimum of Rs. 5 lakh
subject to the condition that amount of such bank guarantee, except last one, shall
not be less than Rs. 5 lakh.
Note 1: Provided further that the validity of Bank Guarantee including the one
given against the earnest money shall be in conformity with provisions contained
in the clause 17 which shall be extended from time to time depending upon
extension of contract under provision of Clause 2 & Clause 5.

Note 2: Note 1 above shall be applicable for both clause 1 and 1 A.

A.A.I. C-NIL I-NIL O-NIL Page 16


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

Clause 2

Compensation If the contractor fails to maintain the required progress in terms of clause 5 or to
for Delay complete the Work and clear the site on or before the contract or justified
extended date of completion as per clause 5(excluding any extension under clause
5.5) as well as any extension granted under clause 12 and 15, he shall, without
prejudice to any other right or remedy available under the law to the AAI on
account of such breach, pay as compensation the amount calculated at the rates
stipulated below as the authority specified in schedule ‘F’ may decide on the
amount of Tendered Value of the work for every completed day/month (as
determined) that the progress remains below that specified in Clause 5 or that the
work remains incomplete. This will also apply to items or group of items for
which a separate period of completion has been specified.
i) Compensation for delay If the completion of work is delayed due to
of work reasons attributed to contractor, AAI shall be
entitled for compensation for delay as detailed
below :

i. For works costing upto Rs. 20.00 Lac:


1.0% (one percent) of tendered value per
week of delay or lesser amount as decided
by the competent authority subject to a
maximum of 10% of contract value.
ii For the works costing more than Rs20Lac
a. For the works having completion period less
than 2 years
0.5% (half percent) of tendered value per
week of delay or lesser amount as decided
by the competent authority subject to a
maximum of 10% of the tendered value.

b. For the works having completion period


more than 2 years
0.5% of tendered value per fortnight of delay
or lesser amount as decided by the
competent authority subject to a maximum
of 10% of the tendered value.

Provided always that the total amount of compensation for delay to be paid under
this condition shall not exceed 10% of the Tendered Value of work or of the
Tendered Value of the Sectional part of work as mentioned in schedule ‘F’ for
which a separate period of completion is originally given.
In case no compensation has been decided by the authority in Schedule ‘F’ during
the progress of work, this shall be no waiver of right to levy compensation by the
said authority if the work remains incomplete on final justified extended date of
completion. If the Engineer in Charge decides to give further extension of time
allowing performance of work beyond the justified extended date, the contractor
shall be liable to pay compensation for such extended period. If any variation in
amount of contract takes place during such extended period beyond justified
extended date and the contractor becomes entitled to additional time under clause
12, the net period for such variation shall be accounted for while deciding the
period for levy of compensation. However, during such further extended period
beyond the justified extended period, if any delay occurs by events under sub
clause 5.2, the contractor shall be liable to pay compensation for such delay.

A.A.I. C-NIL I-NIL O-NIL Page 17


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

Provided that compensation during the progress of work beyond the justified
extended date of completion for delay under this clause shall be for non-
achievement of sectional completion or part handing over of work on stipulated /
justified extended date for such part work or if delay affects any other works /
services. This is without prejudice to right of action by Engineer-in- Charge under
clause 3 for delay in performance and claim of compensation under that clause.
In case action under clause 2 has not been finalized and the work has been
determined under clause 3, the right of action under this clause shall remain post
determination of contract but levy of compensation shall be for days the progress
is behind the schedule on date of determination, as assessed by the authority in
schedule ‘F’, after due consideration of justified extension. The compensation for
delay, if not decided before the determination of contract, shall be decided after
of determination of contract.
The amount of compensation may be adjusted or set-off against any sum payable
to the’ Contractor under this or any other contract with AAI. In case, the
contractor does not achieve a particular milestone mentioned in schedule F, or the
re-scheduled milestone(s) in terms of Clause 5.4, the amount shown against that
milestone shall be withheld, to be adjusted against the compensation levied as
above. With-holding of this amount on failure to achieve a milestone, shall be
automatic without any notice to the contractor. However, if the contractor catches
up with the progress of work on the subsequent milestone(s), the withheld amount
shall be released. In case the contractor fails to make up for the delay in
subsequent milestone(s), amount mentioned against each milestone missed
subsequently also shall be withheld. However, no interest, whatsoever, shall be
payable on such withheld amount.

Clause2A
Incentive for In case, the contractor completes the work ahead of stipulated date of completion,
early a bonus @ 1 % (one per cent) of the tendered value per month computed on per
completion day basis, shall be payable to the contractor, subject to a maximum limit of 5%
(five per cent) of the tendered value. The amount of bonus, if payable, shall be
paid along with final bill after completion of work. Provided always that
provision of the Clause 2A shall be applicable only when so provided in
‘Schedule F’. This clause shall be applicable for the work which estimated cost
put to tender is Rs. 50.00 Cr. and above for pavement work and Rs.100.00 Cr. and
above for building work.

Clause2B
Release of Withheld amount towards compensation for delay over and above Rs. 50.00
withheld lacs, can be released against Bank Guarantee (on the format given at Appendix-
amount against 1) or in the form of fixed deposit receipts or guarantee bonds of any Scheduled
compensation Bank but not Co-operative or Gramin Bank, pending finalization of case of
for delay. extension of time by competent authority as per delegation of powers.
Concerned Executive
Director (Engg) will authorize such action on receipt of proposal from the
Engineer-In-Charge through proper channel.

Clause 3
When Contract Subject to other provisions contained in this clause, the Engineer-in-Charge may,
can be without prejudice to his any other rights or remedy against the contractor in respect
Determined of any delay, inferior workmanship, any claims for damages and / or any other
provisions of this contract or otherwise, and whether the date of completion has or
has not elapsed, by notice in writing absolutely determine the contract in any of
the following cases:
A.A.I. C-NIL I-NIL O-NIL Page 18
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

i. If the contractor having been given a notice by the Engineer-in-Charge in


writing to rectify, reconstruct or replace any defective work or that the work
is being performed in an inefficient or otherwise improper or un-workman
like manner shall omit to comply with the requirement of such notice for a
period of seven days thereafter.
ii. If the contractor has, without reasonable cause, suspended the progress of the
work or has failed to proceed with the work with due diligence and
continues to do so after a notice in writing of seven days from the Engineer-
in-Charge.
iii. If the contractor fails to complete the work or section of work with individual
date of completion on or before the stipulated or justified extended date on
or before such date of completion, and the Engineer in Charge without any
prejudice to any other right or remedy under any other provision in the
contract has given further reasonable time in a notice given in writing in that
behalf as either mutually agreed or in absence of such mutual agreement by
his own assessment making such time essence of contract and in the opinion
of Engineer in Charge, the contractor will be unable to complete the same or
does not complete the same within the period specified.
iv. If the contractor persistently neglects to carry out his obligations under the
contract and / or commits default in complying with any of the terms and
conditions of the contract and does not remedy it or take effective steps to
remedy it within 7 days after a notice in writing is given to him in that behalf
by the Engineer-in-Charge.
v. If the contractor shall offer or give or agree to give to any person in AAI
service or to any other person on his behalf any gift or consideration of any
kind as an inducement or reward for doing or forbearing to do or for having
done or forborne to do any act in relation to the obtaining or execution of
this or any other contract for AAI.
vi. If the contractor shall enter into a contract with Airports Authority of India in
connection with which commission has been paid or agreed to be paid by
him or to his knowledge, unless the particulars of any such commission and
the terms of payment thereof have been previously disclosed in writing to
the Engineer-in-charge.
vii. If the contractor shall obtain a contract with AAI as a result of wrong
tendering or other non-bonafide methods of competitive tendering or
commits any breach of Integrity Pact.
viii. If the contractor being an individual, or if a firm, any partner thereof shall at
any time be adjudged insolvent or have a receiving order or order for
administration of his estate made against him or shall take any proceedings
for liquidation or composition (other than a voluntary liquidation for the
purpose of amalgamation or reconstruction) under any Insolvency Act for
the time being in force or make any conveyance or assignment of his effects
or composition or arrangement for the benefit of his creditors or purport so
to do, or if any application be made under any Insolvency Act for the time
being in force for the sequestration of his estate or if a trust deed be executed
by him for benefit of his creditors.
ix. If the contractor being a company shall pass a resolution or the court shall
make an order that the company shall be wound up or if a receiver or a
manager on behalf of a creditor shall be appointed or if circumstances shall
arise which entitle the court or the creditor to appoint a receiver or a
manager or which entitle the court to make a winding up order.
x. If the contractor shall suffer an execution being levied on his goods and
allow it to be continued for a period of 21 days.

A.A.I. C-NIL I-NIL O-NIL Page 19


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

xi. If the contractor assigns (excluding part(s) of work assigned to other


agency(s) by the contractor as per terms of contract), transfers, sublets
(engagement of labour on a piece-work basis or of labour with materials not
to be incorporated in the work, shall not be deemed to be subletting) or
otherwise parts with or attempts to assign, transfer, sublet or otherwise parts
with the entire works or any portion thereof without the prior written
approval of the Engineer-in-Charge. When the contractor has made himself
liable for action under any of the cases aforesaid, the Engineer-in-Charge on
behalf of the Chairman, AAI shall have powers :
a. To determine the contract as aforesaid so far as performance of work by
the Contractor of work is concerned (of which determination notice in
writing to the contractor under the hand of the Engineer-in-Charge shall
be conclusive evidence). Upon such determination, the Earnest Money
Deposit, Security Deposit already recovered and Performance Guarantee
under the contract shall be liable to be forfeited and shall be absolutely
at the disposal of the AAI.
b. After giving notice to the contractor to measure up the work of the
contractor and to take such whole, or the balance or part thereof, as shall
be un-executed out of his hands and to give it to another contractor or
any other means to complete the work. The contractor, whose contract is
determined as above, shall not be allowed to participate in the tendering
process for the balance work. In the event of above courses being
adopted by the Engineer-in-Charge, the contractor shall have no claim to
compensation for any loss sustained by him by reasons of his having
purchased or procured any materials or entered into any engagements or
made any advances on account or with a view to the execution of the
work or the performance of the contract. And in case action is taken
under any of the provision aforesaid, the contractor shall not be entitled
to recover or be paid any sum for any work thereof or actually
performed under this contract unless and until the Engineer-in-Charge
has certified in writing the performance of such work and the value
payable in respect thereof and he shall only be entitled to be paid the
value so certified.

CLAUSE 3 A

In case, the work cannot be started due to reasons not within the control of the
contractor within 1/8th of the stipulated time for completion of work or one
month whichever is higher, either party may close the contract by giving notice to
the other party stating the reasons. In such eventuality, the Earnest Money
Deposit and the Performance Guarantee of the contractor shall be refunded within
30 days.
Neither party shall claim any compensation for such eventuality. This clause is
not applicable for any breach of the contract by either party.

A.A.I. C-NIL I-NIL O-NIL Page 20


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 4

Contractor In any case in which any of the powers conferred upon the Engineer-in-Charge
liable to pay by Clause-3 thereof, shall have become exercisable and the same are not
compensation exercised, the non-exercise thereof shall not constitute a waiver of any of the
even if action conditions hereof and such powers shall notwithstanding be exercisable in the
not taken under event of any future case of default by the contractor and the liability of the
Clause-3 contractor for compensation shall remain unaffected. In the event of the
Engineer-in-Charge putting in force all or any of the powers vested in him under
the preceding clause he may, if he so desires after giving a notice in writing to
the contractor, take possession of (or at the sole discretion of the Engineer-in-
Charge which shall be final and binding on the contractor) use as on hire (the
amount of the hire money being also in the final determination of the Engineer-
in-Charge) all or any tools, plant, materials and stores, in or upon the works, or
the site thereof belonging to the contractor, or procured by the contractor and
intended to be used for the execution of the work/ or any part thereof, paying or
allowing for the same in account at the contract rates, or, in the case of these not
being applicable, at current market rates to be certified by the Engineer-in-
Charge, whose certificate thereof shall be final, and binding on the contractor,
clerk of the works, foreman or other authorised agent to remove such tools,
plant, materials, or stores from the premises (within a time to be specified in
such notice) in the event of the contractor failing to comply with any such
requisition, the Engineer- in-Charge may remove them at the contractor’s
expense or sell them by auction or private sale on account of the contractor and
his risk in all respects and the certificate of the Engineer-in-Charge as to the
expenses of any such removal and the amount of the proceeds and expenses
of any such sale shall be final and
conclusive against the contractor.

CLAUSE 5

Time and The time allowed for execution of the Works as specified in the Schedule ‘F’ or
Extension for the extended time in accordance with these conditions shall be the essence of the
Delay Contract. The execution of the works shall commence from such time period as
mentioned in schedule ‘F’ or from the date of handing over of the site whichever
is later. If the Contractor commits default in commencing the execution of the
work as aforesaid, AAI shall without prejudice to any other right or remedy
available in law, be at liberty to forfeit the earnest money & performance
guarantee absolutely.
5.1 After the Contract is awarded, within 15 days, the Contractor shall submit a
Time and Progress Chart for each mile stone and get it approved by the
Engineer-in-charge. The Chart shall be prepared in direct relation to the time
stated in the Contract documents for completion of items of the works. It shall
indicate the forecast of the dates of commencement and completion of various
trades of sections of the work and may be amended as necessary by agreement
between the Engineer-in-Charge and the Contractor within the limitations of
time imposed in the contract documents, and further to ensure good progress
during the execution of the work, the contractor shall in all cases in which the
time allowed for any work, exceeds one month (save for special jobs for which a
separate programme has been agreed upon) complete the work as per mile
stones given in Schedule ‘F’.
Project Management shall be done.
a. For works costing upto Rs. 5.00 Cr. -- CPM/ PERT Chart

A.A.I. C-NIL I-NIL O-NIL Page 21


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

b. Works costing more than Rs. 5.00 Cr. -- By using Project Management
Software like Primavera /MS
Project or any other software
with the approval of
Engineer-in-charge.
c. Contractor shall submit monthly progress reports (2 copies) highlighting
status of various activities and physical completion of work.

PROGRAMME CHART

i. The Contractor shall prepare an integrated programme chart in Project


Management Software for the execution of work, showing clearly all
activities from the start of work to completion, with details of manpower,
equipment and machinery required for the fulfillment of the programme
within the stipulated period or earlier and submit the same for approval to the
Engineer-in- Charge within fifteen days of award of the contract. A recovery
of Rs. 2500/- (for works costing upto Rs. 5.00 Crores) / Rs. 5000/- (for works
costing more than Rs. 5. 00 Crores) shall be made on per day basis in case of
delay in submission of the above programme.
ii. The programme chart should include the following:
a. Descriptive note explaining sequence of the various activities.
b. Network (PERT / CPM / BARCHART).
c. Programme for procurement of materials by the contractor.

Programme for deployment of machinery / equipment’s having adequate


capacity, commensurate with the quantum of work to be done within the
stipulated period, by the contractor. In addition to above, to achieve the
progress of work as per programme, the contractor must bring at site
adequate shuttering material required for cement concrete and R.C.C. works
etc. for three floors within one month from the date of start of work till the
completion of RCC work as per requirement of work. The contractor shall
submit shuttering schedule adequate to complete structure work within laid
down physical milestone.
iii. If at any time, it appears to the Engineer-in-Charge that the actual progress of
work does not conform to the approved programme referred above or after
rescheduling of milestones, the contractor shall produce a revised
programme within 7 (seven) days, showing the modifications to the
approved programme to ensure timely completion of the work. The modified
schedule of programme shall be approved by the Engineer in Charge. A
recovery of Rs. 2500/- (for works costing upto Rs.5.00 Crores) / Rs. 5000/-
(for works costing more than Rs.5.00 Crores) shall be made on per day basis
in case of delay in submission of the modified programme.
iv. The submission for approval by the Engineer-in-Charge of such programme
or such particulars shall not relieve the contractor of any of the duties or
responsibilities under the contract. This is without prejudice to the right of
Engineer-in-Charge to take action against the contractor as per terms and
conditions of the agreement.
v. The contractor shall submit the progress report using MS Project/Primavera
software with base line programme referred above for the work done during
previous month to the Engineer-in-charge on or before 5th day of each
monthfailingwhicharecoveryRs.2500/-(forworkscostinguptoRs.5.00 Crores)
/ Rs. 5000/- (for works costing more than Rs.5.00 Crores) shall be made on
per day basis in case of delay in submission of the monthly progress report.

A.A.I. C-NIL I-NIL O-NIL Page 22


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

5.2 If the work(s) be delayed by:-


i. Force majeure, or an act of terrorism
ii. Abnormally bad weather,or
iii. Serious loss or damage by fire,or
iv. Civil commotion, local commotion of workmen, strike or lockout, affecting
any of the trades employed on the work,or
v. Delay on the part of other contractors or tradesmen engaged by Engineer-in-
Charge for executing work not forming part of the Contract, or
vi. Non-availability of stores, which are the responsibility of AAI to supply or
vii. Non-availability or break down of tools and Plant to be supplied or supplied
by AAI or
viii. Any other cause which, in the absolute discretion of the Engineer-in-Charge
is beyond the Contractor’s control.
then upon the happening of any such event causing delay, the contractor
shall immediately give notice thereof in writing to the Engineer-in-Charge
but shall never the less use constantly his best endeavors to prevent or make
good the delay and shall do all that may be reasonably required to the
satisfaction of the Engineer-in-charge to proceed with the works. The
contractor shall also sign the hindrance register at appropriate place for each
hindrance.
5.3 Request for rescheduling of Milestones and extension of time, to be eligible for
consideration, shall be made by the contractor in writing within fourteen days of
the happening of the event causing delay on the prescribed form to the authority
indicated in schedule ‘F’. The contractor may also, if practicable, indicate in
such a request the period for which extension is desired.
5.4 In any such case the Engineer-in-Charge with the approval of authority indicated
in Schedule ‘F’ may give a fair and reasonable extension of time and reschedule
the Milestones for completion of work. Such extension or re- scheduling of the
milestone shall be communicated to the contractor by the Engineer-in-charge in
writing, within 1 month or 4 weeks of the date of receipt of such request
respectively. Non-application by the contractor for extension of time / re-
scheduling of milestones shall not be a bar for giving a fair and reasonable
extension / re-scheduling of milestones by the Engineer-in-charge with the
approval of authority indicated in schedule ‘F’ and this shall be binding on the
contractor.

CLAUSE 6

Measurements Engineer-in-charge shall, except as otherwise provided, ascertain and determine


of Work by measurement, the value in accordance with the contract of work done.
Done All measurement of all items having financial value shall be entered in
Measurement Book and/or level field book so that a complete record is obtained
of all works performed under the contract.
All measurements and levels shall be taken jointly by the Engineer-in-Charge or
his authorised representative and by the contractor or his authorised
representative from time to time during the progress of the work and such
measurements shall be signed and dated by the Engineer-in-Charge and the
contractor or their representatives in token of their acceptance. If the contractor
objects to any of the measurements recorded, a note shall be made to that effect
with reason and signed by both the parties.
If for any reason the contractor or his authorised representative is not available
and the work of recording measurements is suspended by the Engineer-in-
Charge

A.A.I. C-NIL I-NIL O-NIL Page 23


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

or his representative, the Engineer-in-Charge and the Department shall not


entertain any claim from contractor for any loss or damages on this account. If
the contractor or his authorised representative does not remain present at the
time of such measurements after the contractor or his authorised representative
has been given a notice in writing three (3) days in advance or fails to
countersign or to record objection within a week from the date of the
measurement, then such measurements recorded in his absence by the Engineer-
in- Charge or his representative shall be deemed to be accepted by the
Contractor.
The contractor shall, without extra charge, provide all assistance with every
appliance, labour and other things necessary for measurements and recording
levels.
Except where any general or detailed description of the work expressly shows to
the contrary, measurements shall be taken in accordance with the procedure set
forth in the specifications notwithstanding any provision in the relevant
Standard Method of measurement or any general or local custom. In the case of
items which are not covered by specifications, measurements shall be taken in
accordance with the relevant standard method of measurement issued by the
Bureau of Indian Standards and if for any item no such standard is available,
then a mutually agreed method shall be followed.
The contractor shall give, not less than seven days’ notice to the Engineer-in-
Charge or his authorised Representative of the work, before covering up or
otherwise placing beyond the reach of measurement any work in order that the
same may be measured and correct dimensions thereof be taken before the same
is covered up or placed beyond the reach of measurement and shall not cover up
and place beyond reach of measurement any work without consent in writing of
the Engineer-in-Charge or his authorised representative of the work who shall
within the aforesaid period of seven days inspect the work, and if any work shall
be covered up or placed beyond the reach of measurements without such notice
having been given or the Engineer-in- Charge’s consent being obtained in
writing, the same shall be uncovered at the Contractor’s expense, or in default
thereof no payment or allowance shall be made for such work or the materials
with which the same was executed.
Engineer-in-Charge or his authorised representative may cause either
themselves or through another officer of the department to check the
measurements recorded jointly or otherwise as aforesaid and all provisions
stipulated herein above shall be applicable to such checking of measurements or
levels.
It is also a term of this contract that recording of measurements of any item of
work in the measurement book and/or its payment in the interim, on account or
final bill shall not be considered as conclusive evidence as to the sufficiency of
any work or material to which it relates nor shall it relieve the contractor from
liabilities from any over measurement or defects noticed till completion of the
defects liability period.

Clause 6 A
Computerized Computerized measurement is mandatory for works costing more than Rs 5.00
Measurement Lacs. However in case of works costing lesser than Rs. 5.00 Lacs Engineer-in-
Book Charge may decide for adopting computerized measurement if required, except as
otherwise provided, ascertain and determine by measurement the value of work
done in accordance with the contract. All measurements of all items having
financial value shall be entered by the contractor and compiled in the shape
of the Computerized Measurement Book having pages of A-4 size as per the
format of the department so that a complete record is obtained of all the items of
works performed under the contract.
A.A.I. C-NIL I-NIL O-NIL Page 24
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

All such measurements and levels recorded by the contractor or his authorised
representative from time to time, during the progress of the work, shall be got
checked by the contractor from the Engineer-in-Charge or his authorised
representative as per interval or program fixed in consultation with Engineer-in-
Charge or his authorised representative. After the necessary corrections made by
the Engineer-in- Charge, the measurement sheets shall be returned to the
contractor for incorporating the corrections and for resubmission to the
Engineer-in-Charge for the dated signatures by the Engineer-in-Charge and the
contractor or their representatives in token of their acceptance.
Whenever bill is due for payment, the contractor would initially submit draft
computerized measurement sheets and these measurements would be got
checked/test checked from the Engineer-in-Charge and/or his authorized
representative. The contractor will, thereafter, incorporate such changes as may
be done during these checks/test checks in his draft computerized
measurements, and submit to the department a computerized measurement book,
duly bound, and with its pages machine numbered. The Engineer-in-Charge
and/or his authorised representative would thereafter check this MB, and record
the necessary certificates for their checks / test checks.
The final, fair, computerized measurement book given by the contractor, duly
bound, with its pages machine numbered, should be 100% correct, and no
cutting or overwriting in the measurements would thereafter be allowed. If at all
any error is noticed, the contractor shall have to submit a fresh computerized
MB with its pages duly machine numbered and bound, after getting the earlier
MB cancelled by the department. Thereafter, the MB shall be taken in the
records of Engineer-in-charge, and allotted a number as per the Register of
Computerized MBs. This should be done before the corresponding bill is
submitted to the Engineer-in-charge for payment. The contractor shall submit
two spare copies of such computerized MB’s for the purpose of reference and
record by the various officers of the department.
The contractor shall also submit to the department separately his computerized
Abstract of Cost and the bill based on these measurements, duly bound, and its
pages machine numbered along with two spare copies of the “bill. Thereafter,
this bill will be processed by the Engineer-in-charge and allotted a number as
per the computerized record in the same way as done for the measurement book
meant for measurements.
The contractor shall, without extra charge, provide all assistance with every
appliance, labour and other things necessary for checking of measurements /
levels by the Engineer-in-charge or his representative.
Except where any general or detailed description of the work expressly shows to
the contrary, measurements shall be taken in accordance with the procedure set
forth in the specifications notwithstanding any provision in the relevant
Standard Method of measurement or any general of local custom. In the case of
item which are not covered by specifications, measurements shall be taken in
accordance with the relevant standard method of measurement issued by the
Bureau of Indian Standards and if for any item no such standard is available
then a mutually agreed method shall be followed.
The contractor shall give not less than seven days’ notice to the Engineer-in-
Charge or his authorized representative of the work before covering up or
otherwise placing beyond the reach of checking and / or test checking the
measurement of any work in order that the same be checked and / or test
checked and correct dimensions thereof be taken before the same is covered up
or placed beyond the reach of checking and / or test checking measurement and
shall not cover up and place beyond reach of measurement any work without
consent in

A.A.I. C-NIL I-NIL O-NIL Page 25


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

writing of the Engineer-in-charge or his authorized representative of the work


who shall within the aforesaid period of seven days inspect the work, and if any
work shall be covered up or placed beyond the reach of checking and / or test
checking measurements without such notice having been given or the Engineer-
in charge’s consent being obtained in writing the same shall be uncovered at the
contractor’s expense, or in default thereof no payment or allowance shall be
made for such work or the materials with which the same was executed.
Engineer-in-charge or his authorised representative may cause either themselves
or through another officer of the department to check the measurements
recorded by contractor and all provisions stipulated herein above shall be
applicable to such checking of measurements or levels.
It is also a term of this contract that checking and/or test checking the
measurements of any item of work in the measurement book and/or its payment
in the interim, on account of final bill shall not be considered as conclusive
evidence as to the sufficiency of any work or material to which it relates nor
shall it relieve the contractor from liabilities from any over measurement or
defects noticed till completion of the defects liability period.

CLAUSE 7

Payment on No payment shall be made for work, estimated to cost Rs. One lac or less till
Intermediate after the whole of the work shall have been completed and certificate of
Certificate to be completion given. For works estimated to cost over Rs. One lac, the interim or
regarded as running account bills shall be submitted by the contractor for the work executed
Advances on the basis of such recorded measurements on the format of the Department in
triplicate on or before the date of every month fixed for the same by the
Engineer-in-Charge. The contractor shall not be entitled to be paid any such
interim payment if the gross work done together with net payment/ adjustment
of advances for material collected, if any, since the last such payment is less
than the amount specified in Schedule ‘F’, in which case the interim bill shall be
prepared on the appointed date of the month after the requisite progress is
achieved. Engineer-in- Charge shall arrange to have the bill verified by taking or
causing to be taken, where necessary, the requisite measurements of the work.
In the event of the failure of the contractor to submit the bills, Engineer-in-
Charge shall prepare or cause to be prepared such bills in which event no claims
whatsoever due to delays on payment including that of interest shall be payable
to the contractor. Payment on account of amount admissible shall be made by
the Engineer-in-Charge certifying the sum to which the contractor is considered
entitled by way of interim payment at such rates as decided by the Engineer-in-
Charge. The amount admissible shall be paid by 10th working day after the day
of presentation of the bill by the Contractor to the Engineer-in-Charge or his
Asstt. Manager / Manager (Engg.) together with the account of the material
issued by the department, or dismantled materials, if any. In the case of works
outside the headquarters of the Engineer- in-Charge, the period of ten working
days will be extended to fifteen working days.
All such interim payments shall be regarded as payment by way of advances
against final payment only and shall not preclude the requiring of bad, unsound
and imperfect or unskilled work to be rejected, removed, taken away and
reconstructed or re-erected. Any certificate given by the Engineer-in-charge
relating to the work done or materials delivered forming part of such payment,
may be modified or corrected by any subsequent such certificate(s) or by the
final certificate and shall not by itself be conclusive evidence that any work or
materials to which it relates is are in accordance with the contract and

A.A.I. C-NIL I-NIL O-NIL Page 26


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

specifications. Any such interim payment, or any part thereof shall not in any
respect conclude, determine of affect in any way powers of the Engineer-in-
charge under the contract or any of such payments be treated as final settlement
and adjustment of accounts or in any way vary or affect the contract.
Pending consideration or extension of date of completion, interim payments
shall continue to be made as herein provided without prejudice to the right of the
department to take action under the terms of this contract for delay in the
completion of work, if the extension of date of completion is not granted by the
competent authority.
The Engineer-in-Charge in his sole discretion on the basis of a certificate from
the Asstt Manager / Manager (Engg) to the effect that the work has been
completed up to the level in question make interim advance payments without
detailed measurements for work done (other than foundations, items to be
covered under finishing items) up to lintel level (including sunshade etc.) and
slab level, for each floor working out at 75% of the assessed value. The advance
payments so allowed shall be adjusted in the subsequent interim bill by taking
detailed measurements thereof.

CLAUSE 8

Completion Within ten days of the completion of the work, the contractor shall give notice
Certificate and of such completion to the Engineer-in-Charge and within thirty days of the
Completion receipt of such notice, the Engineer-in-Charge shall inspect the work and if there
Plans is no defect in the work, shall furnish the contractor with a final certificate of
completion, otherwise a provisional certificate of physical completion indicating
defects (a) to be rectified by the contractor and/or (b) for which payment will be
made at reduced rates, shall be issued. But no final certificate of completion
shall be issued, nor shall the work be considered to be complete for ‘Civil
Construction Works’ until the contractor shall have removed from the premises
on which the work shall be executed all scaffolding, surplus materials, rubbish
and all huts and sanitary arrangements required for his/their work people on the
site in connection with the execution of the works as shall have been erected or
constructed by the contractor(s) and cleaned off the dirt from all wood work,
doors, windows, walls, floor or other parts of the building, in, upon, or about
which the work is to be executed or of which he may have had possession for
the purpose of the execution; thereof, and not until the work shall have been
measured by the Engineer-in-charge. If the contractor shall fail to comply with
the requirements of this Clause as to removal of scaffolding, surplus materials
and rubbish and all huts and sanitary arrangement as aforesaid and cleaning off
dirt on or before the date fixed for the completion of work, the Engineer-in-
charge may at the expense of the contractor remove such scaffolding, surplus
materials and rubbish etc., and dispose of the same as he thinks fit and clean off
such dirt as aforesaid, and the contractor shall have no claim in respect of
scaffolding or surplus materials as aforesaid except for any sum actually realized
by the sale thereof.
a.For electrical and mechanical capital works: The contractor shall remove the
rubbish from the site. Following conditions must be met before recording
completion certificate :
Submits completion plan, maintenance manual, manufactures catalogue and
gives performance test for system.
b. For repair works: The performance of the repaired system has been tested
and found satisfactory.
c. For AMC work: The system has been tested for its performance /
completeness and taken over by AAI / next agency for operation and
maintenance.
A.A.I. C-NIL I-NIL O-NIL Page 27
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE8A

Contractor to When the annual repairs and maintenance of works are carried out, the splashes
keep site clean and droppings from white washing colour washing, painting etc., on walls, floor,
windows etc. shall be removed and the surface cleaned simultaneously with the
completion of these items of work in the individual rooms, quarters or premises
etc.
Where the work is done without waiting for the actual completion of all the
other items of work in the contract, in case the contractor fails to comply with
the requirements of this clause, the Engineer-in-charge shall have the right to get
this work done at the cost of the contractor either departmentally or through any
other agency. Before taking such action, the Engineer-in-charge shall give ten
days notice in writing to the contractor.

CLAUSE8B

Completion The contractor shall submit completion plan as required vide General
Plans to be Specifications for Electrical works (Part-I internal) 2013 and (Part -II External)
Submitted by 1994 or latest available specifications, as applicable within thirty days of the
the Contractor
completion of the work.
The contractor shall submit completion plan for building works, all services, and
obtain occupancy certificate from local bodies on the basis of completion
drawings within a period of 30 days from the date of completion.
The contractor shall also submit catalogues of all equipment’s and maintenance
manual for the complete E & M systems. If contractor fails to submit
completion plans of all works, he shall be liable to pay compensation @ 0.5% of
the tendered value of works costing up to Rs. 5 Crores subject to maximum of
Rs. 1.00 Lac and 0.25% for works costing more than Rs. 5 crores subject to
maximum of Rs. 1.5.Lac. The decision of Project-in-charge in this regard shall
be final and binding on the contractor.

CLAUSE 9

Payment of final The corrected final bill shall be submitted by the contractor in the same manner
bill as specified in interim bills within three months of physical completion of the
work or within one month of the date of the final certificate of completion
furnished by the Engineer-in-charge whichever is earlier. No further claims shall
be made by the contractor after submission of the final bill and these shall be
deemed to have been waived and extinguished. Payments of those items of the
bill in respect of which there is no dispute and of items in dispute, for quantities
and rates as approved by Engineer-in- charge, will, as far as possible be made
within the period specified herein under, the period being reckoned from the
date of receipt of the bill by the Engineer-in-charge or his authorized Asstt.
Manager / Manager (Engg.), complete with account of materials issued by the
Department and dismantled materials.
Sl. Value ofwork Timelimit
1 If the Tendered value of work is up toRs.50 2 months
lac
2 If the Tendered value of work ismorethan 3 months
Rs.50 lac and up to Rs. 2.5Crore:
If the Tendered value of workexceeds Rs. 2.5 6 months
Crore:

A.A.I. C-NIL I-NIL O-NIL Page 28


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

In case of delay in payment of final bills after prescribed time limit, a simple
interest @ 5% per annum shall be paid to the contractor from the date of expiry
of prescribed time limit which will be compounded on yearly basis, provided the
final bill submitted by the contractor found to be in order.
The Final bill shall be prepared for both L1 & L2 bidders for all tendered items
(excluding Extra Items based on market rate) and payment shall be made on the
basis of lower of the two.

CLAUSE 9 A

Payment of Payments due to the contractor and refund of various nature may, if so desired
contractor’s by him and wherever possible in banks be made through electronic payment
bills to Banks mechanism instead of direct to him, provided that the contractor furnishes to the
Engineer-in- Charge.
i. Information’s as per proforma attached.
ii. An authorization in the form of a legally valid document such as power of
attorney conferring authority on the bank to receive payments and
iii. His own acceptance of the correctness of the amount made out as being due
to him by Authority or his signature on the bill or other claim preferred
against Authority before settlement by the Engineer-in-charge of the account
or claim by payment to the bank. While the receipt given by such banks
shall constitute a full and sufficient discharge for the payment, the contractor
shall whenever possible present his bills duly receipted and discharged
through his bank.
Nothing herein contained shall operate to create in favour of the bank any rights
or equities vis-à-vis the Airports Authority of India.

CLAUSE 10

Materials Materials which Authority will supply are shown in Schedule ‘B’ which also
supplied by stipulates quantum, place of issue and rate(s) to be charged in respect thereof.
Authority The contractor shall be bound to procure them from the Engineer-in-charge.
As soon as the work is awarded, the contractor shall finalise the programme for
the completion of work as per clause 5 of this contract and shall give his
estimates of materials required on the basis of drawings/ or schedule of
quantities of the work. The contractor shall give in writing his requirement to
the Engineer-in-charge, which shall be issued to him keeping in view the
progress of work as assessed by the Engineer-in- Charge in accordance with the
agreed phased programme of work indicating monthly requirements of various
materials. The contractor shall place his indent in writing for issue of such
materials at least 7 days in advance of his requirement.
Such materials shall be supplied for the purpose of the contract only and the
value of the materials so supplied at the rates specified in the aforesaid schedule
shall be set off or deducted, as and when materials are consumed in items of
work (including normal wastage) for which payment is being made to the
contractor, form any sum then due or which may therefore become due to the
contractor under the contract or otherwise or from the security deposit. At the
time of submission of bills, the contractor shall certify that balance of materials
supplied is available at site in original good condition.
The contractor shall submit along with every running bill (on account or interim
bill) material-wise reconciliation statements supported by complete calculations

A.A.I. C-NIL I-NIL O-NIL Page 29


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

reconciling total issue, total consumption and certified balance (diameter /


section-wise in the case of steel) and resulting variations and reasons thereof.
Engineer-in-charge shall (whose decision shall be final and binding on the
contractor) be within his rights to follow the procedure of recovery in clause 42
at any stage of the work if reconciliation is not found to be satisfactory.
The contractor shall bear the cost of getting the material issued, loading,
transporting to site, unloading, storing under cover as required, cutting
assembling and joining the several parts together as necessary. Notwithstanding
anything to the contrary contained in any other clause of the contract and all
stores / materials so supplied to the contractor or procured with the assistance of
the AAI shall remain the absolute property of Authority and the contractor shall
be the trustee of the stores/ materials, and the said stores/ materials shall not be
removed/ disposed off from the site of the work on any account and shall be at
all times open to inspection by the Engineer-in-charge or his authorised agent.
Any such stores / materials remaining unused shall be returned to the Engineer-
in-charge in as good a condition in which they were originally supplied at a
place directed by him, at a place of issue or any other place specified by him as
he shall require, but in case it is decided not to take back the stores / materials
the contractor shall have no claim for compensation on any account of such
stores / materials so supplied to him as aforesaid and not used by him or for any
wastage in or damage to in such stores / materials.
On being required to return the stores / materials, the contractor shall hand over
the stores/ materials on being paid or credited such price as the Engineer-in-
charge shall determine, having due regard to the condition of the stores /
materials. The price allowed for credit to the contractor, however, shall be at the
prevailing market rate not exceeding the amount charged to him, excluding the
storage charge, if any. The decision of the Engineer-in-charge shall be final and
conclusive. In the event of breach of the aforesaid condition, the contractor shall
in addition to throwing himself open to account for contravention of the terms of
the licenses or permit and / or for criminal breach of trust, be liable to Authority
for all advantages or profits resulting or which in the usual course would have
resulted to him by reason of such breach. Provided that the contractor shall in no
case be entitled to any compensation or damages on account of any delay in
supply or non-supply thereof all or any such materials and stores provided
further that the contractor shall be bound to execute the entire work if the
materials are supplied by the Authority within the original scheduled time for
completion of the work plus 50% thereof or schedule time plus 6 months
whichever is more if the time of completion of work exceeds 12 months, but if a
part of the materials only has been supplied within the aforesaid period, then the
contractor shall be bound to do so much of the work as may be possible with the
materials and stores supplied in the aforesaid period. For the completion of the
rest of the work, the contractor shall be entitled to such extension of time as may
be determined by the Engineer-in-charge whose decision in this regard shall be
final and binding on the contractor.
The contractor shall see that only the required quantities of materials are got
issued. Any such material remaining unused and in perfectly good / original
condition at the time of completion or determination of the contract shall be
returned to the Engineer-in- charge at the stores from which it was issued or at a
place directed by him by a notice in writing. The contractor shall not be entitled
for loading transporting, unloading and stacking of such unused material except
for the extra lead, if any involved, beyond the original place of issue.

A.A.I. C-NIL I-NIL O-NIL Page 30


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 10 A

Materials to be 1. The contractor shall, at his own expense, provide all materials, required for
provided by the the works other than those which are stipulated to be supplied by the
contractor Authority.
and Mandatory 2. The contractor shall, at his own expense and without delay; supply to the
Tests Engineer in- charge samples of materials to be used on the work and shall
get these approved in advance. All such materials to be provided by the
contractor shall be in conformity with the specifications laid down or
referred to in the contract. The contractor shall, if requested by the
Engineer-in-charge furnish proof, to the satisfaction of the Engineer-in-
charge that the materials so comply. The Engineer-in-charge shall within
thirty days of supply of samples or within such further period as he may
require intimate to the Contractor in writing whether samples are approved
by him or not. If samples are not approved, the Contractor shall forthwith
arrange to supply to the Engineer-in charge for his approval, fresh samples
complying with the specifications laid down in the contract. When
materials are required to be tested in accordance with specifications,
approval of the Engineer-in-charge shall be issued after the test results are
received.
3. The contractor shall at his risk and cost submit the samples of materials to
be tested or analyzed and shall not make use of or incorporate in the work
any materials represented by the samples until the required tests or analysis
have been made and materials finally accepted by the Engineer-in-charge.
4. If any additional tests apart from mandatory tests specified in the contract
are required to be carried out at the instance of AAI or any other advisory
body, to ensure conformity of the item to the contract specifications, the
cost of such tests shall be borne by AAI. In case the material / equipment
fails in the above tests, the expenditure incurred by AAI on testing of such
material or equipment along with incidental charges borne by AAI (if any)
shall be recovered from the dues of the contractor and action shall be taken
under Clause 16 and other relevant clauses of the contract.
5. The contractor shall not be eligible for any claim or compensation either
arising out of any delay in the work or due to any corrective measures
required to be taken on account of and as a result of testing of materials.
6. The contractor shall, at his risk and cost, make all arrangements and shall
provide all facilities as the Engineer-in-charge may require for collecting
and preparing the required number of samples for such tests at such time
and to such place or places as may be directed by the Engineer-in-charge
and bear all charges and cost of testing unless specifically provided for
otherwise elsewhere in the contract or specifications. The Engineer-in-
charge or his authorised representative shall at all times have access to the
works and to all workshops and places where work is being prepared or
from where materials manufactured, articles or machinery are being
obtained for the works and the contractor shall afford every facility and
every assistance in obtaining the right to such access.
7. The Engineer-in-charge shall have full powers to require the removal from
the premises of all materials which in his opinion are not in accordance
with the specifications and in case of default, the Engineer-in-charge shall
be at liberty to employ at the expense of the contractor, other persons to
remove the same without being answerable or accountable for any loss or
damage that may happen or arise to such materials. The Engineer-in-charge
shall also have full powers to require other proper materials to be
substituted thereof and in case of default, the Engineer-in-charge may cause
the same to be supplied and all costs which may be attracted for such
removal and substitution shall be borne by the Contractor.
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

8. The contractor shall at his own expense, provide a material testing lab at
the site for conducting routine field tests. The lab shall be equipped at least
with the testing equipment as specified in Schedule F.
9. Details in respect of all mandatory tests shall be maintained in the desired
format and attached with each Running Account Bill.

CLAUSE 10 B

(1) Secured 1. The Contractor, on signing an indenture in the form to be specified by the
Advance on Engineer-in- charge, shall be entitled to be paid during the progress of the
Nonperishable execution of the work upto 75% of the assessed value of any materials
materials which are in the opinion of the Engineer-in-charge nonperishable, non-
fragile and noncombustible and are in accordance with the contract and
which have been brought on the site in connection therewith and are
adequately stored and/ or protected against damage by weather or other
causes but which have not at time of advance been incorporated in the
works. When materials on account of which an advance has been made
under this sub-clause are incorporated in the work, the amount of such
advance shall be recovered/ deducted from the next payment made under
any of the clause or clauses of this contract.
Such secured advance shall also be payable on other items of perishable
nature, fragile and combustible with the approval of the Engineer-in-charge
provided the contactor provides a comprehensive insurance cover for the
full cost of such materials. The decision of the Engineer-in-charge shall be
final and binding on the contractor in this matter. No secured advance, shall
however, be paid on high-risk materials such as ordinary glass, sand, petrol,
diesel etc.
The secured advance shall also be payable against items brought at site for
use in electrical and mechanical systems. Such secured advance shall be
paid on submission of Collateral Bank Guarantee submitted by the vendor
against the payment in case equipment/system fails to perform on testing
and commissioning. Normally secured advance is paid up to 75% of the
assessed value of items but in any case it shall not exceed 80% of cost of
items indicated for supply of equipment.
(II) Mobilization 2. Mobilization advance not exceeding 10% of the tendered value shall be paid
Advance for the works costing more than Rs 5.00 Cr, subject to the availability of
funds and if requested by the contractor in writing within period as
indicated below.
a. For the works costing between Rs. 5 crores – Rs.100 crores the
application for the issue of mobilization advance must be received in
writing within 30 days of handing over of the site.
b. For the works costing more than Rs. 100 crores the application for the
issue of mobilization advance must be received in writing within 45
days of handing over of the site.
c. The contractor shall execute a Bank Guarantee Bond from any
Scheduled Bank but not Co-operative or Gramin Bank as specified by
Engineer-in-charge for 110% of value of installment of mobilization
advance before such advance is released. The first installment should
not exceed Rs.20.00 Cr. for the work for which the estimated cost is
kept as Rs.500.00 Cr. or more. The No. of installments shall be
decided
A.A.I. C-NIL I-NIL O-NIL Page 32
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

by AAI depending on progress of work and availability of funds.


d. The second and subsequent installments shall be released by the
Engineer-in-charge only after the contractor furnishes a proof of the
satisfactory utilization of the earlier installment to the entire
satisfaction of the Engineer-in-charge. Provided provision of Clause
10B (II) shall be applicable only when so provided in Schedule ‘F’.
The contractor shall accordingly submit Bank Guarantee in parts for
release of corresponding mobilization advance and validity of BG shall
be for a extended period of 3 months beyond stipulated date of
completion.
Interest on 3. The mobilization advance bear simple interest at the rate of 10% per annum
Mobilization and shall be calculated from the date of payment to the date of recovery,
advance both days inclusive, on the outstanding amount of advance.
a. However, in rare cases, wherein progress of work is delayed beyond
stipulated period of completion due to reasons beyond control of
contractor, deferment in recovery of mobilization advance with
accumulated interest thereon may be considered by AAI. In such case
of deferred recovery, an enhanced rate of interest i.e 15% per annum
shall be payable with recovery of outstanding mobilization amount @
50% of gross value of running account bill(s), subject to Engineer-In-
Charge certifying that deferment towards recovery of outstanding
advance is proposed in the overall interest of the project and is
necessitated to improve the progress of work.
Recovery of 4. Recovery of such advanced of sums against above and the interest thereon
Mobilization shall be made by deduction from (the contractor’s bill) the on-account
advance payments in suitable percentage in relation to the stipulated period of
completion as detailed below :
a. 25% of the amount advanced plus interest due upto 1/4th of the
stipulated period of the completion.
b. 60% of the amount advanced plus interest due upto ½ of the stipulated
period of the completion.
c. 100% of the amount advanced plus interest due upto 3/4th of the
stipulated period of the completion or 80% of the progress of work
whichever is earlier.
d. Wherein progress of work is delayed beyond stipulated period of
completion due to reasons beyond control, deferment in recovery of
mobilization advance with accumulated interest thereon may be
considered at an enhanced rate of interest i.e. 15% per annum with
recovery of outstanding mobilization advance @50% of gross value
of running account bill.
e. In case requisite amount as recoverable above is not available in on-
account payments mentioned above, the agency shall deposit the
same within 7 days of its due otherwise all Bank Guarantees
submitted by the agency towards mobilization advance shall be
encashed by the Engineer-in-charge.

A.A.I. C-NIL I-NIL O-NIL Page 33


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 10 C

Payment on If after submission of the tender, the price of any material incorporated in the
Account of works (excluding the materials covered under Clause 10CA and not being a
Increase in material supplied from the Engineer-in-charge’s stores in accordance with
Prices/
Wages due Clause 10 thereof) and/ or wages of labour increases as a direct result of the
to Statutory coming into force of any fresh law or statutory rule or order (but not due to any
Order(s) variation of rates in GST applicable on such materials being considered under
this clause) beyond the prices / wages prevailing at the time of last stipulated
date for receipt of the tenders including extensions, if any, for the work, during
contract period including the justified period extended under the provisions of
the Clause 5 of the Contract without any action under Clause 2, then the amount
of the contract shall accordingly be varied.
If after submission of the tender, the price of any material incorporated in the
works (excluding the material covered under clause 10CA and not being a
material supplied from the Engineer-in-charge’s stores in accordance with
clause 10 thereof) and / or wages of labour as prevailing at the time of last
stipulated date of receipt of tender including extensions, if any, is decreased as a
direct result of the coming into force of any fresh law or statutory rule or order
(not due to any changes in GST /Custom duty). Authority shall in respect of
materials incorporated in the works (excluding the material covered under
clause 10CA and not being materials supplied from the Engineer-in-charge’s
stores in accordance with Clause 10 hereof) and/ or labour engaged on the
execution of the work after the date of coming into force of such law, statutory
rule or order be entitled to deduct from the dues of the contractor, such amount
as shall be equivalent to the difference between the prices of the materials and/
or wages as prevailed at the time of the last stipulated date for receipt of tenders
including extensions if any for the work and the prices of materials and/ or
wages of labour on the coming into force of such law, statutory rule or order.
This will be applicable for the contract period including the justified period
extended under the provisions of clause 5 of the contract without any action
under clause 2.
Engineer-in-charge shall call books of account and other relevant documents
from the contractor to satisfy himself about reasonability of increase in prices of
materials and wages. The contractor shall, within a reasonable time of his
becoming aware of any alteration in the price of any such materials and/ or
wages of labour, give notice thereof to the Engineer-in-charge stating that the
same is given pursuant to this condition together with all information relating
thereto which he may be in position to supply.
For this purpose, the labour component of 85% of the value of the work
executed during period under consideration shall not exceed the percentage as
specified in Schedule F, and the increase / decrease in labour shall be considered
on the minimum daily wages in rupees of any unskilled mazdoor,
fixed under any law, statutory rule or order.
The cost of work for which escalation applicable (w) is same as cost of work
done as worked out as indicated in clause 10 CC minus the amount of full
assessed value of secured advances.

A.A.I. C-NIL I-NIL O-NIL Page 34


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 10 CA

Payment due If after submission of the tender, the price of materials specified in Schedule-F
to variation in increases/ decreases beyond the base price(s) as indicated in schedule F for the
prices of work, then the amount of the contract shall accordingly be varied and provided
materials after further that any such variations shall be effected for stipulated period of contract
receipt of tender including the justified period extended under the provisions of clause 5 of the
contract without any action under Clause 2.
However for work done/ during the justified period extended as above, it will be
limited to indices prevailing at the time of updated stipulated date of completion
considering the effect of extra work (Extra time to be calculated on pro-rata
basis only as cost of extra work X stipulated period/ tendered cost).
The increase/ decrease in prices of cement, steel reinforcement, structural steel
and POL shall be determined by the Price indices issued by the Director
General, CPWD. For other items provided in the Schedule ‘F’, this shall be
determined by the All India Wholesale Price Indices of materials as published
by Economic Advisor to Government of India, Ministry of Commerce and
Industry. Base price for cement, steel reinforcement, structural steel and POL
shall be as issued under authority of Director General, CPWD applicable for
Delhi including Noida, Gurgaon, Faridabad and Ghaziabad and for other places
as issued under the authority of Zonal Chief Engineer, CPWD and base price of
other materials issued by concerned Zonal Chief Engineer and as indicated in
Schedule ‘F’. In case, price index of a particular material is not issued by
Ministry of Commerce and Industry then the price index of nearest similar
material as indicated in Schedule F shall be followed.
The amount of the contract shall accordingly be varied for all such materials
worked out as per the formula given below for individual material:
Adjustment for component of individual material.
V = P x Q x Cl-Cl0
Cl0
where,
V = Variation in material cost i.e. increase or decrease in the amount in rupees
to be paid or recovered
P = Base price of material as issued under authority of DG, CPWD or concerned
Zonal Chief Engineer CPWD and as indicated in Schedule ‘F’.
For Projects and original works
Q = Quantity of material brought at site for bonafide use in the works since
previous bill excluding any such quantity consumed in the deviated
quantity of items beyond deviation limit and extra/substituted item, paid/to
be paid at rates derived on the basis of market rates under clause 12.2
For maintenance works
Q = Quantity of material brought at site for bonafide use in the works since
previous bill including any such quantity consumed in the deviated quantity
of items beyond deviation limit paid at agreement rates and
extra/substituted item being scheduled items, but excluding non scheduled
extra/substituted item paid/to be paid at market rates under clause 12.2

A.A.I. C-NIL I-NIL O-NIL Page 35


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

Cl0 = Price index for cement, steel reinforcement bars, structural steel and POL
as issued by the DG, CPWD and corresponding to the time of base price of
respective material indicated in schedule ‘F’. For other items, if any
provided in Schedule ‘F’, All India Wholesale Price Index for the material
as published by the Economic Advisor to Government of India, Ministry
of Industry and Commerce and corresponding to the time of base price of
respective material indicated in Schedule ‘F’.
Cl = Price index for cement, steel reinforcement bars, structural steel and POL
as issued under the authority of DG, CPWD for period under
consideration. For other items, if any, provided in Schedule ‘F’ All India
Wholesale Price Index for the material for the period under consideration
as published by Economic Advisor to Government of India, Ministry of
Industry and Commerce.
If actual purchase price of material is less than base price P and
CI ≥ CIo then, this clause shall not be applicable.
Note:
i. In respect of justified period extended under the provisions of Clause 5 of
the contract without any action under clause 2, the index prevailing at the
time of updated stipulated date of completion considering the effect of
extra work (extra time to be calculated on prorata basis only as cost of
extra work X stipulated period/ tendered cost) shall be considered.

Provided always that provisions of the preceding Clause 10 C shall not be


applicable in respect of materials covered in this Clause.

ii. If during progress of work or at the time of completion of work, it is


noticed that any material brought at site is in excess of requirement, then
amount of escalation if paid earlier on such excess quantity of material
shall be recovered on the basis of cost indices as applied at time of
payment of escalation or as prevailing at the time of effecting recovery,
whichever is higher.
iii. Cement mentioned wherever in this clause includes cement component
used in RMC brought at site from outside approved RMC plants, if any.
iv. The date wise record of ready mix concrete shall be kept in a register and
cement consumption for the same shall be calculated accordingly.
If built-up steel items are brought at site from workshop, than the variation
shall be paid for structural steel up-to the period when the built-up item/
finished product is brought at site.

A.A.I. C-NIL I-NIL O-NIL Page 36


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

Clause 10CC

Payment due If the prices of materials (not being materials supplied or services rendered at
to fixed prices by the Department in accordance with clause 10 & 34 thereof) and/
Increase/ or wages of labour required for execution of work increase, the contractor shall
Decrease in be compensated for such increase as per provisions detailed below and the
Prices / amount of the contract shall accordingly be varied, subject to the condition that
Wages such compensation for escalation in prices and wages shall be available only for
(excluding the work done during the stipulated period of the contract including the justified
material period extended under the provisions of clause 5 of the contract without any
covered action under clause 2.
under
clause 10CA) No such compensation shall be payable for a work for which the stipulated period
after Receipt of completion is equal to or less than the time as specified in Schedule ‘F’. Such
of compensation for escalation in the prices of materials and labour, when due, shall
Tender for be worked out based on the following provisions:
works.
i. The base date for working out such escalation shall be the last stipulated date
of the receipt of tenders including extension, if any.
ii. The cost of work on which escalation will be payable shall be reckoned as
below:
a. Gross value of work done upto this quarter (A)
b. Gross value of work done upto the last quarter (B)
c. Gross value of work done since previous quarter (A-B) (C)
d. Full assessed value of secured advance (excluding material covered
under clause 10CA) fresh paid in this quarter (D)
e. Full assessed value of secured advance (excluding material covered
under clause 10CA) recovered in this quarter (E)
f. Full assessed value of secured advance for which escalation is payable
In this quarter (D-E) (F)
g. Advance payment made during this quarter (G)
h. Advance payment recovered during this quarter (H)
i. Advance payment for which escalation is payable in this quarter (G-H)
(I)
j. Extra items/ deviated quantities of items paid as per clause 12 based (J)
on prevailing market rates during this quarter:
Then, M=(C+F+I-J)
N= 0.85 M
k. Less cost of material supplied by the department as per clause 10 and
recovered during the quarter (K)
l. Less cost of services rendered at fixed charges as per Clause 34 and
recovered during the quarter (L)

m. Less cost of Engineering Consultancy Services render a fixed


charges as per BOQ and paid the quarter (X).
Cost of work for which escalation is applicable W=N-(K+L+X)

iii. Components for materials, (except Bitumen, cement, reinforcement bars,


structural steel or others material covered under clause 10CA) labour, P.O.L.
etc. shall be pre-determined for every work and incorporated in the
conditions of contract attached to the tender papers included in Schedule F.
The decision of the Engineer-in charge in working out such percentage shall
be binding on the contracts.
iv. The compensation for escalation for other materials (except Bitumen, cement,

A.A.I. C-NIL I-NIL O-NIL Page 37


Clauses of Contract

reinforcement bars, structural steel or others material covered under clause


10CA) and P.O.L. shall be worked as per the formula(m & n) given below:
a. Adjustment for civil component (except Bitumen, cement, reinforcement
bars, structural steel and others material covered under clause 10CA) /
electrical component of construction.

Materials m. Formula for adjustment in material cost

Vm = W x Xm x Ml-Ml0
100 Ml0
Vm = Variation in material cost i.e. increase or decrease in the amount in
rupees to be paid or recovered.
W = Cost of work done, worked out as indicated in sub para (ii)of Clause 10
CC
Xm = Component of ‘materials’ (except cement, structural steel,
reinforcement bars, POL and other materials covered under clause10 CA)
expressed as percent of the total value of work.

Ml = All India wholesale price index for civil component/ electrical component*
of construction material as worked out on the basis of All India Wholesale Price
Index for Individual Commodities / Group Items for the period under
consideration as published by the Economic Advisor to Government of
India, Ministry of Industry & Commerce and applying weightage to the
Individual Commodities/ Group Items(in respect to the justified period extended
under the provisions of clause 5 of the contract without any action under Clause
2, the index prevailing at the time of updated stipulated date of completion
considering the effect of extra work(extra time to be calculated on prorate basis
only as cost of extra work x stipulated period/tendered cost, shall be considered.)

Ml0 = All India wholesale price index for civil component/ electrical component*
of construction material as worked out on the basis of All India Wholesale Price
Index for Individual Commodities / Group Items valid on the last stipulated date
of receipt of tenders including extensions, if any, as published by the Economic
Advisor to Government of India, Ministry of Industry and Commerce and
applying weightage to the Individual Commodities / Group Items.
* Note: relevant component only will be applicable

POL n. Formula for adjustment in POL cost

VF = W x Z x Fl-Fl0
100 Fl0
VF = Variation in cost of Fuel, Oil & Lubricant i.e. increase or decrease in the
amount in rupees to be paid or recovered.
W = Cost of work done, worked out as indicated in sub para (ii) of Clause 10 CC
Z = Component of Fuel, Oil and Lubricant expressed as a percentage of the total
value of the work
Fl = All India wholesale price index for Fuel, Oil and Lubricant for the period
under consideration as published by the Economic Advisor to Government
of India, Ministry of Industry & Commerce (in respect to the justified period
extended under the provisions of clause 5 of the contract without any
action under Clause 2, the index prevailing at the time of updated stipulated
date of completion or the prevailing index of the period under consideration,
whichever is less, shall be considered)
Fl0 = All India wholesale price index for Fuel, Oil and Lubricant valid on
the last stipulated date of receipt of tenders including extensions, if any.

A.A.I. C-NIL I-NIL O-NIL Page 38


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

v. The following principles shall be followed while working out the indices
mentioned in above Para
a. The compensation for escalation shall be worked out at quarterly intervals
and shall be with respect to the cost of work done as per bills paid during
the three calendar months of the said quarter. The dates of preparation of
bills as finally entered in the measurement book/date of submission of bill
finally by the contractor to the department in case of computerized
measurement book shall be the guiding factor to decide the bills relevant
to the quarterly interval. The first such payment shall be made at the end
of three months after the month (excluding the month in which the tender
was accepted) and thereafter at three months’ interval. At the time of
completion of the work, the last period for payment might become less
than 3 months depending on the actual date of completion.
b. The index (MI/FI etc.) relevant to any quarter/ period for which such
compensation is paid shall be the arithmetical average of the indices
relevant to the three calendar months. If the period up to date of
completion after the quarter covered by the last such installment of
payment is less than three months, the index MI and FI shall be the
average of the indices for the months falling within that period.
Labour
vi Formula for adjustment in Labour cost
The compensation for escalation for labour shall be worked out as per the
formula given below:
Vl = W x Y x Ll-Ll0
100 Ll0
Vl = Variation in labour cost i.e. amount of increase or decrease in rupees
to be paid or recovered
W = Value of work done, worked out as indicated in sub para (ii) above
Y = Component of labour expressed as a percentage of the total value of the
work
Ll = Minimum wage in rupees of an unskilled adult male mazdoor, fixed under
any law, statutory rule or order as applicable on the last date of the quarter
previous to the one under consideration (in respect to the justified period
extended under the provisions of clause 5 of the contract without any action
under Clause 2, the minimum wage prevailing on the last date of
quarter previous to the quarter pertaining to updated stipulated date of
completion considering the effect of extra work (extra time to be calculated
on prorate basis only as cost of extra work x stipulated period/tendered cost,
shall be considered.)
Ll0 = Minimum daily wage in rupees of an unskilled adult male mazdoor, fixed
under any law, statutory rule or order as on the last stipulated date of receipt
of tender including extension if any.

A.A.I. C-NIL I-NIL O-NIL Page 39


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

vii. The following principles will be followed while working out the
compensation as per sub para (vi) above:
a. The minimum wage of an unskilled male mazdoor mentioned in sub para
(vi) above shall be the higher of the wage notified by Government of
India, Ministry of Labour and that notified by the local administration
both relevant to the place of work and the period of reckoning.
b. The escalation for labour also shall be paid at the same quarterly intervals
when escalation due to increase in cost of materials and/ or P.O.L. is paid
under this clause. If such revision of minimum wages take place during
any such quarterly intervals, the escalation compensation shall be payable
at revised rates only for work done in subsequent quarters.
c. Irrespective of variations in minimum wages of any category of labour,
for the purpose of this clause, the variation in the rate for an unskilled
male mazdoor alone shall form the basis for working out the escalation
compensation payable on the labour component.
viii. In the event the price of materials and/ or wages of labour required for
execution of the work decrease/s, there shall be a downward adjustment of
the cost of work so that such price of materials and/ or wages of labour shall
be deductible from the cost of work under this contract and in this regard the
formula herein before stated under this Clause 10CC shall mutatis mutandis
apply, provided that:
a. No such adjustment for the decrease in the price of materials and/or
wages of labour aforementioned would be made in case of contracts in
which the stipulated period of completion of the work is equal to or less
than the time as specified in Schedule F.
b. The Engineer-in-charge shall otherwise be entitled to lay down the
procedure by which the provision of this sub clause shall be
implemented from time to time and the decision of the Engineer-in-
charge in this behalf shall be final and binding on the contractor.
ix. Provided always that :
a. Where provisions of clause 10CC are applicable, provisions of clause 10
C will not be applicable but provisions of clause 10CA will be
applicable.
b. Where provisions of clause 10CC are not applicable, provisions of
Clause 10C and 10CA will become applicable.

Note: Updated stipulated date of completion ( period of completion plus extra time
for extra work for compensation under clause 10C, 10CA and 10CC, the
factor of 1.25 taken into account for calculating the extra time under clause
12.1 for extra time shall not be considered while calculating the updated
stipulated date of completion for this purpose in clause 10C. clause 10 CA,
and clause 10CC.
The date of preparation of bill shall be as finally entered in the measurement
book by AM / Mgr. / SM / AGM or the date of submission of bill by the
contractor to the Department. This shall be the guiding factor to decide the
bill relevant to that period in case of computerized billing.

A.A.I. C-NIL I-NIL O-NIL Page 40


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 10 D

Dismantled The contractor shall treat all materials obtained during dismantling of a
Material structure, excavation of the site for a work etc. as property of AAI and such
materials shall be disposed of to the best advantage of Authority according
AAI to the instructions in writing issued by the Engineer-in-charge.
Property

CLAUSE11

Work to be The contractor shall execute the whole and every part of the work in the
executed in most substantial and workmanlike manner both as regards materials and
accordance otherwise in every respect in strict accordance with the specifications. The
with
specifications, contractor shall also conform exactly, fully and faithfully to the design,
drawings, drawings and instructions in writing in respect to the work signed by the
orders etc. Engineer in charge and the contractor shall be furnished free of charge one
copy of the contract documents together with specifications, designs,
drawings and instructions as are not included in the standard specifications
of Central Public Works Department specified in Schedule F or in any
Bureau of Indian Standard or any other published standard or code or
Schedule of Rates or any other printed publication referred to elsewhere in
the contract. The contractor shall comply with the provisions of the
contract and with the care and diligence execute and maintain the works
and provide all labour and materials, tools and plants including for
measurements and supervision of all works, structural plans and other
things of temporary or permanent nature required for such execution and
maintenance in so far as the necessity for providing these, is specified or is
reasonably inferred from the contract. The contractor shall take full
responsibility for adequacy suitability and safety of all the works and
methods of construction.

CLAUSE12

Deviations / The engineer-in-charge shall have power (i) to make alteration in, omissions
variations from, additions to, or substitutions for the original specifications, drawings,
extent and designs and instructions that may appear to him to be necessary or advisable
pricing during the progress of the work, and (ii) to omit a part of the works in case of
non-availability of a portion of the site or for any other reasons and the contractor
shall be bound to carry out the works in accordance with any instructions given to
him in writing signed by the Engineering- charge and such alterations, omissions,
additions or substitutions shall form part of the contract as if originally provided
therein and any altered, additional or substituted work which the contractor may
be directed to do in the manner specified above as part of the works, shall be
carried out by the contractor on the same conditions in all respects including price
on which he agreed to do the main work except as hereafter provided.
12.1 The time for completion of the works shall, in the event of any deviations
resulting in additional cost over the tendered value being ordered, be extended, if
requested by the contractor, as follows:
i. In the proportion which the additional cost of the altered, additional or
substituted work, bears to the original tendered value plus
ii. 25% of the time calculated in (i) above or such further additional time as
may be considered reasonable by the engineer-in-charge.

A.A.I. C-NIL I-NIL O-NIL Page 41


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

12.2 Deviation, In the case of extra item(s) (items that are completely new, and in addition to the
Extra Items items contained in the contract) the contractor may within fifteen days of
and Pricing receipt of order or occurrence of the item(s) claim rates, supported by proper
analysis, for the work and the Engineer-in-charge shall within Six weeks of the
receipt of the claims supported by analysis, after giving consideration to the
analysis of the rates submitted by the contractor, determine the rates on the basis
of the market rates and the contractor shall be paid in accordance with the rates
so determined.

Deviation, In the case of substituted items (items that are taken up with partial
substituted substitution or in lieu of items of work in the contract), the rate for the
items pricing agreement item (to be substituted) and substituted item shall also be
determined in the manner as mentioned in the following para.
(i) If the market rate for the substituted item so determined is more than the
market rate of the agreement item (to be substituted), the rate payable to
the contractor for the substituted item shall be the rate for the agreement
item (to be substituted) so increased to the extent of the difference
between the market rates of substituted item and the agreement item (to
be substituted).
(ii) If the market rate for the substituted item so determined is less than the
market rate of the agreement item (to be substituted), the rate payable to
the contractor for the substituted item shall be the rate for the agreement
item (to be substituted) so decreased to the extent of the difference
between the market rates of substituted item and the agreement item (to
be substituted).

Deviation, In the case of contract items, substituted items, contract cum substituted items,
Deviated which exceed the limits laid down in schedule F, the contractor may within
Quantities, fifteen days of receipt of order or occurrence of the excess, claim revision of
Pricing the rates, supported by proper analysis for the work in excess of the above
mentioned limits, provided that if the rates so claimed are in excess of the
rates specified in the schedule of quantities, the Engineer-in-Charge shall
within prescribed time limit of receipt of the claims supported by analysis,
after giving consideration to the analysis of the rates submitted by the
contractor, determine the rates on the basis of the market rates and the
contractor shall be paid in accordance with the rates so determined.
12.3 The provisions of the preceding paragraph shall also apply to the decrease in
the rates of items for the work in excess of the limits laid down in Schedule F,
and the Engineer-in-Charge shall after giving notice to the contractor within
one month of occurrence of the excess and after taking into consideration any
reply received from him within fifteen days of the receipt of the notice, revise
the rates for the work in question within one month of the expiry of the said
period of fifteen days having regard to the market rates.
12.4 The contractor shall send to the Engineer-in-Charge once every three months,
an upto date account giving complete details of all claims for additional
payments to which the contractor may consider himself entitled and of all
additional work ordered by the Engineer-in-Charge, which he has executed
during the preceding quarter failing which the contractor shall be deemed to
have waived his right. However, the Executive Director Engineering may
authorize consideration of such claims on merits.

A.A.I. C-NIL I-NIL O-NIL Page 42


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

12.5 For the purpose of operation of Schedule F, the following works shall be treated
as works relating to foundation unless & otherwise defined in the contract:
i. For Buildings: All works up to 1.2 meters above ground level or up to floor
1 level whichever is lower.
ii. For abutments, piers and well staining: All works up to 1.2 m above the
bed level.
iii. For retaining walls, wing walls, compound walls, chimneys, overhead
reservoirs/tanks and other elevated structures: All works up to 1.2 m above
the ground level.
iv. For roads, apron, runway & taxi track all items of excavation, filling GSBC
and including treatment of sub-base.
v. For reservoirs/tanks (other than overhead reservoirs/tanks): All works up to
1.2 meters above the ground level.
vi. For basement: All works up to 1.2 m above ground level or up to floor 1
level whichever is lower.
12.6 Any operation incidental to or necessarily has to be in contemplation of tenderer
while filing, tender, or necessary for proper execution of the item included in the
Schedule of quantities or in the schedule of rates mentioned above, whether or
not, specifically indicated in the description of the item and the relevant
specifications, shall be deemed to be included in the rates quoted by the tenderer
or the rate given in the said schedule of rates, as the case may be. Nothing extra
shall be admissible for such operations.

A.A.I. C-NIL I-NIL O-NIL Page 43


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 13

Foreclosure of If at any time after acceptance of the tender or during the progress of work the
contract due purpose or object for which the work is being done changes due to any
to supervening cause and as a result of which the work has to be abandoned or
Abandonment reduced in scope the Engineer-in-Charge shall give notice in writing to that
or Reduction effect to the contractor and the contractor stating the decision as well as the
in cause for such decision and the contractor shall act accordingly in the matter.
Scope of Work The contractor shall have no claim to any payment of compensation or otherwise
whatsoever, on account of any profit or advantage which he might have derived
from the execution of the works in full but which he did not derive in
consequence of the foreclosure of the whole or part of the works. The contractor
shall be paid at contract rates, full amount for works executed at site and, in
addition, a reasonable amount as certified by the Engineer-in-Charge for the
items hereunder mentioned which could not be utilized on the work to the full
extent in view of the foreclosure;

ii Any expenditure incurred on preliminary site work, e.g. temporary access


roads, temporary labour huts, staff quarters and site office; storage
accommodation and water storage tanks.

iii AAI shall have the option to take over contractor’s materials or any part
thereof either brought to site or of which the contractor is legally bound to
accept delivery from suppliers (for incorporation in or incidental to the
work) provided, however AAI shall be bound to take over the materials or
such portions thereof as the contractor does not desire to retain. For
materials taken over or to be taken over by AAI, cost of such materials as
detailed by Engineer-in- Charge shall be paid. The cost shall, however,
take into account purchase price, cost of transportation and deterioration
or damage which may have been caused to materials whilst in the custody
of the contractor.

iv If any materials supplied by AAI are rendered surplus, the same except
normal wastage shall be returned by the contractor to AAI at rates not
exceeding those at which these were originally issued, less allowance for
any deterioration or damage which may have been caused whilst the
materials were in the custody of the contractor. In addition, cost of
transporting such materials from site to AAI stores, if so required by AAI,
shall be paid.

v Reasonable compensation for transfer of T & P from site to contractor’s


permanent stores or to his other works, whichever is less. If T & P are not
transported to either of the said places, no cost of transportation shall be
payable.

vi Reasonable compensation for repatriation of contractor’s site staff and


imported labour to the extent necessary.

The contractor shall, if required by the Engineer- in-Charge, furnish to him,


books of account, wage books, time sheets and other relevant documents and
evidence as may be necessary to enable him to certify the reasonable amount
payable under this condition.
The reasonable amount of items on (i), (iv) and (v) above shall not be in excess
of 2% of the cost of the work remaining incomplete on the date of closure, i.e.
total stipulated cost of the work as per accepted tender less the cost of work
actually
A.A.I. C-NIL I-NIL O-NIL Page 44
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

executed under the contract and less the cost of contractor’s materials at site
taken over by the AAI as per item (ii) above. Provided always that against any
payments due to the contractor on this account or otherwise, the Engineer- in-
Charge shall be entitled to recover or be credited with any outstanding balances
due from the contractor for advance paid in respect of any tool, plants and
materials and any other sums which at the date of termination were recoverable
by the AAI from the contractor under the terms of the contract.
In the event of action being taken under clause 13 to reduce the scope of work,
the contractor may furnish fresh Performance Guarantee on the same conditions,
in the same manner and at the same rate for the balance tendered amount and
initially valid upto the extended date the completion or stipulated date of
completion if no extension has been granted plus 180 days beyond that.
Wherever, such a fresh Performance Guarantee is furnished by the contractor,
the Engineer in Charge may return the previous Performance Guarantee.

CLAUSE 14

Carrying out a. If contractor:


part Work at i. At any time makes default during currency of work or does not execute any
risk & cost part of the work with due diligence and continues to do so even after a
of contractor notice in writing of 7 days in this respect from the Engineer-in-Charge; or
ii. Commits default in complying with any of the terms and conditions of the
contract and does not remedy it or takes effective steps to remedy it within
7 days even after a notice in writing is given in that behalf by the Engineer-
in-Charge; or
iii. Fails to complete the work(s) or items of work with individual dates of
completion, on or before the date(s) so determined, and does not complete
them within the period specified in the notice given in writing in that
behalf by the Engineer-in-Charge.
b. The Engineer- in-Charge without invoking action under clause 3 may, without
prejudice to any other right or remedy against the contractor which have either
accrued or accrue thereafter to AAI, by a notice in writing to take the part
work / part incomplete work of any item(s) out of his hands and shall have
powers to:
i. Take possession of the site and any materials, constructional plant,
implements, stores, etc.,thereon; and/or
ii. Carry out the part work / part incomplete work of any item(s) by any
means at the risk and cost of the contractor.
c. The Engineer-in-Charge shall determine the amount, if any, is recoverable
from the contractor for completion of the part work/ part incomplete work of
any item(s) taken out of his hands and executed at the risk and cost of the
contractor, the liability of contractor on account of loss or damage suffered by
AAI because of action under this clause shall not exceed 10% of the tendered
value of the work.
d. In determining the amount, credit shall be given to the contractor with the
value of work done in all respect in the same manner and at the same rate as if
it had been carried out by the original contractor under the terms of his
contract, the value of contractor's materials taken over and incorporated in the
work and use of plant and machinery belonging to the contractor. The
certificate of the Engineer-in-Charge as to the value of work done shall be
final and conclusive against the contractor provided always that action under
this clause shall only be taken after giving notice in writing to the contractor.
Provided also that if the expenses incurred by the department are less than the
amount payable to the contractor at his agreement rates, the difference shall
not be payable to the contractor.
A.A.I. C-NIL I-NIL O-NIL Page 45
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

e. Any excess expenditure incurred or to be incurred by AAI in completing the


part work/ part incomplete work of any item(s) or the excess loss of damages
suffered or may be suffered by AAI as aforesaid after allowing such credit
shall without prejudice to any other right or remedy available to AAI in law or
per as agreement be recovered from any money due to the contractor on any
account, and if such money is insufficient, the contractor shall be called upon
in writing and shall be liable to pay the same within 30 days.
f. If the contractor fails to pay the required sum within the aforesaid period of 30
days, the Engineer-in-Charge shall have the right to sell any or all of the
contractors' unused materials, constructional plant, implements, temporary
building at site etc. and adjust the proceeds of sale thereof towards the dues
recoverable from the contractor under the contract and if thereafter there
remains any balance outstanding, it shall be recovered in accordance with the
provisions of the contract/ provisions of law.

In the event of above course being adopted by the Engineer-in-Charge, the


contractor shall have no claim to compensation for any loss sustained by him by
reason of his having purchased or procured any materials or entered into any
engagements or made any advance on any account or with a view to the
execution of the work or the performance of the contract.

CLAUSE 15

Suspension i. The contractor shall, on receipt of the order in writing of the Engineer-in-
of Work Charge, (whose decision shall be final and binding on the contractor) suspend
the progress of the works or any part thereof for such time and in such manner
as the Engineer-in- Charge may consider necessary so as not to cause any
damage or injury to the work already done or endanger the safety thereof for
any of the following reasons:
a. on account of any default on the part of the contractor or;
b. for proper execution of the works or part thereof for reasons other than the
default of the contractor; or
c. For safety of the works or part thereof.
The contractor shall, during such suspension, properly protect and secure the
works to the extent necessary and carry out the instructions given in that behalf by
the Engineer-in-Charge.
ii. If the suspension is ordered for reasons (b) and (c) in sub-para (i) above (but
not attributed to contractor):
a. the contractor shall be entitled to an extension of time equal to the period
of every such suspension PLUS 25% for completion of the item or group
of items of work for which a separate period of completion is specified in
the contract and of which the suspended work forms a part, and;
b. If the total period of all such suspensions in respect of an item or group of
items or work for which a separate period of completion is specified in the
contract exceeds thirty days, the contractor shall, in addition, be entitled to
such compensation as the Engineer-in-Charge may consider reasonable in
respect of salaries and/or wages paid by the contractor to his employees
and labour at site, remaining idle during the period of suspension, adding
thereto 2% to cover indirect expenses of the contractor provided the
contractor submits his claim supported by details to the Engineer-in-
Charge within fifteen days of the expiry of the period of 30 days.

A.A.I. C-NIL I-NIL O-NIL Page 46


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

c. If the works or part thereof is suspended on the orders of the Engineer-in-


Charge for more than three months at a time, except when suspension is
ordered for reasons (a) in sub-para (i) above, the contractor may after
receipt of such order serve a written notice on the Engineer-in-Charge
requiring permission within fifteen days from receipt by the Engineer-in-
charge of the said notice, to proceed with the work or part thereof in
regard to which progress has been suspended and if such permission is not
granted within that time, the contractor, if he intends to treat the
suspension, where it affects only a part of the works as on omission of
such part by AAI or where it affects whole of the works, as an
abandonment of the works by AAI, shall within ten days of expiry of such
period of 15 days give notice in writing of his intention to the Engineer-
in-Charge. In the event of the contractor treating the suspension as an
abandonment of the contract by AAI, he shall have no claim to payment
of any compensations on account of any profit or advantage which he
might have derived from the execution of the work in full but which he
could not derive in consequence of the abandonment. He shall, however,
be entitled to such compensation, as the Engineer-in-Charge may consider
reasonable, in respect of salaries and/or wages paid by him to his
employees and labour at site, remaining idle in consequence adding to the
total thereof 2% to cover indirect expenses of the contractor provided the
contractor submits his claim supported by details to the Engineer-in-
Charge within 30 days of the expiry of the period of 3 months.

CLAUSE 15 A
Compensatio The contractor shall not be entitled to claim any compensation from AAI for the
n in case of losses suffered by him on account of delay by AAI in the supply of materials in
delay due to Schedule ‘B’ where such delay is covered by the difficulties relating to supply of
late supply of wagons, force majeure or any reasonable cause beyond the control of AAI.
stipulated
material by This clause 15 A will not be applicable for works where no material is stipulated
AAI. for issue by AAI.
CLAUSE 16

Action in All works under or in course of execution or executed in pursuance of the


case Work contract, shall at all times be open and accessible to the inspection and
not done as supervision of the Engineer-in-Charge, his authorize subordinates in charge of the
per work and all the superior officers, officer of the Quality Assurance Unit of the
Specifications AAI or any organization engaged by the Department of Quality Assurance and of
the Chief technical Examiner’s Office, and the contractor shall, at all times,
during the usual working hours and at all other times at which reasonable notice
of the visit of such officers has been given to the contractor, either himself be
present to receive orders and instructions or have a responsible agent duly
accredited in writing, present for that purpose. Orders given to the Contractor’s
agent shall be considered to have the same force as if they had been given to the
contractor himself.
If it shall appear to the Engineer-in -charge or his authorized subordinates in
charge of the work or to the Executive Director-In-charge of quality assurance or
his subordinate officers or the officers of the organization engaged by the AAI for
quality Assurance or to the Chief Technical Examiner or his subordinate officers,
that any work has been executed with unsound, imperfect, or unskillful
workmanship, or with materials or articles provided by him for the execution of
the work which are unsound or of a quality inferior to that contracted or otherwise

A.A.I. C-NIL I-NIL O-NIL Page 47


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

not in accordance with the contract, the contractor shall, on demand in writing
which shall be made within twelve months (six months in the case of work costing
Rs.10 lac and below except road work) of the completion of the work from the
Engineer-in-Charge specifying the work, materials or articles complained of
notwithstanding that the same may have been passed, certified and paid for
forthwith rectify, or remove and reconstruct the work so specified in whole or in
part, as the case may require or as the case may be, remove the materials or
articles so specified and provide other proper and suitable materials or articles at
his own charge and cost. In the event of the failing to do so within a period
specified by the Engineer-in-Charge in his demand aforesaid, then the contractor
shall be liable to pay compensation at the same rate as under clause 2 of the
contract (for non-completion of the work in time) for this default.
In such case the Engineer-in-Charge may not accept the item of work at the rates
applicable under the contract but may accept such items at reduced rates as the
authority specified in schedule ‘F’ may considered reasonable during the
preparation of on account bills or final bill if the item is so acceptable without
detriment to the safety and utility of the item and the structure or he may reject
the work outright without any payment and/or get it and other connected and
incidental items rectified, or removed and re-executed at the risk and cost of the
contractor. Decision of the Engineer-in-Charge to be conveyed in writing in
respect of the same will be final and binding on the contractor.

CLAUSE17

Contractor If the contractor or his working people or servants shall break, deface, injure or
Liable for destroy any part of building in which they may be working, or any building, road,
Damages, road kerb fence, enclosure, water pipe, cables, drains, electric or telephone post or
defects
during wires, trees, grass or grassland, or cultivated ground contiguous to the premises
maintenance on which the work or any part is being executed, or if any damage shall happen to
period the work while in progress, from any cause whatever or if any defect, shrinkage
or other faults appear in the work within twelve months (six months in the case
of work costing Rs. Ten lacs and below except road work) after a
certificate final or otherwise of its completion shall have been given by the
Engineer-in-charge as aforesaid arising out of defect or improper materials or
workmanship the contractor shall upon receipt of a notice in writing on that
behalf make the same good at his own expense or in default the Engineering-
charge cause the same to be made good by other workmen and deduct the
expense from any sums that may be due or at any time thereafter may become
due to the contractor, or from his security deposit or the proceeds of sale thereof
or of a sufficient portion thereof. The security deposit of the contractor shall not
be refunded before the expiry of twelve months (six months in the case of work
costing Rs. Ten lacs and below except road work) after the issue of the certificate
final or otherwise, of completion of work, or till the final bill has been prepared
and passed whichever is later. Provided that in the case of road work, if in the
opinion of the Engineer-in-charge, half of the security deposit is sufficient, to
meet all liabilities of the contractor under this contract, half of the security
deposit will be refundable after six months and the remaining half after twelve
months of the issue of the said certificate of completion or till the final bill has
been prepared and passed whichever is later.
In case of Maintenance and Operation works of E&M services, the security
deposit deducted from contractors shall be refunded within one month from the
date of final payment or within one month from the date of completion of the
maintenance contract whichever is earlier.

A.A.I. C-NIL I-NIL O-NIL Page 48


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 18

Contractor The contractor shall provide at his own cost all materials (except such special
to Supply materials, if any, as may in accordance with the contract be supplied from the
Tools & Engineer-in charge’s stores) machinery, tools & plants as specified in Schedule F.
Plants etc. in addition to this, appliances, implements, other plants, ladders, cordage, tackle,
scaffolding and temporary works required for the proper execution of the work,
whether original, altered or substituted and whether included in the specifications
or other documents forming part of the contract or referred to in these conditions
or not, or which may be necessary for the purpose of satisfying or complying with
the requirements of the Engineer-in charge as to any matter as to which under
these conditions he is entitled to be satisfied, or which he is entitled to require
together with carriage therefor to and from the work. The contractor shall also
supply without charge the requisite number of persons with the means and
materials, necessary for the purpose of setting out works, and counting, weighing
and assisting the measurement for examination at any time and from time to time
of the work or materials. Failing his so doing, the same may be provided by the
Engineer-in-charge at the expense of the contractor and the expenses may be
deducted, from any money due to the contractor, under this contract or otherwise
and / or from his security deposit or the proceeds of sale thereof, or of a sufficient
portions thereof.

CLAUSE 18 A

Recovery of In every case in which by virtue of the provisions sub-section(i) of Section 12,
Compensation of the Workmen’s Compensation Act, 1923, AAI is obliged to pay
paid to compensation to a workman employed by the contractor, in execution of the
Workmen works, AAI will recover from the contractor, the amount of the compensation
so paid, and, without prejudice to the rights of the AAI under sub-section(2) of
Section 12, of the said act, AAI shall be at liberty to recover such amount or
any part thereof by deducting it from the security deposit or from any sum due
by AAI to the contractor whether under this contract or otherwise. AAI shall
not be bound to contest any claim made against it under subsection(1) of
Section 12, of the said Act, except on the written request of the contractor and
upon his giving to AAI full security for all costs for which AAI might become
liable in consequence of contesting such claim.

CLAUSE 18 B

Ensuring In every case in which by virtue of the provisions of the Contract Labour
Payment and (Regulation and Abolition) act 1970, and the Contract Labour (Regulation and
Amenities to Abolition) Central Rules, 1971, AAI is obliged to pay any amounts of wages
Workers if to a workman employed by the contractor in execution of the works, or to
Contractor incur any expenditure in providing welfare and health amenities required to be
fails provided under the above said Act and the rules under Clause 19H or under
the AAI Contractor’s Labour Regulations or under the Rules framed by AAI
from time to time for the protection of health and sanitary arrangements for
workers employed by AAI Contractors, AAI will recover from the contractor
the amount of wages so paid or the amount of expenditure so incurred and
without prejudice to the rights of the AAI under sub section (2) of Section 20,
sub section (4) of Section 21, of the Contract Labour (Regulation and
Abolition) Act, 1970, AAI shall be at liberty to recover such amount or any
part thereof by deducting it from the security deposit or from any sum due by
AAI to the contractor whether under this contract or otherwise AAI shall not
be bound to contest any claim made against it under sub section (1) of Section
A.A.I. C-NIL I-NIL O-NIL Page 49
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

20, sub section (4) of Section 21, of the said Act, except on the written request
of the contractor and upon his giving to the AAI full security for all costs for
which AAI might become liable in contesting such claim.

CLAUSE 19

Labour The contractor shall obtain a valid license under the contract labour (R&A) Act,
laws to be 1970 and the Contract Labour (Regulation and Abolition) Central Rules, 1971,
complied before the commencement of the work, and continue to have a valid license until
by the the completion of the work. The contractor shall also abide by the provisions of
Contractor the Child Labour (Prohibition and Regulation) Act, 1986.
The contractor shall also comply with the provisions of the building and other
construction workers (Regulation of Employment & Conditions of Service) Act,
1996 and the building and other Construction Workers Welfare Cess Act, 1996.
Any failure to fulfill these requirements shall attract the penal provisions of this
contract arising out of the resultant non-execution of the work.

CLAUSE19A

No labour below the age of fourteen years shall be employed on the work.
CLAUSE19B
Payment of Payment of wages:
wages i The contractor shall pay to labour employed by him either directly or through
subcontractors, wages not less than fair wages as defined in the AAI
Contractor’s Labour Regulation or as per the provisions of the Contract
Labour (Regulation and Abolition) act, 1970 and the contract labour
(Regulation and Abolition) Central Rules, 1971 wherever applicable.
ii The contractor shall, notwithstanding the provisions of any contract to the
contrary, cause to be paid fair wage to labour indirectly engaged on the work,
including any labour engaged by his sub-contractors in connection with the
said work, as if the labour had been immediately employed by him.
iii In respect of all labour directly or indirectly employed in the works for
performance of the contractor’s part of this contract, the contractor shall
comply with or cause to be complied with the Airports Authority of India
contractor’s Labour Regulations made by AAI from time to time in regard to
payment of wages wage period, deductions from wages recovery of wages not
paid and deductions unauthorisedly made, maintenance of wage books or
wage slips, publication of scale of wages and other terms of employment,
inspection and submission of periodical returns and all other matters of the
like nature or as per the provisions of the Contract Labour (Regulation and
Abolition) Act, 1970 and the Contract Labour (Regulation and Abolition)
Central Rules, 1971, wherever applicable.
iv The following deductions shall be permissible to be made by the Engineer-in-
Charge.
a. The Engineer-in-charge concerned shall have the right to deduct from the
moneys due to the contractor or any sum required or estimated to be
required for making good the loss suffered by a worker or workers by
reason of non-fulfillment of the conditions of the contract for the benefit of
the workers, non-payment of wages or of deductions made from his or their
wages which are not justified by their terms of the contract or non-
observance of the Regulations.
b. Under the provision of Minimum Wages (Central) Rule 1950 the contractor
is bound to allow to the labours directly or indirectly employed in the
works one day rest for 6 days continuous work and pay wages at the same
rate as for duty. In the event of default, the Engineer-in-charge shall have

A.A.I. C-NIL I-NIL O-NIL Page 50


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

the right to deduct the sum or sums not paid on account of wages for
weekly holidays to any labours and pay the same to the persons entitled
thereto from any money due to the contractor by the Engineer-in-charge
concerned.
In the case of Union Territory of Delhi, however, as the all-inclusive minimum
daily wages fixed under Notification of the Delhi Administration
No.F.12(162)MWO/DAB/43884-91, dated 31.12.1979 as amended from time to
time are inclusive of wages for the weekly day of rest, the question of extra
payment for weekly holiday would not arise.
v. The contractor shall comply with the provisions of the Payment of wages Act,
1936, Minimum Wages Act, 1948, Employees Liability Act, 1938,
Workmen’s Compensation Act, 1923, Industrial Disputes Act, 1947,
Maternity Benefits Act, 1961, and the Contractor’s Labour (Regulation and
Abolition) Act 1970, or the modifications thereof or any other laws relating
thereto and the rule made thereunder from time to time.
vi. The contractor shall indemnify and keep indemnified Authority against
payments to be made under and for the observance of the laws aforesaid and
the AAI Contractor’s Labour Regulations without prejudice to his right to
claim indemnity from his sub-contractors.
vii.The laws aforesaid shall be deemed to be a part of this contract and any
breach thereof shall be deemed to be a breach of this contract.
viii.Whatever is the minimum wage for the time being, or if the wage payable
is higher than such wage, such wage shall be paid by the contractor to the
workmen directly without the intervention of Jamadar and that Jamadar shall
not be entitled to deduct or recover any amount from the minimum wage
payable to the workmen as and by way of commission or otherwise.
ix. The contractor shall ensure that no amount by way of commission or
otherwise is deducted or recovered by the Jamadar from the wage of
workmen.
, CLAUSE19C
In respect of all labour directly or indirectly employed in the work for the
performance of the contractor’s part of this contract, the contractor shall at his
own expense arrange for the safety provisions as per AAI Safety Code framed
from time to time and shall at his own expense provide for all facilities in
connection therewith. In case the contractor fails to make arrangement and
provide necessary facilities as aforesaid, he shall be liable to pay a penalty of Rs.
200/- for each default and in addition, the Engineer-in charge shall be at liberty to
make arrangement and provide facilities as aforesaid and recover the costs
incurred in that behalf from the contractor.

CLAUSE19D
The contractor shall submit by the 4th and 19th of every month, to the Engineer-
in charge a true statement showing in respect of the second half of the preceding
month and the first half of the current month respectively:
i. the number of labourers employed by him on the work,
ii. their working hours,
iii. the wages paid to him,
iv. the accidents that occurred during the said fortnight showing the circumstances
under which they happened and the extent of damage and injury caused by
them, and the number of female workers who have been allowed maternity
benefit according to Clause 19F and the amount paid to them Failing which the
contractor shall be liable to pay to AAI, a sum not exceeding Rs. 200/- for
each default or materially incorrect statement. The decision of the Engineer-
in-charge shall be final in deducting from any bill due to the contractor; the
amount levied as fine and shall be binding on the contractor.
A.A.I. C-NIL I-NIL O-NIL Page 51
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE19E
In respect of all labour directly or indirectly employed in the works for the
performance of the contractor’s part of this contract, the contractor shall comply
with or cause to be complied with all the rules framed by AAI from time to time
for the protection of health and sanitary arrangements for workers employed by
the AAI and its contractor.

CLAUSE19F
Leave and pay during leave shall be regulated as follows:
1. Leave:
i. In the case of delivery - maternity leave not exceeding 8 weeks, 4 weeks
upto and including the day of delivery and 4 weeks following that day.
ii. In the case of miscarriage - upto 3 weeks from the date of miscarriage.
2. Pay:
i. In the case of delivery – leave pay during maternity leave will be at the rate
of women’s average daily earnings, calculated on total wages earned on the
days when full time work was done during a period of three months
immediately preceding the date on which she gives notice that she expects to
be confined or at the rate of Rupee one only a day whichever is greater.
In the case of miscarriage – leave pay at the rate of average daily earning
calculated on the total wages earned on the days when full time work was
done during a period of three months immediately preceding the date of such
miscarriage.
3. Conditions for the grant of Maternity Leave:
No maternity leave benefit shall be admissible to a woman unless she has been
employed for a total period of not less than six months immediately preceding
the date on which she proceeds on leave.
4. The contractor shall maintain a register of Maternity (Benefit) in the Prescribed
Form as shown in appendix – III and IV, and the same shall be kept at the
place of work.

A.A.I. C-NIL I-NIL O-NIL Page 52


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 19 G

In the event of the contractor (s) committing a default or breach of any of the
provisions of the Airports Authority of India Contractor’s Labour Regulations
and Model Rules for the protection of health and sanitary arrangements for the
workers as amended from time to time or furnishing any information or
submitting or filling any statement under the provisions of the above Regulations
and Rules which is materially incorrect, he / they shall, without prejudice to any
other liability, pay to the AAI a sum not exceeding Rs.200/- for every default,
breach or furnishing, making, submitting, filing such materially incorrect
statements and in the event of the contractor(s) defaulting continuously in this
respect, the penalty may be enhanced to Rs.200/- per day for each day of default
subject to a maximum of 5 per cent of the estimated cost of the work put to
tender. The decision of the Engineer-in-Charge shall be final and binding on the
parties.
Should it appear to the Engineer-in-Charge that the contractor (s) is / are not
properly observing and complying with the provision of the AAI Contractor’s
Labour Regulations and Model Rules and the provisions of the Contract Labour
(Regulation and Abolition ) Act 1970, and the Contract Labour (R&A) Central
Rules 1971, for the protection of health and sanitary arrangements for work –
people employed by the contractor (s) (hereinafter referred as “the said Rules”)
the Engineer-in-Charge shall have power to give notice in writing to the
contractor
(s) requiring that the said Rules be complied with and the amenities prescribed
therein be provided to the work-people within a reasonable time to be specified in
the notice. If the contractor (s) shall fail within the period specified in the notice
to comply with and/ observe the said Rules and to provide the amenities to the
work-people as aforesaid, the Engineer-in-Charge shall have the power to provide
the amenities hereinbefore mentioned at the cost of the contractor (s). The
contractor (s) shall erect, make and maintain at his / their own expense and to
approved standards all necessary huts and sanitary arrangements required for his /
their work –people on the site in connection with the execution of the works, and
if the same shall not have been erected or constructed, according to approved
standards, the Engineer-in-Charge shall have power to give notice in writing to
the contractor (s) requiring that the said huts and sanitary arrangements be
remodeled and / or reconstructed according to approved standards, and if the
contractor (s) shall fail to remodel or reconstruct such huts and sanitary
arrangements according to approved standards within the period specified in the
notice, the Engineer-in-Charge shall have the power to remodel or reconstruct
such huts and sanitary arrangements according to approved standards at the cost
of the contractor (s).

CLAUSE 19 H

The contractor (s) shall at his / their own cost provided his / their labour with a
sufficient number of huts (hereinafter referred to as the camp) on the following
specifications on a suitable plot of land to be approved the Engineer-in-Charge.
i. Facility to be provided
a. The minimum height of each hut at the eaves level shall be 2.10m (7ft.) and
the floor area to be provided will be at the rate of 2.7 sq.m. (30 sq.ft.) for
each member of the worker’s family staying with the labourer.
b. The contractor shall in addition construct suitable cooking places having a
minimum area of 1.80m x 1.50m (6’ x 5’) adjacent to the hut for each
family.

A.A.I. C-NIL I-NIL O-NIL Page 53


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

c. The contractor(s) shall also construct temporary latrines and urinals for the
use of the labourers each on the scale of not less than four per each one
hundred of the total strength, separate latrines and urinals being provided
for women.
d. The contractor (s) shall construct sufficient number of bathing and
washing places one unit for every 25 persons residing in the camp. These
bathing and washing places shall be suitably screened.
ii. Specifications
a. All the huts shall have walls of sun-dried or burnt-bricks laid in mud mortar
or other suitable local materials as may be approved by the Engineer-in-
Charge in case of sun-dried bricks, the walls should be plastered with mud
gobri on both sides. The floor may be kutcha but plastered with mud gobri
and shall be at least 15 cm (6”) above the surrounding ground. The roofs
shall be laid with the thatch or any other materials as may be approved by
the Engineer-in-Charge and the contractor shall ensure that throughout the
period of their occupation, the roofs remain water – tight.
b. The contractor (s) shall provide each hut with proper ventilation.
c. All doors, windows and ventilators shall be provided with suitable leaves
for security purposes.
d. There shall be kept an open space of at least 7.2 m (8 yards) between the
rows of huts which may be reduced to 6m (20 ft.) according to the
availability of site with the approval of the Engineer-in-Charge. Back to
back construction will be allowed.
iii. Water Supply
The contractor (s) shall provided adequate supply of water for the use of
labourers. The provisions shall not be less than two gallons of pure and
wholesome water per head per day for drinking purposes and three gallons of
clean water per head per day for bathing and washing purposes. Where piped
water supply is available supply shall be at stand posts and where the supply is
from wells or river, tanks which may be of metal or masonry, shall be provided.
The contractor (s) shall also at his / their own cost make arrangements for laying
pipe lines for water supply to his / their labour camp from the existing mains
wherever available and shall pay all fees and charges therefor.
iv. The site selected for the camp shall be high ground, removed from jungle.
v. Disposal of Excreta:
The contractor (s) shall make necessary arrangement for the disposal of excreta
from the latrines by trenching or incineration which shall be according to the
requirements laid down by the Local Health Authorities. If trenching or
incineration is not allowed, the contractor (s) shall make arrangements for the
removal of the excreta through the Municipal Committee / authority and inform it
about the number of labourers employed so that arrangements may be made by
such Committee / authority for the removal of excreta. All charges on this account
shall be borne by the contractor and paid direct by him to the
Municipality / authority. The contractor shall provide one sweeper for every eight
seats in case of dry system.
vi. Drainage
The contractor (s) shall provide efficient arrangements for draining away sullage
water so as to keep the camp neat and tidy.
vii. The contractor (s) shall make necessary arrangements for keeping the camp
area sufficiently lighted to avoid accidents to the workers.
viii. Sanitation
The contractor(s) shall make arrangements for conservancy and sanitation in the
labour camps according to the rules of the Local Public Health and Medical
Authorities.

A.A.I. C-NIL I-NIL O-NIL Page 54


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE19I

The Engineer-in-Charge may require the contractor to dismiss or remove from the
site of the work any person or persons in the contractors’ employ upon the work
who may be incompetent or misconduct himself and the contractor shall forthwith
comply with such requirements. In respect of maintenance/repair or renovation
works etc. where the labour have an easy access to the individual work premises,
the contractor shall issue identity cards to the labourers, whether temporary or
permanent and he shall be responsible for any untoward action on the part of such
labour. Assistant Manager/Junior Executive will display a list of contractors
working in the colony/Blocks on the notice board in the colony and also at the
service center, to apprise the residents about the same.

CLAUSE19J

It shall be the responsibility of the contractor to see that the building under
construction is not occupied by anybody unauthorized during construction, and is
handed over to the Engineer-in-Charge with vacant possession of complete
building. If such building though completed is occupied illegally, then the
Engineer-in-Charge shall have the option to refuse to accept the said
building/buildings in that position. Any delay in acceptance on this account will
be treated as the delay in completion and for such delay, a levy upto 5% of
tendered value of work may be imposed by the General Manager Engg. Whose
decision shall be final both with regard to the justification and quantum and be
binding on the contractor. However, the Executive Director Engg., through a
notice may require the contractor to remove the illegal occupation any time on or
before construction and delivery.

CLAUSE 19 K

Employment The contractor shall at all stages of work deploy skilled / semi-skilled tradesmen
of skilled / who are qualified and possess certificate in particular trade from CPWD Training
semiskilled Institute / Industrial Training Institute/National Institution of Construction
workers Management and research (NICMAR) National Academy of Construction, CIDC
or any similar reputed and recognized Institute managed / certified by State /
Central Government. The number of such qualified tradesmen shall not be less
than 20% of total skilled / semi-skilled workers required in each trade at any stage
of work. The contractor shall submit number of man days required in respect of
each trade, its scheduling and the list of qualified tradesmen along with requisite
certificate from recognized Institute to Engineer in charge for approval.
Notwithstanding such approval, if the tradesmen are found to have inadequate
skill to execute the work of respective trade, the contractor shall substitute such
tradesmen within two days of written notice from Engineer –in- Charge. Failure
on the part of contractor to obtain approval of Engineer-in-Charge or failure to
deploy qualified tradesmen will attract a compensation to be paid by contractor at
the rate of Rs.100 per such tradesman per day. Decision of Engineer in Charge as
to whether particular tradesman possesses requisite skill and amount of
compensation in case of default shall be final and binding.
Provided always, that the provision of this clause shall not be applicable for works
with estimated cost put to tender being less than Rs.5 crores.

A.A.I. C-NIL I-NIL O-NIL Page 55


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 19 L

Registration The ESI and EPF contributions on the part of employer in respect of this contract
with EPFO shall be paid by the contractor. These contributions on the part of the employer
and ESIC paid by the contractor shall be reimbursed by the Engineer-in-charge to the
contractor on actual basis.

CLAUSE 19 M

Compliance The contractor is required to follow latest NGT guidelines at the instruction
of NGT site and any violation of such guidelines will be in his account.
guidelines

CLAUSE 20

Minimum The contractor shall comply with all the provision of the Minimum Wages Act,
Wages 1948, and Contract Labour (Regulation and Abolition) Act, 1970 amended from
Act to be time to time and rules framed thereunder and other labour laws affecting contract
Complied
with labour that may be brought into force from time to time.

CLAUSE 20(A)

Employees The Contractor shall comply with all the provisions of the Employees Provident
Provident Fund & Misc. Provisions Act, 1952/ Jammu & Kashmir Employees Provident
Fund & Funds (and Miscellaneous Provisions) Act, 1961 and ESI Act, 1948, amended
Miscellaneous from time to time and rules framed thereunder. Some of the provisions are given
Provision Act below:
1952/Jammu a. The contractor shall intimate his PF Account Code No. allotted by Regional PF
& Kashmir Commissioner and ESI Registration No. allotted by ESI Corporation after
Employees award of work and shall continue to have valid PF Account Code No. and ESI
Provident Registration No. till actual completion of the contract.
Funds (and b. The contractor shall provide a list of contract Workers engaged for contract
Miscellaneous work along with their PF Account No. & ESI Registration No.
s Provisions) c. The contractor by 20th of every month shall provide a monthly statement
Act, 1961and showing recoveries of contribution and proof of remittance of provident fund
State contribution to RPFC and ESI contributions to ESI Corporation in respect of
Insurance Workers engaged in contract work.
(ESI) Act, d. The contractor shall provide copies of PF & ESI challans of monthly
1948. contributions in respect of contract workers engaged for contract work on
month to month basis.
AAI reserves the right to withhold minimum amount as detailed under, from the
running account payments, if PF / ESI contributions are not paid by the contractor
and proof to that effect have not been produced regularly on due dates. To
withhold 3% for building work & 1.5% for road/pavement work of the total
amount of work done during the period considered.
ESI & EPF amount paid to the statutory authorities by the contractor shall be
reimbursed on actual basis on submission of documentary evidence.

A.A.I. C-NIL I-NIL O-NIL Page 56


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE21

Work not to The contract shall not be assigned or sublet without the written approval of
be sublet. Engineer-in-Charge. And if the contractor shall assign or sublet his contract, or
Action in attempt to do so, or become insolvent or commence any insolvency proceedings
case of or make any composition with his creditors or attempt to do so, or if any bribe,
insolvency gratuity, gift, loan, perquisite, reward or advantage pecuniary or otherwise,
shall either directly or indirectly, be given, promised or offered by the
contractor, or any of his servants or agent to any public officer or person in the
employ of AAI in any way relating to his office or employment, or if any such
officer or person shall become in any way directly or indirectly interested in the
contract, the Engineers in Charge on behalf of the AAI shall have power to
adopt the course
specified in Clause 3 hereof in the interest of AAI and in the event of such course
being adopted, the consequences specified in the said Clause 3 shall ensue.

CLAUSE22

All sums payable by way of compensation under any of these conditions shall be
considered as reasonable compensation to be applied to the use of AAI without
reference to the actual loss or damage sustained and whether or not any damage
shall have been sustained.

CLAUSE23

Changes in Where the contractor is a partnership firm, the previous approval in writing of the
firm’s Engineer-in-Charge shall be obtained before any change is made in the
Constitution constitution of the firm. Where the contractor is an individual or a Hindu
To be undivided family business concern such approval as aforesaid shall likewise be
intimated obtained before the contractor enters into any partnership agreement where under
the partnership firm would have the right to carry out the works hereby
undertaken by the contractor. If previous approval as aforesaid is not obtained, the
contract shall be deemed to have been assigned in contravention of Clause 21
hereof and the same action may be taken and the same consequences shall ensue
as provided in the said Clause 21.

CLAUSE24

All works to be executed under the contract shall be executed under the direction
and subject to the approval in all respects of the Engineer-in-Charge who shall be
entitled to direct at what point or points and in what manner they are to be
commenced, and from time to time carried on.

A.A.I. C-NIL I-NIL O-NIL Page 57


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 25

Dispute Except where otherwise provided in the contract, all questions and disputes
Resolution relating to the meaning of the specifications, design, drawings and instruction
Mechanism here-in before mentioned and as to the quality of workmanship or materials used
and on the work or as to any other question , claim, right, matter or thing whatsoever,
Arbitration in any way arising out of or relating to the contract, designs, drawings,
specifications, estimates, instructions, orders or these conditions or otherwise
concerning the work or the execution or failure to execute the same whether
arising during the progress of the work or after the cancellation, termination,
completion or abandonment thereof shall be dealt with as mentioned hereinafter:

i. If the contractor considers any work demanded of him to be outside the


requirement of the contract, or disputes any drawing, record or decision given
in writing by the Engineer-in-Charge or if the Engineer in Charge considers
any act or decision of the contractor on any matter in connection with or
arising out of the contract or carrying out of the work, to be unacceptable and
is disputed such party shall promptly within 15 days of the arising of the
disputes request the Executive Director (Engg.)/Regional Executive
Director/Member (Plg) /Chairman, AAI as the case may be, who shall refer
the dispute to Dispute Redressal Committee (DRC) within 15 days along with
a list of disputes with amounts claimed if any, in respect of each such
disputes. The Dispute Redressal Committee (DRC) shall give the opposing
party two weeks for written response, and give its decision within a period of
60 days extendable by 30 days by consent of both the parties from the receipt
of reference from the Executive Director (Engg.)/Regional Executive
Director/Member (Plg) /Chairman, AAI. Provided that no party shall be
represented before the Dispute Redressal Committee by an advocate / legal
counsel etc.
If the Dispute Redressal Committee (DRC) fails to give its decision within
aforesaid period or any party is dis-satisfied with the decision of Dispute
Redressal Committee (DRC) or expiry of time limit given above, then either
party may within a period of 30 days from the receipt of the decision of Dispute
Redressal Committee (DRC), give notice to the Executive Director
(Engg.)/Regional Executive Director/Member (Plg) /Chairman, AAI as the case
may be for appointment of Arbitrator on prescribed proforma as per Appendix-
XVII. under intimation to the other party.
It is also a term of contract and each party invoking Arbitration must exhaust the
aforesaid mechanism of settlement of claims/disputes prior to invoking
Arbitration.
The Executive Director (Engg.)/Regional Executive Director/Member (Plg)
/Chairman, AAI shall in such case appoint the sole arbitrator or one of the three
arbitrators as the case may be within 30 days of receipt of such a request and refer
such disputes to arbitration. Wherever the Arbitral Tribunal consists of three
Arbitrators, the contractor shall appoint one arbitrator within 30 days of making
request for arbitration or of receipt of request by Engineer in Charge to Executive
Director (Engg.)/Regional Executive Director/Member (Plg) /Chairman, AAI for
appointment of arbitrator, as the case may be, and two appointed arbitrators shall
appoint the third arbitrator, who shall act as the presiding arbitrator. In the event
of
a. A party fails to appoint the second arbitrator, or
b. The two appointed arbitrators fail to appoint the Presiding Arbitrator, then
Member (Plg) / Chairman, AAI shall appoint the second or Presiding
Arbitrator as the case may be.

A.A.I. C-NIL I-NIL O-NIL Page 58


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

ii Disputes or difference shall be referred for adjudication through arbitration by


a Tribunal having Sole Arbitrator where tendered amount is Rs. 300.00 Cr or
less. Where tendered value is more than Rs. 300.00 Cr., Tribunal shall consist
of three arbitrators as above. The requirements of the arbitration and the
conciliation act, 1996 (26 of 1996) and further modified Act in 2015 and any
further statutory modifications or reenactment thereof and the rules made
thereunder and for the time being in force shall be applicable.

It is a term of this contract that the party invoking Arbitration shall give a list
of disputes with amounts, claimed, if any, in respect of each such disputes
along with the notice for appointment of Arbitrator and giving reference to the
decision of the DRC.
It is also term of this contract that any member of Arbitration Tribunal shall
be a graduate engineer with experience in handling public works, engineering
contracts at a level not lower than Chief Engineer. This shall be treated as
mandatory qualification to be appointed as Arbitrator.

Parties, before or at the time of appointment of Aarbitral Tribunal may agree


in writing for fast track arbitration as per the Arbitration and Conciliation Act,
1996 (26 of 1996) as amended in 2015.

Subject to provision in the Arbitration and Conciliation Act, 1996 (26 of 1996)
as amended in 2015 whereby the counter claims if any can be directly filed
before the arbitrator without any requirement of reference by the Appointing
Authority, the Arbitrator shall adjudicate on only such disputes as are referred
to him by the appointing authority and give separate award against each
disputes and claim referred to him and in all cases where the total amount of
the claims by any party exceed Rs. 1,00,000/-, the Arbitrator shall give
reasons for the award.
It is also a term of the contract that if any fees are payable to the arbitrator,
these shall be paid as per the Act. It is also a term of the contract that the
arbitrator shall be deemed to have entered on the reference on the date he
issues notice to both the parties calling them to submit their statement of
claims and counter statement of claims.
The place of the arbitration shall be mentioned in schedule ‘F’. In case there is
no mention of place of arbitration, the Arbitral Tribunal shall determine the
place of arbitration. The venue of the arbitration shall be such place as may be
fixed by the Arbitral Tribunal in consultation with both the parties. Failing any
such agreement, then the Arbitral Tribunal shall decide the venue.

CLAUSE 26

Contractor to The contractor shall fully indemnify and keep indemnified the Chairman AAI
indemnify against any action, claim or proceeding relating to infringement or use of any
AAI against patent or design or any alleged patent or design rights and shall pay and royalties
Patent Rights which may be payable in respect of any article or part thereof included in the
contract. In the event of any claims made under or action brought against AAI in
respect of any such matters as aforesaid, the contractor shall be immediately
notified thereof and the contractor shall be at liberty, at his own expense, to settle
any dispute or to conduct any litigation that may arise there from, provided that
the contractor shall not be liable to indemnify the AAI if the infringement of the
patent or design or any alleged patent or design right is the direct result of an
order passed by the Engineer-in-Charge in this behalf.

A.A.I. C-NIL I-NIL O-NIL Page 59


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE27

Lump sum When the estimate on which a tender is made, includes lump sum in respect of
Provisions parts of the work, the contractor shall be entitled to payment in respect of the
in Tender items of work involved or the part of the work in question at the same rates as are
payable under this contract for such items ,or if the part of work in question is
not, in the opinion of the Engineer-in-Charge payable of measurement, the
Engineer-in-Charge may at his discretion pay the lump- sum amount entered in
the estimate, and the certificate in writing of the Engineer-in-Charge shall be final
and conclusive against the contractor with regard to any sum or sums payable to
him under the provision of the clause.

CLAUSE28

Action where In the case of any class of work for which there is no such specifications as
no referred to in Clause 11, such work shall be carried out in accordance with the
specifications Bureau of Indian Standards Specifications. In case there are no such
are specified specifications in Bureau of Indian Standards, the work shall be carried out as
per manufacturers’ specifications.
In case there are no such specifications as required above, the work shall be
carried out in all respects in accordance with the instructions and requirements
of the Engineer-in-Charge.

CLAUSE 29

With-holding i. Whenever any claims for payment of a sum of money arises out of or under
and lien in the contract or against the contractor, the Engineer-in-Charge or the AAI shall
respect of be entitled to withhold and also have a lien to retain such sum or sums in
sums due from whole or in part from the security, if any deposited by the contractor and for
contractor the purpose aforesaid, the Engineer-in-Charge or the AAI shall be entitled to
withhold the security deposit if any, furnished as the case may be and also
have a lien over the same pending finalization or adjudication of any such
claim. In the event of the security being insufficient to cover the claimed
amount or amounts or if no security has been taken from the contractor, the
Engineer-in-Charge or the AAI shall be entitled to withhold and have lien to
retain to the extent of such claimed amount or amounts referred to above
from any sum or sums found payable or which may at any time thereafter
become payable to the contractor under the same contract or any other
contract with the Engineer-in Charge of the AAI or any contracting person
through the Engineer-in-Charge pending finalization of adjudication of any
such claim.
It is an agreed term of the contract that the sum of money or moneys so
withheld or retained under the lien referred to above by the Engineer-in-
Charge or AAI will be kept withheld or retained as such by the Engineer-in-
Charge or AAI till the claim arising out of or under the contract is determined
by the arbitrator. (if the contract is governed by the arbitration clause) or by
the competent court, as the case may be and that the contractor will have no
claim for interest or damages whatsoever on any account in respect of such
withholding or retention under the lien referred to above and duly notified as
such to the contractor. For the purpose of this clause, where the contractor is a
partnership firm or a limited company, the Engineer-in-Charge or the AAI
shall be entitled to withhold and also have a lien to retain towards such
claimed amount or amounts in whole or in part from any sum found payable
to any partner/limited company as the case may be, whether in his individual

A.A.I. C-NIL I-NIL O-NIL Page 60


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

capacity or otherwise.
ii. AAI shall have the right to cause an audit and technical examination of the
works and the final bills of the contractor including all supporting vouchers,
abstract, etc,. to be made after payment of the final bill and if as a result of
such audit and technical examination any sum is found to have been overpaid
in respect of any work done by contractor under the contract or any work
claimed to have been done by the him under the contract and found not to
have been executed, the contractor shall be liable to refund the amount of
over payment and it shall be lawful for AAI to recover the same from him in
the manner prescribed in sub-clause (i) of this clause or in any other manner
legally permissible; and if it is found that the contractor was paid less than
what was due to him under the contract in respect of any work executed by
him under it, the amount of such under payment shall be duly paid by AAI to
the contractor, without any interest thereon whatsoever.
Provided that the AAI shall not be entitled to recover any sum overpaid, nor
the contractor shall be entitled to payment of any sum paid short where such
payment has been agreed upon between the Executive Director Engineering /
General Manager Engineering on the one hand and the contractor on the other
under any term of the contract permitting payment for work after assessment
by the Executive Director Engineering / General Manager Engineering.

CLAUSE 29 A

Lien in respect i. Any sum of money due and payable to the contractor (including the security
of claims in deposit refundable to him) under the contract may be withheld or retained by
other Contracts way of lien by the Engineer-in-Charge or the AAI or any other contracting
person or persons through Engineer-in-Charge against any claim of the
Engineer-in-Charge or AAI or such other person or persons in respect of
payment of a sum of money arising out of or under any other contract made
by the contractor with the Engineer-in-Charge or the AAI or with such other
person or persons.
ii. It is an agreed term of the contract that the sum of money so withheld or
retained under this clause by the Engineer-in-Charge or the AAI will be kept
withheld or retained as such by the Engineer-in-Charge or the AAI or till his
claim arising out of the same contract or any other contract is either mutually
settled or determined by the arbitration clause or by the competent court, as
the case may be and that the contractor shall have no claim for interest or
damages whatsoever on this account or on any other ground in respect of any
sum of money withheld or retained under this clause and duly notified as such
to the contractor.

CLAUSE 30

Employment of i. The contractor shall not employ coal mining or controlled area labour falling
coal mining or under any category whatsoever or in connection with the work or recruit
controlled area labour from area within a radius of 32 km (20 miles) of the controlled area.
labour not Subject as above the contractor shall employ imported labour only i.e.,
permissible deposit imported labour or labour imported by contractors from area, from
which import is permitted.
ii. Where ceiling price for imported labour has been fixed by State or Regional
Labour Committees not more than that ceiling price shall be paid to the
labour by the contractor.
iii. The contractor shall immediately remove any labourer who may be pointed

A.A.I. C-NIL I-NIL O-NIL Page 61


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

out by the Engineer-in-Charge as being a coal mining or controlled area


labourer. Failure to do so shall render the contractor liable to pay to AAI a
sum calculated at the rate of Rs.10/- per day per labourer. The certificate of
the Engineer-in –Charge about the number of coal mining or controlled area
labourer and the number of days for which they worked shall be final and
binding upon all parties to this contract.
iv. It is declared and agreed between the parties that the aforesaid stipulation in
this clause is one in which the public are interested within the meaning of the
exception in Section 74 of Indian Contract Act, 1872.
Explanation :-
Controlled area mean the following areas:
Districts of Dhanbad, Hazaribagh, Jamtara- Sub-Division under Santhal
Pargana Commissionery, District of Bankuara, Birbhum, Burdwan, District of
Bilaspur. Any other area which may be declared a Controlled Area by or with
the approval of the Central Government.

CLAUSE 31

Unfiltered The contractor(s) shall make his/their own arrangements for water required for
water supply the work and nothing extra will be paid for the same. This will be subject to the
following conditions.
i. That the water used by the contractor (s) shall be fit for construction purposes
to the satisfaction of the Engineer-in-Charge.
ii. The Engineer-in-Charge shall make alternative arrangements for supply of
water at the risk and cost of contractor (s) if the arrangements made by the
contractor (s) for procurement of water are in the opinion of the Engineer-in-
Charge, unsatisfactory.

CLAUSE 31A

Departmental Water if available may be supplied to the contractor by the department subject to
water supply, if the following conditions:-
available i. The water charges @1% shall be recovered on gross amount of the work
done.
ii. The contractor(s) shall make his/their own arrangement of water connection
and laying of pipelines from existing main of source of supply.
iii. The Department do not guarantee to maintain uninterrupted supply of water
and it will be incumbent on the contractor (s) to make alternative
arrangements for water at his/their own cost in the event of any temporary
break down in the AAI’s water main so that the progress of his/their work is
not held up for want of water. No claim of damage or refund of water charges
will be entertained on account of such break down.

CLAUSE 32

Alternate water i. Where there is no piped water supply arrangement and the water is taken by the
arrangements contractor from the wells or hand pump constructed by the AAI, no charge shall
be recovered from the contractor or that account. The contractor shall, however,
draw water at such hours of the day that it does not interfere with the normal use
for which the hand pumps and well are intended. He will also be responsible for
all damage and abnormal repairs arising out of his use, the cost of which shall
be recoverable from him. The Engineer-in-Charge shall be the final
authority to determine the cost recoverable from the contractor on this
account and his decision shall be binding on the contractor.

A.A.I. C-NIL I-NIL O-NIL Page 62


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

ii. The contractor shall be allowed to construct temporary wells in AAI land for
taking water for construction purposes only after he has got permission of the
Engineer-in-Charge in writing. No charges shall be recovered from the
contractor on this account but the contractor shall be required to provide
necessary safety arrangements to avoid any accidents or damage to adjacent
buildings, roads and service lines. He shall be responsible for any accidents or
damage caused due to construction and subsequent maintenance of the wells
and shall restore the ground to its original condition after the wells are
dismantled on completion of the work.

CLAUSE 33
Return of Notwithstanding anything contained to the contrary in this contract, where any
Surplus materials for the execution of the contract are procured with the assistance of
materials AAI either by issue from AAI stocks or purchase made under orders or permits or
licenses issued by AAI, the contractor shall hold the said materials economically
and solely for the purpose of the contract and not dispose of them without the
written permission of the AAI and return, if required by the engineer-in-Charge,
all surplus or unserviceable materials that may be left with him after the
completion of the contract or at its termination for any reason whatsoever on
being paid or credited such prices as the Engineer-in-Charge shall determine
having due regard to the condition of the materials. The price allowed to the
contractor however shall not exceed the amount charged to him excluding the
element of storage charges. The decision of the Engineer-in-Charge shall be final
and conclusive. In the event of breach of the aforesaid condition, the contractor
shall in addition to throwing himself open to action for contravention of the terms
of the license or permit and / or for criminal breach of trust, be liable to AAI for
all moneys, advantages or profits resulting or which in the usual course would
have resulted to him by reason of such breach.

CLAUSE 34
Hire of plant & i. The Contractor shall arrange at his own expense all tools, plant, machinery and
Machinery equipment(hereinafter referred to as T&P) required for execution of the work
except for the Plant & Machinery listed in Schedule ‘C’ and stipulated for
issue to the contractor. If the contractor requires any item of T&P on hire from
the T&P available with the AAI over and above the T&P stipulated for issue,
the AAI will, if such item is available, hire it to the contractor at rates to be
agreed upon between him and the Engineer-in-charge. In such a case, all the
conditions hereunder for issue of T & P shall also be applicable to such T&P
as is agreed to be issued.
ii. Plant & Machinery when supplied on hire charges shown in Schedule ‘C’ shall
be made over and taken back at the departmental equipment yard / shed shown
in Schedule ‘C’ and the contractor shall bear the cost of carriage from the
place of issue to the site of work and back. The contractor shall be responsible
to return the plant and machinery with condition in which it was handed over
to him, and he shall be responsible for all damage caused to the said plant and
machinery at the site of work or elsewhere in operation and otherwise during
transit including damage to or loss of plant and for all losses due to his failure
to return the same soon after the completion of the work for which it was
issued. The Engineer-in-charge shall be the sole judge to determine the
liability of the contractor and its extent in this regard and his decision shall be
final and binding on the contractor.

A.A.I. C-NIL I-NIL O-NIL Page 63


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

iii. The plant and machinery as stipulated above will be issued as and when
available and if required by the contractor. The contractor shall arrange his
programme of work according to the availability of the plant and machinery
and no claim, whatsoever, will be entertained from him for any delay in supply
by the department.
iv. The hire charges shall be recovered at the prescribed rates from and inclusive
of the date the plant and machinery made over upto and inclusive of the date of
the return in good order even though the same may not have been working for
any cause except major breakdown due to no fault of the contractor or faulty
use requiring more than three working days continuously (excluding
intervening holidays and Sundays) for bringing the plant in order. The
contractor shall immediately intimate in writing to the Engineer-in-charge
when any plant or machinery gets out of order requiring major repairs as
aforesaid. The Engineer-in- charge shall record the date and time of receipt of
such intimation in the log sheet of the plant or machinery. Based on this if the
breakdown before lunch period or major breakdown will be computed
considering half a day’s breakdown on the day of complaint. If the breakdown
occurs in the post lunch period of major breakdown will be computed starting
from the next working day. In case of any dispute under this clause, the
decision of the Executive Director (Engg) /General Manager (Engg) shall be
final and binding on the contractor.
v. The hire charges shown above are for each day of 8 hours (inclusive of the one
hour lunch break) or part thereof.
vi. Hire charges will include service of operating staff as required and also supply
of lubricating oil and stores for cleaning purposes. Power fuel of approved
type, firewood, kerosene oil etc. for running the plant and machinery and also
the full time chowkidar for guarding the plant and machinery against any loss
or damage shall be arranged by the contractor who shall be fully responsible
for the safeguard and security of plant and machinery. The contractor shall on
or before the supply of plant and machinery sign an agreement indemnifying
the Department against any loss or damage caused to the plant and machinery
either during transit or at site of work.
vii. Ordinarily, no plant and machinery shall work for more than 8 hours a day
inclusive of one hour lunch break. In case of an urgent work however, the
Engineer-incharge may, at his discretion, allow the plant and machinery to
be worked for more than normal period of 8 hours a day. In that case, the
hourly hire charges for overtime to be borne by the contractor shall be 50%
more than the normal proportionate hourly charges (1/8th of the daily
charges) subject to a minimum of half day’s normal charges on any
particular day. For working out hire charges for over time, a period of half
an hour and above will be charged as one hour and a period of less than half
an hour will be ignored.
viii. The contractor shall release the plant and machinery every seventh day for
periodical servicing and / or wash out which may take about three to four
hours or more. Hire charges for full day shall be recovered from the
contractor for the day of servicing / wash out irrespective of the period
employed in servicing.
ix. The plant and machinery once issued to the contractor shall not be returned
by him on account of lack of arrangements of labour and materials, etc. on
his part, the same will be returned only when they are required for major
repairs or when in the opinion of the Engineer-in-charge, the work or a
portion of work for which the same was issued is completed.
x. Log Book for recording the hours of daily work for each of the plant and
machinery supplied to the contractor will be maintained by the Department
and will be countersigned by the contractor or his authorised agent daily. In

A.A.I. C-NIL I-NIL O-NIL Page 64


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

case the contractor contests the correctness of the entries and / or fails to sign
the Log Book, the decision of the Engineer-in-charge shall be final and
binding on him. Hire charges will be calculated according to the entries in
the Log Book and will be binding on the contractor. Recovery on account of
hire charges for road rollers shall be made for the minimum number of days
worked out on the assumption that a roller can consolidate per day and
maximum quantity of materials or area surfacing as noted against each in the
annexed statement (see attached annexure).
xi. In the case of concrete mixers, the contractors shall arrange to get the hopper
cleaned and the drum washed at the close of the work each day or each
occasion. (a) In case rollers for consolidation are employed by the contractor
himself, log book for such rollers shall be maintained in the same manner as
is done in case of departmental rollers, maximum quantity of any items to be
consolidated for each roller-day shall also be same as in Annexure to Clause
34(x). For less use of rollers, recovery for the less roller days shall be made
at the stipulated issue rate.
xii. The contractor shall be responsible to return the plant and machinery in the
condition in which it was handed over to him and he shall be responsible for
all damage caused to the said plant and machinery at the site of work or
elsewhere in operation or otherwise or during transit including damage to or
loss of parts, and for all losses due to his failure to return the same soon after
the completion of the work for which it was issued. The Engineer-in-charge
shall be the sole judge to determine the liability of the contractor and its
extent in this regard and his decision shall be final and binding on the
contractor.
xiii. The contractor will be exempted from levy of any hire charges for the
number of days he is called upon in writing by the Engineer-in-charge to
suspend execution of the work, provided AAI’s plant and machinery in
question have, in fact, remained idle with the contractor because of the
suspension.
xiv. In the event of the contractor not requiring any item of plant and machinery
issued by AAI though not stipulated for issue in Schedule ‘C’ any time after
taking delivery at the place of issue, he may return it after two days written
notice or at any time without notice if he agrees to pay hire charges for two
additional days without, in any way, affecting the right of the Engineer-in-
charge to use the said plant and machinery during the said period of two
days as he likes including hiring out to a third party.

CLAUSE 35

Condition i. The contractor undertakes to make arrangement for the supervision of the
relating to use work by the firm supplying the tar or bitumen used.
of asphaltic ii. The contractor shall collect the total quantity of tar or bitumen required for
materials the work as per standard formula, before the process of painting is started
and shall hypothecate it to the Engineer-in-Charge. If any bitumen or tar
remains unused on completion of the work on account of lesser use of
materials in actual execution of for reasons other than authorised changes of
specifications and abandonment of portion of work, a corresponding
deduction equivalent to the cost of unused materials as determined by the
Engineer-in-Charge shall be made and the material return to the contractors.
Although the materials are hypothecated to AAI, the contractor undertakes
the responsibility for their proper watch, safe custody and protection against
all risks. The materials shall not be removed from site of work without the
consent of the Engineer-in-Charge in writing.

A.A.I. C-NIL I-NIL O-NIL Page 65


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

iii. The contractor shall be responsible for rectifying defects noticed within a
year from the date of completion of the work and the portion of the security
deposit relating asphaltic work shall be refunded after the expiry of this
period.

CLAUSE 36

Employment of Contractors Superintendence, Supervision, Technical staff & Employees


Technical Staff i. The contractor shall provide all necessary superintendence during execution of
and employees the work and all along thereafter as may be necessary for proper fulfilling of
the obligations under the contract.

The Contractor shall immediately after receiving letter of acceptance of the


tender and before commencement of the work, intimate in writing to the
Engineer-in-Charge, the name (s), qualifications experience, age, address (s)
and other particulars along with certificates, of the principal technical
representative to be charge of the work and other technical representative (s)
who will be supervising the work. Minimum requirement of such technical
representative (s) and their qualifications and experience shall not be lower
than specified in schedule ‘F”. The Engineer-in-Charge shall within 3 days
of receipt of such communication intimate in writing his approval or
otherwise of such a representative (s) to the contractor. Any such approval
may at any time be withdrawn and in case of such withdrawal, the contractor
shall appoint another such representative (s) according to the provisions of
this clause. Decision of the tender accepting authority shall be final and
binding on the contractor in this respect. Such a principal technical
representative and other technical representative (s) shall be appointed by the
contractor soon after receipt of the approval from Engineer-in-charge and
shall be available at site before start of work.

All the provisions applicable to the principal technical representative under


the clause will also be applicable to other technical representative(s). The
principal technical representative and other technical representative (s) shall
be present at the site of work for supervision at all times when any
construction activity is in progress and also present himself/themselves, as
required to the Engineer-in-Charge and / or his designated representative to
take instructions. Instructions given to the principal technical representative
or other technical representative (s) shall be deemed to have the same force
as if these have been given to the contractor. The Principal Technical
Representative and other technical representatives shall be actually available
at site fully during all stages of execution work, during recording / checking
/ test checking of measurements of works whenever so required by the
Engineer-in-Charge and shall also note down instructions conveyed by the
Engineer-in-Charge or his designated representative (s) in the site order book
and shall affix his/their signature in token of noting down the instructions
and in token of acceptance of measurements / checked measurements / test
checked measurements. The representative (s) shall not look after any other
work. Substitutes, duly approved by engineer – in-Charge of the work in
similar manner as aforesaid shall be provided in event of absence of any of
the representative (s) by more than two days. If the Engineer–in–Charge,
whose decision in this respect is final and binding on the contractor, is
convinced that no such technical representative (s) is/are effectively
appointed or is/are effectively attending or fulfilling the provision of this
clause, a recovery (non-refundable) shall be effected from the contractor as
specified in Schedule ‘F’ and the decision
A.A.I. C-NIL I-NIL O-NIL Page 66
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

of the Engineer–in- Charge as recorded in the site order book and


measurement recorded checked/test checked in Measurement Books shall be
final and binding on the contractor. Further if the contractor fails to appoint
suitable technical Principal technical representative and / or other technical
representative (s) and if such appointed persons are not effectively present or
are absent by more than two days without duly approved substitute or do not
discharge their responsibility satisfactorily, the Engineer–in–Charge shall
have full powers to suspend the execution of the work until such date as
suitable other technical representative (s) is / are appointed and the
contractor shall be held responsible for the delay so caused to the work. The
contractor shall submit a certificate of employment of the technical
representative (s) (in the form of copy of Form- 16 or CPF deduction issued
to the Engineer employed by him) along with every running account bill /
final bill and shall produce evidence if at any times so required by the
Engineer– in–Charge.

ii. The contractor shall provide and employ on the site only such technical
assistants as are skilled, and experienced in their respective fields and such
foremen and supervisory staff as are competent to give proper supervision to
the work. The contractor shall provide and employ skilled, semi-skilled and
unskilled labour as is necessary for proper and timely execution of the work.
The Engineer-in-Charge shall be at liberty to object to and require the
contractor to remove from the works any person who in his opinion
misconducts himself, or is incompetent or negligent in the performance of
his duties or whose employment is otherwise considered by the Engineer-in
Charge to be undesirable. Such person shall not be employed again at works
site without the written permission of the Engineer-in-Charge and the
persons so removed shall be replaced as soon as possible by competent
substitutes.

iii. The contractor shall not change his engineer/supervisory staff after approval
of the Engineer-In-Charge. If Contractor wants to replace any of his staff
due to unavoidable circumstances, he will seek permission of Engineer-In-
Charge indicating reasons for such change, qualification and experience of
the alternative employee suggested by him. The qualification and experience
of the alternative staff shall not be inferior to the person employed earlier.

CLAUSE 37

Levy/Taxes/ 1. Taxes:
Royalty/ Land
a. Rates to be quoted by the parties should be inclusive of all taxes, duties,
License fee
CESS, fee, royalty charges etc. levied under any statute but exclusive of
payable by
GST for all the items.
Contractor
b. However GST, as applicable, shall be paid to the contractor, for any
taxable supply / services / construction rendered by the agency to AAI,
against a valid GST invoice as per terms and conditions of the contract.
c. In case supplies / services / works involve imports; the same should be
identified separately. Basic Custom Duty & IGST will be paid directly by
AAI by utilizing EPCG license / Duty Credit Scrip under Service Export
from India Scheme (SEIS) of Govt. of India.

A.A.I. C-NIL I-NIL O-NIL Page 67


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

2. Royalty:
a. The contractor shall at his own expense, provide all materials required for
the works other than those which are to be supplied by AAI. The
contractor shall deposit royalty and obtain necessary permit for
collection of stone, sand, red bajri, kankar etc. from the local authority in
the matter and will abide by the notification issued by Central Govt. /
State Government / Local State Authorities as applicable from time to
time in this regard. The contractor is also bound to allow deduction from
his bills any difference in statutory taxes/royalty and penalty proposed by
Local State Authorities to AAI till finalization of settlement of all
demands in this regard by Central / State Govt.
b. This will also be applicable to forest produce.
c. If pursuant to or under any law, notification or order any royalty, cess or
the like becomes payable by the AAI and does not any time become
payable by the contractor to the State Government. Local authorities in
respect of any material used by the contractor in the works then in such a
case, it shall be lawful to the AAI and it will have the right and be
entitled to recover the amount paid in the circumstances as aforesaid
from dues of the contractor.
3. License fee for land
a. The contractor shall be liable to pay license fee for the land allotted by
AAI for installation of plants, labour camp, cement godown and site
office at AAI prevailing rates of license fee for unpaved land at the time
of call of tender.
b. In addition a security deposit at the rate of Rs 500/- per sqm in the form
of DD/BG shall also be deposited by the contractor. In case contractor
do not deposit security deposit same shall be deducted from Ist Running
Account Bill.
c. Such security deposit shall be released only after allotted land has been
fully vacated by the contractor to entire satisfaction of Engineer-in-
Charge.

CLAUSE 38
Conditions for 1. Rates to be quoted by the parties should be inclusive of all taxes, duties, CESS,
reimbursement fee, royalty charges etc. levied under any statute applicable on last stipulated
of levy/taxes if date of receipt of tender including extension if any but exclusive of GST. No
levied after adjustment i.e. increase or decrease shall be made for any variation in the rate
receipt of of GSI Building and Other Construction Workers Welfare Cess or any tax, levy
tenders or Cess applicable on inputs.
However, effect of variation, as per Govt. order after the last date of receipt of
tender including extension if any, in rates of GST or Building and Other
Construction Workers Welfare Cess or imposition or repeal of any other tax, levy
or Cess applicable on output of the works contract shall be adjusted on either
side, increase or decrease.
Provided further that for Building and Other Construction Workers Welfare Cess
or any tax (other than GST), levy or Cess varied or imposed after the last date of
receipt of tender including extension if any, any increase shall be reimbursed to
the contractor only if the contractor necessarily and properly pays such increased
amount of taxes / levies / Cess.
Provided further that such increase in tax / levy / Cess including GST shall not
reimbursed if made in the extended period of contract for which the contractor
alone is responsible for delay as determined by authority for extension of time
under Clause 5 in Schedule F.
A.A.I. C-NIL I-NIL O-NIL Page 68
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

2. The contractor shall keep necessary books of accounts and other documents for
the purpose of this condition as may be necessary and shall allow inspection of
the same by a duly authorised representative of AAI or the Engineer-in-Charge
and further shall furnish such other information /document as the Engineer-in-
Charge may require from time to time.
3. The contractor shall, within a period of 30 days of the imposition of any such
further tax or levy or Cess, give a written notice thereof to the Engineer-in-
charge that the same is given pursuant to the condition, together with all
necessary information / documents relating thereto.

CLAUSE 39

Termination of Without prejudice to any of the rights or remedies under this contract, if the
contract on contractor dies, the Engineer-in-charge on behalf of the AAI shall have the option
death of of terminating the contract without compensation to the contractor.
contractor

CLAUSE 40

If relative The contractor shall not be permitted to tender for works in AAI wherein his near
working in AAI relative is posted as an Officer responsible for award and execution of work. He
then the shall also intimate the names of persons who are working with him in any
contractor not capacity or / are subsequently employed by him and who are near relatives to any
allowed to officer of AAI. Any breach of this condition by the Contractor would render him,
tender. the contract liable to be rejected at any stage.

NOTE: By the term “near relatives” is meant wife, husband, parents and grand
parents, children and grandchildren, brothers and sisters, uncles, aunts and
cousins and their corresponding in-laws.

CLAUSE 41

No any officer Engineer or any officer employed in engineering or administrative duties in an


in Department engineering department of AAI shall not work as a contractor or employee of
of Engineering contractor for a period of one year after his retirement from AAI service without
to work as the prior permission of AAI in writing. This contract is liable to be cancelled if
contractor either the contractor or any of his employees is found at any time to be such a
within one year person who had not obtained the permission of AAI as aforesaid, before
of retirement submission of the tender or engagement in the contractor’s service, as the case
may be.

A.A.I. C-NIL I-NIL O-NIL Page 69


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 41(a)

Integrity Pact Signing of Integrity Pact (As per Appendix XVIII) is mandatory for every
and bidder/contractor if provided so in Schedule F.
Independent All tenderers shall have to submit an undertaking as per Appendix XVIII along
External with tender documents. AAI shall appoint Independent External Monitor(s) to
Monitor. oversee effective implementation of Integrity Pact for such works / supplies. For
this purpose, a panel of Independent External Monitors shall be constituted by the
Authority in concurrence with Central Vigilance Commission (CVC).
i. The Contractor / Supplier shall have to act in accordance with the conditions
laid down in the integrity pact.
a. Signing of Integrity Pact is mandatory for every Bidder / Contractor in
this procurement / bid process the signed original pact to be send to
the office of Bid Manager and should reach before the due date
mentioned in NIT.
b. The Bidder / contractor shall commit itself to ensure taking all
measures necessary to prevent corrupt practices, unfair means and
illegal activities during any stage of its bid or during any pre-contract
or post-contract stage as specified in section 3 of the integrity pact.
c. Any breach of the aforesaid provisions by the Bidder or any one
employed by it or acting on its behalf (whether with or without the
knowledge of the Bidder) shall entitle the authority to take all or any
one of the action as specified in section 6 of the integrity pact.

ii. In case any violation of above conduct is established, AAI reserves right to
take following actions.
a. If contractor commits a violation of its commitments and obligations
under the Integrity Pact Program during bidding process, he shall be
liable for disqualification from tender process and forfeiture of his
Earnest Money Deposit / Bid Security.
b. In case of violation of the Integrity Pact after award of the contract,
Authority is entitled to terminate the contract and shall be entitled to
demand and recover from the contractor damages equivalent to 5% of
the contract value or the amount equivalent to Security Deposit or
Performance Bank Guarantee, whichever is higher.
c. Authority may initiate appropriate proceedings against the contractor.
d. Contractor will be liable to pay damages as determined by the
Authority.
e. Contractor against whom an action for violation of its commitments
and obligations has been taken earlier again commits a violation, the
Authority is entitled to debar such contractor for future tender /
contract processes for a period as deemed fit.
f. A violation is considered to have occurred if the Authority is fully
satisfied with the available documents and evidence submitted along-
with Independent External Monitor’s recommendations / suggestions
that no reasonable doubt exist in the matter.
iii. Person signing IP shall not approach the Courts while representing the
matters to IEMs and he / she will await their decision in the matter.

A.A.I. C-NIL I-NIL O-NIL Page 70


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE42

Return of i. After completion of the work and also at any intermediate stage in the event
material and of non-reconciliation of materials issued, consumed and in balance – (see
recovery for Clause 10), Theoretical quantity of materials issued by the AAI for use in the
excess material work shall be calculated on the basis and method given hereunder;
issued. i. Quantity of cement & bitumen shall be calculated on the basis of
quantity of cement & bitumen required for different items of work as
shown in the Schedule of Rates mentioned in Schedule ‘F’. In case any
item is executed for which standard co-efficient for the consumption of
cement or bitumen are not available in the above mentioned schedule /
statement or cannot be derived from the same shall be calculated on the
basis of standard formula to be laid down by the Engineer-in-Charge.
ii. Theoretical quantity of steel reinforcement or structural steel sections
shall be taken as the quantity required as per design or as authorised by
Engineer-in- Charge, including authorised lappages, chairs etc. plus 3%
wastage due to cutting into pieces, such theoretical quantity being
determined and compared with the actual issues each diameter-wise,
section wise and category wise separately.
iii. Theoretical quantity of G.I. & C.I. or other pipes, conduits, wires and
cables pig lead and G.I. / M.S. sheets shall be taken as quantity actually
required and measures plus 5% for wastage due to cutting into pieces
(except in the case of G.I./M.S. sheets it shall be 10%), such
determination & comparison being made diameter-wise & category-
wise.
iv. For any other material as per actual requirements.
ii. Over the theoretical quantities of materials so computed a variation shall be
allowed as specified in Schedule ‘F’. The difference in the net quantities of
material actually issued to the contractor and the theoretical quantities
including such authorised variation, if not returned by the contractor or if not
fully reconciled to the satisfaction of the Engineer-in-Charge within fifteen
days of the issue of written notice by the Engineer-in-Charge to this effect
shall be recovered at the rates specified in Schedule ‘F’, without prejudice to
the provision of the relevant conditions regarding return of materials
governing the contract. Decision of Engineer-in-Charge in regard to
theoretical quantities of materials, which should have been actually used as
per the Annexure of the standard schedule of rates and recovery at rates
specified in Schedule ‘F’ shall be final and binding on the contractor. For
non scheduled items, the decision of the Engineer – in - charge regarding
theoretical quantities of materials which should have been actually used,
shall be final and binding on the contractor.
g. The said action under this clause is without prejudice to the right of the AAI
to take action against the contractor under any other conditions of contract
for not doing the work according to the prescribed specifications.
h. For materials brought by the contractor for use in item of work at site,
similar theoretical consumption shall be prepared and submitted to the
Engineer-in-Charge for verification. If it is found that material consumed in
the work is less than the theoretical consumption after taking into account
permissible minus variation, the recovery for corresponding material shall be
effected as per rates specified in schedule ‘F’ under Clause 42.

A.A.I. C-NIL I-NIL O-NIL Page 71


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 43

Compensation The work (whether fully constructed or not) and all materials, machines, tools
during warlike and plants scaffolding, temporary buildings and other things connected therewith
situations / act shall be at the risk of the contractor until the work has been delivered to the
of terrorism Engineer-in-Charge and a certificate from him to that effect obtained. In the event
of the work or any materials properly brought to the site for incorporation in the
work being damaged or destroyed in consequence of hostilities or warlike
operation or act of terrorism, the contractor shall when ordered (in writing) by the
Engineer-in-Charge to remove any debris from the site, collect and properly stack
or remove in store all serviceable materials salvaged from the damaged work and
shall be paid at the contract rates in accordance with the provision of this
agreement for the work of clearing the site of debris, stacking or removal of
serviceable material and for reconstruction of all works ordered by the Engineer-
in-Charge, such payments being in addition to compensation upto the value of the
work original executed before being damaged or destroyed and not paid for.
In case of works damaged or destroyed but not already measured and paid for, the
compensation shall be assessed by the Engineer-in charge upto Rs.5,000/- and by
the Executive Director Engg. concerned for a higher amount. The contractor shall
be paid for the damages / destruction suffered and for restoring the material at the
rate based on analysis of rates tendered for in accordance with the provision of
the contract. The certificate of the Engineer-in- Charge regarding the quality and
quantity of materials and the purpose for which they were collected shall be final
and binding on all parties to this contract.
Provided always that no compensation shall be payable for any loss in
consequence of hostilities or warlike operation (a) unless the contractor had taken
all such precautions against air raid as are deemed necessary by the A.R.P.
Officers or the Engineer-in- Charge (b) for any material etc. not on the site of the
work or for any tools plant, machinery, scaffolding, temporary building and other
things not intended for the work.
In the event of the contractor having to carry out reconstruction as aforesaid, he
shall be allowed such extension of time for its completion as is considered
reasonable by the Engineer – in - charge.

CLAUSE 44

Apprentices The contractor shall comply with the provisions of the Apprentices Act, 1961 and
Act provisions the rules and orders issued thereunder from time to time. If he fails to do so, his
to be complied failure will be a breach of the contract and the Executive Director Engg. / General
with Manager (Engg.) may, in his discretion, cancel the contract. The contractor shall
also be liable for any pecuniary liability arising on account of any violation by
him of the provisions of the said Act.
CLAUSE 45

Release of Security Deposit of the work shall not be refunded till the contractor produces a
security deposit clearance certificate from the Labour Officer. As soon as the work is virtually
after labour complete the contractor shall apply for the clearance certificate to the Labour
clearance Officer under intimation to the Engineer-in-Charge. The Engineer-in-Charge, on
receipt of the said communication, shall write to the Labour Officer to intimate if
any complaint is pending against the contractor in respect of the work. If no
complaint is pending, on record till after 3 months after completion of the work
and / or no communication is received from the Labour Officer to this effect till
six months after the date of completion, it will be deemed to have received the
clearance certificate and the Security Deposit will be released if otherwise due.
A.A.I. C-NIL I-NIL O-NIL Page 72
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

CLAUSE 46

Contractor’s i. From commencement to completion of the Works, the Contractor shall take
Liability and full responsibility for the case thereof and for taking precautions to prevent
Insurance of loss or damage and to minimize loss or damage to the greatest extent
Works possible and shall be liable for any damage or loss that may happen to the
Works or any part thereof and all AA l’s T & P from any cause whatsoever
(save and except the Excepted Risks) and shall at his own cost repair and
make good the same so that at completion, the Works and all AAI’s T & P
shall be in good order and condition and in conformity in every respect with
the requirements of the Contract and instructions of the Engineer-in-Charge.

ii. In the event of any loss or damage to the Works or any Part thereof or to any
T & P, to any material or articles at the Site from any of the Excepted Risks
the following provisions shall have effect:
a. The Contractor shall, as may be directed in writing by the Engineer-in-
Charge, remove from the Site any debris and so much of the works as
shall have been damaged, taking to AAI’s store such AAI’s T & P,
articles and/or materials as may be directed;
b. The contractor shall, as may be directed in writing by the Engineer-in-
Charge, proceed with the erection and completion of the Works under
and in accordance with the provisions and Conditions of the Contract;
and
iii. Provided always that the Contractor shall not be entitled to payment under
the above provisions in respect of so much loss or damage as has been
occasioned by any failure on his part to perform his obligation under the
Contract or not taking precautions to prevent loss or damage or minimize the
amount of such loss or damage.
iv. Without limiting its obligations and responsibilities under other clauses of
General Conditions of Contracts ,the contractor at his own cost shall insure
,in the joint name of AAI and the contractor, against all losses or damages
from whatever cause, arising (other than the accepted risks )for which he is
responsible under the terms of the contract and in such manner that the AAI
and the contractor are covered during the period of construction of works
and any loss or damage occasioned by the contractor in the course of any
operation carried out by them for the purpose of complying with its
obligations of defects liability clause hereof;
a. All works including temporary works to their full value executed from
time to time.
b. The construction materials and equipments to their full value brought on
to the site by the contractor.
v. The Contractor shall indemnify and keep indemnified AAI against all losses
and claims for injuries or damage to any persons or any property whatsoever
which may arise out of or in consequence of the construction and
maintenance of Works and against all claims, demands proceedings, damage
costs, charges and expenses whatsoever in respect of or in relation thereto.
vi. Before commencing execution of the work, the Contractor shall, without in
any way limiting his obligations and responsibilities under this condition,
insure at his own cost against any damage, loss or injury which may occur to
any AAI property, or to any person for at least the minimum amount of
Rs. 1.00 lakh with unlimited number of occurrences (including any
employee of AAI) by or arising out of carrying out of the Contract.
vii. The contractor shall at all times indemnify AAI against all claims, damages
or compensation under the provisions of Payment or Wages Act, 1936,

A.A.I. C-NIL I-NIL O-NIL Page 73


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

Minimum Wages Act, 1948, Employer’s Liability Act, 1938, the


Workmen’s Compensation Act, 1923, Industrial Disputes Act, 1947 and the
Maternity Benefit Act, 1961 or any modifications thereof or any other law
relating thereto and rules made there under from time to time or as a
consequence of any accident or injury to any workman or other persons in or
about the Works, whether in the employment of the Contractor or not, his
agents or servants, and also against all costs, charges and expenses of any
suit, action or proceedings arising out of such accident or injury and against
all sum or sums which may with the consent of the Contractor be paid to
compromise or compound any claim. Without limiting his obligations and
liabilities as above provided, the Contractor shall insure against all claims,
damages or compensation payable under the Workmen’s Compensation Act,
1923 or any modification thereof or any other law relating thereto.
viii. All insurance mentioned above shall be effected with any subsidiary of the
General Insurance Company of India or by a company approved by the
Insurance Regulatory Authority of India.
ix. The aforesaid insurance policy / policies shall provide that they shall not be
cancelled till the Engineer-in-Charge has agreed to their cancellation in
writing.
x. The Contractor shall prove to the Engineer-in-Charge from time to time that
he has taken out all the insurance policies referred to above and has paid the
necessary premiums for keeping the policies alive till expiry of the Defects
Liability Period. A self-certified copy of such policies is required to be
submitted to the Engineer-in-charge.
xi. The Contractor shall ensure that similar insurance policies are taken out by
his subcontractors (if any) and shall be responsible for any claims or losses
to AAI resulting from their failure to obtain adequate insurance protection in
connection thereof. The contractor shall produce or cause to be produced by
his subcontractor (if any) as the case may be, the relevant policy or policies
and premiums receipts as and when required by the Engineer-in-Charge. A
self-certified copy of such policies is required to be submitted to the
Engineer-in-charge.
xii. If the Contractor and/or his subcontractor (if any) shall fail to effect and
keep in force the insurance referred to above or any other insurance which
he/they may be required to effect under the terms of the Contract then and in
any such case AAI may, without being bound to, effect and keep in force
any such insurance and pay such premium or premiums as may be necessary
for that purpose and from time to time deduct the amount so paid by AAI
from any moneys due or which may become due to the Contractor or recover
the same as a debt due from the Contractor.
xiii. In case contractor takes Contractor All Risk (CAR) Policy in joint name of
AAI and Contractor for full tendered value along with third party liability
(max of 10% of tendered value or as applicable as per Insurance Regulatory
Authority of India) then there is no requirement for taking separate insurance
by sub-contractors.
However, workmen compensation policy is required to be taken separately
by main contractor and sub-contractor for workers employed by them.

CLAUSE 47
Composite i. The tenders have been called for composite work consisting of civil
Contract and construction and other associated specialized works. The pre-qualification
responsibilities criteria shall be applicable for each subhead of work independently. The
of main agency agency meeting PQ criteria for the main work shall be considered for
execution of composite work. However the agency shall be allowed to
execute only those specialized subheads of works for which bidder meet PQ
A.A.I. C-NIL I-NIL O-NIL Page 74
Clauses of Contract AIRPORTS AUTHORITY OFINDIA

criteria individually.
ii. The main contractor shall be permitted to execute only those works (covered
under one or more subhead) for which he meets all requirements of pre-
qualification including financial, technical and technological requirement
specified in the PQ criteria.
iii. Main contractor will associate expert agencies for the execution of
specialized works under various subheads for which he himself has failed to
meet PQ criteria. In such case he will appoint his associate for the execution
of each specialized work with the approval of the NIT approving authority.
The main contractor shall intimate the names of only those agencies who
fully meet the PQ criteria for each specialized work for the acceptance of the
department.
iv. Main contractor shall not be permitted to change their associate agencies in
the course of execution of work. If change of agency is inevitable then a
request shall be submitted to the engineer-in-charge in writing giving full
justification for change of agency. The proposal should include name of the
alternate agency along with his financial, technical capabilities and work
experience in the appropriate field. Such change shall be allowed only after
receiving approval from the competent authority.

Composite This clause is applicable for the works for which the estimated cost put to
contract- tender is more than Rs.500.00 crores.
Tripartite i. The main contractor shall finalise his rates, terms and conditions and mode of
agreement execution of work with specialised agencies for all works covered in various
subhead of works on receipt of work order but specifications, preferred
makes of materials and performance of system shall remain as specified in
tender document.
ii. The main contractor shall arrange an agreement between department, main
contractor and associated agencies for all subheads on receipt of work order
from the engineer-in-charge. Main contractor and expert agency shall be
jointly responsible for quality of work and performance of the system.
iii. Main contractor shall submit list of associated agency for each specialized
work within 1/12th of stipulated completion period or within one month from
issue of work order whichever is later along with documentary evidence for
financial soundness, technical capabilities and their experience for executing
similar specialized works along with his application seeking acceptance for
the name of associated agency. Approval / rejection for the name of
associated agency shall be accorded thereafter by NIT approving authority
within a period of 15 days each subhead wise.
iv. The main contractor shall submit duly signed tripartite agreement on the
format provided by AAI within 2/12th of stipulated completion period or 60
days whichever is later for acceptance and signature of department. The
extension of time for signing of this agreement shall not be generally
permitted. The signing time shall only be extended if handing over of site is
delayed due to reasons beyond control of the contractor.
Conditions of i. Main contractor shall be responsible for submission of earnest money.
composite ii. The mobilization advance shall be paid to main contractor as per terms and
contract conditions of contract and indicated under Clause 10 B. The first installment
of mobilization advance shall be corresponding to the value of work which
shall be executed by the main contractor. The subsequent mobilization
advances corresponding to value of work covered in each subhead shall be
released on signing of each Tripartite Agreement with expert agency for the
same.
iii. The security deposit shall be deducted from the running bills of main
contractor after adjustment of full earnest money.

A.A.I. C-NIL I-NIL O-NIL Page 75


Clauses of Contract AIRPORTS AUTHORITY OFINDIA

iv. Main contractor shall be responsible for completion of work as per time
schedule indicated in the NIT. The compensation for the delay shall be levied
on the main contractor only.
v. The coordination meetings called by AAI or its representative shall be
attended by associated expert agencies as and when required. Expert agency
shall be responsible for technical soundness, quality of work and adherence to
tender specifications. The main contractor as well as associated agency shall
be responsible for rectification of deficiencies noticed in specialized work.
Payment i. It will be the responsibility of main contractor to finalize expert agencies for
Conditions for the execution of works covered under all subheads of NIT and get the
Composite tripartite agreements signed as per NIT requirement at an early date. The
Contract main contractor shall not be paid for value of work covered under second
running bill & subsequent bills till all Tripartite Agreements are signed by all
agencies concerned.
ii. The main contractor must fill the ratio of work which shall govern the ratio of
direct payment to the expert agency and to the main contractor for each
subhead of work in schedule F. This ratio may also be indicated in tripartite
agreement. Thus direct payment to each expert agency shall be released in the
same ratio from the net payment (after all deductions).
iii. The running bill for specialized work shall be processed as per terms and
conditions of the contract. All deductions like security deposit, income tax
and part rate for incomplete work or due to any other reason shall be made as
per contract conditions from each running bill. In case the ratio as desired
under (ii) is not filled by the main contractor AAI will make payment of 75%
of the net payable amount to the expert agency directly and balance 25%
shall be paid to the main contractor.

Clause 48

Escrow i. All payments for the works estimated cost more than Rs.500 Cr shall be
Account made only through Escrow Account opened by the contractor. However for
works costing less than Rs.500 Cr., it shall be at the discretion of Technical
Sanctioning authority to opt for Escrow account or not. The bank charges for
Escrow Account shall be borne by contractor. The detailed conditions of
Escrow Account shall be drawn in consultation with associated bank.
ii. Mobilization advance for mobilization of resources and purchase of plant &
machinery shall be credited directly to the escrow account opened for this
contract through bank transfer as per terms and condition of contract. The
agency shall be able to utilize 25% (or as decided by TS authority) of each
installment of mobilization advance to meet minor expenses like
construction of site office, purchase of office equipment and other minor
works, while release of balance 75% fund shall be regulated by the
department. The contractor shall seek prior concurrence of Engineer-in
Charge for release of payment to the supplier etc. through Escrow Account
by the Bank. Funds against cheque issued by contractor shall be released by
Bank on receipt of written consent from Engineer-in Charge.
iii. Payment received and credited against each RA Bill, can be utilized 25%
directly by the contractor for minor expenses like salary, stationary, office
expenses etc. AAI shall exercise control for release of payment by contractor
for balance 75%.
iv. The Contractor shall submit his proposal to the Engineer-in-
Charge/Authority for utilization of funds made available by AAI (75%
against each RA bill)

A.A.I. C-NIL I-NIL O-NIL Page 76


Clauses of Contract

a. Name of agency for whom payment is proposed to be released.


b. Details of work executed/material supplied by agency to whom he
intends to release payment.
c. Nature of advance payment if any, has to be released to the supplier
for supply of material for the project only.
d. Documentary evidence in support of his claim.
v. Engineer –in-charge will examine and approve full / part of such payments
as per agency’s request within maximum of three working days. The terms
and condition of Escrow Account shall be finalized with bank according to
terms and conditions of contract. Bank shall release payment against such
cheques only after written consent of authorised officer of AAI is received.
vi. Contractor shall be permitted to close Escrow Account on receipt of final
payment for the work/project or on receipt of letter for foreclosure of work
by the AAI. All balances and liabilities against this Escrow Account shall be
left at the disposal of the contractor.

Note : In case of difference or ambiguity in Hindi and English version anywhere, the English
version will prevail.

A.A.I. C-NIL I-NIL O-NIL Page 77


AAI Safety Code AIRPORTS AUTHORITY OFINDIA

AIRPORTS AUTHORITY OF INDIA

SAFETY CODE
1. Suitable Scaffolds should be provided for workmen for all works that cannot safely be done
from the ground, or from solid construction except such short period work as can be done
safely from ladders. When a ladder is used, an extra mazdoor shall be engaged for holding the
ladder and if the ladder is used for carrying materials as well suitable footholds and hand-hold
shall be provided on the ladder and the ladder shall be given an inclination not steeper than ¼
to 1 (¼ horizontal and 1 vertical).

2. Scaffolding of staging more than 3.6m (12ft.) above the ground or floor, swung or suspended
from an overhead support or erected with stationary support shall have a guard rail properly
attached or bolted, braced and otherwise secured at least 90 cm. (3ft.) high above the floor or
platform of such scaffolding on staging and extending along the entire length of the outside
and ends thereof with only such opening as may be necessary for the delivery of materials.
Such scaffolding or staging shall be so fastened as to prevent it from swaying from the
building or structure.

3. Working platforms, gangways and stairways should be so constructed that they should not sag
unduly or unequally, and if the height of the platform or the gangway or the stairway is more
than 3.6 m (12ft.) above ground level or floor level, they should be closely boarded, should
have adequate width and should be suitably fastened as described in (2) above.

4. Every opening in the floor of a building or in a working platform shall be provided with
suitable means to prevent the fall of person or materials by providing suitable fencing or
railing whose minimum height shall be 90 cm.(3ft.)

5. Safe means of access shall be provided to all working platforms and other working places.
Every ladder shall be securely fixed. No portable single ladder shall be over 9m. (30ft.) in
length while the width between side rails in rung ladder shall in no case be less than 29 cm.
(11 ½ “) for ladder upto and including 3m. (10ft.) in length. For long ladders, this width
should be increased at least ¼” for each additional 30cm. (1 foot) of length. Uniform step
spacing of not more than 30cm shall be kept. Adequate precautions shall be taken to prevent
danger from electrical equipment. No materials on any of the site or work shall be so stacked
or placed as to cause danger or inconvenience to any person or the public. The contractor
shall provide all necessary fencing and lights to protect the public from accident and shall be
bound to bear the expenses of defence of every suit, action or other proceedings at law that
may be brought by any person for injury sustained owing to neglect of the above precautions
and to pay any damages and cost which may be awarded in any such suit, action or
proceedings to any such person on which may, with the consent of the contractor, be paid to
compensate any claim by any such person.

6. a. Excavation and Trenching – All trenches 1.2 m. (4ft.) or more in depth, shall at all times
be supplied with at least one ladder for each 30m. (100ft.) in length or fraction thereof,
Ladder shall extend from bottom of the Trench to at least 90cm (3fts) above the surface of
the ground. The side of the trenches which are 1.5 m. (5 ft.) or more in depth shall be
stepped back to give suitable slope or securely held by timber bracing, so as to avoid the
danger of sides collapsing. The excavated material shall not be placed within 1.5 m. (5 ft.)
of the edges of the trench or half of the depth of the trench whichever is more. Cutting
shall be done from top to bottom. Under no circumstances, undermining or undercutting
shall be done.

A.A.I. C-NIL I-NIL O-NIL Page 78


AAI Safety Code AIRPORTS AUTHORITY OFINDIA

b. Safety Measures for digging bore holes: -


i. If the bore well is successful, it should be safely capped to avoid caving and collapse
of the bore well. The failed and the abandoned ones should be completely refilled to
avoid caving and collapse;
ii. During drilling, Sign boards should be erected near the site with the address of the
drilling contractor and the Engineer-in-charge of the work;
iii. Suitable fencing should be erected around the well during the drilling and after the
installation of the rig on the point of drilling, flags shall be put 50 Mtr all around the
point of drilling to avoid entry of people/animals;
iv. After drilling the bore well, a cement platform (0.50 Mtr x 0.50 Mtr x 1.20 Mtr) 0.60
Mtr above ground level and 0.60 Mtr below ground level should be constructed
around the well casing;
v. After the completion of the bore well, the contractor should cap the bore well properly
by welding steel plate, cover the bore well with the drilled wet soil and fix thorny
shrubs over the soil. This should be done even while repairing the pump;
vi. After the bore well is drilled the entire site should be brought to the ground level;

7. Demolition – Before any demolition work is commenced and also during the progress of the
work,
i) All roads and open areas adjacent to the work site shall either be closed or suitably
protected.
ii) No electric cable or apparatus which is liable to be a source of danger or a cable or
apparatus used by the operator shall remain electrically charged.
iii) All practical steps shall be taken to prevent danger to persons employed from risk of fire
or explosion or flooding. No floor, roof or other part of the building shall be so
overloaded with debris or materials as to render it unsafe.

8. All necessary personal safety equipment as considered adequate by the Engineer-in-Charge


should be kept available for the use of the person employed on the site and maintained in a
condition suitable for immediate use, and the contractor should take adequate steps to ensure
proper use of equipment by those concerned. The following safety equipment shall invariably
be provided.
i) Workers employed on mixing asphaltic materials, cement and lime mortars shall be
provided with protective footwear and protective goggles.
ii) Those engaged in white washing and mixing or stacking of cement bags or any material
which is injurious to the eyes shall be provided with protective goggles.
iii) Those engaged in welding works shall be provided with welder’s protective eye-shields.
iv) Stone breaker shall be provided with protective goggles and protective clothing and
seated at sufficiently safe intervals.
v) When workers are employed in sewers and manholes, which are in active use, the
contractors shall ensure that the manhole covers are opened and ventilated at least for an
hour before the workers are allowed to get into the manholes, and the manholes so opened
shall be cordoned off with suitable railing and provided with warning signals or boards to
prevent accident to the public. In addition, the contractor shall ensure that the following
safety measures are adhered to:-
a) Entry for workers into the line shall not be allowed except under supervision of the Sr.
Superintendent (Engg.) or any other higher officer.
b) At least 5 to 6 manholes upstream and downstream should be kept open for at least 2 to 3
hours before any man is allowed to enter into the manhole for working inside.
c) Before entry, presence of toxic gases should be tested by inserting wet lead acetate paper
which changes colour in the presence of such gases and gives indication of their presence.

A.A.I. C-NIL I-NIL O-NIL Page 79


AAI Safety Code AIRPORTS AUTHORITY OFINDIA

d) Presence of Oxygen should be verified by lowering a detector lamp into the manhole. In
case, no Oxygen is found inside the sewer line, workers should be sent only with oxygen
kit.
e) Safety belt with rope should be provided to the workers. While working inside the
manholes, such rope should be handled by two men standing outside to enable him to be
pulled out during emergency.
f) The area should be barricaded or condoned off by suitable means to avoid mishaps of any
kind. Proper warning signs should be displayed for the safety of the public whenever
cleaning works are undertaken during night or day.
g) No smoking or open flames shall be allowed near the blocked manhole being cleaned.
h) The malba obtained on account of cleaning of blocked manholes and sewer lines should
be immediately removed to avoid accidents on account of slippery nature of the malba.
i) Workers should not be allowed to work inside the manhole continuously. He should be
given rest intermittently. The Engineer-in-Charge may decide the time upto which a
worker may be allowed to work continuously inside the manhole.
j) Gas masks with Oxygen Cylinder should be kept at site for use in emergency.
k) Air-blowers should be used for flow of fresh air through the manholes. Whenever called
for, portable air blowers are recommended for ventilating the manholes. The Motors for
these shall be vapour proof and of totally enclosed type. Non sparking gas engines also
could be used but they should be placed at least 2 meters away from the opening and on
the leeward side protected from wind so that they will not be a source of friction on any
inflammable gas that might be present.
l) The workers engaged for cleaning the manholes / sewers should be properly trained
before allowing to work in the manhole.
m) The workers shall be provided with Gumboots or non-sparking shoes bump helmets and
gloves non sparking tools safety lights and gas masks and portable air blowers (when
necessary). They must be supplied with barrier cream for anointing the limbs before
working inside the sewer lines.
n) Workmen descending a manhole shall try each ladder stop or rung carefully before
putting his full weight on it to guard against insecure fastening due to corrosion of the
rung fixed to manhole well.
o) If a man has received a physical injury, he should be brought out of the sewer
immediately and adequate medical aid should be provided to him.
p) The extent to which these precautions are to be taken depend on individual situation but
the decision of the Engineer-in-Charge regarding the steps to be taken in this regard in an
individual case will be final.
(vi) The Contractor shall not employ men and women below the age of 18 years on
the work of painting with products containing lead in any form. Wherever men
above the age of 18 are employed on the work of lead painting, the following
precaution should be taken:-
a) No paint containing lead or lead products shall be used except in the form of paste or
readymade paint.
b) Suitable face masks should be supplied for use by the workers when paint is applied in
the form of spray or a surface having lead paint is dry rubbed and scrapped.
c) Overall shall be supplied by the contractors to the workmen and adequate facilities shall
be provided to enable the working painters to wash during and on the cessation of work.

9. An additional clause (viii)(i) of AAI Safety Code (iv) the Contractor shall not employ women
and men below the age of 18 on the work of painting with product containing lead in any form,
wherever men above the age of 18 are employed on the work of lead painting, the following
principles must be observed for such use:
i) White lead, sulphate of lead or product containing these pigment, shall not be used in
painting operation except in the form of pastes or paint ready for use.
ii) Measures shall be taken, wherever required in order to prevent danger arising from the
application of a paint in the form of spray.
A.A.I. C-NIL I-NIL O-NIL Page 80
AAI Safety Code AIRPORTS AUTHORITY OFINDIA

iii) Measures shall be taken, wherever practicable, to prevent danger arising out of from dust
caused by dry rubbing down and scraping.
iv) Adequate facilities shall be provided to enable working painters to wash during and on
cessation of work.
v) Overall shall be worn by working painters during the whole of working period.
vi) Suitable arrangement shall be made to prevent clothing put off during working hours
being spoiled by painting materials.
vii) Cases of lead poisoning and suspected lead poisoning shall be notified and shall be
subsequently verified by medical man appointed by competent authority of AAI.
viii) AAI may require, when necessary medical examination of workers.
ix) Instructions with regard to special hygienic precautions to be taken in the painting trade
shall be distributed to working painters.

10. When the work is done near any place where there is risk of drowning, all necessary
equipments should be provided and kept ready for use and all necessary steps taken for
prompt rescue of any person in danger and adequate provision, should be made for prompt
first aid treatment of all injuries likely to be obtained during the course of the work.

11. Use of hoisting machines and tackle including their attachments, anchorage and supports shall
conform to the following standards or conditions:
i) (a) These shall be of good mechanical construction, sound materials and adequate
strength and free from patent defects and shall be kept repaired and in good working
order.
(b) Every rope used in hoisting or lowering materials or as a means of suspension
shall be of durable quality and adequate strength, and free from patent defects.
ii) Every crane driver or hoisting appliance operator shall be properly qualified and no
person under the age of 21 years should be in charge of any hoisting machine including
any scaffolding winch or give signals to operator.
iii) In case of every hoisting machine and of every chain ring hook, shackle swivel and pulley
block used in hoisting or as means of suspension, the safe working load shall be
ascertained by adequate means. Every hoisting machine and all gear referred to above
shall be plainly marked with the safe working load. In case of a hoisting machine having a
variable safe working load each safe working load and the condition under which it is
applicable shall be clearly indicated. No part of any machine or any gear referred to above
in this paragraph shall be loaded beyond the safe working load except for the purpose of
testing.
iv) In case of departmental machines, the safe working load shall be notified by the Electrical
Engineer-in-Charge. As regards contractor’s machines the contractors shall notify the safe
working load of the machine to the Engineer-in-Charge whenever he brings any
machinery to site of work and get it verified by the electrical Engineer concerned.

12. Motors, gearing, transmission, electric wiring and other dangerous parts of hoisting
appliances should be provided with efficient safeguards. Hoisting appliances should be
provided with such means as will reduce to the minimum the risk of accidental descent of the
load. Adequate precautions should be taken to reduce to the minimum the risk of any part of a
suspended load becoming accidentally displaced. When workers are employed on electrical
installations which are already energized, insulating mats, wearing apparel, such as gloves,
sleeves and boots as may be necessary should be provided. The worker should not wear any
rings, watches and carry keys or other materials which are good conductors of electricity.

13. All scaffolds, ladders and other safety devices mentioned or described herein shall be
maintained in safe condition and no scaffold, ladder or equipment shall be altered or removed
while it is in use. Adequate washing facilities should be provided at or near places of work.

A.A.I. C-NIL I-NIL O-NIL Page 81


AAI Safety Code AIRPORTS AUTHORITY OFINDIA

14. These safety provisions should be brought to the notice of all concerned by display on a notice board
at a prominent place at work spot. The person responsible for compliance of the safety code shall be
named therein by the contractor.

15. To ensure effective enforcement of the rules and regulations relating to safety precautions the
arrangements made by the contractor shall be open to inspection by the Labour Officer or Engineer-
in- Charge of the department or their representatives.

16. Notwithstanding the above clauses from (1) to (15), there is nothing in these to exempt the contractor
from the operations of any other Act or Rules in force in the Republic of India.

A.A.I. C-NIL I-NIL O-NIL Page 82


Model Rules AIRPORTS AUTHORITY OFINDIA

MODEL RULES FOR THE PROTECTION OF


HEALTH AND SANITARY ARRANGEMENTS FOR WORKERS
EMPLOYED BY AAI OR ITS CONTRACTORS

1. APPLICATION
These rules shall apply to all buildings and construction works in charge of AAI in
which twenty or more workers are ordinarily employed or are proposed to be
employed in any day during the period during which the contract work is in progress.

2. DEFINITION
Work place means a place where twenty or more workers are ordinarily employed in
connection with construction work on any day during the period during which the
contract work is in progress.

3. FIRST-AID FACILITIES
(i) At every work place, there shall be provided and maintained, so as to be easily
accessible during working hours, first-aid boxes at the rate of not less than one box
for 150 contract labour or part thereof ordinarily employed.
(ii) The first-aid box shall be distinctly marked with a red cross on white back ground and
shall contain the following equipment.
(a) For work places in which the number of contract labour employed does not exceed 50
Each first –aid box shall contain the following equipments:
1. 6 small sterilized dressings
2. 3 medium size sterilized dressings
3. 3 large size sterilized dressings
4. 3 large sterilized burn dressings
5. 1 (30 ml) bottle containing a two per cent alcoholic solution of iodine.
6. 1 (30 ml) bottle containing salvolatile having the dose and mode of administration
indicated on the label.
7. 1 snakebite lancet.
8. 1 (30 gms) bottle of potassium permanganate crystals.
9. 1 pair scissors.
10. 1copy of the first-aid leaflet issued by the Director General, Factory Advice Service
and Labour Institute, Government of India.
11. 1 bottle containing 100 tablets (each of 5 gms) of aspirin.
12. Ointment for burns.
13. A bottle of suitable surgical antiseptic solution.
(b) For work places in which the number of contract labour exceed 50. Each first-aid box
shall contain the following equipments.
1. 12 small sterilized dressings.
2. 6 medium size sterilized dressings.
3. 6 large size sterilized dressings
4. 6 large size sterilized burn dressings.
5. 6 (15 gms) packets sterilized cotton wool.
6. 1 (60 ml). Bottle containing two per cent alcoholic solution iodine.
7. 1 (60 ml) bottle containing salvolatile having the dose and mode of administration
indicated on the label.
8. 1 roll of adhesive plaster.
9. 1 snake bite lancet.
10. 1 (30 gms) bottle of potassium permanganate crystals.
11. 1 pair scissors.
12. 1 copy of the first-aid leaflet issued by the Director General Factory Advice Service
and Labour Institute / Government of India.
13. A bottle containing 100 tablets (each of 5 gms) of aspirin.

A.A.I. C-NIL I-NIL O-NIL Page 83


Model Rules AIRPORTS AUTHORITY OFINDIA

14. Ointment for burns.


15. A bottle of suitable surgical antiseptic solution.

(iii) Adequate arrangements shall be made for immediate recoupment of the equipment when
necessary.
(iv) Nothing except the prescribed contents shall be kept in the First-aid box.
(v) The first-aid box shall be kept in charge of a responsible person who shall always be readily
available during the working hours of the work place.
(vi) a person in charge of the First-aid box shall be a person trained in First-aid treatment in the
work places where the number of contract labour employed is 150 or more.
(vii) In work places where the number of contract labour employed is 500 or more and hospital
facilities are not available within easy distance from the works. First-aid posts shall be
established and run by a trained compounder. The compounder shall be on duty and shall be
available at all hours when the workers are at work.
(viii) Where work places are situated in places which are not towns or cities, a suitable motor
transport shall be kept readily available to carry injured person or person suddenly taken ill
to the nearest hospital.

4. DRINKING WATER
i) In every work place, there shall be provided and maintained at suitable places, easily
accessible to labour, a sufficient supply of cold water fit for drinking.
ii) Where drinking water is obtained from an intermittent public water supply, each work place
shall be provided with storage where such drinking water shall be stored.
iii) Every water supply or storage shall be at a distance of not less than 50 feet from any latrine
drain or other source of pollution. Where water has to be drawn from an existing well
which is within such proximity of latrine, drain or any other source of pollution, the well
shall be properly chlorinated before water is drawn from it for drinking. All such wells shall
be entirely closed in and be provided with a trap door which shall be dust and waterproof.
iv) A reliable pump shall be fitted to each covered well, the trap door shall be kept locked and
opened only for cleaning or inspection which shall be done at least once a month.

5. WASHING FACILITIES
i) In every work place adequate and suitable facilities for washing shall be provided and
maintained for the use of contract labour employed therein.
ii) Separate and adequate cleaning facilities shall be provided for the use of male and femal
workers.
iii) Such facilities shall be conveniently accessible and shall be kept in clean and hygienic
condition.

6. LATRINES AND URINALS


i) Latrines shall be provided in every work place on the following scale namely:
a) Where female are employed, there shall be at least one latrine for every 25 females.
b) Where males are employed, there shall be at least one latrine for every 25 males.
ii) Provided that, where the number of males or females exceeds 100, it shall be sufficient if
there is one latrine for 25 males or females as the case may be upto the first 100, and one
for every 50 thereafter.
iii) Every latrine shall be under cover and so partitioned off as to secure privacy, and shall have
a proper door and fastenings.
iv) Construction of latrines: The inside walls shall be constructed of masonry or some suitable
heat-resisting nonabsorbent materials and shall be cement washed inside and outside at least
once a year, Latrines shall not be of a standard lower than borehole system.
A.A.I. C-NIL I-NIL O-NIL Page 84
Model Rules AIRPORTS AUTHORITY OFINDIA

v) (a) Where workers of both sexes are employed, there shall be displayed outside each block
of latrine and urinal, a notice in the language understood by the majority of the workers
“For Men only” or “For Women Only” as the case may be.
(b) The notice shall also bear the figure of a man or of a woman, as the case may be.
vi) There shall be at least one urinal for male workers upto 50 and one for female workers upto
fifty employed at a time, provided that where the number of male or female workmen, as
the case may be exceeds 500, it shall be sufficient if there is one urinal for every 50 males
or females upto the first 500 and one for every 100 or part thereafter.
vii) (a) The latrines and urinals shall be adequately lighted and shall be maintained in a clean
and sanitary condition at all times.
(b) Latrines and urinals other than those connected with a flush sewage system shall
comply with the requirements of the Public Health Authorities.
viii) Water shall be provided by means of tap or otherwise so as to be conveniently accessible in
or near the latrines and urinals.
ix) Disposal of excreta: Unless otherwise arranged for by the local sanitary authority,
arrangements for proper disposal of excreta by incineration at the work place shall be
made by means of a suitable incinerator. Alternately excreta may be disposed of by
putting a layer of night soil at the bottom of a pucca tank prepared for the purpose and
covering it with a 15 cm. Layer of waste or refuse and then covering it with a layer of
earth for a fortnight (when it will turn to manure).
x) The contractor shall at his own expense, carry out all instructions issued to him by the
Engineer-in-Charge to effect proper disposal of night soil and other conservancy work in
respect of the contractor’s workmen or employees on the site. The contractor shall be
responsible for payment of any charges which may be levied by Municipal or Cantonment
Authority for execution of such on his behalf.

7. PROVISION OF SHELTER DURING REST


At every place there shall be provided, free of cost, four suitable sheds, two for meals
and the other two for rest separately for the use of men and women labour. The height
of each shelter shall not be less than 3 meters (10 ft.) from the floor level to the lowest
part of the roof. These shall be kept clean and the space provided shall be on the basis
of 0.6 sq.m. (6 sft) per head. Provided that the Engineer-in-Charge may permit subject
to his satisfaction, a portion of the building under construction or other alternative
accommodation to be used for the purpose.

8. CRECHES
i) At every work place, at which 20 or more women workers are ordinarily employed, there
shall be provided two rooms of reasonable dimensions for the use of their children under
the age of six years. One room shall be used as a play room for the children and the other
as their bedroom. The rooms shall be constructed with specifications as per clause 19 H
(ii) a, b & c.
ii) The rooms shall be provided with suitable and sufficient openings for light and
ventilation. There shall be adequate provision of sweepers to keep the places clean.
iii) The contractor shall supply adequate number of toys and games in the play room and
sufficient number of cots and beddings in the bed room.
iv) The contractor shall provide one ayaa to look after the children in the crèche when the
number of women workers does not exceed 50 and two when the number of women
workers exceed 50.
v) The use of the rooms earmarked as crèches shall be restricted to children, their attendants
and mothers of the children.

A.A.I. C-NIL I-NIL O-NIL Page 85


Model Rules AIRPORTS AUTHORITY OFINDIA

9. CANTEENS
i) In every work place where the work regarding the employment of contractor labour is
likely to continue for six months and where in contract labour numbering one hundred or
more are ordinarily employed, an adequate canteen shall be provided by the contractor for
the use of such contract labour.
ii) The canteen shall be maintained by the contractor in an efficient manner.
iii) The canteen shall consist of at least a dining hall, kitchen, storeroom, pantry and washing
places separately for workers and utensils.
iv) The canteen shall be sufficiently lighted at all times when any person has access to it.
v) The floor shall be made of smooth and impervious materials and inside walls shall be
lime washed or colour washed at least once in each year. Provided that the inside walls of
the kitchen shall be lime washed every four months.
vi) The premises of the canteen shall be maintained in a clean and sanitary condition.
vii) Waste water shall be carried away in suitable covered drains and shall not be allowed to
accumulate so as to cause a nuisance.
viii) Suitable arrangements shall be made for the collection and disposal of garbage.
ix) The dining hall shall accommodate at a time 30 per cent of the contract labour working at
a time.
x) The floor area of the dining hall, excluding the area occupied by the service counter and
any furniture except tables and chairs shall not be less than one square metre (10 sft) per
diner to be accommodated as prescribed in sub-Rule (ix).
xi) (a) A portion of the dining hall and service counter shall be partitioned off and reserved
for women workers in proportion to their number. (b) Washing places for women shall be
separate and screened to secure privacy.
xii) Sufficient tables stools, chairs or benches shall be available for the number of diners to be
accommodated as prescribed in sub-Rule (ix).
xiii) (a) 1. There shall be provided and maintained sufficient utensils crockery, furniture and
any other equipment necessary for the efficient running of the canteen.
2. The furniture utensils and other equipment shall be maintained in a clean and
hygienic condition.
(b) 1. Suitable clean clothes for the employees serving in the canteen shall be
provided and maintained.
2. A service counter, if provided, shall have top of smooth and impervious material.
3. Suitable facilities including an adequate supply of hot water shall be provided for the
cleaning of utensils and equipments.
xiv) The food stuffs and other items to be served in the canteen shall be in conformity with the
normal habits of the contract labour.
xv) The charges for food stuffs, beverages and any other items served in the canteen shall be
based on ‘No Profit, No loss’ and shall be conspicuously displayed in the canteen.
xvi) In arriving at the price of foodstuffs, and other article served in the canteen, the following
items shall not be taken into consideration as expenditure namely :-
a) The rent of land and building.
b) The depreciation and maintenance charges for the building and equipments
provided for the canteen.
c) The cost of purchase, repairs and replacement of equipments including furniture,
crockery, cutlery and utensils.
d) The water charges and other charges incurred for lighting and ventilation.
e) The interest and amounts spent on the provision and maintenance of equipments
provided for the canteen.
xvii) The accounts pertaining to the canteen shall be audited once every 12 months by
registered accountants and auditors.

A.A.I. C-NIL I-NIL O-NIL Page 86


Model Rules AIRPORTS AUTHORITY OFINDIA

10. ANTI-MALARIAL PRECAUTIONS


The contractor shall at his own expense, conform to all anti-malarial instructions given to him
by the Engineer-in-Charge including the filling up of any borrow pits which may have been
dug by him.

11. The above rules shall be incorporated in the contracts and in notices inviting tenders and shall form an
integral part of the contracts.

12. AMENDMENTS
AAI may, from time to time, add to or amend these rules and issue directions - it may
consider necessary for the purpose of removing any difficulty which may arise in the
administration thereof.

A.A.I. C-NIL I-NIL O-NIL Page 87


AAI Contractor’s Labour Regulations AIRPORTS AUTHORITY OFINDIA

AIRPORTS AUTHORITY OF INDIA


Contractor’s Labour Regulations
1. SHORT TITLE
These regulations may be called the AAI Contractors Labour Regulations.

2. DEFINITIONS
(i) Workman means any person employed by AAI or its contractor directly or indirectly
through a subcontractor with or without the knowledge of the AAI to do any skilled,
semiskilled or unskilled manual, supervisory, technical or clerical work for hire or reward,
whether the terms of employment are expressed or implied but does not include any person:-
a) Who is employed mainly in a managerial or administrative capacity:or
b) Who, being employed in a supervisory capacity draws wages exceeding five hundred
rupees per mensem or exercises either by the nature of the duties attached to the office or
by reason of powers vested in him, functions mainly of managerial nature:or
c) Who is an out worker, that is to say, person to whom any article or materials are given out
by or on behalf of the principal employers to be made up cleaned, washed, altered,
ornamental finished, repaired adopted or otherwise processed for sale for the purpose of
the trade or business of the principal employers and the process is to be carried out either
in the home of the out worker or in some other premises, not being premises under the
control and management of the principal employer. No person below the age of 14 years
shall be employed to act as a workman.

(ii) Fair Wages means wages whether for time or piece work fixed and notified under the
provisions of the Minimum Wages Act from time to time.
(iii) Contractors shall include every person who undertakes to produce a given result other
than a mere supply of goods or articles of manufacture through contract labour or whosupplies
contract labour for any work and includes a sub contractor.
(iv) Wages shall have the same meaning as defined in the Payment of Wages Act.
3. i) Normally working hours of an adult employee should not exceed 9 hours a day. The
working day shall be so arranged that inclusive of interval for rest, if any, it shall not spread
over more than 12 hours on any day.
ii) When an adult worker is made to work for more than 9 hours on any day or for more than
48 hours in any week, he shall be paid over time for the extra hours put in by him at double
the ordinary rate of wages.
iii) a) Every worker shall be given a weekly holiday normally on a Sunday, in accordance
with the provisions of the Minimum Wages (Central) Rules 1960 as amended from time to
time irrespective of whether such worker is governed by the Minimum Wages Act or not.
b) Where the minimum wages prescribed by the Central/State Government under the
Minimum Wages Act are not inclusive of the wages for the weekly day of rest, the worker
shall be entitled to rest day wages at the rate applicable to the next preceding day, provided he
has worked under the same contractor for a continuous period of not less than 6 days.
c) Where a contractor is permitted by the Engineer-in-Charge to allow a worker to work on a
normal weekly holiday, he shall grant a substituted holiday to him for the whole day on one of
the five days immediately before or after the normal weekly holiday and pay wages to such
worker for the work performed on the normal weekly holiday at overtime rate.

4. DISPLAY OF NOTICE REGARDING WAGES ETC.


The contractor shall before he commences his work on contract, display and correctly
maintain and continue to display and correctly maintain in a clear and legible condition in
conspicuous places on the work, notices in English and in the local Indian languages spoken
by the majority of the workers giving the minimum rates of wages fixed under Minimum
Wages Act, the actual wages being paid, the hours of work for which such wage are earned,
wages periods, dates of payments of wages and other relevant information as per Appendix-
’VIII’.

A.A.I. C-NIL I-NIL O-NIL Page 88


AAI Contractor’s Labour Regulations AIRPORTS AUTHORITY OFINDIA

5. PAYMENT OF WAGES
(i) The contractor shall fix wage periods in respect of which wages shall be payable.
(ii) No wage period shall exceed one month.
(iii) The wages of every person employed as contract labour in an establishment or by a contractor
where less than one thousand such persons are employed shall be paid before the expiry of
seventh day and in other cases before the expiry of tenth day after the last day of the wage
period in respect of which the wages are payable.
(iv) Where the employment of any worker is terminated by or on behalf of the contractor the
wages earned by him shall be paid before the expiry of the second working day from the date
on which his employment is terminated.
(v) All payment of wages shall be made on a working day at the work premises and during the
working time and on a date notified in advance and in case the work is completed before the
expiry of the wage period, final payment shall be made within 48 hours of the last working
day.
(vi) Wages due to every worker shall be paid to him direct or to other person authorized by him in
this behalf.
(vii) All wages shall be paid in current coin or currency or in both.
(viii) Wages shall be paid without any deductions of any kind except those specified by the Central
Government by general or special order in this behalf or permissible under the Payment of
Wages Act 1956.
(ix) A notice showing the wages period and the place and time of disbursement of wages shall be
displayed at the place of work and a copy sent by the contractor to the Engineer-in-Charge
under acknowledgement.
(x) It shall be the duty of the contractor to ensure the disbursement of wages in the presence of
the Senior Superintendent Engg or authorized representative of the Engineer-in-Charge who
will be required to be present at the place and time of disbursement of wages by the contractor
to workmen.
(xi) The contractor shall obtain from Engineer in charge or the authorized representative of the
Engineer-in-Charge a certificate under his signature at the end of the entries in the “Register
of Wages” or the “Wage-cum-Muster Roll” as the case may be in the following form:
“Certified that the amount shown in column No. ..................has been paid to the workman
concerned in my presence on …………..at ........................ ”

Note: In case of payment of wages paid through bank, the contractor shall submit a copy of
bank statement for relevant period duly signed by him.

6. FINES AND DEDUCTIONS WHICH MAY BE MADE FROM WAGES


(i) The wages of a worker shall be paid to him without any deduction of any kind except the
following:
a) Fines
b) Deductions for absence from duty i.e. from the place or the places where by the terms of
his employment he is required to work. The amount of deduction shall be in proportion to the
period for which he was absent.
c) Deduction for damage to or loss of goods expressly entrusted to the employed person for
custody, or for loss of money or any other deduction which he is required to account, where
such damage or loss is directly attributable to his neglect or default.
d) Deduction for recovery of advances or for adjustment of overpayment of wages, advances
granted shall be entered in a register.
e) Any other deduction which the Central Government may from time to time allow.

(ii) No fines should be imposed on any worker save in respect of such acts and omissions on his
part as have been approved of by the Chief Labour Commissioner.
Note: An approved list of Acts and Omissions for which fines can be imposed is enclosed at
Appendix-XII.

A.A.I. C-NIL I-NIL O-NIL Page 89


AAI Contractor’s Labour Regulations AIRPORTS AUTHORITY OFINDIA

(iii) No fine shall be imposed on a worker and no deduction for damage or loss shall be made from
his wages until the worker has been given an opportunity of showing cause against such fines
or deductions.
(iv) The total amount of fine which may be imposed in any one wage period on a worker shall not
exceed an amount equal to three paise in a rupee of the total wages, payable to him in respect
of that wage period.
(v) No fine imposed on any worker shall be recovered from him by installment, or after the expiry
of sixty days from the date on which it was imposed.
(vi) Every fine shall be deemed to have been imposed on the day of the act or omission in respect.
of which it was imposed.

7. LABOUR RECORDS
(i) The contractor shall maintain a Register of persons employed on work on contract in Form
XIII of the CL(R&A) Central Rules 1971(Appendix-VI)
(ii) The contractor shall maintain a Muster Roll register in respect of all workmen employed by
him on the work under Contract in Form XVI of the CL (R&A) Rules 1971(Appendix-VII).
(iii) The contractor shall maintain a Wage Register in respect of all workmen employed by him on
the work under contract in Form XVII of the CL (R&A) Rules 1971(Appendix-VIII)
(iv) Register of accident - The contractor shall maintain a register of accidents in such form as
may be convenient at the work place but the same shall include the following particulars:
(a) Full particulars of the labourers who met with accident.
(b) Rate of Wages
(c) Sex
(d) Age
(e) Nature of accident and cause of accident
(f) Time and date ofaccident
(g) Date and time when admitted in Hospital
(h) Date of discharge from the Hospital
(i) Period of treatment and result of treatment
(j) Percentage of loss of earning capacity and disability as assessed by Medical officer
(k) Claim required to be paid under Workmen’s Compensation Act.
(l) Date of payment of compensation
(m) Amount paid with details of the person to whom the same was paid
(n) Authority by whom the compensation was assessed.
(o) Remarks
(v) The contractor shall maintain a Register of Fines in the Form XII of the CL(R&A) Rules
1971 (Appendix-XIII).
The contractor shall display in a good condition and in a conspicuous place of work the
approved list of acts and omissions for which fines can be imposed (Appendix-XII)
(vi) The contractor shall maintain a Register of deductions for damage or loss in Form XX of
the CL (R&A) Rules1971 (Appendix-XIV)
(vii) The contractor shall maintain a Register of Advances in Form XXIII of the CL (R&A) Rules
1971 (Appendix-XV)
(viii) The contractor shall maintain a Register of Overtime in Form XXIII of the CL (R&A) Rules
1971 (Appendix-XVI).

8. ATTENDANCE CARD-CUM-WAGE SLIP

(i) The contractor shall issue an Attendance card-cum-wage slip to each workman employed by
him in the specimen format (Appendix-IX)
(ii) The card shall be valid for each wage period.
(iii) The contractor shall mark the attendance of each workman on the card twice each day, once at
the commencement of the day and again after the rest interval, before he actually starts work.
(iv) The card shall remain in possession of the worker during the wage period under reference.

A.A.I. C-NIL I-NIL O-NIL Page 90


AAI Contractor’s Labour Regulations AIRPORTS AUTHORITY OFINDIA

(v) The contractor shall complete the wage slip portion on the reverse of the card at least a day
prior to the disbursement of wages in respect of the wage period under reference.
(vi) The contractor shall obtain the signature or thumb impression of the worker on the wage slip
at the time of disbursement of wages and retain the card with himself.

9. EMPLOYMENT CARD

The contractor shall issue an Employment Card in Form XIV of the CL (R&A) Central
Rules 1971 to each worker within three days of the employment of the worker (Appendix-X).

10. SERVICE CERTIFICATE


On termination of employment for any reason whatsoever the contractor shall issue to the
workman whose services have been terminated, a Service certificate in Form XV of the
CL(R&A) Central Rules 1971.

11. PRESERVATION OF LABOUR RECORDS


All records required to be maintained under Regulations Nos. 6 & 7 shall be preserved in
original for a period of three years from the date of last entries made in them and shall be
made available for inspection by the Engineer-in-Charge or Labour Officer or any other
officers authorised by the Ministry of Urban Development in this behalf.

12. POWER OF LABOUR OFFICER TO MAKE INVESTIGATIONS OR ENQUIRY


The Labour Officer or any person authorized by Central Government on their behalf shall
have power to make enquiries with a view to ascertaining and enforcing due and proper
observance of Fair Wage Clauses and the Provisions of these Regulations. He shall
investigate into any complaint regarding the default made by the contractor or sub contractor
in regard to such provision.

13. REPORT OF LABOUR OFFICER

The Labour Officer or other persons authorized as aforesaid shall submit a report of result of
his investigation or enquiry to the Engineer-in-Charge concerned indicating the extent, if any,
to which the default has been committed with a note that necessary deductions from the
contractor’s bill be made and the wages and other dues be paid to the labourers concerned. In
case an appeal is made by the contractor under Clause 13 of these regulations, actual payment
to labourers will be made by the Engineer-in-Charge after G.M. Engg. has given his decision
on such appeal.
(i) Engineer-in-Charge shall arrange payments to the labour concerned within 45 days from
the receipt of the report from the Labour Officer or the G.M. Engineer as the case may be.

14. APPEAL AGAINST THE DECISION OF LABOUR OFFICER


Any person aggrieved by the decision and recommendations of the Labour Officer or other
person so authorized may appeal against such decision to the Engineer-in-Charge concerned
within 30 days from the date of decision, but subject to such appeal, the decision of the officer
shall be final and binding upon the contractor.

15. PROHIBITION REGARDING REPRESENTATION THROUGH LAWYER

(i) A workman shall be entitled to be represented in any investigation or enquiry under these
regulations by:

a) An officer of a registered trade union of which he is a member.


b) An officer of a federation of trade unions to which the trade union referred to in Clause (a) is
affiliated.

A.A.I. C-NIL I-NIL O-NIL Page 91


AAI Contractor’s Labour Regulations AIRPORTS AUTHORITY OFINDIA

c) Where the employer is not a member of any registered trade union, by an officer of a
registered trade union, connected with the industry in which the worker is employed or by any
other workman employed in the industry in which the worker is employed.

(ii) An employer shall be entitled to be represented in any investigation or enquiry under these
regulations by:
a) An officer of an association of employers of which he is a member.
b) An officer of a federation of associations of employers to which association referred to in
Clause (a) is affiliated.
c) Where the employers is not a member of any association of employers, by an officer of
association of employer connected with the industry in which the employer is engaged or by
any other employer, engaged in the industry in which the employer is engaged.

(iii) No party shall be entitled to be represented by a legal practitioner in any investigation or


enquiry under these regulations.

16. INSPECTION OF BOOKS AND SLIPS


The contractor shall allow inspection of all the prescribed labour records to any of his workers
or to his agent at a convenient time and place after due notice is received or to the Labour
Officer or any other person, authorized by the Central Government on his behalf .

17. SUBMISSION OF RETURNS


The contractor shall submit periodical returns as may be specified from time to time.

18. AMENDMENTS
The Central Government/AAI may from time to time add to or amend the regulations and on
any question as to the application/interpretation or effect of those regulations the decision of
the General Manager (Engg.) concerned shall be final.

A.A.I. C-NIL I-NIL O-NIL Page 92


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-I

FORM OF BANK GUARANTEE IN LIEU OF SECURITY DEPOSIT & AMOUNT


WITHHELD AGAINST COMPENSATION FOR DELAY IN INDIVIDUAL
CONTRACT
(on Non-Judicial Stamp Paper of Rs.100/-)

[Refer Clause 1Aand 2B]

To
The Airports Authority of India
…………………………………….
……………………………………..
1. In consideration of the Airport Authority of India having its head office at New Delhi
[hereinafter called the “AAI” which expression shall unless repugnant to the subject or
context include its administrator, successors and assigns) having agreed under the terms and
condition of Contract Agreement No. ………………………dated. ................... made
between……….and AAI in connection with the work of.................................................….
(hereinafter called the said contract) to accept Deed of Guarantee as herein provided for
Rs…………………….(Rupees……………..only) from a Nationalized Bank in lieu of the
Security deposit to be made by the contractor or lieu of the amount withheld towards
compensation for delay pending final extension of time to be made from the contractors
contained in the said Contractor. We, the… ..................... bank (hereinafter referred to as “the
said Bank” and having our registered office at ................................... do hereby undertake and
agree to identify and keep indemnified AAI from time to time to the extent of
Rs…………………… (Rupees… ............................... only) against any loss or damage, cost,
charges and expenses caused to or suffered by or that may be caused to or suffered by AAI
by reason of any breach or breaches by the said Contractor of any of the terms and condition
contained in the said contract and to unconditionally pay the amount claimed by AAI on
demand and without demur to the extent aforesaid.

2. We ................................................. Bank, further agree that AAI shall be the sole judge of and
as to whether the said Contractor has committed any breach or breaches of any of the terms
and conditions of the said contract and the extent of loss, damage, costs, charges and expenses
caused to or suffered by or that may be caused to or suffered by AAI on account thereof and
the decision of AAI that the said Contractor has committed such breach and breaches and as
to the amount or amounts of loss, damage, costs, charges and expenses caused to or suffered
of that may be caused to or suffered by AAI from time to time shall be final and binding on
us.

3. We, the said Bank, further agree that the Guarantee herein contained shall remain in full force
and effect during the period that would be taken for the performance of the said contracts and
till all the dues of AAI under the said contract or by virtue of any of the terms and conditions
governing the said contract including compensation for delay if any as decided by AAI, have
been fully paid and its claims satisfied or discharged and till the Accepting Authority of the
contract certifies that the terms and condition and accordingly Contract have been fully and
properly carried out by the said contractor and accordingly discharges this guarantee subject,
however that AAI shall have no claim under this Guarantee after 90(Ninety) days from the
date of expiry of the defects Liabilities periods or Final /Extension of Time grated by AAI as
provided available in agreements clause no……………..as provided in the said Contract,
i.e……….(date) or from the date of cancellation of the said contract, as the case may be,
unless a notice of the claim under this Guarantee has been served on the Bank before the
expiry of the period in which case the same shall be enforceable against the Bank not with
standing the fact, that the same is enforced after the expiry of the said period.

A.A.I. C-NIL I-NIL O-NIL Page 93


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

4. AAI shall have the fullest liberty without affecting in any way the liability of the bank under
this Guarantee or Indemnity from time to time to vary any of the terms and conditions of the
said contract or to extend time of performance by the said Contractor or to postpone for any
time and form time to time any of the powers exercisable by it against the said Contractor and
either to enforce or forbear from enforcing any of terms and conditions governing the said
contract or securities available to AAI and the said Bank shall not be released from its
liability under these present by any exercise by AAI of any liberty with reference to the
matters aforesaid or by reason of time being given to the said contractor or any other
forbearance, act or omission on the part by AAI or any indulgence by AAI to the said
Contractor or any other matter or thing whatsoever which under the law relating to sureties
would but for this provision have the effect of so releasing the Bank from its such liability.

5. It shall not be necessary for AAI to proceed against the contractor before proceeding against
the Bank and the Guarantee herein contained shall be enforceable against the Bank,
notwithstanding any security which AAI may have obtained or obtain from the Contractor at
the time when proceedings are taken against the Bank hereunder be outstanding or unrealized.

6. We, the said Bank, lastly undertake not to revoke this Guarantee during its currency except
with the previous consent of AAI in writing and agree that any charge in the Constitution of
the said Contract or the said Bank shall not discharge our liability hereunder.

In presence of
Dated this Day of
WITNESS
1.

2.
For and on behalf of (The Bank)
Signature

Name Designation
Authorization No.
Name&Place
Bank’s Seal

The above Guarantee is accepted by Airports Authority of India.


For and on behalf of Airports Authority of India
Signature
Name
Designation
Dated

A.A.I. C-NIL I-NIL O-NIL Page 94


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-1A

FORM OF BANK GUARANTEE AGAINST EARNEST MONEY DEPOSIT

WHEREAS, contractor ________________(Name of contractor) (herein after called “the contractor”) has
submitted his tender dated _________(date) for the construction of“____________ ” (name of work) (herein after
called “the TENDER”).

KNOW ALL PEOPLE by the represents that we_______________ (name of bank) having our registered office at
__________________(herein after called “the bank”) are bound unto Airports Authority of India through its “Bid
Manager/Engineer-in-charge/AAI’s Authorized representative” (Designation & address) (herein after called the
“Bid Manager/Engineer-in-charge/AAI’s Authorized representative”, as the case may be which expression shall
unless repugnant to the subject or contact includes its administrators, successors and assigns) in the sum of
(Rs. ___________ In words _________) for which payment will truly to be made to the said “Bid
Manager/Engineer-in-charge/AAI’s Authorized representative” the bank binds itself, his successors and assigns
by these presents.

SEALED with the Common Seal of the Bank this _________ day of _______ 20____. THE CONDITIONS of
this obligation are:
(1) If after tender opening the Contractor withdraws, his tender during the period of validity of tender
(including extended validity of tender) specified in the Form of Tender.
(2) If the contractor having been notified of the acceptance of his tender by the “Bid Manager/Engineer-in-
charge/AAI’s Authorized representative”.

(a) Fails or refuses to execute the form of Agreement in accordance with the instructions to contractor, if
required–
OR
(b) Fails or refuses to furnish the performance guarantee, in accordance with the provisions of tender
document and instructions to contractor,
OR
(c) Fails or refuses to start the work, in accordance with the provisions of the contract and instructions to
contractor,
OR
(d) Fails or refuses to submit fresh bank guarantee of an equal amount of this bank guarantee against
security deposit after award of contract.

We undertake to pay to the “Bid Manager/Engineer-in-charge/AAI’s Authorized representative” either up to the


above amount or part thereof upon receipt of his first return demand, without the Bid Manager/Engineer-in-
charge/AAI’s Authorized representative” having to substantiates his demand, provided that in his demand the
Bid Manager/Engineer-in-charge/AAI’s Authorized representative” will note that the amount claimed by him is
due to him owing to the concurrence of one or any of the above conditions, specifying the occurred condition or
conditions.
This guarantee will remain in force up to and including the date*______after the deadline for submission of
tender as such deadline is stated in the instructions to contractor or as it may be extended by the Bid
Manager/Engineer-in-charge/AAI’s Authorized representative”, notice of which extension (s) to the bank is hear
by waived. Any demand in respect of this guarantee should reach the bank not later than the above date.

DATE ……………. SIGNATURE OF BANK


WITNESS ………… SEAL
(SIGNATURE NAME AND ADDRESS)

Date to be worked out on the basis of validity period of 6 months from last date of receipt of tender.

A.A.I. C-NIL I-NIL O-NIL Page 95


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-II

PROFORMA FOR MANDATORY TESTS TO BE ATTACHED WITH RUNNING


ACCOUNT BILLS

Name of work: ....................................................... Name of


Contractor…………………………………...
Contract Agreement No. and Date………………………... R/A Bill

No………………………..……

Sl. Item Quantities Frequency No. of Upto No. of No. of Remarks


No. as per as per Tests date Tests Tests
Agreement Specification Required Quantity Required actually
done

1 2 3 4 5 6 7 8 9

Note: If the number of tests done are less than required, then reasons shall be recorded.

Signature of Sudt. (Engg)

Signature of Engineer-in-Charge. Signature of Manager /AM(Engg)

A.A.I. C-NIL I-NIL O-NIL Page 96


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-III

REGISTER OF MATERNITY BENEFITS (Clause 19F)

Name and address of the


contractor…………………………………………………………………………

Name and location of the


work………………………………………………………………………………

Name of the Father’s/husband’s Nature of Period of Date on which


employee name employment actual notice of
employment confinement given
1 2 3 4 5

Date on which maternity leave commenced and ended

In case of delivery In case of delivery


Date of
delivery/miscarriage
Commenced Ended Commenced Ended
6 7 8 9 10

Leave Pay paid to the employee

In case of delivery In case of miscarriage Remark

Rate of leave pay Amount paid Rate of leave Amount


pay paid
11 12 13 14 15

A.A.I. C-NIL I-NIL O-NIL Page 97


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-IV

SPECIMEN FORM OF THE REGISTER, REGARDING MATERNITY BENEFIT


ADMISSION TO THE CONTRACTOR'S LABOUR IN
AIRPORTS AUTHORITY OF INDIA WORKS (CLAUSE 19F)

Name and address of the contractor-------------------------------------------------------------------------------


Name and location of the work------------------------------------------------------------------------------------
------------------------------------------------------------------------------------
1) Name of the woman and her husband's name

2) Designation

3) Date of appointment

4) Date with months and years in which she is employed.

5) Date of discharge/dismissal, ifany

6) Date of production of certificates in respect of pregnancy.

7) Date on which the woman informs about the expected delivery.

8) Date of delivery/miscarriage/death.

9) Date of production of certificate in respect of delivery/miscarriage.

10) Date with the amount of maternity/death benefit paid in advance of expected delivery

11) Date with amount of subsequent payment of maternity benefit

12) Name of the person nominated by the woman to receive the payment of the maternity benefit

after the death.

13) If the woman dies, the date of her death, the name of the person to whom maternity benefit

amount was paid, the month thereof and the date in the register.

14) Signature of the contractor authenticating entries in the register.

15) Remarks column for the use of Inspection Officer.

A.A.I. C-NIL I-NIL O-NIL Page 98


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-V
Labour Board
Name of work
Name of Contractor---------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------Address of Contractor---------------
---------------------------------------------------------------------------------------------------------------------------
--------------------------------------
Name and address of A. A. I. Division ----------------------------------------------------------------------------
------------------------------------------------------------------------------------
Name of A. A. I. Labour Officer -----------------------------------------------------------------------------------
------------------------------------------------------------------------------------
Address of A. A. I. Labour Officer --------------------------------------------------------------------------------
-----------------------------------------------------------------------------------
Name of A.A.I Labour Officer---------------------------------------------------------------------

Sl.No. Category Minimum Actual wage Number Remark


wagefixed paid present

Weekly holiday-----------------------------------------------------------------------------------
Wage period--------------------------------------------------------------------------------------
Date of payment of wages-----------------------------------------------------------------------
Working hours-----------------------------------------------------------------------------------
Rest interval---------------------------------------------------------------------------------------

A.A.I. C-NIL I-NIL O-NIL Page 99


Various Formats to be maintained (Appendix)
AIRPORTS AUTHORITY OFINDIA

Form-XIII APPENDIX-VI
[See rule 2(1)]
[Part-A: For all Establishments]
Register of Workmen Employed by Contractor
Name and address of contractor……………………………………………………………………………………….
Name and address of establishment which contractor is carried on…………………………………………………...
Name and location of work…………………………………………………………………………………………….
Name and address of Principal Employer……………………………………………………………………………...

Name of the Establishment-------------------------------------------Name of Owner----------------------------------------------LIN-----------------------------------------------------


Sl. No. Employee Name Surname Gender Father’s/Spouse Date of Birth# Nationality Education Date of Designation
Code Name Level Joining

1 2 3 4 5 6 7 8 9 10 11

Category Type of Mobile UAN PAN ESIC IP LWF AADHAAR Bank A/c Bank Branch Present Permanent
Address Employment Number (IFSC) Address
*(HS/S/SS/US)
12 13 14 15 16 17 18 19 20 21 22 23 24

Service Book Date of Exit Reason for Exit Mark of Identification Photo Specimen Signature/Thumb Remarks
No. Impression
25 26 27 28 29 30 31

*(Highly Skilled/Skilled/Semi Skilled/Un Skilled)


#Note: In case the age is between 14 to 18 years, mention the nature of work, daily hours of work and Intervals of rest in the remarks
Column.

A.A.I. C-NIL I-NIL O-NIL Page 100


Various Formats to be maintained (Appendix) AIRPORTS AUTHORITY OFINDIA

APPENDIX-VII

Form-XVI
[See Rule 78(1) (a) (i)]

Muster Roll

Name and address of


contractor……………………………………………………………………………………….

Name and address of establishment which contractor is carried


on…………………………………………………...

Name and location of


work…………………………………………………………………………………………….

Name and address of Principal Employer .....................................For the month of fortnight…………….

Sl. Name Se x Father’s/ Date Remark


1 of 3 Husband’s
work 4 1 2 3 4 5
Man
2

A.A.I. C-NIL I-NIL O-NIL Page 101


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

FORM B
[See Rule 78(1) (a) (i)]
APPENDIX-VIII
FORMAT FOR WAGE REGISTER

Name and address of contractor……………………………………………………………………………………….

Name and address of establishment which contractor is carryon…………………………………………………...

Name and location of work…………………………………………………………………………………………….

Name and address of Principal Employer……………………………………For the month of fortnight…………….


Rate of Minimum Wages and since the date..............
Highly Skilled Skilled Semi-Skilled Un Skilled
Minimum Basic
DA

Overtime

Name of the Establishment Name of Owner LIN Wage period


From To (Monthly/Fortnightly/Weekly/Daily/Piece Rated)
Sl. No. in Name Rate of No. of Days Overtime Basic Special DA Payments HRA Others Total
Employee Wage worked hours Basic Overtime
register worked

1 2 3 4 5 6 7 8 9 10 11 12

A.A.I. C-NIL I-NIL O-NIL Page 102


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

Deduction Net Employer Share


Payment PF Welfare Found
PF ESIC Society Income Tax Insurance Others Recoveries Total
13 14 15 16 17 18 19 20 21 22

Receipt by Employee/Bank Date of Payment Remarks


Transaction ID
23 24 25

A.A.I. C-NIL I-NIL O-NIL Page 103


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

FORM C
FORMAT OF REGISTER OF LOAN/ RECOVERIES

Name of Establishment LIN

Sl. Number In Employee Name Recovery Type Particulars Date of damage/Loss* Amount
register (Damage/loss/fine/advance/loans

1 2 3 4 5 6

Whether show cause Explanation heard in Number of First Month/Year Last Month/Year Date of Complete Remarks
issued* presence of* Installments Recovery

7 8 9 10 11 12 13

*Applicable only in case of damage/loss/fine

A.A.I. C-NIL I-NIL O-NIL Page 104


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

Form-XVII [See Rule 78(2)(a)]

Register of wages

Name and address of contractor……………………………………………………………………………………….

Name and address of establishment which contractor is carried on…………………………………………………...

Name and location of work…………………………………………………………………………………………….

Name and address of Principal Employer……………………………………For the month of fortnight…………….

Amount of wages

S. Name of Serial no Descript No. of Units Daily Basic Dearness Over- Other Total Deduc Net Sig. or Initial
No workman in the ion/ days of rates of wage Allowanc time cash tion if amou thumb contract
register nature worked work wages/ s e payme any nt impres or his
of of work done piece rate nt nt. (indic paid sion of represe
workman done (indic ate the ntative
ate nature work
nature ) men
)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A.A.I. C-NIL I-NIL O-NIL Page 105


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-VIIIA
WAGE CARD

Wages Card No…………………………

Name and Address of Contractor……………………Date of issue………………………..

Name and location of work………………………….Designation…………………………

Name of workman………………………………….Month/Fortnight……………………..

Rate of Wages…………………………………………

12 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 31
0 123 456 789 012 345 67880

Morning Rate

Evening Amount

Initial

Received from…………………………………….the sum of Rs…............................................................. on account of my wages


Signature
The Wage Card is valid for one month from the date of issue

A.A.I. C-NIL I-NIL O-NIL Page 106


Various Formats to be maintained (Appendix) AIRPORTS AUTHORITY OFINDIA

19/Form-XIX APPENDIX-IX
78 (2)
[See rule 78 (1) (b)]

Wages Slip

Name and address of contractor……………………………………………………………

Name and Father’s/Husband name of workman…………………………………………...

Name and location of work………………………………………………………………...

For the week/Fortnight/Month ending……………………………………………………..

1. No. of days worked……………………………………………………………………

2. No. of units worked in case of piece rate workers…………………………………….

3. Rate of daily wages/piece rate…………………………………………………………

4. Amount of overtime wages……………………………………………………………

5. Gross wages payable………………………………………………………………….

6. Deduction, if any………………………………………………………………………

7. Net amount of wages paid…………………………………………………………….

Initials of the contractor or his representative

A.A.I. C-NIL I-NIL O-NIL Page 107


Various Formats to be maintained (Appendix) AIRPORTS AUTHORITY OFINDIA

APPENDIX-X

14/Form-XIV
[See rule 76]
Employment Card

Name and address of contractor……………………………………………………………

Name and address of establishment under which is carried……………………………….

Name of work and location of work……………………………………………………….

Name and address of Principal Employee…………………………………………………

1. Name of the workman………………………………………………………………...

2. SI. No. in the register of workman employed………………………………………...

3. Nature of employment/designation…………………………………………………..

4. Wage rate (with particulars of unit in case of piece work)…………………………..

5. Wage period…………………………………………………………………………

6. Tenure of employment………………………………………………………………

7. Remark………………………………………………………………………………

Signature of Contractor

A.A.I. C-NIL I-NIL O-NIL Page 108


Various Formats to be maintained (Appendix) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XI

FORM OF PERFORMANCE SECURITY (GUARANTEE)


Bank Guarantee Bond
(On Non-Judicial Stamp Paper of Rs100/-)

1. In consideration of the Chairman, AAI (hereinafter called “AAI”) having offered to accept the
terms and conditions of the proposed agreement between
………………………………………………………………………………………………
[hereinafter called the said contractor(s)] for the work …………………………… (here in
after “the said agreement”) having agreed to production of a irrevocable Bank Guarantee for
Rs.
….......................... (Rupees ………………………..only) as a security / guarantee from the
contractor(s) for compliance of his obligations in accordance with the terms and conditions in
the said agreement.
We .................................................. (Indicate the name of the Bank) (here in after referred to as
“theBank”)here by undertake to pay to the Chairman, AAIan amount not exceeding Rs.
………………… (Rupees ..............................only) on demand byAAI.

2. We ................................................. (Indicate the name of the Bank) do hereby undertake topay


the amounts due to payable under this Guarantee without any demure, merely on a demand
from AAI stating that the amount claimed is required to meet the recoveries due or likely to
be due from the said contractor(s). Any such demand made on the Bank shall be conclusive as
regards the amount due and payable by the Bank under this Guarantee. However, our liability
under this guarantee shall be restricted to an amount not exceeding Rs. .………………..
(Rupees. ...................................only).

3. We, the said Bank, further undertake to pay the Chairman, AAI any money so demanded not
with standing any dispute or disputes raised by the contractor(s) In any suit or proceeding
pending before any court or tribunal relating thereto, our liability under this present being
absolute and unequivocal.

The payment so made by us under this bond shall be a valid discharge of our liability for
payment there under and the contractor(s) shall have no claim against us for making such
payment.

4. We .............................................. (Indicate the name of bank) further agree that the guarantee
herein contained shall remain in full force and effect during the period that would be taken for
the performance of the said agreement and that it shall continue to be enforceable till all the
dues of AAI under or by virtue of the said agreement have been fully paid and its claims
satisfied or discharged or till Engineer-In-Charge on behalf of AAI certified that the terms
and conditions of the said agreement have been fully and properly carried out by the said
contractor(s) and accordingly discharges this guarantee.

5. We. ........................... (indicate the name of the bank) further agree with AAI thatAAI shall have
the fullest liberty without our consent and without effecting in any manner our obligations
hereunder to vary any of terms and conditions of the said agreement or to extend time of
performance by the said contractor(s) from time to time or to postpone for any time or from time
to time any of the powers exercisable by AAI against in the said contractor(s) and to forebear and
enforce any of the terms and conditions relating to the said agreement and we shall not be relieved
from our liability by reason of any such variation, or extensions being granted to the said
contractor(s) or for any forbearance, act of omission on the part of AAI or any indulgence by the
AAI to the said contractor(s) or by any such matter or thing whatsoever which under the law
relating to securities would, but for this provision, have effect of so relieving us.

A.A.I. C-NIL I-NIL O-NIL Page 109


Various Formats to be maintained (Appendix) AIRPORTS AUTHORITY OFINDIA

6. This guarantee will not be discharged due to the change in the constitution of the Bank or the
contractor(s).

7. We ........................................ (Indicate the name of the bank) lastly undertake not to revoke
this guarantee except with the previous consent of AAI in writing.

8. This guarantee shall be valid up to ................................................. unless extended on demand


by AAI. Not withstanding anything mentioned above, our liability against this guarantee is
restricted to Rs……………….. (Rupees ............................. only) and unless a claim in writing
is lodged within six months of the date of expiry or the extended date of expiry of this
guarantee all our liabilities under this guarantee shall stand discharged.

In presence of
Datedthis Dayof
Witness
1.
2.
For and on behalf of (TheBank)
Signature
Name&Designation

Authorization No.
Name&Place
Bank’s Seal

The above Guarantee is accepted by Airports Authority of India. For and on behalf of Airports
Authority of India
Signature
Name
Designation
Dated
Note: * Date of validity should be schedule date of completion + Six months.

A.A.I. C-NIL I-NIL O-NIL Page 110


Various Formats to be maintained (Appendix) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XI-A

Format for Letter of undertaking from the Depositor to Bank


(To be submitted along with Security Deposit / Earnest Money / Performance Guarantee to
Airports Authority of India)
(To be submitted in the Letter head of the firm)

The Branch Manager,


………………..Bank,
…………………….

Sub: - My / Our Bank Guarantee bearing No……..dated ……. for amount……. Issued in
favour of Airport Authority of India A/c……………

Sir,

The subject Bank Guarantee is obtained from your bank for the purpose of Security
Deposit / Earnest Money / Performance Guarantee on account of contract awarded / to be
awarded by M/s Airports Authority of India to me / us.

I hereby authorized the Airport Authority of India in whose favour the deposit is made
to close the subject Bank Guarantee before maturity/ on maturity toward adjustment of dues
without any reference /consent /notice from me / our side and the bank is fully discharged by
making the payment to Airport Authority of India.

Signature of the Depositor

Place:

Date:

A.A.I. C-NIL I-NIL O-NIL Page 111


Various Formats to be maintained (Appendix) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XII

LIST OF ACTS AND OMISSIONS FOR WHICH FINES CAN BE IMPOSED

In accordance with rule 7(v) of the AAI Contractor's Labour Regulations to be displayed prominently
at the site of work both in English and local Language.

1. Willful in subordination or disobedience, whether alone or in combination with other.

2. Theft fraud or dishonesty in connection with the contractors beside a business or property of

AAI.

3. Taking or giving bribes or any illegal gratifications

4. Habitual late attendance.

5. Drunkenness lighting, riotous or disorderly or in different behavior

6. Habitual negligence.

7. Smoking near or around the area where combustible or other materials are locked

8. Habitual Indiscipline

9. Causing damage to work in the progress or to property of the AAI or of the contractor.

10. Sleeping onduty.

11. Malingering or slowing down work.

12. Giving of false information regarding name, age, father's name,etc.

13. Habitual loss of wage cards supplied by the employer’s

14. Unauthorized use of employer's property of manufacturing or making of unauthorized

particles at the workplace

15. Bad workmanship in construction and maintenance by skilled workers which is not approved

by the Department and for which the contractors are compelled to undertake rectifications.

16. Making false complaints and/or misleading statements.

17. Engaging on trade within the premises of the establishments.

18. Any unauthorized divulgence of business affairs of the employees.

A.A.I. C-NIL I-NIL O-NIL Page 112


Various Formats to be maintained (Appendix) AIRPORTS AUTHORITY OFINDIA

19. Collection or canvassing for the collection of any money within the premises of an

establishment unless authorized by the employer.

20. Holding meeting inside the premises without previous sanction of the employers.

21. Threatening or intimidating any workman or employer during the working hours within the

premises.

A.A.I. C-NIL I-NIL O-NIL Page 113


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XIII

Form-XVII [See Rule 78(2)(d)]

Register of Fines

Name and address of contractor……………………………………………………………………………………….

Name and address of establishment which contractor is carried on…………………………………………………...

Name and location of work…………………………………………………………………………………………….

Name and address of Principal Employer……………………………………………………………….…………….

SI. No. Name of Father’s/ Designatio Act or Date of Whether Name of person Wage Amount Date on Remarks
workman Husband’ n/nature of action for Offence workman in whose period of the which
s employmen which showed presence and imposed fine
Name t fine cause employee’s wages realized
imposed against fine explanation was payable
heard
1 2 3 4 5 6 7 8 9 10 11 12

A.A.I. C-NIL I-NIL O-NIL Page 114


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XIV

Form-XVII
[See Rule 78 (2) (d)]
Register of Deduction for Damage or Loss

Name and address of contractor……………………………………………………………………………………….

Name and address of establishment under which contract is carried on…………………………………………………...

Name and location of work…………………………………………………………………………………………….

Name and address of Principal Employer……………………………………………………………….…………….

SI. Name Father’s Designation Particular Date of Whether Name of Amount No. of Date of
No. of Husband’ /nature of of damag workman person in of install recovery
workma s Name employmen Damages es or showed whose deductio ments First Last
nn t or Loss loss cause presence n Instal Instal Remark
against employee’s imposed lment lment
deductio explanation
n was heard
1 2 3 4 5 6 7 8 9 10 11 12 13

A.A.I. C-NIL I-NIL O-NIL Page 115


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XV

Form-XXII
[See Rule 78 (2) (d)]
Register of Advances

Name and address of contractor…………………………………………………………………………………………………………………….

Name and address of establishment under which contract is carried on………………………………………………….......................................

Name and location of work…………………………………………………………………………………………………………………………

Name and address of Principal Employer……………………………………………………………….………………………………………….

SI. Name Father’s Designation Wage Date and Purpose Number of Date and Date on
No. of Husband’ /nature of period amount for installment amount of which last
workma s Name employmen and of which by which each install ment
nn t wages advance advance advance to be installme was repaid Remark
payable e paid paid repaid nt repaid

1 2 3 4 5 6 7 8 9 10 11

A.A.I. C-NIL I-NIL O-NIL Page 116


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XVI

Form-XXIII [See Rule 78(2)(e)]

Register of Overtime

Name and address of contractor……………………………………………………………………………………….

Name and address of establishment under which contract is carried on…………………………………………………...

Name and location of work…………………………………………………………………………………………….

Name and address of Principal Employer……………………………………………………………….…………….

S. Name of Father’s/ Sex Designation/ Date on Total overtime Normal Overtime Overtim Rate on which Remarks
N workme Husbands nature of which worked at rate of rate of e overtime paid
o n Name employment overtime project in case wages wages earning
worked of piece rate
1 2 3 4 5 6 7 8 9 10 11 12

A.A.I. C-NIL I-NIL O-NIL Page 117


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XVII
NOTICE FOR APPOINTMENT OF ARBITRATOR
[Refer Clause 25]

To
………………………………..
………………………………..
………………………………..

Dear Sir,
In terms of clause 25 of the agreement, particular of which are given below, I/we hereby give notice to
you to appoint an arbitrator for settlement of disputes mentioned below:

1. Name of applicant
2. Whether applicant is Individual/Prop. Firm /PartnershipFirm/Ltd.Co.
3. Full address of the applicant.
4. Name of the work and contract number in which arbitrator sought.
5. Name of the office which enteredin to contract.
6. Contract amount in the work.
7. Date of contract.
8. Date of initiation of work.
9. Stipulated date of completion of work.
10. Actual date of completion of work (if completed).
11. Total number of claimmade.
12. Total amount claimed.
13. Date of intimation of final bill (if work is completed).
14. Date of payment of final bill (if work is completed).
15. Amount of final bill (if work is completed).
16. Date of request made to ED for decision.
17. Date of receipt of ED’s decision.
18. Date of appeal.
19. Date of receipt of decision on our appeal.

Specimen signature of the applicant


(Only the person/authority who
Signed the contract should sign)

I/We certify that the information given above is true to the best of my/our knowledge. I/We enclose following
documents.

1. Statement of claims with amount of claims.


2.
3.
4.

Yours faithfully

(Signature)

Copy to:
1. The Engineer-in-charge. ........................... ,
…………………………

A.A.I. C-NIL I-NIL O-NIL Page 118


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX -XVIII

INTEGRITY PACT

The integrity pact shall be signed by both the parties in the following format

“This Pact made this ……..day of …… between Airports Authority of India, a body
corporate constituted by the Central Government under the Airports Authority of
India Act,1994 and having its Corporate Office at Rajiv Gandhi Bhawan, New Delhi,
and offices at ………….in India, hereinafter called the Authority (which term shall
unless excluded by or is repugnant to the context, be deemed to include its Chairman,
or Member, Executive Directors, Airport Directors, officers or any of them specified
by the Chairman in this behalf, and shall also include its successors and assigns) of
the one part

AND

……represented by ……… of the other part, hereinafter called the “Bidder/Contractor


“(which term shall unless excluded by or is repugnant to the context be deemed to
include its heirs, representatives, successors and assigns of the Bidder/Contractor)
WHEREAS the Authority intends to award, under laid down organizational
procedures, tender/ contractfor ..............................The Authority, while discharging its
functions on business principles, values proper compliance with all relevant laws and
regulations, and the principles of natural ,justice, ethics, equity, fairness and
transparency in its relations with the Bidders/ Contractors.

WHEREAS the Authority is desirous to make its business mechanism more


transparent, thus to ensure strict adherence of the aforesaid objectives/goals, the
Authority hereby adopts the instrument developed by the renowned international non‐
governmental organization “Transparency International” (T I ) headquartered in
Berlin ( Germany ). The Authority will appoint an Independent External Monitor
(IEM) who will monitor the tender process and the execution of the contract for
compliance with the principles mentioned above.

AND WHEREAS the Bidder is submitting a tender to the Authority for


…………………….In response to the NIT(Notice Inviting Tender) dated………
Contractor is signing the contract for execution of ……NOW, therefore, To avoid all
forms of corruption by following a system that is fair, transparent and free from any
influence/prejudiced dealings prior to, during and subsequent to the currency of the
contract to be entered into with a view to Enabling the Authority to obtain the desired
said stores/equipment/execution of works at a competitive price in conformity with
the defined specifications by avoiding the high cost and the distortionary impact of
corruption on public procurement, and Enabling Authority to abstain from bribing or
indulging in any corrupt practice in order to secure the contract by providing
assurance to them that their competitors will also abstain from bribing and other
corrupt practices and the Authority will commit to prevent corruption, in any form, by
its officials by following transparent procedures. The parties hereto hereby agree to
enter into this Integrity Pact and agree as follows:

A.A.I. C-NIL I-NIL O-NIL Page 119


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

1. Commitments of the Authority;

1.1 The Authority undertakes that no official of the Authority, connected directly or
indirectly with the contract, will demand, take a promise for or accept, directly or
through intermediaries, any bribe, consideration, gift, reward, favour or any
material or immaterial benefit or any other advantage from the BIDDER, either
for themselves or for any person, organization or third party related to the
contract in exchange for an advantage in the bidding process, bid evaluation,
contracting or implementation process related to the contract.

1.2 The Authority will, during the pre‐contact stage, treat all BIDDERs alike, and
will provide to all BIDDERs the same information and will not provide any such
information to any particular BIDDER which could afford an advantage to that
particular BIDDER in comparison to other BIDDERs.

1.3 All the officials of the Authority will report to the appropriate authority office any
attempted or completed breaches of the above commitments as well as any
substantial suspicion of such a breach.

1.4 In case any such preceding misconduct on the part of such official(s) is reported
by the BIDDER to the Authority with full and verifiable facts and the same is
prima facie found to be correct by the Authority, necessary disciplinary
proceedings, or any other action as deemed fit, including criminal proceedings
may be initiated by the Authority and such a person shall be debarred from
further dealings related to the contract process. In such a case while an enquiry is
being conducted by the Authority the proceedings under the contract would not be
stalled.

2. Commitments of Bidders/Contractor.

The Bidder/Contractor commits itself to take all measures necessary to prevent


corrupt practice, unfair means and illegal activities during any stage of its bid or
during any pre‐contract or post‐contract stage in order to secure the contract or in
furtherance to secure it and in particular commit itself to the following.

2.1 The Bidder/Contractor will not offer, directly or through intermediaries, any
bribe, gift, consideration, reward, favour, any material or immaterial benefit or
other advantage, commission, fees, brokerage or inducement to any official of the
Authority, connected directly or indirectly with the bidding process, or to any
person, organization or third party related to the contract in exchange for any
advantage in the bidding, evaluation, contracting and implementation of the
contract.

2.2 The Bidder/Contactor further undertakes that it has not given, offered or promised
to give, directly or indirectly any bribe, gift, consideration, reward, favour, any
material or immaterial benefit or other advantage, commission, fees, brokerage or
inducement to any official of the Authority or otherwise in procuring the Contract
or forbearing to do or having done any act in relation to the obtaining or
execution of the contractor any other contract with the Authority for showing or

A.A.I. C-NIL I-NIL O-NIL Page 120


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

forbearing to show favour or disfavour to any person in relation to the contract or


any other contract with the Authority.

2.3 The Bidder / Contactor has not entered and will not enter with other bidders into
any undisclosed agreement or understanding, whether formal or informal. This
applies in particular to prices, specification, certifications, subsidiary contracts,
submission or non‐submission of bids or any actions to restrict competitiveness or
to introduce cartelization in the bidding process.

2.4 The Bidder/Contractor shall, when presenting his bid, disclose the name and
address of agents and representatives and Indian BIDDERs shall disclose their
foreign principals or associates.

2.5 The Bidder/Contactor shall when presenting his bid disclose any and all the
payments he has made or, is committed to or intends to make to agents/brokers or
any other intermediary, in connection with this bid/contract.

2.6 The Bidder/Contractor further confirms and declares to the Authority that the
BIDDER is the original manufacturer/integrator/ authorized government
sponsored export entity of the stores and has not engaged any individual or firm
or company whether Indian or foreign to intercede, facilitate or in any way to
recommend to the Authority or any of its functionaries, whether officially or
unofficially to the award of the contract to the BIDDER, nor has any amount been
paid, promised or intended to be paid to any such individual, firm or company in
respect of any such intercession, facilitation or recommendation.

2.7 The Bidder/Contractor, either while presenting the bid or during pre‐contract
negotiations or before signing the contract, shall disclose any payments he has
made or has committed to or intends to make to officials of the Authority or their
family members, agents, brokers or any other intermediaries in connection with
the contract and the details of services agreed upon for such payments.

2.8 The Bidder/Contractor will not collude with other parties interested in the
contract to impair the transparency, fairness and progress of the bidding process,
bid evaluation, contracting and implementation of the contract.

2.9 The Bidder/Contractor will not accept any advantage in exchange for any corrupt
practice, unfair means and illegal activities.

2.10 The Bidder / Contactor shall not use improperly, for purposes of competition or
personal gain ,or pass on to others, any information provided by the Authority as
part of the business relationship, regarding plans, technical proposals and
business details, including information contained in any electronic data carrier.
The Bidder / Contractor also under takes to exercise due and adequate care lest
any such information is divulged.

2.11 The Bidder/Contractor will inform to the Independent External Monitor.

i) If he receives demand for an illegal/undue payment/benefit.


A.A.I. C-NIL I-NIL O-NIL Page 121
Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

ii) If he comes to know of any unethical or illegalpayment/benefit.

iii) If he makes any payment to any Authority’s associate(s)

2.12 The Bidder/Contactor commits to refrain from giving any complaint directly or
through any other manner without supporting it with full and verifiable facts.

2.13 The Bidder/Contactor shall not instigate or cause to instigate any third person to
commit any of the actions mentioned above.

2.14 If the Bidder/Contractor or any employee of the Bidder/Contractor or any person


acting on behalf of the Bidder/ Contractor, either directly or indirectly, is a
relative of any of the officers of the Authority, or alternatively, if any relative of
an officer of the Authority has financial interest/stake in the Bidder’s/Contractor’s
firm, the same shall be disclosed by the Bidder/Contractor at the time filing of
tender. The term ‘relative’ for this purpose would be as defined in Section 6 of
the Companies Act1956.

2.15 The Bidder/Contractor shall not lend to or borrow any money from or enter into
any monetary dealings or transactions, directly or indirectly, with any employee
of the Authority.

2.16 That if the Bidder/ Contractor, during tender process or before the award of the
contract or during execution of the contract/work has committed a transgression
in violation of section 2 or in any other form such as to put his reliability or
credibility as Bidder/Contractor into question, the Authority is entitled to
disqualify him from the tender process or to terminate the contract for such reason
and to debar the BIDDER from participating in future bidding processes.

3. Previous Transgression

3.1 The Bidder/Contractor declares that no previous transgression occurred in the last
three years immediately before signing of this Integrity Pact, with any other
company in any country in respect of any corrupt practices envisaged hereunder
or with any Public Sector Enterprise in India or any Government Department in
India that could justify Bidders’s exclusion from the tender process.

3.2 The Bidder/Contractor agrees that if it makes incorrect statement on this subject,
he can be disqualified from the tender process or the contract, if already awarded,
can be terminated for such reason and he may be considered for debarment for
future tender/contract processes.

3.3 That the Bidder/Contractor undertakes to get this Pact signed by the
subcontractor(s) and associate(s) whose value of the work contribution exceeds Rs
0.5 Cr. (Rupees zero point five Cr.) and to submit the same to the Authority along-
with the tender document/ contract before contract signing.

3.4. That sub-contractor(s)/ associate(s) engaged by the Contractor, with the approval
of the Authority after signing of the contract, and whose value of the work
contribution exceeds Rs 0.5Cr. (Rupees Zero point five Cr.) will be required to

A.A.I. C-NIL I-NIL O-NIL Page 122


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

sign this Pact by the Contractor, and the same will be submitted to the Authority
before doing/ performing any act/ function by such subcontractor(s) / associate(s)
in relation to the contract/ work.

3.5 That the Authority will disqualify from the tender process all Bidder(s) who don’t
sign this Pact or violate its provisions or fails to get this Pact signed in terms of
policy of authority

3.6 That if the Contractor(s) does/ do not sign this Pact or violate its provisions or
fails to get this Pact signed in terms of policy of authority. Authority will
terminate the contract and initiate appropriate action against such Contractor(s).

4. Earnest Money, Security Deposit, Bank Guarantee, Draft, Pay order or any
other mode and its validity i/c Warranty Period, Performance
Guarantee/Bond.

While submitting bid, the BIDDER shall deposit an EMD/SD/BG/DRAFT/PAY


ORDER ETC I/C WARRANTY PERIOD, PG/BOND, VALIDITY etc., which is
as per terms and conditions and details given in NIT / tender documents sold to
the Bidders.

5. Sanctions for Violations/Disqualification from tender process and exclusion


from future Contacts.

5.1 Any breach of the aforesaid provisions by the BIDDER or any one employed by
it or acting on its behalf (whether with or without the knowledge of the BIDDER)
shall entitle the Authority to take all or any one of the following actions,
wherever required:

i) To immediately call off the pre contract negotiations without assigning any
reason or giving any compensation to the BIDDER. However, the
proceedings with the other BIDDER(s) would continue.

ii) To immediately cancel the contract, if already signed, without giving any
compensation to the BIDDER.

iii) If the Authority has disqualified / debarred the Bidder from the tender
process prior to the award under section 2 or 3 or 4, the Authority is entitled
to forfeit the earnest money deposited/bid security.

iv) To recover all sums already paid by the Authority, and in case of an Indian
BIDDER with interest thereon at 2% higher than the prevailing Prime
Lending Rate of State Bank of India, while in case of a BIDDER from a
country other than India with interest thereon at 2% higher than the LIBOR.
If any outstanding payment is due to the BIDDER from the Authority in
connection with any other contract or any other stores, such outstanding
payment could also be utilized to recover the aforesaid sum and interest.

A.A.I. C-NIL I-NIL O-NIL Page 123


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

v) To en-cash the advance bank guarantee and performance bond/warranty


bond, if furnished by the BIDDER, in order to recover the payments,
already made by the BUYER, along with interest.

vi) To cancel all or any other Contracts with the BIDDER. The BIDDER shall
be liable to pay compensation for any loss or damage to the Authority
resulting from such cancellation/rescission and the Authority shall be
entitled to deduct the amount so payable from the money(s) due to the
BIDDER.

vii) To debar the BIDDER from participating in future bidding processes for a
minimum period of three years, which may be further extended at the
discretion of the Authority.

viii) To recover all sums paid in violation of this Pact by BIDDER(s) to any
middleman or agent or broker with a view to securing the contract.

ix) In case where irrevocable Letters of Credit have been received in respect of
any contract signed by the Authority with the BIDDER, the same shall not
be opened.

x) Forfeiture of Performance Bond in case of a decision by the BUYER to


forfeit the same without assigning any reason for imposing sanction for
violation of this Pact.

xi) That if the Authority have terminated the contract under section 2 or 3 or 4
or if the Authority is entitled to terminate the contract under section 2 or 3
or 4, the Authority shall be entitled to demand and recover from the
contractor damages equivalent to 5% of the contract value or the amount
equivalent to security deposit or performance bank guarantee, whichever is
higher.

xii) That the Bidder / Contractor agrees and undertakes to pay the said amount
without protest or demur subject only to condition that if the
Bidder/Contractor can prove and establish to the satisfaction of the
Authority that the disqualification / debarment of the bidder from the tender
process or the termination of the contract after award of the contract has
caused no damage to the Authority.

5.2 The Authority will been titled to take all or any of the actions mentioned at para
5.1 above.

5.3 (i) to (xii) of this Pact also on the Commission by the BIDDER or any one
employed by it or acting on its behalf (whether with or without the knowledge of
the BIDDER), of an offence as defined in Chapter IX of the Indian Penal code,
1860 or Prevention of Corruption Act, 1988 or any other statute enacted for
prevention of corruption.

A.A.I. C-NIL I-NIL O-NIL Page 124


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

5.4 That if the Bidder/Contractor applies to the Authority for premature revocation of
the debarment and proves to the satisfaction of the Authority that he has installed
a suitable and effective corruption prevention system and also restored/recouped
the damage, if any, caused by him, the Authority may, if thinks fit, revoke the
debarment prematurely considering the facts and circumstances of the case, and
the documents/evidence adduced by the Bidder/Contractor for first time default.

5.5 That a transgression is considered to have occurred if the Authority is fully


satisfied with the available documents and evidence submitted along with
Independent External Monitor’s recommendations/suggestions that no reasonable
doubt is possible in the matter.

5.6 The decision of the Authority to the effect that a breach of the provisions of this
Pact has been committed by the BIDDER shall be final and conclusive on the
BIDDER. However, the BIDDER can approach the Independent External
Monitor(s) appointed for the purpose of this Pact.

6. Allegations against Bidders/Contractors/Sub‐Contractors/Associates:

That if the Authority receives any information of conduct of a Bidder/ Contractor


or Sub- Contractor or of an employee or a representative or an associate of the
Bidder, Contractor or Sub- Contractor which constitute corruption, or if the
Authority has substantive suspicion in this regard, the Authority will inform the
Vigilance Department for appropriate action.

7. Independent External Monitor(s),

7.1. That the Authority has appointed competent and credible Independent External
Monitor(s) for this Pact.

7.2 The task of the Monitor(s) is to review independently and objectively, whether
and to what extent the parties comply with the obligations under this Pact. He will
also enquire into any complaint alleging transgression of any provision of this
Pact made by the Bidder, Contractor or Authority.

7.3. That the Monitor(s) is not subject to any instructions by the representatives of the
parties and would perform his functions neutrally and independently. He will
report to the Chairperson of the Board of the Authority.

7.4 That the Bidder / Contractor accepts that the Monitor(s) has the right to access
without restriction to all project documentation of the Authority including that
provided by the Bidder/Contractor. The Bidder/Contractor will also grant the
Monitor, upon his request and demonstration of a valid interest, unrestricted and
unconditional access to his project documentation including minutes of meeting.
The same is applicable to Sub - Contractors and Associates. The Monitor is under
obligation to treat the information and documents of the Authority and Bidder/
Contractor / Sub- Contractors/ Associates with confidentiality.
7.5. That as soon as the Monitor notices, or believes to notice, a violation of this Pact,
he will so inform the management of the Authority and request the management

A.A.I. C-NIL I-NIL O-NIL Page 125


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

to discontinue or heal the violation, or to take other relevant action. The


Monitor(s) can in this regard submit his recommendations/ suggestions. Beyond
this, the Monitor(s) has no right to demand from the parties that they act in a
specific manner, refrain from action or tolerate action.

7.6 That the Authority will provide to the Monitor(s) sufficient information about all
meetings among the parties related to the project provided such meetings could
have an impact on the contractual relations between the Authority and the
Contractor / Bidder. The parties offer to the Monitor(s) the option to participate in
such meetings.

7.7 That the Monitor(s) will submit a written report to the Chairperson of the Board
of the Authority within 2 weeks from the date of reference or intimation to him
by the Authority and, should the occasion arise, submit proposals for correcting
problematic situations.

7.8 That if the Monitor(s) has reported to the Chairperson of the Board a
substantiated suspicion of an offence under relevant Anti- Corruption Laws of
India and the Chairperson has not, within reasonable time, taken visible action to
proceed against such offence or reported it to the Vigilance Department, the
Monitor may also transmit this information directly to the Central Vigilance
Commissioner, Government of India.

7.9 The word ‘Monitor’ would include singular and plural.

8. Facilitation of Investigation.

In case of any allegation of violation of any provisions of this Pact or payment of


commission, the Authority or its agencies shall be entitled to examine all the
documents including the Books of Accounts of the BIDDER and the BIDDER
shall provide necessary information and documents in English and shall extend all
possible help for the purpose of such Examination.

9. Law and Place of Jurisdiction.

That this Pact is subject to provisions under Indian Law. The place of
performance and jurisdiction is the Corporate Headquarter /the Regional
Headquarter / office of the Authority, asapplicable.

10. Other Legal Actions

10.1 That the changes and supplements as well as termination notice need to be made
in writing.

10.2 That if the Bidder / Contractor are a partnership or a consortium, this Pact must be
signed by all the partners and consortium members or their authorized
representatives.

A.A.I. C-NIL I-NIL O-NIL Page 126


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

11. Pact duration (Validity)

11.1 That this Pact comes into force when both the parties have signed it. It expires for
the Contractor 12 months after the final payment under the respective contract,
and for all other Bidders 3 months after the contract is awarded.

11.2. That if any claim is made / lodged during this period, the same shall be binding
and continue to be valid despite the lapse of this Pact as specified herein before,
unless it is discharged/determined by Chairman of the Authority.

11.3 That should one or several provisions of this Pact turn out to be invalid; the
remainder of this Pact shall remain valid. In this case, the parties will strive to
come to an agreement to their original intentions.

12. Company Code of Conduct

Bidders are also advised to have a company code of conduct (clearly rejecting the
use of bribes and other unethical behavior) and a compliance program for the
implementation of the code of conduct throughout the company.

13. The parties hereby sign this Integrity Pact at on

Buyer
Name of the Officer
Designation
Deptt./Ministry/PSU
Witness

1.

2.

Bidder

CHIEF EXECUTIVE OFFICER


Witness
1.

2.

A.A.I. C-NIL I-NIL O-NIL Page 127


Various Formats to be maintained (Appendix ) AIRPORTS AUTHORITY OFINDIA

APPENDIX-XIX

(To be filled by Contractor)


(CLAUSE-47)

Ratio of direct payment to the specialized : …% of the net payment to be made to Specialized
agency in case of composite contract agency

Sl. Sub-head Nature of work % of the net payment to be


made to Specialized agency
1 Sub-head I

Note:

1. NIT approving authority must ensure that all sub-heads of works are covered in above table.
The bidder must indicate percentage payable to specialized agency in case of all sub-heads.
2. If % is not filled in by the contractor against one or more subhead in this schedule, then 75%
of the net payment admissible as per AAI for the subhead under consideration shall be paid
directly to specialized agency in case of composite contract.

A.A.I. C-NIL I-NIL O-NIL Page 128


Schedules AIRPORTS AUTHORITY OFINDIA

DELETED

SKETCH OF CEMENT GODOWN

A.A.I. C-NIL I-NIL O-NIL Page 129


Schedules AIRPORTS AUTHORITY OFINDIA

SCHEDULES

SCHEDULE `A’

All rates shall be quoted in the format provided and no other format is acceptable. The price bid has been
given as a standard BOQ format at page no. BOQ-1 to BOQ-2 with the tender document, then the same is
to be downloaded and to be filled by all the bidders. Bidders are required to download the BOQ file, open
it and complete the white coloured (unprotected) cells with their respective financial quotes and other
details (such as name of the bidder). No other cells should be changed. Once the details have been
completed, the bidder should save it and submit it online, without changing the File name. if the BOQ file
is found to be modified by the bidder, the bid will be rejected and EMD shall be forfeited.

SCHEDULE `B’

Schedule of materials to be issued to the contractor.

Sl. No. Description of Item Quantity Rates in figures & Place of Issue
words at which the
material will be
charged to the
contractor
1 2 3 4 5

A.A.I. C-NIL I-NIL O-NIL Page 130


Schedules AIRPORTS AUTHORITY OFINDIA

SCHEDULE `C’

Tools and plants to be hired to the contractor.

Sl.No. Description Hire charges perday Place ofIssue


1 2 3 4

NOT APPLICABLE
I

SCHEDULE`D’

Extra schedule for specific requirements/ documents for the work, if any. Not Applicable

SCHEDULE`E’

Reference to General Condition of contract

Name of work: Levelling and grading of area at 24 & 06 side in newly acquired land at S.V. Airport,
Raipur.

Estimated cost of work: Rs. 3,05,35,323/-

i. Earnest Money: Rs. 6,10,706/-


ii Performance Guarantee: 5% of contractvalue
iii Security deposit: 5% or 10% of contract value (Delete whichever not applicable)

A.A.I. C-NIL I-NIL O-NIL Page 131


Schedules AIRPORTS AUTHORITY OFINDIA

SCHEDULE `F’

GENERAL RULES & DIRECTION

Officer inviting tender : AGM (Engg.-C)-I, S.V. Airport, Raipur.

Maximum percentage for quantity of items of a: 30 % (Overall)


work to be executed beyond which rates are to be
determined in accordance with Clauses 12.2& b: 100 % (For foundation items)
12.3

Definitions:

Office inviting tender : AGM(E-C)-I, O/o Airport Director,


Airports Authority of India
S.V. Airport, Raipur
2(v) Engineer-in-Charge : AGM (E-C)-I, AAI, RAIPUR
2(viii) Accepting Authority : As per DOP of AAI
2(x) Percentage on cost materials & Labour : 15%
to cover all overheads & Profits
2(xi) Standard schedule of rates : DSR 2018, with up to date correction slips as on last
date of submission of tenders & Market rates based
on MoRTH Specifications.
2(xii) Department : AAI, Engineering Wing, Raipur
Clause 1

(i) Time allowed for submission of


Performance Guarantee from the date of Not Applicable
issue of letter of acceptance

(ii) Maximum allowable period of extension Not Applicable

Clause 2
Authority for fixing compensation under As per DOP of AAI
Clause 2

Clause 2A

Whether Clause 2A shall be applicable Yes/ No


Clause 5

Number of days from the date of issue of


letter of acceptance for reckoning date of 10 days
start

A.A.I. C-NIL I-NIL O-NIL Page 132


Schedules AIRPORTS AUTHORITY OFINDIA

Mile Stone(s) as per table given below:


Sl.No. Description of Milestones (Physical) Time allowed Amount to be withheld in case of
in days (from non achievement of
date of start) milestone
1 Total 25% Progress 60 Days 5% of targeted mile stone amount
2 Total 66% Progress 158 Days 3% of targeted mile stone amount
3 Total 100% Progress 240 Days 2% of targeted mile stone amount

Time allowed for execution of work. : 08 (Eight) Months

Authority to decide:
i Extension of time : As per DOP
ii Re-scheduling of milestone : GM (Engg), ER
iii Shifting of date of start in : ED(Engg), ER
case of delay in handing over
of site

Clause 6, 6A

Clause applicable–(6 or 6A) : Clause 6A is applicable


Clause 7

Gross work to be done together with net


payment/adjustment of advances for material 10.00 Lakhs
collected, if any since the last such payment for
being eligible to interim payment.

Clause 10A
Testing equipment to be provided by the contractor:
All Testing equipment’s required for conducting test as per CPWD specification 2019, MORTH
specification.

Clause 10 B(II)

Whether Clause 10B (II) shall Yes/ No


be applicable

Clause10C: Applicable

Component of labour expressed as percent of value of work:


Category of work Material Labour P.O.L

1. Road works and pavement works in Airfields 90% 5% 5%

A.A.I. C-NIL I-NIL O-NIL Page 133


Schedules AIRPORTS AUTHORITY OFINDIA

Clause 10 CA

Materials covered under Nearest Material (other than Base price and its corresponding period of all the
this clause cement*, reinforcement materials covered under clause 10CA
bars, structural steel) for
which All India
Wholesale Price index is to be
followed
Cement (OPC/ PPC) Grey Cement Base price for cement, reinforcement steel and
Structural steel to be determined as issued under
authority of DG(Works). CPWD or concerned
Zonal Chief Engineer, CPWD as on last date of
receipt of tender.
In case base price for cement, reinforcement steel
and Structural Steel as to be issued by CPWD is
not available concerned ED (Engg) empowered to
determine the same.

*Note:
1. Includes cement component used in RMC brought at site from outside approved RMC plants, if any.
2. Base price and its corresponding period of all the materials covered under clause 10CA is to be
mentioned at the time of approval of NIT. In case of recall of tenders, the base price may be modified
by adopting latest base price and its corresponding period.

Clause 10 CC

Clause 10CC to be applicable in contracts with 18 Months


stipulated period of completion exceeding the
period shown in next column

Schedule of component of other materials, Labour, POL etc. for price escalation.

Component of civil (except material covered under clause 10 CA) / Electrical construction materials
express as percentage total value of work …………. …… Xm- %.

Component of labour, expressed as % of total valueofwork………Y - %.

Component of POL, expressed as % of total valueofwork ............... Z- %

Note: Xm..... % should be equal to (100) – (material covered under clause 10 CA i.e. cement, steel
and Other materials specified in clause 10 CA + component of labour + component of POL).

A.A.I. C-NIL I-NIL O-NIL Page 134


Schedules AIRPORTS AUTHORITY OFINDIA

Clause11

Specification to be followed for execution of work a) “CPWD specification 2019 & MORTH
Specification as applicable.

Clause12

12.2 Deviation limit beyond which clauses


& 12.2 & 12.3 shall apply for buildings, 30% (Thirty Percent)
12.3 pavements and all other works above
foundation level.
12.5 Deviation limit beyond which clauses 100% (Hundred Percent)
12.2 & 12.3 shall apply for foundation
work

Clause16

Competent Authority for deciding Jt.GM / DGM (Engg)


reduced rates

Clause18
Mandatory machinery tools & plants to be deployed by the contractor at site:
To be provided as per NIT and other Machinery required for timely completion of work.

Clause 25
Place of Arbitration: RHQ / Kolkata

Clause 36(1)
Requirement of Technical Representative(s) and recovery rate

Sl. Minimum Discipline Designation Rate at which recovery


No. Qualification of (Principal shall be made from the
Experience
Minimum

Technical Technical
Number

contractor in the event of


Representative representative) not fulfilling provision of
clause 36
Figures Words
Rs.
1 Degree Civil Site Engineer 1 yrs 01 Rs. Rupees One
Engineering 1000/- Thousand
Per day per day

A.A.I. C-NIL I-NIL O-NIL Page 135


Schedules AIRPORTS AUTHORITY OFINDIA

a. Assistant Engineers retired from Government services that are holding Diploma will be treated at
par with Graduate Engineers.
b. Diploma holder with minimum 10 year relevant experience with a reputed construction company
can be treated at par with Graduate Engineer for the purpose of such deployment subject to the
condition that such diploma holder should not exceed 50% of requirement of degree engineers

Clause 37
License Fee for unpaved land As per prevailing AAI Rates

Clause 41(a)
Integrity Pact applicable Yes/No

Clause 42

(i) Schedule/statement for determining theoretical DSR 2018 printed by C.P.W.D with up-
quantity of cement & bitumen on the basis of Delhi to-date correction slips till last date of
Schedule of Rates submission of tender, technical
specifications & SOQ.

(ii) Variations permissible on theoretical quantities


a. Cement for works with estimated cost put to 3% plus/minus
tender not more than Rs.5 lakhs.
For works with estimated cost put to tender more 2% plus/minus
than Rs.5lakhs
b. Steel Reinforcement and structural steel section for 2% plus/minus
each diameter, section and category
c. Bitumen 2.5% plus only & NIL on minus side
d. All other materials

RECOVERY RATES FOR QUANTITIES BEYOND PERMISSIBLE VARIATION

Sl. Description of items Rates in figures and words at which recovery shall be
No. made from the contractor
Excess beyond permissible Less use beyond the
variation permissible variation*
1. Cement - Not Permitted
2. Steel reinforcement - Not Permitted
3. Structural Sections - Not Permitted

* Provided work is considered technically sound. Otherwise work has to be re-executed as per
direction of Engineer-in-charge

A.A.I. C-NIL I-NIL O-NIL Page 136


Schedules AIRPORTS AUTHORITY OFINDIA

Clause 48

Escrow Account: Not Applicable


Annexure to clause 34 (x)
Annexure to clause 34 (x) showing quantities of materials for areas of surfacing to be considered for
working out minimum period for which hire charges of road roller are to be recovered.

Sl.No. Material of surfacing Quantity or areas


1. Consolidation of earth sub grade 1860 Sq.m
2. Consolidation of stones soling 15 cm to 22.5 cm thick 170 Cu.m
3. Consolidation of brick soling 10 cm to 20 cm thick 230 Cu.m
4. Consolidation of wearing coat of stone ballast 7.5 cm to 11.5 cm thick 30 Cu.m
5. Consolidation of wearing coat of brick ballast 10 cm thick 60 Cu.m
6. Spreading and consolidation of red bajri 6mm 1860 Sq.m
7. Painting one coat using stone aggregate 12.5mm nominal size
(a) @ 1.65 m3 per 100 m2 and paving bitumen A-90 or S-90@2.25
Kg per m2or
(b) @ 1.50 m3 per 100 m2 and bitumen emulsion or Road tar @2.25 930 Sq.m.
Kg per m2
8. Painting two coats using
(a) For first coat, stone aggregate 12.5 mm nominal size
(i) @ 1.50 m3 per 100 m2 and paving bitumen A-90 or S-90@2 Kg
per m2or
(ii) @ 1.35 m3 per 100 m2 and bitumen emulsion @2 Kg per m2 600
Sq.m. or
(iii) @ 1.25 m3 per 100 m2 with roadtar @2.25 Kg per m2 600 Sq.m.
(b) For 2nd Coat, stone aggregate 10 mm nominal size 0.9 Cu.m. per
100Sq.m with
(i) 1kg of paving bitumen A-90 or S-90 or bitumen emulsion per Sq.m.
or
(ii) 1.25 Kg. of road tar, per Sq.m. 600 Sq.m. 600Sq.m.
9. Re-painting with stone aggregate 10 mm nominal size 0.9 Cu.m. per
100 Sq.m. with
(i) 1kg of paving bitumen A-90 or S-90 per Sq.m. ;k or
(ii)1.25 kg of bitumen emulsion per Sq.m. 1670 Sq.m. 1670 Sq.m.
10. 2 cm premix carpet surfacing using 2.4 m3 of stone aggregate 10 mm 930 Sq.m
nominal size per 100 m2 and binder including tack coat, the binder
being hot cut back bitumen or bitumen emulsion in specified
quantities.
11. 2.5 cm premix carpet surfacing using 3 m3 of stone aggregate 10 mm 930 Sq.m
nominal size per 100 m2and binder including tack coat, the binder
being hot cut back bitumen or bitumen emulsion in specified
Quantities.
12. 4 cm thick bitumen concrete surfacing using stone aggregate 3.8 Cu.m. 460 Sq.m.
(60%20mm nominal size and 40% 12.5 mm nominal size) per 100m2
and coarse sand 1.9 Cu.m. per 100m2 and hot cut back bitumen overa
tack coat of hot cut back bitumen.

A.A.I. C-NIL I-NIL O-NIL Page 137


Schedules AIRPORTS AUTHORITY OFINDIA

13. 5 cm thick bitumen concrete surfacing using stone aggregate 4.8 Cu.m. 370 Sq.m.
(60%25 mm nominal size and 40% 20 mm nominal size) per 100m2
and coarse sand 2.4 Cu.m. per 100m2 and hot cut back bitumen overa
tack coat of hot cut back bitumen.
14. 6 cm thick bitumen concrete surfacing using stone aggregate 5.8 Cu.m. 280 Sq.m.
(60%40 mm nominal size and 40% 25 mm nominal size) per 100m2
and coarse sand 2.9 Cu.m. per 100m2 and hot cut back bitumen overa
tack coat of hot cut back bitumen.
15. 7.5 cm thick bitumen concrete surfacing using stone aggregate 7.3 230 Sq.m.
Cu.m. (60%50 mm nominal size and 40% 40 mm nominal size) per
100m2 and coarse sand 3.65 Cu.m. per 100m2 and hot cut back
bitumen over a tack coat of hot cut back bitumen.
16. 2.5 cm bitumastic sheet using stone aggregate 1.65 Cu.m. (60% 12.5 750 Sq.m.
mm nominal size 40% 10 mm nominal size) per 100 Sq.m. and coarse
sand 1.65 Cu.m. per 100 Sq.m. and hot cut back bitumen over a tack
coat of hot cut back bitumen.
17. 4 cm bitumastic sheet, using stone aggregate 2.6 Cu.m. (60% 12.5 mm 560 Sq.m.
nominal size, 40% 10 mm nominal size) per 100 Sq.m. and coarse
sand2.5Cu.m.per100Sq.m.and hotcut back bitumen overatack
coat of hot cut back bitumen.
18. Laying full grouted surface using stone aggregate 40 mm nominalsize 460 Sq.m.
6.10 Cu.m. per 100 Sq.m. with binder, binding with 20 mm to 12.5
mm nominal size stone grit. 1.83 Cu.m. per 100 Sq.m. and seal coatof
binder and stone grit 10 mm nominal size, 1.07Cu.m. per 100 Sq.m.,
the binder being hot bitumen or tar as specified.
19. Laying full grouted surface using stone aggregate 50 mm nominal size 370 Sq.m.
9.14 Cu.m. per 100 Sq.m. with binder, binding with stone grit 20 mm
to12.5mm nominal size1. 83Cu.m.per100Sq.m. and seal coat of
binder and stone grit 10 mm nominal size, 1.07Cu.m. per 100 Sq.m.,
the binder being hot bitumen or tar,
20. 4cm. thick premix macadam surfacing using stone aggregate 25 mm 560 Sq.m.
nominal size 4.57 Cum. per 100 Sq.m. and hot bitumen binding with
stone aggregate 12.5 mm nominal size 1.52 Cu.m. per 100 Sq.m. and
seal coat of hot bitumen and stone aggregate 10 mm nominal size 1.07
Cu.m. per 100 Sq.m.
21. 5cm. thick premix macadam surfacing using stone aggregate 25 mm 460 Sq.m.
nominal size 6.10 Cu.m. per 100 Sq.m. and hot bitumen binding with
stone aggregate 12.5 mm nominal size 1.52 Cu.m. per 100 Sq.m. and
seal coat of hot bitumen and stone aggregate 10 mm nominal size 1.07
Cu.m. per 100 Sq.m.

A.A.I. C-NIL I-NIL O-NIL Page 138


Performa
ANNEXURE-1

UNDERTAKING TO BE SUBMITTED IN COMPANY’S LETTER HEAD IN ENVELOPE-I.

Asstt. General Manager (Engg.-Civil)-I, Date:


Airports Authority of India,
S.V. Airport, Airport, Raipur-492015

Sir,
ACCEPTANCE OF AAI’S TENDER CONDITIONS
1. The Tender Document for the work of “Levelling and grading of area at 24 & 06 side
in newly acquired land at S.V. Airport, Raipur.” have been sold to me/us by Airports
Authority of India and I/we hereby certify that I/we have inspected the sites and read the
entire terms and conditions of the Tender Documents, Corrigendum and Reply to Query
made available to me/us on e- tender portal of CPP which shall form part of the contract
agreement and I/We shall abide by the conditions/clauses contained therein.
2. I / We hereby unconditionally accept the tender conditions of AAI’s tender documents in
its entirety for the above work.
3. The contents of NIT Documents have been noted and after unconditionally accepting the
tender conditions in its entirety, it is not permissible to upload any additional file or put
any remarks/condition(s) in/along with the tender documents and the same has been
followed in the present case. In case, this provisions of the tender if found violated after
opening of tender, I agree that the tender shall be rejected and AAI shall without prejudice
to any other right or remedy be at liberty to forfeit the 10% of the earnest money absolutely.
4. It is confirmed that we will deploy the required machineries and equipment’s for
completion of work in time without any extra cost on AAI.
5. I / We declare that I/We have not paid and will not pay any bribe to any officer of AAI for
awarding this contract at any stage during its execution or at the time of payment of bills,
and further if any officer of AAI asks for bribe / gratification, I/We will immediately
report it to the appropriate authority in AAI.
6. Earnest Money amount as mentioned in ENIT and at Page No. 131 of GCC shall be
accepted Online through SBI MOPS Gateway using SBI/Other Banks/NEFT/RTGS mode
as mentioned in ENIT.
7. I / We agree that “If at any stage, any information / documents submitted by us are found
to be false, we shall not be considered for evaluation and liable for debarment from
tendering in AAI, apart from any other appropriate / Legal action, including termination
of the contract shall be taken if discovered at a later stage”.
Thanking you,
Yours faithfully,
Date:

(Signature of the tenderer)


With rubber stamp

C-NIL I-NIL O-NIL PR - 1


ANNEXURE -2
FORM OF BANK GUARANTEE TO SECURE A LUMP-SUM / MOBILIZATION
ADVANCE
(On Non-Judicial Stamp Paper)

To

The Airports Authority India

1. In consideration of the Airports Authority India having its head office at New Delhi
(hereinafter called “AAI” which expression shall unless repugnant to the subject or
context include its administrators, successors and assigns) having agreed under the
terms and conditions (Contract Agreement No.
dated made between *
and AAI in connection with the work of (hereinafter called “the said contract”), to
make at the request of the Contractor a lump-sum advance of Rs.
(Rupees only) for utilizing it for the
purpose of the Contract on his furnishing a guarantee acceptable for AAI we, the Bank
(hereinafter referred to as “the said Bank”) and having our registered office at do
hereby guarantee the due recovery by AAI of the said advance with interest thereon -
as provided according to the terms and conditions of the Contract. If the said
Contractor fails to utilize the said advance for the purpose of the Contract and/or the
said advance together with interest thereon as aforesaid is not fully recovered by AAI
we, the Bank hereby unconditionally and irrevocably undertake to pay to
AAI on demand and without demur to the extent of the said sum of Rs Rupees
only) any claim made by AAI on us for the loss or damage caused to
or suffered by AAI by reason of not being able to recover in full the said sum of Rs
(Rupees only) with interest, as aforesaid.
2. We, the Bank, further agree that AAI shall be the sole judge of
and as to whether the said Contractor has not utilized the said advance or any part
thereof for the purpose of the Contract and the extent of loss or damage caused to or
suffered by AAI on account of the said advance together with interest not being
recovered in full and the decision of AAI that the said Contractor has not utilized the
said advance or any part thereof for the purpose of the Contract and as to the amount
or amounts loss or damage caused to or suffered by AAI shall be final and binding on
us.
3. We, the said Bank, further agree that the Guarantee therein contained shall remain in
full force and effect during the period that would be taken for the performance of the
said Contract and till the said advance with interest has been fully recovered and its
claims satisfied or discharged and till the Accepting Authority of the contract certifies
that the said advance with interest has been fully recovered from the said Contractor,
and accordingly on discharges this guarantee subject, however, that AAI shall have no
claim under this Guarantee after 90 (Ninety) days from the date of completion of the
said contract,i.e., (date) or from the date of cancellation of the said Contract, as the
case may be, unless a notice of the claim under this Guarantee has been served on the
Bank before the expiry of the said period in which case the same shall be enforceable
against the Bank notwithstanding the fact, that the same is enforced after the expiry of
the said period.
4. AAI shall have the fullest liberty without effecting in any way the liability of the Bank
under this Guarantee or Indemnity, from time to time to vary any of the terms and
conditions of the said Contract or the advance or to extend time of

C-NIL I-NIL O-NIL PR - 2


performance by the said Contractor or to postpone for any time and from time to time
any of the powers exercisable by it against the said Contactor and either to enforce a
forbear from enforcing any of the terms and conditions governing the said Contract or
the advance or securities available to AAI and the said Bank shall not be released
from its liability under these presents by any exercise by AAI of the liberty with
reference to the matters aforesaid or by reason of time being given to the said
Contractor or any other forbearance, act or omission on the part of AAI or any
indulgence by AAI to the said Contractor or of any other matter or thing whatsoever
after I which under the law relating to sureties would but for this provisions have the
effect of so releasing the Bank from its such liability.
5. It shall not be necessary for AAI to proceed against the Contractor before proceeding
against the Bank if and the Guarantee herein contained shall be enforceable against
the Bank notwithstanding any security which AAI may have obtained or obtain from
the Contractor shall at the time when proceedings are taken against the Bank
hereunder be outstanding or unrealised.
6. We, the said Bank, lastly undertake not to revoke this Guarantee during its currency
except with the previous consent of AAI in writing and agree that any change in the
Constitution of the said Contractor or the said mess Bank shall not discharge our
liability hereunder.
7. Address of Regional / Controlling branch of the issuing branch of bank Guarantee is--
----------------------------------------------------------------------------
In presence of: Dated this Day of 2018

WITNESS:

1 For and on behalf of (The Bank)

Signature………………………

Name&Designation……………………………

Authorization No………………………

Name&Place………………….

Bank’s Seal…………………..

The above Guarantee is accepted by Airports Authority of India.

For and on behalf of Airports Authority of India.

Signature

Name

Designation

Dated

C-NIL I-NIL O-NIL PR - 3


Note:

*For Proprietary Concerns

Shri son of resident of


carrying on business under the name and style of at
(herein after called “the said Contractor” which expression shall unless
the context requires otherwise include his heirs, executors, administrators and legal
representatives).

For Partnership Concerns

1 Shri son of resident of

2 Shri son of resident of


carrying on business in co-partnership under the name and style of
at (hereinafter collectively called “the said contractor”
which expression shall unless the context requires otherwise include each of them and their
respective heirs, executors administrators and legal representatives).

For Companies

M/s a Company registered under the Companies Act, 1956 and


having its registered office in the State of (Here in after called “the said Contractor” which
expression shall unless the context requires otherwise include its administrators, successors
and assigns).

C-NIL I-NIL O-NIL PR - 4


ANNEXURE - 3

GUARANTEE TO BE EXECUTED BY CONTRACTOR FOR REMOVAL OF


DEFECTS AFTER COMPLETION IN RESPECT OF SPECIALIZED WORKS

(SAMPLE COPY)

(Separate Warranty / Guarantee Agreements shall be made for different specialized jobs based
on descriptions provided in the Technical / CPWD Specifications/SCC)

The Agreement made this------------------------------------day of-----------------------------------


- two thousand & nineteen ----------------between----------------------------------------son of---
-------------------------of--------------------------- (herein after called the Guarantor of the one
part) and the Chairman, AAI (hereinafter called the Authority of other part).

WHEREAS THIS agreement is supplementary to a contract (here in after called the Contract)
dated-----------------------and made between the GUARANTORY OF THE ONE PART and
the Chairman, AAI, whereby the Contractor, inter-alia undertook to render the buildings and
structures in the said contract recited completely water and leak proof.

AND WHEREAS THE GURANTOR agreed to give a guarantee to the effects that the said
structures will remain water and leak proof for 10 (Ten) years (05 years Guarantee Bond in
the form of BG for value of 5% of total water proofing system + 05 years Corporate
Guarantee) from the date of giving of water proofing treatment.

NOW THE GUARANTOR herby guarantees that water proofing treatment given by him will
render the structures completely leak proof and minimum life of such water proofing
treatment shall be 10 (Ten) years (05 years Guarantee Bond of value of 5% of total water
proofing system + 05 years Corporate Guarantee) to be reckoned from the date of giving of
water proofing treatment.

Provided that the guarantor will not be responsible for leakage caused by earthquake or
structural defects or misuse of roof or alteration and for such purpose.

a) Misuse of roof shall mean any operation which will damage proofing treatment, like
chopping of firewood and things of the same nature which might cause damage to the
roof.
b) Alteration shall mean construction of an additional storey or a part of the roof or
construction adjoining to existing roof whereby proofing treatment is removed in
parts.
c) The decision of the Engineer-in-charge with regard to cause of leakage shall be final.

C-NIL I-NIL O-NIL PR - 5


During this period of guarantee the guarantor shall make good all defects and in case of any
defect being found render the building water proof to the satisfaction of the Engineer-in
charge at his cost and shall commence the work such rectification within 7 days from the date
of issue of the notice from the Engineer-in-charge calling upon him to rectify the defects
failing which the work shall be got done by the department by some other contractor at the
GUARANTOR’s cost and risk. The decision of the Engineer- in-charge as to the cost,
payable by the Guarantor should be final and binding.

That if Guarantor fails to execute the water proofing or commits breach there under then the
Guarantor will indemnify the Principal Employer and the successors against all loss, damage,
cost, expense or otherwise which may be incurred by him by reasons of any default on the
part of the GUARANTOR in performance and observance of this supplementary agreement.
As to the amount of loss and / or damage and / or cost incurred by the Government the
decision of the Engineer-in-charge will be final and binding on the parties.

IN WITNESS WHEREOF these presents have been executed by the Obligator --------------
-----and by ------------------- and for an on behalf of the Chairman, AAI on the day, month
and year first above written.

SIGNED, SEALED AND delivered by OBLIGATOR IN THE PRESENCE

OF:- 1.

2.

SIGNED FOR AND ON BEHALF OF CHAIRMAN, AAI ------------------- IN THE


PRESENCE OF:-

1.

2.

C-NIL I-NIL O-NIL PR - 6


ANNEXURE - 4

Guarantee Bond for Anti-Termite Treatment


(SAMPLE COPY)

This agreement made this ------------ day of ------------ Two thousand and ----------------
between M/s --------------------------------------------------------------------------------------- [here after
called the Guarantor] of the one part and the Chairman, Airports Authority of India [here in after
called the Authority] of the other part.
Whereas this agreement is supplementary to the contract (there in after called the contract) dated
--------------- made between the GUARANTOR of the one part and Authority of the other part
whereby the contractor inter-alia undertook to render the buildings and structures in the said
contract recited completely Termite proof.
And whereas the GUARANTOR agreed to give a guarantee to the effect that the said structure
will remain Termite-proof for 10 (Ten) years (05 years Guarantee Bond of value of 5% of total
anti termite system + 05 years Corporate Guarantee) to be reckoned from the date of giving of
anti-termite treatment.
During this period of guarantee the guarantor shall make good all defects and for that matter,
shall replace at his risk and cost such wooden members etc. as may be damaged by termites and
in case of any other defect being found he shall render the building termite proof at his cost to the
satisfaction of the Engineer-in-charge and shall commence the works of such rectification within
7 days from date of issuing notice from the Engineer-in-charge calling upon him to rectify the
defects failing which the work shall be got done by the Department by some other contractor at
the GUARANTOR’S cost and risk and in the latter case the decision of the Engineer-in-charge as
to the cost recoverable from the Guarantor should be final and binding.
That, if the Guarantor fails to execute the Anti-Termite treatment or commits breaches hereunder,
then the Guarantor will indemnify Authority and his successors against all loss, damage, cost,
expense, or otherwise which may be incurred by him by reason of any, default on the part of the
GUARANTOR in performance and observance of this supplemental agreement. As to the amount
of loss and/or damage and/or cost incurred by the Authority the decision of the Engineer-in-
charge will be final and binding on the parties.
IN WITNESS WHEREOF these presents have been executed by the obligator--------------------
------------------------------------------------------------------ and by --------------------------------forand
behalf of the Airports Authority of India on the day, month and year first above written.
SIGNED, sealed and delivered by OBLIGATOR in the presence of: -
1.
2.
SIGNED for and on behalf of THE AIRPORTS AUTHORITY OF INDIA by ---------------------------
in the presence of: -

1.

2.

CONTRACTOR ENGINEER-IN-CHARGE

C-NIL I-NIL O-NIL PR - 7


ANNEXURE - 5

AFFIDAVIT FOR ENGAGEMENT OF WORKERS WITH MINIMUM WAGES

I………………..……… (Name), aged …… years, s/o ...................................... (Name),

Proprietor/ Managing Partner/ Managing Director of ……………………………… (Name of

the Agency) do hereby solemnly affirm and state as follows:

I am competent to swear this affidavit on behalf of ................................... (Name of agency).I

state that, in the event of work is awarded to our agency, the wages to be paid to the workers

engaged shall not be less than the minimum wages determined by appropriate Govt.

Authorities from time to time.

Dated this, the ………………….. day of…………………month ............. Year.

DEPONENT

Place:

Date:

Note: This affidavit is to be attested by a First Class Magistrate / Notary Public on Non-

Judicial Stamp paper of Rs. 100/-

C-NIL I-NIL O-NIL PR - 8


88
ANNEXURE – 6

(To be submitted by bidder on company’s letter head - in Envelope-I)

UNDERTAKING

I/We …………..…….. (Name & Post of authorized signatory) on behalf of ..................... (Name of

bidder / consultant) do hereby solemnly declare the following:

i) Our firm has been registered under GST and compliant of GST provision (With registration
no. .................... )
ii) In case of non-compliance of GST provisions and blockage of any input credit, our firm
shall be responsible to indemnify Airports Authority of India.
iii) All input credits shall be passed on to AAI by our firm.

Signature and name of the authorized


Signatory of the bidder/consultant
Date:

Place:

C-NIL I-NIL O-NIL PR - 9


89
ANNEXURE – 7

(To be submitted by bidder on company’s letter head - in Envelope-I)

Undertaking Regarding Debarment/Blacklisting

I/We........................................ (name and post of authorized signatory) on behalf of

………………………..(Name of firm) do here by solemnly affirm and declare as follows:

(i) Our firm is not restrained/debarred/blacklisted by AAI or Central /State Govt.

Depts./PSUs/World Bank/ ADB etc. and the debarment is not in force as on last date of

submission of proposal.

(ii) None of Proprietor/Partners/Board members/Directors of M/s ………………………..

(Name of firm) has remained Proprietor/Partner/Board Member/Director in any firm which

stands debarred/blacklisted by AAI or Central/State Govt. Depts./PSUs/World Bank/ ADB

etc. and the debarment is not in force as on last date of submission of proposal.

(iii) Our firm understand that at any stage, if above statements are found to be false, our firm

shall be liable for debarment from bidding in AAI, apart from any other appropriate

contractual legal action including debarment/blacklisting, termination of the contract etc. as

deemed fit.

Date: [Signature and name of the authorized]

signatory of the firm]

Place:

C-NIL I-NIL O-NIL PR - 10


810
ANNEXURE -8

WORK

DIARY

PART A

1. Name of
Work……………………………………………………………………………………………

2. Contract Agreement No
………………………………………………………………………………..

3. Date of
Acceptance……………………………………………………………………………………..

4. Name & Registered address of


Contractor……………………………………………
……………...

5. Contract
Sum…………………………………………………………………………………………….

6. Period of Contract
………………………………………………………………………………………

7. Name and local address of Contractor / Contractor’s Agent


……………………………………..

8. Date of First Works Order


…………………………………………………………………………….

9. Date of Handing over the Site to contractor


………………………………………………………..

10. Date of commencement of work


…………………………………………………………………….

11. Stipulated date of completion of


contract…………………………………………………………..

12. Suspension orders showing duration and


authority………………………………………

13. Extended date of completion with authority


C-NIL I-NIL O-NIL PR - 11
811
……………………………………………………….

14. Date of actual completion of


work………………………………………………………………….

15. Date of work taken over


……………………………………………………………………………..

16. Date of expiry of Maintenance Period


…………………………………………………………….

17. Date of actual completion of


work………………………………………………………………….

18. Date of work taken over


……………………………………………………………………………..

19. Date of expiry of Maintenance Period


…………………………………………………………….

C-NIL I-NIL O-NIL PR - 12


812
WORK DIARY
PART B

DAILY
RECORD

1. Weather

Labour engaged by Contractor

Skilled Unskilled
Category No Category No Category No Category No
Concreter Paviour Glazier Mate
Bricklayer Tiller Plumber Bhistry
Mason Painter Mazdur (man)
Carpenter Polisher Mazdur (Women)
Joiner Mazdur (boy)

2. Importantmaterialsbroughtossitewithapproximatequantities(rejection,ifany, to bistate)

Schedule ‘B’ material Contractor’s Materials Rejections

Materials Quantity Materials Quantity Materials Quantity

3. Details of plant, equipment and transport and transport working on site

Contractor’s T&P equipment


T&P Hired under Schedule “C” and Transport
T&P Remark’s regarding Remark’s regarding
Quantity breakdown Quantity breakdown
maintenance etc maintenance etc

Road Roller
Concrete Mixer

C-NIL I-NIL O-NIL PR - 13


4. Brief Particulars of work in progress:
……………………………………………………………
5. Important stage completed and passed :
…………………………………………………...
6. Remarks of Visiting Officer :
…………………………………………………..

Date signature of Engineer–in-charge or Date signature of Contractor or his


representative authorized representative

C-NIL I-NIL O-NIL PR - 14


ANNEXURE - 9
FORM OF SUPPLEMENTARY AGREEMENT

This Agreement made this day the …………… ….. between ...............here in after called the
First party which expression shall include his heirs, executors and administrators / their
successors and assigns and the Chairman, Airports Authority of India through
……….. Hereinafter called the Second party which expression shall include his successors
assigns, shown as under:-

1. That this Agreement shall be called as Supplementary Agreement to the Agreement No.
…………….relating to the construction of ........................entered into by the partiesto
this agreement.
2. That WHEREAS the first party has substantially completed the execution of the work
described in and covered by the Agreement No .................. except the item mentioned in
the schedule annexed to this Agreement And whereas the items of the work mentioned in
the schedule annexed to this Agreement can’t now be executed on account of non
completion of the sanitary work, electric installation and some other work; and whereas
both the parties are desirous that the items mentioned in the schedule annexed to this
agreement should be executed by the fist party after the completion of the sanitary work,
electric installation and some other work, it is hereby further agreed as under:-

a) That the first party shall and will execute the work covered by the items mentioned in
the schedule annexed to this agreement at the rates and as per the terms and conditions
of the original Agreement no ..................................................... whenever called upon
to do so by the Engineer-In-Charge, within a period of one year from the date hereof.
b) That the first party shall have absolutely no claim of whatsoever nature against the
second party for doing the work mentioned in the schedule annexed to this Agreement
as required under clause (a) above, except that which he would be entitled to under
the original Agreement No………………

c) That the first party shall be liable to execute all other items arising out of the original
Agreement No .................................which in the opinion of the Engineer-In-Charge
are necessary.
d) That the first party shall start with the work of the remaining items mentioned in the
schedule annexed to this Agreement within……………..days from ..........................on
the receipt of a letter to the effect from the Engineer-In-Charge or from any date fixed
in the said letter and shall complete the said work within the time fixed by the said
Engineer-In-Charge or as extended by him from time to time.
e) That on the due execution and completion of this agreement by the parties, the bill of
the first party in relation to the work already done by him under the original
Agreement No… shall be provisionally finalized by the second party and payment
on account, if any amount is due, shall be made to the first party provided that the
second party shall have a right to retain such amount as is considered reasonable by
him as a security for the execution of the work mentioned in the scheduled annexed to
this agreement and the second party shall have a right to deal with the said amount of
security as the thinks proper under the terms and conditions of the original agreement.
Further, on the due execution and completion of this agreement, the first party should
be entitled to claim back his security deposit relating to the work in question, subject
to the right of the second party to retain such amount as he thinks reasonable as
mentioned above soon after the maintenance period of month(s), as the case may be
mentioned in Clause............................. of the original agreement, is over.

f) That the final bill relating to the entire work under the two agreements should be
prepared after the completion of the entire work covered by Agreement No and this
agreement.

C-NIL I-NIL O-NIL PR - 15


3. Except as modified by this agreement the said Agreement No ................... shall remain in
full force and effect.
IN WITNESS WHEREOF THE ABOVE MENTIONED PARTIES HAVE PUT THEIR
signature
on this day the…………………..

(Signature of Contractor) (Signature of accepting


authority
For and on behalf of Chairman,
Airports Authority of India

(Signature of Witness) (Signature of Witness)

Name & address of witness Name & address of witness

C-NIL I-NIL O-NIL PR - 16


ANNEXURE - 10

FORM OF HYPOTHECATION DEED,

(on Non‐Judicial stamppaper), [GeneralConditionNo.10B (ii)]

THIS INDENTURE made this day……………………….of 200.. between *of the one part and
Airports Authority of India here in after called AAI which expressions hall unless the context requires
otherwise include its administrators, successors and assigns of the other part;

WHEREAS under Condition 10B(ii) of the General Conditions of Contract relating to the Contract
Agreement no. dated entered in to between AAI and the Contractor, the Contractor has
applied toAAI for an advance of Rs.(Rupees only) for plant and equipment
described in the Schedule hereto specifically acquired by the Contractor for the works and brought
to site;

AND WHEREAS one of the conditions on whichthesaid advance of Rs.


(Rupees only) is to be granted by AAI to the Contractor is that the Contractors hall
hypothecate the plant and equipment described in the Schedule here to in favour of AAI as security
or the due repayment of the said advance.

AND WHEREAS the Contractor has represented that he is the owner of the plant and equipment
described in the Schedule hereto.

NOW THIS INDENTURE WITNESSTH THAT in pursuance of the said agreement and in the
consideration of the premises the Contractor both hereby hypothecate, assign and transfer to
AAI the plant and equipment described in the Schedule hereto to the intent that the same shall
remain and form securityfor repayment to AAI of the said advance of Rs. (Rupees
only) together with the interest there on at % per annum.

1. The Contractor hereby agrees, declares and covenants with AAI as follows:

(a) The Contractor shall repay to AAI the said advance of Rs.
(Rupees only) together with interest on as foresaid by (date) and
agrees that the said advance be recovered by AAI making deductions in the manner provided
in condition 54 of the General Conditions of Contract and other conditions of the contract
from the claims made by the Contract or against AAI for on account payment.

(b) The Contractor has paid in full the purchase price of the plant and equipment described in
the schedule hereto and each and everyone of the mand that the same are the absolute
property of the contractor and that the same have not been sold, pledged, mortgaged or
transferred or in anyway dealt with by the Contractor.

(c) So long as any amount remains payable to AAI by the Contractor inrespect of the said advance
of Rs. (Rupees only) the Contractor shall not sell,
pledge, hypothecate, transfer, part with or in anyway deal with the plant and equipment
described in the Schedule hereto.

(d) If the said advanceof Rs. (Rupees only) shall not be


repaid by the Contractor or recovered in the manner described above by the said day of due
to any reason whatsoever or the said Contract has been determined earlier or cancelled or if
the Contractor shall sell, pledge, hypothecate, transfer, part with or in anyway deal with the
plant and equipment or any part thereof or the Contractor or any of the partners in adjudged
in solvent or the contract is to be wound up or makes any composition or arrangement with
C-NIL I-NIL O-NIL PR - 17
its creditors or the Contractor shall commit breach of any of the terms and conditions or
covenants as herein contained or if any of the said plant and equipment or if any other
property whatsoever belonging to the Contractor has been sold or attached for a period of
not less than 21days in execution of the decree of any court for payment of money, the
whole of the said advance of
Rs. (Rupees only) or such part
there of as may have remained unpaid or unrecovered together with interest there on shall
forth with become due and payable.

(e) AAI may on the happening of any of the events mentioned in the preceding clause(d) r in the
event of the said advance or any part there of becoming due and payable and has not been
paid or recovered or cannot be recovered as provided in the said conditions, size and take
possession of the said plant and equipment (and either remain in possession there of without
removing the same or else may remove the same) and sell the said plant and equipment or
any of them either by public auction or private contract and may out of the sale proceeds
retain the balance of the said advance and interest them remaining unpaid and un‐ recovered
and all costs, charges and expenses and payments incurred or made in maintain, defending
or protecting the rights of AAI hereunder and shall payover the surplus, if any, to the
Contractor.

(f) The Contractor shall at all times during the continuance of the security and at the expense of
the Contractor insure and keep insured the plant and equipment described in the Schedule
hereto for the full value thereof in the joint names of the Contractor and AAI with and
insurance company to be approved by the Engineer-in-Charge against the risk of loss or
damage form whatever cause arising other than the Excepted Risks. During the continuance
of the security the Contractor shall pay all premia and sums of money necessary for keeping
such insurance on foot and the insurance policy and receipts in original for premia paid shall
be deposited with the Engineer-in-Charge. The Contractor shall assign all his right, title and
interest in the policy to AAI.

(g) The Contractor shall not permit or suffer the said plant and equipment or any part thereof to
be destroyed or damaged or used or to be used or to deteriorate in a greater degree than it
would deteriorate by reasonable wear and tear thereof in the performance of the Contract.

(h) In the event of any damage or loss happening to the said plant and equipment or any part
thereof from whatever cause other than the Excepted Risks the Contractor shall forth with
have the same repaired or replaced as the case may be or arrange for payment of the entire
amount recovered or to be recovered from the insurance company to. AAI towards the
payment of the said advance of Rs. ............. (Rupees only).

2. Upon repayment or recovery in full of the amount secured on account of this hypothecation
deed the said plant and equipment secured here under shall stand released form hypothecation
but this is without prejudice to the right of AAI under anyother Conditions of the Contract.

C-NIL I-NIL O-NIL PR - 18


SCHEDULE ABOVE REFERRED TO:

Sl.No Particulars of Nos Purchaseprice TotalPrice Advance (75%


Plant and / Price
Equipment Considered of Col.5)
reasonable by
Engineer-in-
Charge

1 2 3 4 5 6

INWITNESS WHEREOF the parties here to have executed these present on the day and year
first aboveWritten Signed and delivered by the within named (Contractor) in the
presence of

WITNES

S 1.

2.

Signed Shri

(Name and Designation)

For and behalf of Airports Authority of India in the presence of Witness

(1)

(2)

Note:

*For Proprietary Concerns

Shri son of resident of carrying on business under the


name and style of at (herein after called “the said Contractor” which
expression shall unless the context requires otherwise include his heirs, executors, administrators
and legal representatives).

ForPartnershipConcerns

1. Shri son of resident of

2. Shri son of resident of carrying on


business in co-partnership under the name and style of
at (herein after collectively called “the said Contractor” which expression shall unless the
context requires otherwise include each of the mand their respective heirs, executors,
administrators and legal representatives)

C-NIL I-NIL O-NIL PR - 19


For Companies

M/s. accompany
registered under the Companies Act,1956 and having its registered office in the State of
(Here in after called“ the said Contractor” which expression shall unless the context require
so ther wise include its administrators, success or sand assigns)

PR-20
ANNEXURE - 11

(To be submitted by bidder on letter head - in Envelope-II)

Undertaking for digitally signed Tender Document

I/We The owner(s)/proprietor(s)


(Name of company/Firm) do hereby declare
that, the tender documents of “Levelling and grading of area at 24 & 06 side in newly
acquired land at S.V. Airport, Raipur” uploaded in CPP Portal are digitally singed by
me.

Name & Signature of contractor / Firm

(with rubber stamp)

Date:

PR-21
ANNEXURE - 12

Certificate of Net Worth from Chartered Accountant having UDIN

“It is to certified that as per audited balance sheet and profit & loss account during the
financial year …………, the Net Worth of M/s ……………… (Name & Registered Address
of Individual/firm/company), as on …………………… (the relevant date) is Rs. …………..
after considering all liabilities. It is further certified that the Net Worth of the company has
not eroded by more the 30% in the las three years ending on (the relevant date).”

Signature of Chartered Accountant


…………………………
Name of Chartered Accountant
…………………………
Membership No. of ICAI
………………………….
Date and Seal

PR-22
Annexure–13

(To be submitted by bidder on company’s letter head - in Envelope-I)

UNDERTAKING FOR DEPLOYMENT OF T&P

Name of Work: “Levelling and grading of area at 24 & 06 side in newly acquired land at S.V.
Airport, Raipur
Name of Contractor / Firm:

I / we have applied for issue of tender for the work of “Levelling and grading of area at 24 &
06 side in newly acquired land at S.V. Airport, Raipur and hereby undertake that: -
• I / we have gone through the tender documents and drawings in its entirety and have
understood the nature of work to be executed.
• I / we will deploy sufficient plant and machinery as per the requirement of work
matching to achieve the milestones/targets and overall completion within the time
period.
• I / we will deploy adequate T&P in working condition with adequate standby
arrangement for efficient / timely execution of the work.
• I / we will abide by any instructions by AAI for such procurement / arrangement of
T&P on lease as is considered necessary for efficient / timely execution of work.

Signature of Contractor:
Date:

PR-23
Special Conditions of Contract
SPECIAL CONDITIONS OF CONTRACT
1. GENERAL

1.1 Special conditions of Contract shall be read in conjunction with General Conditions of Contract,
Technical Specifications, Drawings, BOQ and any other documents forming part of this
contract wherever the context so requires.

1.2 Notwithstanding the sub-division of the documents into these separate sections and volume
every part of each shall be deemed to be supplementary to and complementary of every other
part and shall be read with and into the CONTRACT so far as it may be practicable to do so.

1.3 Where any portion of the General Condition of Contract is repugnant to or at variance with any
provisions of the Special Conditions of Contract, unless a different intention appears, the
provisions of the Special Conditions of Contract shall be deemed to over-ride the provisions of
the General Conditions of Contract and shall to the extent of such repugnancy, or variations,
prevail.

1.4 Nothing extra shall be payable on account of various activities to be performed as per special
conditions of contract except where so specified.

2. COMPLETION SCHEDULE

2.1 The works shall be executed strictly as per time schedule mentioned in NIT. Contractor shall
have to plan his construction programme and activities so as to complete the work in the
stipulated period by working in multiple shifts. The period of completion given includes the
time required for mobilization as well as testing, rectifications, if any, re-testing and completion
in all respects to the entire satisfaction of Engineer-in-Charge.

2.2 The contractor shall furnish within 15 days of letter of award a time schedule program for
completion of the work within the stipulated time and as per conditions of the contract. The
programme should clearly include Manpower, Material and Machinery resources proposed to
be deployed for achieving the targeted progress, justification for same based on machinery
output, the date from which each machinery shall be available at site in working condition etc.
complete. The programme shall be subject to the approval of engineer-in-Charge who may
order changes in the programme. The decision of Engineer-in-Charge shall be final and binding
in this regard.

2.3 Contractor is expected to mobilize and employ sufficient resources to achieve the progress
within the broad frame work of accepted methods of working and safety. In time and progress
chart, deployment of machineries, equipments, apparatus and instruments are to be treated as
one of the sections of the work.

2.4 No additional payment shall be made to the contractor for any multiple shift work or other
incentive methods contemplated by him in his work Schedule even though the time schedule is
approved by the Engineer-in-Charge.

2.5 During the currency of the work the contractor is expected to adhere to the time schedule or mile
stone and total completion and this adherence will be a part of Contractor's performance under
the contract.

C-NIL I-NIL O-NIL SCC-1


2.6 The Engineer-in-Charge can hold the payment till such time; the contractor does not submit the
time schedule programme. The Contractor will be fully responsible to submit scheduled
programme in consultation with Engineer-in-Charge to complete the work within stipulated
time.
2.7 FOR MONITORING OF PROJECT PROGRAMME OF CONSTRUCTION OF
WORKS, PROGRESS REPORT AND PERFORMANCE (i) BAR / GANTT CHART
AND CPM / PERT CHART
2.7.1 The contractor shall submit within fifteen days from date of acceptance of the letter, Bar / Gantt
chart and CPM / PERT Chart. The same shall be got approved from the Engineer-in-Charge
before starting of the works and shall be binding on the contractor .In case of non-submission
of the Bar / Gantt and CPM / PERT Chart by the contractor within fifteen days as stated above,
AAI shall get it done from any consultant at the risk and cost of the contractor and the
programme / Bar / Gantt chart and CPM / PERT Chart so prepared shall be binding on the
contractor.
2.7.2 Contractor shall submit fortnightly progress reports (2 copies) highlighting status of various
activities and physical completion of work.
2.7.3 Contractor shall give every day report on category wise labour and equipment deployed along
with the progress of work done on previous day in the proforma prescribed by the Engineer-in-
Charge.
2.7.4 PERFORMANCE:
a. The contractor shall perform all works in substantial and acceptable manner in accordance with
the plans and specification and in accordance with such further explanatory drawings, details
and instructions as may from time to time be given by the Engineer-in-Charge. The work must
be proceeded within such sections and such times as directed by the Engineer-in-Charge.
b. The contractor shall provide and do everything necessary for the proper execution of the works
according to the true intent and meaning of the drawing and specification taken together the
same may or not be particularly shown on the provided that the same can be reasonably inferred
there from. Figured dimensions to be followed in preference to scale dimensions and all
particulars to be taken from the actual work.
c. It must be clearly understood that the whole of the conditions are intended to be strictly
enforced and that no extra charges in respect of extra work will be allowed unless they are
clearly outside the spirit and meaning of the conditions or unless such works shall have been
ordered in writing by the Engineer-in-Charge.
3 SCOPE OF WORK
The scope of work includes “ Levelling and Grading of area at 24 & 06 side in newly acquired
land at S.V. Airport, Raipur as per BOQ items at Raipur Airport”.
Civil Works-
i. Levelling & grading of area beyond RESA at 24 side and wall to wall grading beyond extended
runway basic strip.
ii. Levelling & grading to remove the bunds of cultivated lands.
iii. Levelling & grading for removing the undulation to avoid the water accumulation at these area.
4. DRAWINGS AND DOCUMENTS
4.1 The drawings accompanying the tender document, if any, are of indicative nature and issued for
tendering purpose, with the purpose to enable the tenderer to make an offer in line with the
requirements of the AAI.
4.2 However, no extra claim whatsoever, shall be entertained for variation in the "Approved for
Construction" and "Tender drawings" regarding any changes. The execution of work shall be as
per approved drawings and detailed specifications.

C-NIL I-NIL O-NIL


SCC-2
5. BILL OF QUANTITIES
5.1 The Bill of Quantities shall be read in conjunction with General Conditions of Contract, Special
Conditions of Contract, Technical Specifications, Drawings and any other Document forming a
part of this tender. The quantities shown against the various items are only approximate and
subject to variations as per provision made in General Conditions of the Contract.
6. LICENSE FEE FOR LAND ALLOTTED BY AAI
The contractor shall not be permitted to enter in (other than for inspection purpose) or take
possession of the site until instructed to do so by the Engineer-in-Charge in writing. The portion
of the site to be occupied by the contractor shall be defined and/or marked on the site plan,
failing which these shall be indicated by the Engineer-in-Charge at site and the contractor shall
on no account be allowed to extend his operations beyond these areas. In respect of any land
allotted to the contractor for purpose of or in connection with the contract, the contractor shall be
issued a license subject to the following and such other terms and conditions as may be imposed
by the licenser: -
(i) Contractor shall pay a nominal license fee for land allotted by AAI for installation of Plants,
Labour Camp (if provided), Cement Godown and site office. License fee from contractor is
chargeable for land @ Rs. 220/- per sqm per annum (for unpaved land). A security deposit
of Rs. 500/- per sqm in the form of Cash/DD/BG is also to be obtained from the contractor
for this purpose. This security deposit can be released only after ensuring that allotted land
has been vacated and Engineer-in-charge to certify this fact in the final bill. Land used for
stacking of material to the extent available is, however, provided at free of cost, with the
approval of Project/Airport In-charge. Land used for site office for AAI’s use will be free of
cost. The allotment of land for purpose of or in connection with the contract subject to the
following and such other terms and conditions as may be imposed by the licenser:
(ii) That such use or occupation shall not confer any right of tenancy of the land to the
contractor.
(iii) That the contractors shall be liable to vacate the land on demand by the Engineer-in-
Charge.
(iv)That the contractor shall have no right to any construction over this land without the written
permission of the Engineer-in-Charge. In case, he is allowed to construct any structure he
shall have to demolish & clear the same before handing over the completed work unless
agreed to the contrary.
6.1 The contractor shall provide, if necessary or if required on the Site, all temporary access thereto
and shall alter, adapt and maintain the same as required from time to time and shall take up and
clear them away as and when no longer required and as and when ordered by the Engineer-in-
Charge and make good all damage done to the Site.
6.2 Land for Labour Camps: Labour camps will be permitted within the premises of Raipur
Airport but excluding operational and restricted area, if land for such purpose is available with
necessary license fee and security deposit as per clause no.-6(i) of SCC, otherwise the
contractor shall make the necessary arrangements at any other suitable place at his own cost,
with prior approval of Engineer-in-Charge.

7. TEMPORARY WORKS
7.1 The Tenderer should see the approaches and conditions of the same. If any approach from main
road is required at site or existing approach is to be made and maintained for cartage of
materials etc. by the Contractor, the same shall be provided, improved and maintained by the
Contractor at his own cost.

C-NIL I-NIL O-NIL SCC-3


7.2 The contractor shall segregate the site of work from other area, if required, in the Terminal
Building by providing wooden/steel barricades of appropriate height with proper
framing, keeping the aesthetic view of building and safety of passengers in mind as
directed by the Engineer-in-Charge to avoid inconvenience to the passenger. The
contractor shall provide and display the informatory sign boards like “Work in
Progress”, “Inconvenience cause is regretted” & “way finding” etc. with AAI logo as
directed by Engineer-In-Charge. After completion of the work these shall be removed and
taken away by the contractor. Cost of providing the barricades, sign boards etc. shall be borne
by the contractor and nothing extra shall be paid on this account.
7.3 All Temporary and ancillary works including enabling works connected with the work shall be
responsibility of the Contractor and the price quoted by them shall be deemed to have included
the cost of such works which shall be removed by the contractor at his cost, immediately after
completion of the work.
7.4 Site clearance (as per the requirements) shall be arranged by the contractor at his own cost and
nothing extra shall be payable on this account. All the salvageable materials received after
demolitions, if any, are to be stacked properly and handed over to Engineer-in-Charge. These
dismantled materials shall be the property of the Airports Authority of India.
8. PAYMENTS OF BILL
8.1 The bill shall be submitted at monthly intervals or before the date as fixed by the Engineer-in-
Charge for all the works executed since previous bill. The contractor shall submit all the bills
on the Performa prescribed by the Engineer-in-Charge, in triplicate. The bill need to be
submitted as per GST invoicing format, or as per relevant rules and regulation prescribed by
AAI.
8.2 The payment shall be made from the AAI Office at S.V. Airport, Raipur.

9. INCOME TAX AND LABOUR CESS


9.1 Income Tax deductions shall be made from all payments made to the Contractor as per the rules
and regulations in force in accordance with the Income Tax Act prevailing from time to time.
For other taxes refer to clause No. 37 on page GCC-67 & 68.
9.2 Labour cess @1% or as per rules and regulations in force shall be deducted from the bills of the
contractors and deposited with designated authorities.
10. WATER

10.1 The contractor shall make his own arrangement of suitable water for construction and his staff
and work men at his own cost. The testing charges for water shall be borne by the contractor.
Wherever AAI’s source of water is used by the contractor, 1% (one percent) of gross bill
amount (Work Done) shall be deducted from his bills.
11. POWER SUPPLY
11.1 The contractor shall make his own arrangement of power supply for construction as well as for
general lighting at his own cost and make necessary payments directly to the
Department/Authority concerned. The contractor shall lay necessary wiring and arrange for
main switch and meter at his own cost and remove the same on completion /termination of the
contract.
11.2 In case AAI’s electricity source is available near the work site and electricity can be spared to
the contractor as per the discretion of Engineer-in-Charge, the contractor may draw electricity
from the AAI’s source as approved by the Engineer-in-Charge. Necessary meter and connection
from the approved source shall be arranged by the contractor. No extra payment towards meter
and connection arrangement shall be made by AAI
11.3 Wherever AAI’s source of electricity is used by the contractor, Charges as fixed by the local
electricity Board / Authority / AAI for per unit shall be charged from the Contractor.
C-NIL I-NIL O-NIL SCC-4
12. CONTRACT AGREEMENT
12.1 The contract agreement shall be executed on a non-judicial stamp paper of value Rs. 100/- and
cost of the stamp paper shall be borne by the Contractor.
12.2 Contractor's tender including the letters of clarifications between the contractor and the AAI
prior to the award of contract shall form a part of the Contract Agreement to the extent they
have been accepted by AAI.
13 CONSTRUCTION EQUIPMENT
13.1 The contractor shall without prejudice to his overall responsibility to execute and complete the
work as per specifications and time schedule, progressively deploy adequate equipment’s, tools,
tackles and augment the same as decided by the Engineer-in-Charge depending on the
exigencies of the work so as to suit the construction schedule.

13.2 EQUIPMENTS FOR NIGHT WORKING:


In case, it appears, at any stage that the project may not be completed within the stipulated
period due to restricted working hours in the day in view of operational reasons, the contractor
shall execute the work during the night as and when asked by the Engineer-in-Charge in
writing. Nothing extra shall be payable to contractor for working in night time. For proper
execution, the work site shall be properly illuminated by the contractor at his own expenses.
13.3 No Construction equipment shall be supplied by the AAI.

14. SITE ORGANISATION

14.1 Subject to the provisions in the tender document and without prejudice to contractors’ liabilities
and responsibilities to provide adequate qualified and skilled personnel on the work, contractor
shall deploy site organization and augment the same as decided by the Engineer-in-Charge
depending on the exigencies of work. No engineering personnel deployed at site shall be
removed from the site without prior approval of the Engineer-in-charge.

15. CLOSING DAY’S WORK


15.1 After the closure of day's work, all equipment and materials must be placed at a location,
approved by Engineer-in-charge.

16. INSPECTION OF SITE AND TESTING


i) The Engineer-in-Charge or his authorized representative shall have full power to inspect any
portion of the work, examine the materials and workmanship at the contractors works or at any
other place from where the material is obtained. Acceptance of any material shall in no way
relieve the contractor of his responsibility for meeting the requirement of the specifications.

ii) Routine type tests for the various items of material shall be performed at the contractor's works
and test certificates furnished. The contractor shall permit the Engineer-in-Charge or his
authorized representative to be present during any of or all the tests. After notification to the
Engineer-in-Charge that the work has been completed, the contractor shall make under the
direction and in the presence of Engineer-in-Charge such tests and inspections as have been
specified or as the Engineer-in-Charge shall consider necessary to determine whether or not the
full intent of requirements of the plans and specifications have been fulfilled. In case the work
does not meet the full intent of the specifications it shall be rectified by the Contractor at no
extra cost and the contractor shall bear all the expenses for any further tests considered
necessary.

iii) All tools, instruments, plants, material and labour/operating personnel for thetest shall be
provided by the contractor at his own cost.
C-NIL I-NIL O-NIL SCC-5
iv) The Engineer-in-Charge may at his discretion, check the test results obtained at contractors
laboratory by independent tests at an approved laboratory. The cost of such material, transport,
cost of testing etc. shall be borne by the contractor.

17. ADMISSION TO SITE

17.1 For the works falling within the restricted area, execution shall be restricted to operational
requirement. The contractor is expected to finish the work before each break by adequate
planning with suitable constructions joints etc. as per the satisfaction of Engineer-in-charge. All
men & vehicles shall be permitted to enter the aerodrome operational area only on possession
of the security passes issued by AAI / Security agencies on the recommendations of Engineer-
in-charge. The contractor shall apply in writing in advance of the commencement of work for
issue of security passes and shall submit a list of personal concerned with their addresses and
shall satisfy the Engineer-incharge who shall at his discretion, have the right to recommend the
issue of passes to control the admission of contractor, his agents, his staff and workmen. The
contractor shall ensure that his men shall work in areas / zones allotted to them. Passes shall be
deposited with the Engineer-in-charge on demand and in any case immediately after completion
of work. The contractor’s staff/workmen shall observe all the rules promulgated from time to
time by the concerned authorities such as prohibition of smoking & lighting, search of persons
on entry and exit, keeping to specified routs etc. Any person found violating the security rules
laid down by the authorities will be expelled from the area without assigning any reason
whatsoever and contractor shall have no claim on this account. No time extension shall be
granted and nothing extra shall be payable by AAI on account of restriction due to non-
operational hours and working in restricted working conditions.

For entry of any vehicle inside the airport operational area a separate temporary vehicle entry
permit shall be issued, and the same will be charged as per AAI existing fee as applicable from
time to time. Nothing extra shall be paid to contractor /agency on this account.
Besides levying charges on entry of vehicles in operational area, it has been decided to levy
charges on the issuance of Airfield Driving Permit (ADP) after according necessary training.
The charges for issuance of ADP shall be as per rates prevalent at that time.

It may also be noted that, in addition to the aforesaid charges for vehicle permit, GST at the
prevalent rate will also be charged as per the Govt. policy.

C-NIL I-NIL O-NIL SCC-6


ISSUANCE OF VEHICLE PERMITS

Vehicle Entry Permit is required to be issued to vehicles which are required to operate on
airside area.
Documents required:

✓ Notification from the employer / owner of vehicle regarding requirement of vehicle in


operational area.
✓ Copy of Registration Certificate.
✓ Copy of Insurance policy of vehicle.
✓ Copy of Pollution check certificate of vehicle.

Vehicle inspection before issuance of Vehicle Entry Permit

The vehicle inspection is required to be carried out by safety officer before issuance of vehicle
entry permit. The following aspects to be ensured: -
• Vehicle is in road worthy condition
• Obstacle lights in accordance with CAR wherever night operation / low visibility operations
take place.
• Vehicle marking ensured: - logo of company / agency.

Speed governors to restrict spee


d of vehicle.

18. STORES AND MATERIALS

18.1 No storage accommodation will be arranged by AAI. Contractor shall make all such
arrangements at his own cost to the satisfaction of Engineer-in-Charge.

19. SITE FOR STACKING OF MATERIALS, MACHINES, INSTALLATIONS OF


T&P AND CONSTRUCTION OF TEMPORARY HUTMENTS.
19.1 The contractor shall be allowed to install plants and machineries, store and stack the material
within premises / area at Raipur Airport. However, installing crushing plant within AAI area
will not be permitted. For further details, please see clause 6 of SCC.

19.2 The contractor shall co-operate with any other agency working on the same project, compare
plans, specifications and the time schedule and so arrange his work that there will be no
interference. The contractor shall forward to the Engineer-in-Charge all correspondence and
drawings so exchanged. Failure to this will render the contractor responsible for bearing the
cost of any subsequent change found necessary. Contractor should co-ordinate in such a way
that on no account there should be any disturbance to the work.

C-NIL I-NIL O-NIL SCC-7


20. STANDARD OF WORKMANSHIP

20.1 To determine the acceptable standard of workmanship, the contractor shall execute portion of
the item of work as sample for approval of the Engineer-in-Charge, before taking up the actual
execution of the particular item of work.

21. BYE-LAWS

21.1 The contractor shall comply with all bye-laws and regulations of local and statutory authorities
having jurisdiction over the works and shall be responsible for payment of all fees and other
charges and for giving and receiving of all necessary notices and keeping the Engineer-in-
Charge, informed of the said compliance with the bye-laws, payments made, notices issued and
received.
21.2 The contractor shall indemnify the AAI against all claims in respect of patent rights, design,
trademarks of name or other protected rights in respect of any plant, machine, work or materials
used for or in connection with the work or temporary works and from and against all claims,
demands, proceedings, cost, charges and expenses whatsoever in respect of or in relation
thereto. The contractor shall defend all actions arising from such claims and shall himself pay
all royalties, license fees, damages, costs and charges of all and every sort that may be legally
incurred in respect thereto.

22. SITE PRECAUTIONS


i) Any materials or T & P etc. found lying outside the sites approved by the Engineer-in-Charge
shall be removed by the Engineer-in-Charge at the risk and cost of the contractor.

ii) With regard to construction safety measures, the contractor shall adhere to various Indian
Standard Codes of Practice, requirements of Provincial Government and local Municipal
Authority wherever the provisions of the latter two agencies shall be more stringent than the
provisions of the former. When these codes do not exist, the contractor shall adhere to such
safety measures as directed by the Engineer-in-Charge.

iii) The contractor shall, during construction, provide barricades as per specifications prescribed by
the Engineer-in-Charge to segregate the working area to ensure safety of all concerned. No
extra payment shall be made to the contractor on this account.

iv) The contractor shall be responsible for any damage, resulting from his operations, either to
buildings, structures, airport fixtures such as underground cable, contact lights, hard surface
areas, water mains, other operational installations, Airport roads etc. The contractor shall
restore, replace or repair any such damage to the complete satisfaction of the Engineer-in-
Charge and in default the Engineer-in-Charge may cause the same to be made good by any
other means and deduct the expenses from any sums due to contractor.

23. The contractor shall take all precautions to avoid all accidents by exhibiting necessary day &
night caution boards, speed limit boards, red flags, red lights and providing barriers. He shall be
responsible for all damages and accidents caused due to negligence on his or his personal’s part.
No hindrances shall be caused to traffic during execution of work.

24. No payment will be made to the contractor for damage caused by rains or other natural
calamities during the execution of the works and no such claim on this account will be
entertained.

C-NIL I-NIL O-NIL SCC-8


25. The contractor shall remove the labour huts, temporary barricades etc. on completion of the
work and leave the site in a neat and tidy state. The payment of final bill will be subject to the
compliance of this condition by the contractor.

26. MATERIAL AT SITE

(a) Materials brought to the site by the contractor shall be stored by the contractor in a safe/dry
storage space. The contractor shall be responsible for safe custody of materials at site till such
time, the installation is commissioned and handed over to the Engineer-in-Charge.

(b) Cement bags shall be stored in separate godowns to be constructed by Contractor at his own
cost with weather proof roofs and walls. Each godown shall be provided with a single door with
two locks, the keys of one lock shall remain with AAI Engineer-in-Charge of work and that of
the other lock with the authorized agent of the contractor at the site of work so that the cement
is removed from the godown according to the daily requirement with the knowledge of both the
parties and the account maintained in the prescribed proforma.

(c) The contractor is required to submit the bill receipt for steel, cement, paint and any item
incorporated in work for which Engineer-In-Charge directs.

27 ARRANGEMENT TO BE MADE BY THE CONTRACTOR AT SITE


SITE OFFICE, VEHICLES AND OTHER PLANTS & EQUIPMENTS

27.1 Contractor has to arrange required T&P and machinery for execution of work. Rent of land to
be used for T & P, Contractor’s site office, Labour huts etc. by the contractor shall be
charged at rates & security deposit as per clause 6 of SCC. Necessary registers and stationeries
required for entering data and test results shall be provided by the contractor at his own cost as
directed by the Engineer- in-Charge.

27.2 Necessary diesel/petrol/fuel & lubricants etc. for smooth running of all the equipments, vehicles
and machineries deployed for the work shall be provided by the contractor at his own expense.
In the event of any break down of the plant, vehicles and machineries deployed for the work,
the contractor shall take prompt remedial measure to put them back in working condition and
nothing extra will be paid. To minimize break down period, necessary spare parts shall be kept
readily available at site by the contractor at his own expense.

27.3 The equipment required for execution of work should be positioned as per instructions of
Engineer-in-charge. No rent or security deposit of land shall be charged for stacking of
material/ movable machinery required for execution of work in available land in consultation
with Engineer-in-charge.

27.4. The agency is also required to provide specific safety devices to the manpower deployed at site
for the work as detailed below:‐

i) Safety helmets and foot wears are to be provided for the workers.
ii) Safety belts, protective Goggles, Hand gloves etc are to be provided as per requirement and
nature of job.

C-NIL I-NIL O-NIL SCC-9


28 RECOVERIES

28.1 The works diary shall be got printed by the contractor and also pages shall be machine
numbered. The proforma for the same is given at Annexure – 8. Additional sheets should also
enclose with each page so as to furnish any additional information. Work diary shall be signed
by the contractor/ Engineering Representative on daily basis by presenting himself in the site
office of Engineer-in-charge. Failure to do so render agency liable to pay penalty @ Rs. 100/-
per day for each day of such lapses. In case of failure to do so the details as filled up by AAI
representative shall be treated as final.

28.2 However, these recoveries as stipulated above do not relieve the contractor to pay levy of
compensation for delay as per clause no. 2 of GCC, in case work is not completed within the
stipulated time.

29. APPARTITIONING OF WORK


The Airport Authority of India reserves the right to apparition the work at different levels
amongst not more than two contractors, by negotiations, if necessary.
30. USE OF PORTLAND POZZOLONA CEMENT (PPC)
The contractor is allowed to use PPC in case of non-availability of 43 grade OPC where ever
applicable with prior approval of Engineer-in-charge.

In order to encourage use of fly ash as per Govt. of India guidelines, Portland Pozzolana
Cement (PPC) of approved grade shall be used for the work. It shall be ensured that the
percentage of fly ash is printed on each bag of cement (PPC) by the manufacturer. In case, it is
not printed on each bag, a certificate from the PPC manufacturer indicating the same shall be
obtained before allowing such cement in works.
i) In case OPC is used by the agency, Engineer-In-Charge may permit use of the same.
ii) In case the contractor uses OPC, he must use 43 grade OPC. The contractor is allowed to use 53
grade OPC only in case of non-availability of 43 grade OPC wherever possible with prior
approval of Engineer-In-Charge. However, nothing shall be paid extra to contractor on this
account.
31. PERFORMANCE
The contractor shall perform all works in substantial and acceptable manner in accordance with
the plans and specifications and in accordance with such further and explanatory drawings,
details and instructions as may from time to time be given by the Engineer-in-Charge. The work
must be progressed within such sections and at each time as directed by the Engineer-in-
Charge.
32. DIFFERENCE BETWEEN FIRST LOWEST BIDDER AND SECOND LOWEST
BIDDER
32.1 Final bill will be worked out at the accepted tender rates and also with quoted rates of
second lowest. The amount of final bill to be paid will be restricted to the lowest of the
two.

33. PRICES
The rates quoted shall be in Indian Rupees only and inclusive of cost of material, all taxes,
(Except GST), duties, levies, labour cess, applicable customs duty in case of imported items,
labour, tools & plants, packing, freight / transportation of items from factory up to the
installation site, Octroi & insurance up to the site, loading, unloading and hoisting arrangement
for installation, fee(s) for testing, inspection documents including the fee(s) payable for
obtaining statutory license / approval etc. from concerned department .

C-NIL I-NIL O-NIL SCC-10


34. SOURCE OF MATERIAL

34.1Aggregate shall be procured from approved quarries subject to fulfillment of test criteria as
specified in BOQ items / Technical Specifications and approval of Engineer-In- Charge.

34.2No crushing of aggregate will be allowed within AAI premises and its vicinity.

35. SITE CONDITIONS, REQUIREMENTS AND SOURCES OF MATERIALS.

a) The contractor shall be responsible for the true and proper setting out of the work and for the
correctness of the positions levels and dimensions and alignments of all parts of the works and
for the provisions of all necessary applications and labour in connections therewith.

b) If any time during the progress of the work any error may appear or arise in the position, levels,
dimension or alignments of any part of the work, the contractor on being required to do so by
the Engineer-in-Charge shall at his own expense rectify such errors to the satisfaction of the
Engineer-in-Charge.

c) The checking or any setting out of any line by the Engineer-in-Charge or his representative
shall not relieve in any way the contractor of responsibility for the correctness thereof and shall
carefully project and preserve all bench marks, site rails, pegs and other things used in the set
out of work.

d) All duties concerning establishment of a set of bench marks, permanent theodolite stations,
centre of pillars etc. for performing all the functions of us till the physical completion of all
items in question shall be carried out by the contractor at his own cost.

e) He shall also keep proper record of such permanent bench marks established, denoting therein
their correct levels.

f) The work establishing all such bench marks shall be carried out only by experience staff of the
contractor with the help of precision instrument suitable for this type of work. The instruments
shall be checked for their accuracy and for permanent adjustment before the commencement of
the work and also frequent intervals during the progress of the work.

g) All such bench marks established by the contractor shall be subjected to check and approval of
the Engineer-in-Charge or his duly representative and variations noticed in the work as a result
of improper establishment or maintenance of such bench marks shall be at the contractor’s risk
and expense.

h) The contractor has to adjust his work and progress to work in co-ordination with other agencies
working at site.

i) The materials such as Granite, Sand and other materials shall be brought to site only after
approval of the quarry / source by the Engineer-in-Charge.

NUISANCE:

36. The Contractor shall not at anytime do, cause or permit any nuisance on the Site or do anything
which shall cause unnecessary disturbance or inconvenience to owners, tenants or occupiers of
other properties near the Site and to the Public generally.

C-NIL I-NIL O-NIL SCC-11


WATCHING AND LIGHTING:

37. The Contractor shall provide and maintain at his own expense all lights, guards, fencing and
watching when and where necessary or required by the Engineer-in-Charge for the protection of the
Works or for the safety and convenience of those employed on the Works.

38. DUTIES AND POWERS OF ENGINEER-IN-CHARGES’S REPRESENTATIVE:

The duties of the representative of the Engineer-in-Charge, are to watch and supervise the
Works and to test and examine any materials to be used or workmanship employed in
connection with the Works. He shall have no authority to order any work involving any extra
payment by AAI nor to make any variation in the Works.

38.1The Engineer-in-Charge may from time to time in writing delegate to his Representative any of
the powers and authorities vested in the Engineer-in-Charge and shall furnish to the Contractor a
copy of all such written delegation of powers and authorities. Any written instruction or written
approval given by the Representative of the Engineer-in-Charge to the Contractor within the
terms of such delegations shall bind the Contractor and AAI as though it had been given by the
Engineer-in-Charge.

38.2Failure of the Representative of the Engineer-in-Charge to disapprove any work or materials


shall not prejudice the power of the Engineer-in-Charge thereafter to disapprove such work or
materials and to order the pulling down, removal or breaking up thereof.

38.3If the Contractor shall be dissatisfied with any decision of the Representative of the Engineer- in-Charge,
he shall be entitled to refer the matter to the Engineer-in Charge who shall thereupon confirm, reverse or
vary such decision.

39. WORK DURING NIGHT OR ON SUNDAYS AND HOLIDAYS:

Subject to any provisions to the contrary contained in the Contract, permanent works shall be
carried out during night or on Sundays or on authorized holidays with the permission of the
Engineer-in-Charge.

40. TESTS:
The various tests as indicated in the CPWD specifications, BIS, particular / Technical
specification, MORTH specification as considered necessary by the Engineer-in-Charge shall
be carried out in the laboratory as approved by the Engineer-in-Charge. The contractor shall
bear the entire cost of samples, testing charges, carriage and any other incidental expenditure
incurred, thereon. The result shall be final and binding on the contractor.

40.1 For the civil works the work shall in general conform to the CPWD specification 2019 Vol. I &
II with correction slips issued up to date and MORTH Specification with correction slips /
amendments upto date. Should there be any difference in the provision of the said specifications
for any item of work and the description of the item given in the schedule of quantities, the latter
shall prevail. If any item is not covered in CPWD specifications, any other related specifications
or printed publication on general specifications refer to elsewhere in the contract with up-to-date
correction slips shall be followed.

40.2All the materials to be used on the work shall be of best quality available and shall have the
approval of Engineer-in-Charge before use.

C-NIL I-NIL O-NIL SCC-12


41. The contractor shall arrange to provide portable lights and markings with the luminous paint to
indicate the areas under construction or repairs as per the direction of Engineer-in-Charge. These
lights shall be of the approved colour and capacity and shall be operated throughout the night and
during bad weather. In addition to these markings, lights, cone markers painted with luminous
paints shall also be put.

42. The contractor will remove the labour huts on completion of the work. The payment of final bill
will be subject to the compliance of this condition by the contractor.

43. The contractor shall provide suitable temporary diversion arrangement for flow of water in the
existing drain, pumping and bailing out water from the drain, if required, for proper execution of
the works, at his own cost & as per directions of Engineer-in-Charge.

44. The contractor shall make necessary arrangement for all machinery, equipment etc. considered
necessary by the Engineer-in-Charge for completion of works within the stipulated time. The rates
quoted by the contractor shall include the cost of providing / running all such machinery,
equipment etc. Nothing extra shall be paid on this account.

45. The contractor shall regulate the movement of vehicles in accordance with the regulations of local
traffic authority and shall provide necessary roads, diversions etc. for access of vehicles to the site
of work. Nothing extra over and above quoted by him shall be paid on this account.

46. SAMPLING AND TESTING

a. The contractor shall provide proper facilities at all times for the inspection and testing of
materials and the Engineer-in-Charge shall have access at all times to the place of stores or
manufacture. The contractor shall give sufficient advance notice of placing order so as to permit
test to be completed before the material is incorporated in the work and shall afford such
facilities as the Engineer-in-Charge may require for collection and forwarding samples and
making inspection. The contractor shall not make use of or incorporate in the work the
materials represented by the samples, until tests have been made and materials found to be in
accordance with the specifications.

b. All tests of materials furnished by the contractor shall be made in accordance with commonly
recognized methods of Indian or of other international organization or such other method and
test as are prescribed in the specification or are in use in conformity with standard practice of
the department and all charges will be borne by the contractor.

c. Field tests of materials will be carried out by the Engineer-in-Charge as deemed necessary and
these tests shall be made in accordance with the standard practices of the department. The cost
involved in all such field tests will be borne by the contractor.

d. The various tests as indicated in the specifications or as considered necessary by the Engineer-
in-Charge shall be carried out in the laboratory as approved by the Engineer-in-Charge. The
contractor shall bear the entire cost of samples, testing charge, carriage and other incidental
expenditure incurred thereof. The result shall be final and binding on the contractor.

e. The contractor shall submit certified true copies of the vouchers for verification of actual
purchase of any materials whenever directed by the Engineer-in-Charge.

f. The contractor shall not be entitled for any extra payment whatsoever on account of the above
special conditions of contract until and unless specified otherwise.

C-NIL I-NIL O-NIL SCC-13


SCC-13
AIRPORTS AUTHORITY OF INDIA

g. Contractor shall distinctly display a board at work site on the cement store indicating
the opening balance on a particular day, receipt during the day and issue during the day
and closing balance at the end of the day. (The entries shall be updated immediately on
physical issues).

47. If any additional tests apart from mandatory tests specified in the Contract are required to
be carried out at the instance of AAI or Chief Technical Examiners Organization, to ensure
conformity of the item to the Contract specifications, the cost of such tests shall be borne
by Airports Authority of India. In case the material / equipment fails in the above tests, the
expenditure incurred by AAI on testing of such material or equipment along with
incidental charges borne by AAI (if any) shall be recovered from the dues of the contractor
and action shall be taken under Clause 16 of GCC and other relevant clauses of the
contract.

C-NIL I-NIL O-NIL SCC-14


SCC-14
AIRPORTS AUTHORITY OF INDIA

TECHNICAL SPECIFICATIONS
1.00 PREAMBLE
1.01 These technical specifications shall be read in conjunction with the various other documents forming
the contract, namely Notice Inviting Tender & Instructions to Tenderers, Conditions of Contract, Special
Conditions of Contract, Bill of Quantities and other related documents, together with any addenda thereto
issued.
2.0 SCOPE OF WORK
2.01 The work to be carried out under this contract shall consist of various items as per description of works
contained in the Bill of Quantities. Any discrepancy between the details given in Bill of Quantities and that
provided in Technical Specifications of the corresponding items, the provisions of the Bill of Quantities
shall take precedence.
2.01.1 The item rates quoted by the Contractor shall, unless otherwise specified also include compliance
with/supply of the following:-
a. General works such as setting out, clearance of site before setting out and clearance of works after
completion.
b. A detailed program for the construction and completion of works (using CPM/PERT techniques)
including updating of all such activities on the basis of decisions taken at the periodic site review
meetings as directed by the Engineer-in-Charge.
c. Samples of various materials proposed to be used on the work for conducting tests thereon is
required as per the provisions of the contract.
d. Design of mixes as per relevant clauses of the specifications given proportions of ingredients,
source of aggregates and binder along with accompanying trial mixes to be submitted to the
Engineer-in-Charge for his approval before use on the works.
e. Required apparatus and staffs for conducting day to day quality control tests.
f. Any other item of work which is not specifically provided in the Bill of Quantities but which is
necessary for complying with the provisions of the contract.
3.00 OBLIGATIONS OF THE CONTRACTOR
3.01 In order to ensure that the contract work is executed strictly in accordance with this Agreement and in
time, the Contractor shall have the following obligations at no extra cost to the Engineer-in-Charge in
addition to such other obligations and responsibilities as have been specified elsewhere in this Contract.
i. Provision of adequate number of constructional Plant and machinery for mechanized system of
construction, handling and transportation;
ii. Provision of special magazine at the site for storage of explosives, if necessary, for which
required license shall be obtained from the concerned authorities;
iii. Fulfill all the Contractor's labour regulations i.e. fair wages, display of notices regarding wages,
payment of wages, labour records, attendance cards-cum-wage slips, labour welfare etc. as per
standard practices and norms applicable at site;
3.02 All fossils, gold, silver, oil and other minerals, precious stones, coins, article of value, of antiquity and
structures and other remains / things of geological or archaeological interest discovered on the site of the
works shall be notified by the Contractor immediately to the Engineer-in-Charge for onward information to
the concerned authorities.
3.03 The Contractor shall take all reasonable precaution to prevent his workmen or any other person from
removing or damaging any such article(s) or thing(s) and protect the same till the removal as per the
instructions of the Engineer-in-Charge.
3.04 Clearance of the site of all rubbish, debris, vats, tanks, materials, temporary structures, plant and
machinery, scaffoldings and filling of all pits, excavation and hand over the site in a tidy and cleaned
condition.

C-NIL I-NIL O-NIL SCC-15 TS-1


AIRPORTS AUTHORITY OF INDIA

3.05 Opening up of covered work if instructed by the Engineer, if such covering was done before inspection
by the Engineer or without permission/approval from the Engineer-in-Charge.
3.06 During the construction of the airfield pavement, the light foundations will have to be provided as per
the drawings, specifications and directions of the Engineer-in-Charge at such appropriate stage as decided
by him. The Contractor shall obtain the approval of the Engineer-in-Charge the work plan for placing the
light foundation at their designated places. The rest of the pavement will be constructed around these
foundations in place without causing any damage to the foundation. The rate quoted shall include all these
requirements. During execution of works for providing shoulders, rolling operation should be conducted
with atmost care so as not to damage the existing light fittings. Excavation and compaction around light
fittings shall be done manually.
3.07 Wherever the word “Engineer” has been mentioned in the Technical Specifications that will imply
“Engineer-in-Charge”.
4.00 GENERAL
4.01 The works will be executed as indicated in the nomenclature of each item and technical specifications
as given hereunder as made applicable to this contract.
4.02 In the absence of any definite provision in the technical specifications contained herein, reference may
be made to the latest CPWD, MORTH, IRC, ICAO Specifications and IS codes, in that order. Wherever
these are silent, the construction and completion of the works shall conform to sound engineering practice
and in case of any dispute arising out of the interpretation of the above, the decision of the Engineer-in-
Charge shall be final and binding on the Contractor.
4.03 In addition, the abbreviations CPWD, MORTH, IRC, ICAO, IS, BS, ASTM, AASHTO shall be
considered to have the following meaning:-
CPWD : Central Public Works Department
MORTH : Ministry of Road Transport and Highways, Government of India
IRC : Indian Road Congress
ICAO : International Civil Aviation Organisation
IS : Indian Standard of the Bureau of Indian Standards.
BS : British Standard of the British Standard
ASTM : American Standards of the American Society of Testing Materials
AASHTO : American Association of State Highway and Transportation Officials.

All the codes of practice, standards and specifications applicable shall be the latest editions with upto date
correction slips etc. or as directed by the Engineer-in-Charge.
5.00 TESTING
5.01 It is made clear that cost of testing, cost of material for testing, all field apparatus required for sampling
and testing as per CPWD/MoRTH/IS codes and manpower incident to such testing will be provided along
with necessary transport arrangement to and fro to the approved testing agency or laboratory by the
Contractor during the construction phase of the work and defect liability period. The expenditure in this
regard shall be borne by the Contractor and nothing extra shall be payable by AAI on this account.
Field laboratory with all the required apparatus and staffs shall be established by the Contractor at site of
work for carrying out field tests at stipulated frequencies.

5.02 FIELD LABORATORY


5.02.1 Scope
The work covers the provision and maintenance of an adequately equipped field laboratory as required for
site control on the quality of materials and the works.

TS-2
C-NIL I-NIL O-NIL SCC-16
AIRPORTS AUTHORITY OF INDIA

5.02.2 Description
The Contractor shall arrange at his own cost to provide fully furnished and adequately equipped field
laboratory constructed by him. The field laboratory shall preferably be located adjacent to the site office of
the Engineer and provided with amenities like water supply, electric supply etc. The floor space requirement
for the field laboratory shall include office space for the Engineers, one from the Contractor's side and
another from the Engineer – in – Charge’s side and a store for the storage of samples. The remaining space
shall be provided for the installation of equipment, laboratory tables and cupboards, working space for
carrying out various laboratory tests, besides a wash basin and a curing tank for the curing of samples,
around 4m x 2m x 1m in size.
5.02.3 The Engineer-in-Charge may at his discretion, check the test results obtained at contractors laboratory
by independent tests at an approved laboratory. The cost of such material, transport, cost of testing etc. shall
be borne by the contractor.
6.00 SAMPLING AND TESTING
6.01 The Contractor or his accredited representative shall be present during sampling/testing and signify his
concurrence for sampling/ testing carried out by signing the test records. The Contractor shall be liable of all
actions consequent to the test and their results as if he himself attended to the tests. The Contractor is duly
advised to be present himself for sampling and testing or in the alternative, have fully qualified duly
authorized Engineer for this purpose.
7.00 CONSTRUCTION EQUIPMENT
7.01 General
All tools, equipment and machineries necessary for proper levelling & grading shall be at the project site in
good working condition and shall have been inspected by the Engineer before the construction work
permitted to start. Throughout the construction of the project, the construction agency shall maintain all
necessary tools, equipment and machineries in first class working condition to ensure proper execution of
the work. Arrangements shall also be made for requisite number of stand by units in the event or break-
downs during construction.
List of Tools, Equipment and Machineries
List of Tools, Plants, Equipments and Machineries for Construction Work:
i. Hydraulic Excavator 0.9 cum bucket capacity @60 cum per hour.
ii. Tipper 5.5 cum capacity.
iii. Dozer 80 HP for spreading @200 cum per hour
iv. Motor grader for grading @100 cum per hour.
v. Vibratory Roller 8 to 10 tonne @100 cum per hour.
vi. Water tankers/water sprinkler or browser fitted with pump.
8.0 GENERAL LIST OF CODES, STANDARDS AND SPECIFICATIONS ADOPTED IN THE
TENDER DOCUMENTS.
8.01 The following IRC standards and IS, ASTM, British Standards, Codes, CPWD Specifications and
MoRTH Specification have generally been adopted in the tender documents. This list however does not
limit the use of any other relevant code or standards by the Engineer-in-charge solely at his discretion either
referred to in the tender documents or not, to achieve the desired quality of work. All the codes practice,
standards and specifications applicable shall be the latest edition with all correction slips, etc, or as directed
by the Engineer-in-Charge.

NUMBER/DESIGNATION TITLE
IRC SPECIFICATION
Recommended Practice for Borrowpits for Road Embankment
IRC:10
Constructed by Manual Operation.
Standard Specification and Code Practice for Water Bound
IRC:19
Macadam (Second Revision)
Hand Book of Quality Control for construction of Roads and
IRC:SP 11
Runway (First Revision)

C-NIL I-NIL O-NIL SCC-17


TS-3
AIRPORTS AUTHORITY OF INDIA

Guidelines on use of Polymer and rubber modified bitumen in road


IRC:SP 53
construction.
INDIAN STANDARDS
IS:838 Coarse and fine aggregates from natural sources for concrete.
IS:456 Code of practice for plain and reinforced concrete.
IS:460 (Part I to III) Testing Sieves
IS:516 Methods of test for strength of concrete.
Method of test for water absorption, apparent specific gravity and
IS:1124
porosity of Natural Building Stone.
IS:1199 Methods of sampling and analysis of concrete.
IS:2386 Methods of test for aggregate for concrete:-
(Part –I) Particle size and shape.
(Part –II) Estimation of deleterious materials and organic impurities.
(Part –III) Specific gravity, density, voids, absorption and bulking.
(Part –IV) Mechanical Properties.
(Part –V) Soundness
(Part –VI) Measuring mortar making properties of fine aggregates.
(Part –VII) Alkali-Aggregate reactivity
(Part –VIII) Petrography Examination
IS:2720 Methods of tests for soils:
(Part –II) Determination of water content
(Part-III) (Section-I) Determination of specific gravity, section I fine grained soils.
Determination of specific gravity, fine medium and coarse grained
(Part-III) (Section-II)
soils.
Part-IV Grain size analysis
Part-V Determination of liquid and plastic limit.
Determination of water content dry density relation using light
Part-VII
compaction.
Determination of water content dry density relation using heavy
Part-VIII
compaction.
Part-XVI Laboratory determination of CBR.
Part-XXVII Determination of total soluble sulphate.
Part-XXVIII Determination of dry density of soils in place by core cutter method.
Part XXIX Determination of dry density of soils in place by core cutter method.
Method of determining the aggregate impact value of soft coarse
IS:5640
aggregate.
Method of test for determination of stripping value of road
IS:6241
aggregates.
IS:8112
43 grade ordinary Portland Cement. Pozzolana Portland Cement.
IS: 1489
BS:5212, Part-I, 1990 Two parts polysulphide based sealants.
ASTM/BS STANDARDS/SPECIFICATION
Test for resistance to plastic flow of bituminous mixtures using
ASTM:D-1559
Marshall apparatus.

C-NIL I-NIL O-NIL SCC-18


AIRPORTS AUTHORITY OF INDIA

Extraction quantitative, of bitumen from bituminous paving


ASTM:D-2172
mixtures.
Sieves for testing purpose “Wire Cloth sieve round hole and
ASTM:E-11-39
square” hole plate screen of Sieves.
BS:410 Test Sieves.
“Specification for Road and Bridge Works” fourth revision
MORTH Specification reprinted in September, 2004. Issued by Ministry of Surface
Transport (Roads Wing) and published by Indian Roads Congress.
Annexure 14 of the concention on
ICAO’s Annex 14
International Civil Aviation.

9.0 SUBMISSION AND APPROVAL OF PROPOSED FINISHED LEVELS AND PROFILE


There is provision to take spot levels specified in various item before commencement of that item. The
contractor after taking complete spot levels shall submit the proposed finished levels and profile alongwith
anticipated quantity of item(s) as per ICAO to Engineer-in-Charge for his approval. The contractor will
review the same, in case of any modification in proposed in finished levels/profile are suggested by
Engineer-in-Charge before his approval. Nothing shall be paid extra on this account.

TS-4
C-NIL I-NIL O-NIL SCC-19
AIRPORTS AUTHORITY OF INDIA

Item No. 1 Earth work in excavation with hydraulic excavator of 0.9 cum bucket capacity
including cutting and loading in tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross section, and transporting to the embankment / filling
location within all lifts and leads within AAI premises including construction of embankment
with excavated earth at locations by spreading soil in layer not exceeding 20 cm in loose
including breaking chods, watering and consolidating each layer with 8 to 10 tome capacity
vibratory roller to achieve min. 95% relative compaction (field density), required slope as per
MoRTH specification and direction and satisfaction of Engg-in-charge.

SCOPE
This work shall consist of excavation, removal and satisfactory disposal of all materials necessary for
the construction of runway, shoulder and basic strip in accordance with requirements of these
Specifications and the lines, grades and cross-sections shown in the drawings or as indicated by the
Engineer-in-charge. It shall include the hauling and stacking of or hauling to sites of embankment and
subgrade construction, suitable cut materials as required, as also the disposal of unsuitable cut
materials in specified manner, trimming and finishing of the runway, shoulder and basic strip to
specified dimensions or as directed by the Engineer-in-charge. The work also include construction of
embankment including sub grades, shoulder and basic strip etc backfill with approved excavated
material in accordance with requirements of these Specifications and the lines, grades and cross-
sections shown in the drawings or as indicated by the Engineer-in-charge.

2 CONSTRUCTION OPERATIONS
2.1 Setting out:
After the site has been cleared such as trees, bushes, shrubs, stumps, roots, grass, weeds, top organic
soil as per site requirement, the limits of excavation or embankment or excavation/embankment shall
be set out true to lines, curves, slopes, grades and sections as shown on the drawings or as directed
by the Engineer. The embankment/ subgrade shall be build sufficiently wider then the design
dimension so that surplus material may be trimmed, ensuring that the remaining material is to the
desired density. The Contractor shall provide all labour, survey instruments and materials such as
strings, pegs, nails, bamboos, stones, lime, mortar, concrete, etc., required in connection with the
setting out of works and the establishment of bench marks. The Contractor shall be responsible for
the maintenance of bench marks and other marks and stakes as long for the maintenance of bench
marks and other marks and stakes as long as in the opinion of the Engineer-in-charge, they are
required for the work.
2.2 Excavation – General:
All excavations shall be carried out in conformity with the directions laid here –in-under and in a
manner approved by the Engineer-in-charge. The work shall be so done that the suitable materials
available from excavation are satisfactorily utilized as decided upon beforehand.
While planning or executing excavations, the contractor shall take all adequate precautions against
soil erosion, water pollution etc., and take appropriate drainage measures to keep the site free of
water in accordance with the site condition.
The excavations shall conform to the lines, grades, side slopes and levels shown on the drawings or as
directed by the Engineer-in-charge. The Contractor shall not excavate outside the limits of excavation.
Subject to the permitted tolerances, any excess depth/width excavated beyond the specified
levels/dimensions on the drawings shall be made good at the cost of the contractor with suitable
material of characteristics similar to that removed and compacted to the requirements of table-1.
All debris and loose material on the slopes of cuttings shall be removed. No backfilling shall be
allowed to obtain required slopes excepting that when boulders or soft materials are encountered in
cut slopes, these shall be excavated to approved depth on instructions of the Engineer and the
resulting cavities filled with suitable material and thoroughly compacted in an approved manner.

TS-5
C-NIL I-NIL O-NIL SCC-20
AIRPORTS AUTHORITY OF INDIA

After excavation, the sides of excavated area shall be trimmed and the area contoured to minimize
erosion and ponding, allowing for natural drainage to take place. The excavated area shall be rolled
with minimum 3 passes of roller and finished at desired slope for drainage as per direction Engineer-
in-Charge.

2.3 Embankment
2.3.1 Physical requirements:
The materials used in embankments, sub grades, earthen shoulders and miscellaneous backfills shall
be excavated soil, moorum, gravel, a mixture of these or any other material approved by the
Engineer-in-charge. Such materials shall be free of logs, stumps, roots, rubbish or any other ingredient
likely to deteriorate or affect the stability of the embankment/subgrade.
The size of the coarse material in the mixture of earth shall ordinarily not exceed 75 mm when being
placed in the embankment and 50 mm when placed in the subgrade. However, the Engineer-in-charge
may at his discretion permit the use of material coarser than this also if he is satisfied that the same
will not present any difficulty as regards the placement of fill material and its compaction to the
requirements of these Specifications. The maximum particle size shall not be more than two - thirds of
the compacted layer thickness.
2.3.2. General requirements:
The materials for embankment shall be obtained from available at site nearby runway excavation or
any other excavation under the same contract.
The work shall be so planned and executed that the best available materials are saved for the
subgrade and the embankment portion just below the subgrade.
The Contractor shall obtain representative samples from each of the identified borrow areas within
AAI’s premises and have these tested at the site laboratory following a testing programme approved
by the Engineer-in-charge. It shall be ensured that the subgrade material when compacted to the
density requirements as in Table 1 shall yield the design CBR value of the subgrade.

TABLE 1 COMPACTION REQUIREMENTS FOR


EMBANKMENT AND SUBGRADE

Type of work / material Relative compaction as percentage


of max. laboratory dry density as
per IS : 2720 (Part 8)

1. Embankment and basic strip Not less than 95

The contractor shall at least 7 working days before commencement of compaction submit the
following to the Engineer-in-charge for approval:
i) The values of maximum dry density and optimum moisture content obtained in accordance with IS:
2720 (Part 7) or (Part 8), as the case may be, appropriate for each of the fill materials he intends to
use.
ii) A graph of density plotted against moisture content from which each of the values in (i) above of
maximum dry density and optimum moisture content were determined.
iii) The Dry density – moisture content – CBR relationships for light, intermediate and heavy
compactive efforts (light corresponding to IS: 2720 (Part 7), heavy corresponding to IS: 2720 (Part
8) and intermediate in – between the two) for each of the fill materials he intends to use in the
subgrade.

TS-6
C-NIL I-NIL O-NIL SCC-21
AIRPORTS AUTHORITY OF INDIA

2.4. Methods, tools and equipment:


Only such methods, tools and equipment as approved by the Engineer-in-charge shall be adopted
/sued in the work. If so desired by the Engineer-in-charge, the contractor shall demonstrate the
efficacy of the type of equipment to be used before the commencement of work.
2.5. Dewatering:
If water is met with in the excavations or the foundation of the embankment is in area with stagnant
water due to springs, seepage, rain or other causes, it shall be removed by suitable diversions,
pumping or bailing out and the excavation kept dry whenever so required or directed by the Engineer-
in-charge. Care shall be taken to discharge the drained water into suitable outlets as not to cause
damage to the works, crops or any other property. Due to any negligence on the part of the Contractor,
if any such damage is caused, it shall be the sole responsibility of the contractor to repair/restore to
the original condition at his own cost or compensate for the damage.
2.6 Disposal of excavated materials:

All the excavated materials shall be the property of the AAI. The material obtained from the
excavation of runway, shoulders and basic strip etc., shall be used for filling up of (i) runway
subgrade,(ii) basic strip as directed by the Engineer-in-charge, including leveling and spreading with
all lifts and lead within airport premises and no extra payment shall be made for the same.
All hard materials, such as hard moorum, rubble, etc., not intended for use as above shall be stacked
neatly on specified land as directed by the Engineer-in-charge with all lifts and lead within airport
premises.
2.7 Compacting ground supporting embankment/subgrade:
Where necessary, the original ground shall be leveled to facilitate placement of first layer of
embankment, scarified, mixed with water and then compacted by rolling so as to achieve minimum dry
density as given in Table1.
2.8. Spreading material in layers and bringing to appropriate moisture content
2.8.1 The embankment and subgrade material shall be spread in layers of uniform thickness not
exceeding 200 mm compacted thickness over the entire width of embankment by mechanical
means, finished by a motor grader and compacted as per clause 2.9. The motor grader blade
shall have hydraulic control suitable for initial adjustment and maintain the same so as to
achieve the specific slope and grade. Successive layers shall not be placed until the layer
under construction has been thoroughly compacted to the specified requirements as in Table
1 and got approved by the Engineer-in-charge. Each compacted layer shall be finished
parallel to the final cross-section of the embankment.
2.8.2 Moisture content of the material shall be checked at the site of placement prior to
commencement of compaction; if found to be out of agreed limits, the same shall be made
good. Where water is required to be added in such constructions, water shall be sprinkled
from a water tanker fitted with sprinkler capable of applying water uniformly with a
controllable rate of flow to variable widths of surface but without any flooding. The water
shall be added uniformly and thoroughly mixed in soil by blading, discing or harrowing until
uniform moisture content is obtained throughout the depth of the layer.
If the material delivered to the bed is too wet, it shall be dried, by aeration and exposure to
the sun, till the moisture content is acceptable for compaction. Should circumstances arise,
where owing to wet weather, the moisture content cannot be reduced to the required amount
by the above procedure, compaction work shall be suspended.
Moisture content of each layer of soil shall be checked in accordance with IS: 2720 (Part 2),
and unless otherwise mentioned, shall be so adjusted, making due allowance for evaporation
losses, that at the time of compaction it is in the range of 1 percent above to 2 percent below
the optimum moisture content determined in accordance with IS: 2720 (Part 7) or IS: 2720
(Part 8) as the case may be.
After adding the required amount of water, the soil shall be processed be means of graders,
harrows, rotary mixers or as otherwise approved by the Engineer-in-charge until the layer is

TS-7
C-NIL I-NIL O-NIL SCC-22
AIRPORTS AUTHORITY OF INDIA

uniformly wet.
Clods or hard lumps of earth shall be broken to have a maximum size of 75 mm when being
placed in the embankment and a maximum size of 50 mm when being placed in the subgrade.
2.8.3. Embankment and other areas of fill shall, unless otherwise required in the contract or
permitted by the Engineer-in-charge, be constructed evenly over their full width and their fullest
possible extent and the contractor shall control and direct construction plant and other vehicular
traffic uniformly over them. Damage by construction plant and other vehicular traffic shall be made
good by the contractor with material having the same characteristics and strength as the material had
before it was damaged.
Embankments and other areas of unsupported fills shall not be constructed with steeper side slopes,
or to greater widths than those shown in the contract, except to permit adequate compaction at the
edges before trimming back, or to obtain the final profile following any settlement of the fill and the
underlying material.
2.9 Compaction:
Only the compaction equipment approved by the Engineer-in-charge shall be employed to compact
the different material types encountered during construction. Smooth wheeled, vibratory, pneumatic
tyred, sheepsfoot or pad foot rollers, etc. of suitable size and capacity as approved by the Engineer-in-
charge shall be used for the different types and grades of materials required to be compacted either
individually or in suitable combinations.
The compaction shall be done with the help of vibratory roller of 80 to 100 k N static weight with
plain or pad foot drum or heavy pneumatic tyred roller of adequate capacity capable of achieving
required compaction.
The contractor shall demonstrate the efficacy of the equipment he intends to use by carrying out
compaction trials. The procedure to be adopted for these site trials shall first be submitted to the
Engineer-in-charge for approval.
Earthmoving plant shall not be accepted as compaction equipment nor shall the use of a lighter
category of plant to provide any preliminary compaction to assist the use of heavier plant be taken
into account.
Each layer of the material shall be thoroughly compacted to the densities specified in Table 1.
Subsequent layers shall be placed only after the finished layer has been tested according to quality
control test criteria and accepted by the Engineer-in-charge. The Engineer-in-charge may permit
measurement of field dry density bya nuclear moisture/density gauge used in accordance with agreed
procedure and the gauge is calibrated to provide results identical to that obtained from tests in
accordance with IS: 2720 (Part 28). A record of the same shall be maintained by the contractor.
When density measurement reveal any soft areas in the embankment/ subgrade / earthen shoulders,
further compaction shall be carried out as directed by the Engineer-in-charge. If inspite of that the
specified compaction is not achieved, the material in the soft areas shall be removed and replaced by
approved material, compacted to the density requirements and satisfaction of the Engineer-in-charge.

3.0 Repairing of damages caused by rain/ spillage of water:


The soil in the affected portion shall be removed in such areas as directed by the Engineer-in-charge
before next layer is laid and refilled in layers and compacted using appropriate mechanical means
such as small vibratory roller, plate compactor or power rammer to achieve the required density. If
the cut is not sufficiently wide for use of required mechanical means for compaction, the same shall be
widened suitably to permit their use for proper compaction. Tests shall be carried out as directed by
the Engineer-in-charge to ascertain the density requirements of the repaired area. The work of
repairing the damages including widening of the cut, if any, shall be carried out by the contractor at
his own cost, including the arranging of machinery/ equipment for the purpose.
4. Quality control test
The works carried out by the contractor shall conform to the specification.
For ensuring the requisite quality of construction, the works shall be subjected to quality control tests,
as described hereinafter. The testing frequencies set forth are the desirable minimum and the
Engineer-in-charge shall have the full authority to carry out additional tests as frequently as he may

TS-8
C-NIL I-NIL O-NIL SCC-23
AIRPORTS AUTHORITY OF INDIA

deem necessary, to satisfy himself that the works comply with the appropriate specifications.
Where no specific testing procedure is mentioned, the tests shall be carried out as per the prevalent
accepted engineering practice to the directions of the Engineer-in-charge.

Following quality control tests shall be carried out at frequencies noted against each.

TEST
S. No. FREQUENCY
i) Density Test (IS:2720 Part -8) Two tests per 3000 cum. of soil.
ii) Moisture Content Test (IS:2720 Two tests per 3000 cum. of soil.
Part -2)

5. Measurements for Payment


Excavation for runway, shoulder and basic strip shall be measured by taking cross sections at 3 mtr
intervals in both direction in the original position before the work starts and after its completion and
computing the volumes in cu. m. by the method of average end.

6. Rates
Rates for the item shall include the cost of all operations, plant, machinery and labour involve in all
respect described above including all lifts and leads within Airports premises complete to the
satisfaction of Engineer-in-charge.

TS-9
C-NIL I-NIL O-NIL SCC-24
AIRPORTS AUTHORITY OF INDIA

Item No. 2 :- Supplying and filling gravelly soil (inclusive of royalty & carriage) suitable for
embankment construction in layers of 20 cms compacted depth, breaking the clods/ over size
material, removal of stumps/roots and the like while spreading, consolidating each layer with
vibratory road rollers of 80 to 100 KN static weight to not less than 95 % of the maximum
laboratory dry density as per IS 2720 (Part 8) and fine dressing to required grade and cross
slope as directed by Engr.-in-charge and as per particular specification.
(The item includes cost of work, payment of necessary royalty, carriage of good earth upto work site
for all leads and lifts involved for compacted quantity only).

1 Scope
The work also include construction of embankment including sub grades, shoulder and basic strip etc
backfill with approved material in accordance with requirements of these Specifications and the lines,
grades and cross-sections shown in the drawings or as indicated by the Engineer- in-charge.

2 Material and General Requirement


2.1 Physical requirements:

The materials used in embankments, sub grades, earthen shoulders and miscellaneous backfills shall
be excavated soil, Moorum, gravel, a mixture of these or any other material approved by the
Engineer- in-charge. Such materials shall be free of logs, stumps, roots, rubbish or any other
ingredient likely to deteriorate or affect the stability of the embankment/subgrade.
The following types of material shall be considered unsuitable for embankment:
(a) Materials from swamps, marshes and bogs;
(b) Peat, log, stump and perishable material; any soil that classifies as OL, OI, OH or Pt in
accordance with IS : 1498;
(c) Materials susceptible to spontaneous combustion;
(d) Materials in a frozen condition;
(e) Materials with salts resulting in leaching in the embankment.
(f) Good Earth having liquid Limit exceeding 50 and plastically Index exceeding 25 and CBR less
than 10%

The size of the coarse material in the mixture of earth shall ordinarily not exceed 75 mm when being
placed in the embankment and 50 mm when placed in the subgrade. However, the Engineer- in-
charge may at his discretion permit the use of material coarser than this also if he is satisfied that the
same will not present any difficulty as regards the placement of fill material and its compaction to the
requirements of these Specifications. The maximum particle size shall not be more than two - thirds of
the compacted layer thickness.
2.2. General requirements:
2.2.1. Borrow materials:

Where the materials are to be obtained from approved borrow areas in accordance with quality
conformity to required specification by the Engineer-in-charge. The arrangement for locating the
source of supply of material for embankment and subgrade as well as compliance to environmental
requirements in respect of excavation and borrow areas as stipulated, from time to time by the
Ministry of Environment and Forests, Government of India and the local bodies, as applicable, shall be
the sole responsibility of the contractor The materials for embankment shall be obtained from
approved sources.
Good earth shall have a uniformity coefficient not less than 5, capable of producing a well closed
surface finish. If the material passing 425 micron sieve is plastic, it shall have a liquid limit not greater
than 45 percent and a plasticity index not greater than 20 percent determined in accordance with
IS:2720 (Part-V). The soil shall be free from harmful salt like soluble sulphate.
The soluble sulphate shall not exceed 0.2% by weight and organic matter shall not exceed 1%. The
test shall be done as and when required

TS-10
C-NIL I-NIL O-NIL SCC-25
AIRPORTS AUTHORITY OF INDIA

Sample of good earth intended to be used for sub-grade shall be tested in the laboratory as a routine
for the following properties:-
i) Liquid Limit
ii) Plastic Limit
iii) Determination of the modified standard proctor density and corresponding optimum moisture
content.
iv) Natural Moisture Content
v) Deleterious Constituents

The work shall be so planned and executed that the best available materials are saved for the
subgrade and the embankment portion just below the subgrade.
The Contractor shall obtain representative samples from each of the identified borrow areas and have
these tested at the site laboratory following a testing programme approved by the Engineer- in-
charge. It shall be ensured that the subgrade material when compacted to the density requirements as
in Table 1 shall yield the design CBR value of the subgrade.
TABLE 1 COMPACTION REQUIREMENTS FOR EMBANKMENT AND SUBGRADE
Type of work / material Relative compaction as percentage of
max. laboratory dry density as per IS :
2720 (Part 8)
1. Embankment and basic strip Not less than 95

The contractor shall at least 7 working days before commencement of compaction submit the
following to the Engineer-in-charge for approval:
(i) The values of maximum dry density and optimum moisture content obtained in accordance with
IS: 2720 (Part 7) or (Part 8), as the case may be, appropriate for each of the fill materials he
intends to use.
(ii) A graph of density plotted against moisture content from which each of the values in (i) above
of maximum dry density and optimum moisture content were determined.
(iii) The Dry density – moisture content – CBR relationships for light, intermediate and heavy
compactive efforts (light corresponding to IS: 2720 (Part 7), heavy corresponding to IS: 2720
(Part 8) and intermediate in – between the two) for each of the fill materials he intends to use
in the subgrade.

3 Construction Operations

3.1 Setting out:


After the site has been cleared such as trees, bushes, shrubs, stumps, roots, grass, weeds, top organic
soil as per site requirement, the limits of embankment shall be set out true to lines, curves, slopes,
grades and sections as shown on the drawings or as directed by the Engineer- in- charge. The
embankment/subgrade shall be build sufficiently wider than the design dimension so that surplus
material may be trimmed, ensuring that the remaining material is to the desired density. The
Contractor shall provide all labour, survey instruments and materials such as strings, pegs, nails,
bamboos, stones, lime, mortar, concrete, etc., required in connection with the setting out of works and
the establishment of bench marks. The Contractor shall be responsible for the maintenance of bench
marks and other marks and stakes as long for the maintenance of bench marks and other marks and
stakes as long as in the opinion of the Engineer- in-charge, they are required for the work.
3.2. Dewatering:
If water is met with in the foundation of the embankment is in area with stagnant water due to
springs, seepage, rain or other causes, it shall be removed by suitable diversions, pumping or bailing
out and the excavation kept dry whenever so required or directed by the Engineer- in-charge. Care
shall be taken to discharge the drained water into suitable outlets as not to cause damage to the
works, crops or any other property. Due to any negligence on the part of the Contractor, if any such
damage is caused, it shall be the sole responsibility of the contractor to repair/restore to the original

TS-11
C-NIL I-NIL O-NIL SCC-26
AIRPORTS AUTHORITY OF INDIA

condition at his own cost or compensate for the damage.


3.3. Methods, tools and equipment:
Only such methods, tools and equipment as approved by the Engineer- in-charge shall be adopted
/sued in the work. If so desired by the Engineer- in-charge, the contractor shall demonstrate the
efficacy of the type of equipment to be used before the commencement of work.
3.4 Compacting ground supporting embankment/subgrade:
Where necessary, the original ground shall be leveled to facilitate placement of first layer of
embankment, scarified, mixed with water and then compacted by rolling so as to achieve minimum
dry density as given in Table1.
3.5. Spreading material in layers and bringing to appropriate moisture content
3.5.1 The embankment and subgrade material shall be spread in layers of uniform thickness no
exceeding 200 mm compacted thickness over the entire width of embankment by mechanical
means, finished by a motor grader and compacted as per clause 2.9. The motor grader blade
shall have hydraulic control suitable for initial adjustment and maintain the same so as to
achieve the specific slope and grade. Successive layers shall not be placed until the layer under
construction has been thoroughly compacted to the specified requirements as in Table 1 and
got approved by the Engineer- in-charge. Each compacted layer shall be finished parallel to the
final cross-section of the embankment.
3.5.2 Moisture content of the material shall be checked at the site of placement prior to
commencement of compaction; if found to be out of agreed limits, the same shall be made good.
Where water is required to be added in such constructions, water shall be sprinkled from a
water tanker fitted with sprinkler capable of applying water uniformly with a controllable rate
of flow to variable widths of surface but without any flooding. The water shall be added
uniformly and thoroughly mixed in soil by blading, discing or harrowing until uniform moisture
content is obtained throughout the depth of the layer.
If the material delivered to the bed is too wet, it shall be dried, by aeration and exposure to the
sun, till the moisture content is acceptable for compaction. Should circumstances arise, where
owing to wet weather, the moisture content cannot be reduced to the required amount by the
above procedure, compaction work shall be suspended.
Moisture content of each layer of soil shall be checked in accordance with IS: 2720 (Part 2), and
unless otherwise mentioned, shall be so adjusted, making due allowance for evaporation losses,
that at the time of compaction it is in the range of 1 percent above to 2 percent below the
optimum moisture content determined in accordance with IS: 2720 (Part 7) or IS: 2720 (Part
8) as the case may be.
After adding the required amount of water, the soil shall be processed be means of graders,
harrows, rotary mixers or as otherwise approved by the Engineer- in-charge until the layer is
uniformly wet.
Clods or hard lumps of earth shall be broken to have a maximum size of 75 mm when being
placed in the embankment and a maximum size of 50 mm when being placed in the subgrade.
3.5.3. Embankment and other areas of fill shall, unless otherwise required in the contract or
permitted by the Engineer- in-charge, be constructed evenly over their full width and their
fullest possible extent and the contractor shall control and direct construction plant and other
vehicular traffic uniformly over them. Damage by construction plant and other vehicular traffic
shall be made good by the contractor with material having the same characteristics and
strength as the material had before it was damaged.
Embankments and other areas of unsupported fills shall not be constructed with steeper side
slopes, or to greater widths than those shown in the contract, except to permit adequate
compaction at the edges before trimming back, or to obtain the final profile following any
settlement of the fill and the underlying material.
3.6. Compaction:
Only the compaction equipment approved by the Engineer- in-charge shall be employed to compact
the different material types encountered during construction. Smooth wheeled, vibratory, pneumatic
tyred, sheepsfoot or pad foot rollers, etc. of suitable size and capacity as approved by the Engineer- in-
charge shall be used for the different types and grades of materials required to be compacted either
individually or in suitable combinations.

TS-12
C-NIL I-NIL O-NIL SCC-27
AIRPORTS AUTHORITY OF INDIA

The compaction shall be done with the help of vibratory roller of 80 to 100kN static weight with plain
or pad foot drum or heavy pneumatic tyred roller of adequate capacity capable of achieving required
compaction.
The contractor shall demonstrate the efficacy of the equipment he intends to use by carrying out
compaction trials. The procedure to be adopted for these site trials shall first be submitted to the
Engineer- in-charge for approval.
Earthmoving plant shall not be accepted as compaction equipment nor shall the use of a lighter
category of plant to provide any preliminary compaction to assist the use of heavier plant be taken
into account.
Each layer of the material shall be thoroughly compacted to the densities specified in Table 1.
Subsequent layers shall be placed only after the finished layer has been tested according to quality
control test criteria and accepted by the Engineer- in-charge. The Engineer- in-charge may permit
measurement of field dry density by a nuclear moisture/density gauge used in accordance with
agreed procedure and the gauge is calibrated to provide results identical to that obtained from tests in
accordance with IS: 2720 (Part 28). A record of the same shall be maintained by the contractor. When
density measurement reveal any soft areas in the embankment/ subgrade / earthen shoulders,
further compaction shall be carried out as directed by the Engineer- in-charge. If inspite of that the
specified compaction is not achieved, the material in the soft areas shall be removed and replaced by
approved material, compacted to the density requirements and satisfaction of the Engineer- in-charge.
3.7. Repairing of damages caused by rain/ spillage of water:
The soil in the affected portion shall be removed in such areas as directed by the Engineer- in-charge
before next layer is laid and refilled in layers and compacted using appropriate mechanical means
such as small vibratory roller, plate compactor or power rammer to achieve the required density. If
the cut is not sufficiently wide for use of required mechanical means for compaction, the same shall be
widened suitably to permit their use for proper compaction. Tests shall be carried out as directed by
the Engineer-in-charge to ascertain the density requirements of the repaired area. The work of
repairing the damages including widening of the cut, if any, shall be carried out by the contractor at
his own cost, including the arranging of machinery/ equipment for the purpose.
4. Quality control test
The material supplied and the works carried out by the contractor shall conform to the specification.
For ensuring the requisite quality of construction, the materials and works shall be subjected to
quality control tests, as described hereinafter. The testing frequencies set forth are the desirable
minimum and the Engineer- in-charge shall have the full authority to carry out additional tests as
frequently as he may deem necessary, to satisfy himself that the materials and works comply with the
appropriate specifications.
Where no specific testing procedure is mentioned, the tests shall be carried out as per the prevalent
accepted engineering practice to the directions of the Engineer-in-charge.
Following quality control tests shall be carried out at frequencies noted against each.

S. No. TEST FREQUENCY

i) Sand Content (IS:2720Part -4) Two tests per 3000 cum. of soil.

ii) Plasticity Test(IS:2720Part-5) Two tests per 3000 cum. of soil.

iii) Density Test (IS:2720 Part -8) Two tests per 3000 cum. of soil.

iv) Deleterious Content Test (IS:2720 As and when required by the Engineer.
Part -27)

v) Moisture Content Test (IS:2720 Two tests per 3000 cum. of soil.
Part -2)

TS-13
C-NIL I-NIL O-NIL SCC-28
AIRPORTS AUTHORITY OF INDIA

5. MEASUREMENTS FOR PAYMENT


Earth embankment / subgrade construction shall be measured separately by taking levels at 3 mtr.
Intervals in the original position before the work starts and after its completion and computing the
volumes of earthwork in cubic meters by the method of average end areas.
6. RATES
Rates for the item shall include the cost of all operations, material, plant, machinery and labour
involve in all respect described above including all lifts and leads within Airports premises complete
to the satisfaction of Engineer-in-charge.

TS-14
C-NIL I-NIL O-NIL SCC-29
Bill of Quantity

C-NIL I-NIL O-NIL SCC-1


BOQ-1
BOQ-2