Doc No: SGG23177NS-A-001-Rev.

00
Prepared by: Lydia

FAT PLAN For A0790 VDC CPT11 GIS


Project

Sieyuan Electric Co., Ltd.

27/02/2024
Doc No: SGG23177NS-A-001-Rev.00
Prepared by: Lydia

Agenda
(BRE 4 ENIND 012020 Lot10 SE Dias Macedo GIS Factory Acceptance Test)
(Sieyuan Electric Co., Ltd.)

Address (No.3399, Huaning Road, Minhang Dist., Shanghai, 201108, P.R.C)


Day 1 Day 2 Day 3 Day 4 Day 5 Day 6
Type of
No. Description of Test
test
AM PM AM PM AM PM AM PM AM PM AM PM

Design and visual check


1 Ro 1 Bay
设计和外观检查

Mechanical operating &


2 mechanical characteristic test Ro 1 Bay
机械操作和机械特性试验
Measure the resistance of the main
3 circuit Ro 1 Bay
主回路电阻测量
Withstand Voltage Test on the
auxiliary and control circuit
4 Ro 1 Bay
(mechanism parts )
辅助回路绝缘试验

Preparation for HV test


5 Ro 1 Bay 1 Bay 1 Bay
高压测试准备

Dielectric test on the main circuit


6 Ro 1 Bay
主电路绝缘试验

Preparattion for GAS leakage test


7 Ro 1 Bay 1 Bay 1 Bay
气密准备

Gas Leakage test


8 Ro 1 Bay
气密测试
Wiring check and interlocking
function test on Local control
9 cabinet and the test of Ro 1 Bay
Interchangeability of components
接线检查以及联锁试验

Note: The test schedule is rough plan and it may be changed according to the actual situation.
Doc No: SGG23177NS-A-001-Rev.00
Prepared by: Lydia

Test requirement:

Sieyuan Routine Test Requirement for 145kV GIS


Sieyuan Requirement
No. Test Item Test Equipment Test standard and parameter 145kV GIS
Witness

Dielectric test on the main circuit power frequency voltage


(power frequency withstand test:275kV 1min
220KV power frequency partial IEC62271-203-7.102/Technical Spec
1 voltage test, partial discharge Partial Discharge
discharge measurement system IEC62271-203-7.1.2/Technical Spec Measuring Voltage:174kV
measurement) >1min, <5pC
Tests on auxiliary circuits,
equipment and interlocks (Voltage
>100MΩ
2 test on auxiliary and control Insulation resistance tester IEC62271-203-7.103/Technical Spec 2 KV/1 min
circuits,functional and wiring
checks)
Tests to verify the resistance of the High precision circuit resistance
3 IEC62271-203-7.3/Technical Spec Meet standard requirements
main circuit tester
Quantitative SF6 leakage
4 Tightness test (Gas leakage test) IEC62271-203-7.4/Technical Spec <30ppm
detector
Mechanical operation test for CB High-voltage switch
5 IEC62271-203-7.102/Technical Spec Meet standard requirements
DS ES FES characteristic tester
6 Wiring check IEC62271-203-7.103/Technical Spec Meet standard requirements

7 Design and visual check Visually and tape IEC62271-203-7.103/Technical Spec Meet standard requirements

8 Pressure test for partitions Routine test report IEC62271-203-7.103/Technical Spec Meet standard requirements
Doc No:SGF23177NS-A-001-Rev.00

INSPECTION AND TEST PLAN


Component/ Agency
NO Activities Verification document Acceptance criteria Remarks
Operation M EPC C
1 Factory Acceptances Test
Power frequency voltage
H W/R R IEC62271-203-7.1
Partial discharge test Transport unit routine test
Bay Resistance Tests of the main circuit report (Bay) H W/R R IEC62271-203-7.3
(Transport unit means
1.1 (Transport
Gas leakage tests workshop production flow H W/R R IEC62271-203-7.4
unit) pattern bay)
Mechanical operation test H W/R R IEC62271-203-7.102
Pressure test for partitions Supplier’s report H R R IEC62271-203-7.104
Wiring Check LCP procedure control H W/R R
1.2 LCC Tests on auxiliary circuits, equipment and interlocks: Voltage tests on card IEC62271-203-7.103
Routine test report H W/R R
auxiliary and control circuits
a)Verification of terminal markings
b)Polarity testc)Dimensions
d)Measurement of insulation resistance If applicable
e)Power-frequency withstand test
1.3 CT Supplier’s report H R R IEC 61869-2
f)Inter-turn over-voltage test Outsource
g)Magnetization curves unit
h)Test for ratio error and phase displacement
i)Determination of the instrument security factor
a) Verification of terminal marking
b) Power frequency withstand tests on primary winding and partial If applicable
discharges measurement
1.4 PT Supplier’s report H R R IEC 61869-3
c) Power frequency withstand tests between section and on secondary Outsource
winding unit
d) Accuracy class designation
1)Any other test required as per IEC shall be carried out;
Note: 2)All the documents/records will be verified by Sieyuan EPC & Customer ;
3)Test report shall be provided by manufacturer for the tests which are done at the Sieyuan factory, and the sub-supplier test report should also be provided by Sieyuan.
Legend:
Approved by : Lydia Gu M : SIEYUAN GIS EPC: Sieyuan EPC C : Customer
H : Hold W : Witness R : Record