Client Majid Al Futtaim Properties LLC Project Name Al Zahia Community - Al Yasmeen Prepared / Reviewed By : Engr. Ramasamy
Lead Consultant Engineering Consultants Group Discipline Structural Approved By : Engr. Amar Al Shibiby
Main Contractor United Engineering Construction LLC
Sub Contractor Cave General Transport Page : 1 of 1
Responsibility
Item No.
Applicable
Frequency of Control Data / Main
Inspection / Test to be carried out Acceptance Criteria Specification / Inspection Method Sub Consultant
Test / Inspection Forms Contractor Third Party
Standard Contractor Engineer
(UNEC)
Prior to
As per project Proj. specification section Laboratory test
3 Material submittal commencement of Material submittal H R H R
specifications 31 20 00 report
backfilling work
Prior to
As per project Proj. specification section Laboratory test
4 Suitability test for backfilling commencement of Inspection request H W R
specifications 31 20 00 report
work
Survey primary control
Prior to
log shall be verified & IR for survey
5 Establish reference benchmarks commencement of SM benchmark Surveying H H
signed of by the relevant primary control log
work
authority
Prior to
As per project Proj. specification section Material inspection
6 Material Delivery commencement of Delivery note H H
specifications 31 20 00 request
work
Client Majid Al Futtaim Properties LLC Project Name Al Zahia Community - Al Yasmeen Prepared / Reviewed By : Engr. Ramasamy
Lead Consultant Engineering Consultants Group Discipline Structural Approved By : Engr. Amar Al Shibiby
Main Contractor United Engineering Construction LLC
Sub Contractor Cave General Transport Page : 1 of 1
Responsibility
Item No.
Applicable
Frequency of Control Data / Main
Inspection / Test to be carried out Acceptance Criteria Specification / Inspection Method Sub Consultant
Test / Inspection Forms Contractor Third Party
Standard Contractor Engineer
(UNEC)
Method statement,
Sub Grade / Each As per project Proj. specification section check
10 Levelling and compaction Inspection request H H H R
layer specifications 31 20 00 list ,compaction
test result
as per Engineer As per project Proj. specification section Laboratory test
11 CBR Test Inspection request H H H R
requirement specifications 31 20 00 report
Method statement,
Sub Base/ Each As per project Proj. specification section check
12 Road Base Test Inspection request H H H R
layer specifications 31 20 00 list ,compaction
test result
Carry out compaction test on each As per project Proj. specification section Laboratory test
13 Each Layer Inspection request H H H R
backfill layer specifications 31 20 00 report
LEGEND: H- Hold for Inspection W- Witness Inspection S- Surveillance Inspection R- Record Review